Case Study: Turnaround & Inspection Planning

Objectives: • Simultaneously minimizes both T&I costs and Supply-Demand disruption costs • Unifies Revamping and Retrofit modeling with Repair decision-making • Considers Construction/Commissioning/Correction tasks as sequence-dependent cleaning operations • Does not require special formulation – uses typical supply-demand logistics modeling with sequence-dependent changeovers/setups to model correction/maintenance activities.

1

New Maintenance Scheduling Approach using MILP and Sequence-Dependent Changeover

Policies

Demand

Demand

Maintenance

Supply