Adamawa, Borno and Yobe States- North East NigeriaSHELTER/NFI & CCCM SECTOR END OF YEAR REVIEW

The boundaries and names shown and the designation used on this map do not imply official endorsement oracceptance by the Shelter/NFI and CCCM Sector or the Nigerian government.They are only for operational humanitarian activities.

Jan - Dec 2018

Target: 55,350 hhReached: 38,446 hh

Ensure sufficient coordinated and adequate delivery ofemergency shelter solutions to respond to the immediateshelter needs of the affected people

Deliver reinforced/ transitional shelters and repair assistanceto respond to the specific shelter needs of the affectedpeople

EMERGENCY SHELTER SOLUTIONS

Target(hh): 31,240 6,600 14,250Reached (hh): 6,215 7,154 3,671

Construction Conditional cash Repairs

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

1,001 - 5,000

5,001 - 6,500

Hard to Reach LGAs

1 - 1,000

Legend

Households assisted0

TRANSITIONAL SHELTER SOLUTIONS

Lor

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

1,001 - 5,000

5,001 - 6,500

Hard to Reach LGAs

1 - 1,000

Legend

Households assisted0

Abadam Abadam

SHELTER AND NON - FOOD ITEMS (NFIs)

Target: 106,500 hhReached: 47,249 hh

Deliver flexible, coordinated, adequate and harmonized NFI kits

NON - FOOD ITEMS (NFIs)

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

1,001 - 5,000

5,001 - 6,500

Hard to Reach LGAs

1 - 1,000

Legend

Households assisted0

Abadam

KEY FACTS AND FIGURES

2018 HRP Target: 1.3 Million0.24 MillionPeople assisted:

(HRP only)

2018 HRP partnersACTED, CRS, DRC, HARAF, INTERSOS, IOM, NRC, Solidarités International, UNHCR.

* unique individuals assisted with NFI kits to avoid double count as some individualswere assisted in more than one category.

$10.3M (15%)

$57.1M (85%)

$67.4millionrequirement

Funding requirements

received unmet

15,915

199,100

21,230

Adamawa Borno Yobe

Beneficiaries by State

Tracking and monitoring displacement and mobility toinform interventions across sectors

Support the maintenance, upgrade, care and decong-estion of sites through planning and improvements

TRACKING DISPLACEMENT MAINTENANCE OF SITES

DISPLACEMENT MANAGEMENT SYSTEMS (CCCM)

Enhanced displacement management throughcapacity building, on-site or mobile facilitation andcamp management support

DISPLACEMENT MANAGEMENT

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

Hard to Reach LGAs

LGA without DMS activity

Legend

LGA with DMS activity

Abadam

KEY FACTS AND FIGURES

2018 HRP Target: 0.9 Million0.74 MillionPeople assisted:

2018 HRP partnersACTED, INTERSOS, IOM, UNHCR.

$8.0M (43%)

$10.5M (57%)

$18.5million

requirement

Funding requirements

received unmet

12,493

718,882

9,591

Adamawa Borno Yobe

Beneficiaries by State

Sites with adequate site facilitation: 130 151Reception centres established/improved: 10 9No. of individuals trained: 3,000 718

Target Reached

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

Hard to Reach LGAs

LGA without DMS activity

Legend

LGA with DMS activity

Sites assessed and layout mapping 50 6developed/ renewed:Sites improved through maintenance: 40 4

Target Reached

Fune

Biu

Song

Toungo

Fufore

Damboa

Konduga

Kukawa

Tarmua

Gujba

Jada

Bursari

Fika

Kaga

Geidam

Hong

Marte

Yusufari

Gubio

Yunusari

Jakusko

Mobbar

Gulani

Ganye

Gombi

Hawul

Dikwa

Girei

Guzamala

Damaturu

Shani

Chibok

Askira/Uba

Demsa

Maiha

Monguno

Bayo

Mayo-Belwa

Machina

Shelleng

KarasuwaNguru

Lamurde

Nangere

Numan

Guyuk

Bade

Yola South

Mubi North

Bade

Potiskum

KwayaKusar

Mubi South

Maiduguri

Yola North

Jere

Borno

Adamawa

Yobe

Kala/BalgeNgala

Nganzai

Mafa

Bama

Gwoza

Magumeri

Michika

Madagali

Hard to Reach LGAs

LGA without DMS activity

Legend

LGA with DMS activity

Displacement reports published: 8 5Individuals biometrically registered: 900,000 527,504Return assessments reports published: 6 6

Target Reached

Data sources:Sector Partners 5Ws, DTM, Financial Tracking Service (FTS)Production date: 26th January 2018