ABC OF BRIDGE NO. 465 I-195 Ramp (Dr-2) Over Warren Avenue FHWA Rhode Island Showcase October 30, 2014
SHRP 2 Solutions
Presentation Outline
• Overview of the Project Scope
• ABC Project Planning
• ABC Design & Construction
• Construction / Contractor Perspective
SHRP 2 Solutions
FHWA Every Day Counts Initiative Designed to identify and deploy innovation aimed at shortening project
delivery, enhancing the safety of our roadways and protecting the
environment.
SHRP 2 Solutions
RIDOT Goals • Safety
• Innovative
• Using Accelerated Bridge Construction Methods • Precast substructure, PBE’s
• Minimize Time • Road closure eliminated phasing
• Cost Effective • Balanced accelerating construction with user costs
• Efficient Intermodal Transportation Network
• Restored link from East Bay to Providence Crossing
SHRP 2 Solutions
RIDOT Goals (Continued) • Public Attentiveness
• Minimize Public Impact • Replace in 20 days with ABC, 2+ years conventional
• Increase Public Awareness • City Officials • Attended Council Meeting • Outreach through multiple media venues: radio,
social, paper, internet, link to web cam on DOT website, door to door with handouts
Overview of the Project
Scope
Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue
SHRP 2 Solutions
SHRP 2 Solutions
Site Location WB I-195 EB I-195
Bridge 465
TAUNTON AVE N
SHRP 2 Solutions
Summary of Existing Bridge
• BRIDGE SUPERSTRUCTURE: Precast Prestressed Concrete I-beams and Reinforced concrete Tee beams
• BRIDGE SPAN: 3 simply supported spans of 31’ – 1 3/8” (span 1) 61’- 1½” (span 2), 31’ – 1 3/8” (span 3)
• BRIDGE WIDTH: 23’ – 0” curb to curb, 28’ – 2” out to out
• SUBSTRUCTURE: Unreinforced concrete gravity abutments on piles and two column reinforced concrete bents on piles
• BRIDGE SKEW: 25o – 9’ – 6”
• BRIDGE SIDEWALKS: Safety walks on both sides
• ROADWAY SURFACE: 3” bituminous wearing surface
SHRP 2 Solutions
Existing Bridge Condition
SHRP 2 Solutions
Overview of Project Scope • Bridge 465
• Replace Superstructure & Piers • Evaluate Abutments • Consider Feasibility of ABC Methods
• I-195 Westbound On-Ramp Approaches • Full Depth Construction for Bridge
Replacement • Guardrail Replacement • Pavement Milling & Overlay
• Warren Avenue • Sidewalk Replacement • Wheelchair Ramp Upgrade • Pavement Milling & Overlay
TAUNTON AVE
N
Bridge 465
WARREN AVE ON-RAMP
SHRP 2 Solutions
Why ABC for New Bridge? • No phase construction option due to narrow 23’ – 0” roadway width
• Significant reduction of bridge closure time
• Detour options available
• Reduce impact to traffic and the public
ABC
Project Planning
Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue
SHRP 2 Solutions
SHRP 2 Solutions
FHWA Framework for Decision-Making
SHRP 2 Solutions
Rapid Onsite Construction Factors • High Traffic Volumes YES
• Emergency Replacement Necessary YES
• Evacuation Route NO
• Required Lane Closures / Detours YES
• Impact on Total Project Critical Path YES
Use Prefabrication
One Month Duration Closure of
On-Ramp over Warren Ave
SHRP 2 Solutions
Closure of I-195 On-Ramp (Bridge 465)
Closure of On-Ramp over Warren Ave & Closure of
Warren Avenue below Bridge 465
(including sidewalks)
Closure of I-195 Off-Ramp (Exit 5)
SHRP 2 Solutions
Closure of Ramps – Two Weekends
Two Weekends
SHRP 2 Solutions
Milestones • #1 Weekend Closure – Demolition
• Re-Open Warren Ave and Exit 5 Ramp
• #2 Weekend Closure – Place Superstructure • Re-Open Warren Ave and Exit 5 Ramp
• #3 One Month Duration - Complete Bridge Construction • Re-open On-ramp Traffic Over Warren Avenue
• #4 Substantial Completion • Complete All Work for Bridge 465 And Warren
Avenue.
SHRP 2 Solutions
Incentive / Disincentive • #1 Completion of Weekend Closure #1 - $400 Per Hour
• Maximum Incentive $20,000
• #2 Completion of Weekend Closure #2 - $400 Per Hour
• Maximum Incentive $20,000
• #3 Bridge Open to Traffic – $12,000 Per Calendar Day
• Maximum Incentive $120,000
Liquidated Damages Substantial Completion – $1,500 Per Day
SHRP 2 Solutions
Incentive / Disincentive • Vehicle Operating Cost
• Value of Travel Time Savings
N Bridge 465
P
ABC Design & Construction
Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue
SHRP 2 Solutions
SHRP 2 Solutions
Overview map
Bridge 465 Constructed in 1959
SHRP 2 Solutions
Bridge 465 – LBG Scope of Work • Replace Superstructure & Piers
• Analyze Abutments & Wingwalls for LRFD Compliance
• Revise profile to meet 14’-3” Minimum Clearance
• Consider ABC Methods
SHRP 2 Solutions
Bridge 465 – Proposed Improvements & Deviation from Original Scope
Full Bridge Replacement:
• Replace Superstructure
• Replace Abutments
• Replace Wingwalls
• Replace Pier Cap, Columns & Footings
SHRP 2 Solutions
Project ABC Methods and Techniques
Prefabricated Bridge Elements &
Systems (PBES)
Modular Construction
Structure Erection
Techniques
Geotechnical Techniques
SHRP 2 Solutions
STEEL BEAM
Bridge 465 – Prefabricated Elements
SHRP 2 Solutions
Bridge 465 – Prefabricated Elements
PRESTRESSED CONCRETE BEAMS AND PRECAST DECK PANELS
SHRP 2 Solutions
Bridge 465 – Prefabricated Elements
NEXT BEAM
SHRP 2 Solutions
Bridge 465 – Prefabricated Elements
Prefabricated Substructure
SHRP 2 Solutions
Bridge 465 – Proposed Single Span Option
29
80’
SHRP 2 Solutions
Bridge 465 – Laydown Areas
B
B
A
SHRP 2 Solutions
Proposed Transverse Section
SHRP 2 Solutions
Superstructure Modular Unit
SHRP 2 Solutions
Superstructure Modular Unit
SHRP 2 Solutions
FOUNDATION SUPPORT IMPROVEMENTS
SHRP 2 Solutions
Proposed Abutment
SHRP 2 Solutions
North Abutment Foundation
SHRP 2 Solutions
North Abutment Foundation
SHRP 2 Solutions
Abutment Footing Closure Pour
SHRP 2 Solutions
Abutment Footing Closure Pour
SHRP 2 Solutions
Precast Wingwall Footing
SHRP 2 Solutions
Precast Abutment Stem Elements
SHRP 2 Solutions
Precast Abutment Stem Elements
SHRP 2 Solutions
Precast Wingwall Stems & Footings
SHRP 2 Solutions
Precast Wingwall Stems & Footings
SHRP 2 Solutions
Completed Precast North Abutment
SHRP 2 Solutions
Completed Precast North Abutment
SHRP 2 Solutions
• Install bearing assemblies. • Install superstructure modular units. • Install diaphragms between beams S2 and S3. • Form and place the reinforcement and concrete for the superstructure closure pour. • Place the precast approach slabs and place the reinforcement and concrete for the
approach closure pour. • Form and place concrete for the safety barrier closure pour. • Place the approach roadway base material. • Place the bridge wearing surface. • Install the strip seal at the north abutment and saw cut pavement and the south
abutment.
Remaining Construction
Construction / Contractor Perspective
Accelerated Replacement of Bridge No. 465 I-195 On-Ramp (DR-2) over Warren Avenue
SHRP 2 Solutions
SHRP 2 Solutions
History
XXX
• Fit for Aetna Bridge
• Incentive/Disincentive
• Duration of Project
Factors Considered Pre-Bid
SHRP 2 Solutions
XXX
• Proper Planning
• Communication with Owner/Engineer
• Capable Resident Engineer
• Quality Subcontractors
Key to Success
SHRP 2 Solutions
XXX
• Tolerances for Precast
• Time Allowed for Submittals
• Precasters Preparedness (mass concrete, 3D
modeling, schedule, etc)
• Area for Construction (equipment, fill, etc)
• Unknowns – weather, equipment
breakdowns, etc.
SHRP 2 Solutions
Challenges
Thank You
David Fish, P.E. Managing Engineer, RIDOT
Jessica Rodas Project Manager, RIDOT
Phineas Fowler, P.E. Principal Structural Engineer, Louis Berger
John Fitzgerald, P.E. Senior Structural Engineer, Louis Berger
Jeffrey Bostock Vice President, AETNA Bridge Co.