OMEGAMORGAN
MOVING THE
SELLEWOOD BRIDGE
Rigging Job of the Year
Project Overview
• The 87-year old Sellwood Bridge in Portland, Oregon
Weight: 3,400 Tons
Length: 1,100 Feet
• Busiest 2 lane bridge in Oregon, with over 30,000 vehicle crossings per day
Location
Location
Limitations
• The Project was a firm-fixed price bid. According to Multnomah County, the government entity responsible for the bridge, Omega Morgan’s solution saved millions of dollars by reducing up to a year of construction time for the new bridge.
• The Bridge’s Main Contractor (Slayden / Sundt) hired Omega Morgan to relocate the bridge so it could remain open to traffic during the construction of a new $308 million bridge.
• The Bridge’s location provided significant additional challenges given surrounding infrastructure (both public and private.)
• The project required minimal traffic disruption.
Limitations
Limitations
Innovation & Ingenuity
• Innovation & Ingenuity Required: • The Bridge was required to be relocated very specifically 1. East End - Shifted 33 Feet North 2. West End - Shifted 66 Feet North 3. Entire span shifted 2 Feet East
• New techniques demonstrated • Creative Application of Old Techniques • Newly Designed Equipment • Modification to Standard Equipment • Resources Used Economically
Innovations & Ingenuity
Innovations & Ingenuity
Innovations & Ingenuity
Innovations & Ingenuity
Engineering & Planning
• Physical Characteristics • 1,100 Feet Long • 3,400 Tons • 87 years old
• Site Characteristics • Intruding surrounding infrastructure • Unstable ground causing existing bents to fail • Critical bridge construction timeline and required minimal traffic
disruption (less than five day shut down) • Winter job schedule; potential for rain, snow or ice
• Job Schedule • Job was completed on time and ahead of schedule (5 days closure
planned, 4 days utilized.)
• Demonstrated Professionalism • Crews worked tirelessly in cooperation with public and private partners
and earned the award for the demolition of the relocated span.
-30
-20
-10
0
10
20
30
40
50
60
9:0
0:0
0 A
M
9:5
0:0
0 A
M
10
:40
:00
AM
Bent 18 January 19, 2013
9:00AM – 11:00AM
SG21RAW
SG18RAW
-40
-20
0
20
40
60
80
100
120 2
:00:0
0 P
M
2:5
0:0
0 P
M
3:4
0:0
0 P
M
Bent 18 January 19, 2013 2:00PM – 4:00PM
SG21RAW
SG18RAW
Safety • Safety program: • Safety Manager included in planning process and execution
of the job. Complete safety plan required and completed by Multnomah County and Slayden / Sundt.
• Proper use of equipment: • Slide gear set up provided for safe, timely execution of
project.
• Results: • As a result of careful planning and execution, there were
zero recordable injuries on the job.