Download - 2. Planning Fundamentals

Transcript
  • 7/25/2019 2. Planning Fundamentals

    1/50

    Planning Fundamentals

    Adapted from Project Management for Business, Engineering, and Technology. Nicholas J.

  • 7/25/2019 2. Planning Fundamentals

    2/50

    Common Elements of Project

    Plan1. Scope Statement, Charter, SOW2. Detailed requirements

    3. Project organization and responsiilit! "ortas#s

    $. Detailed %or# de"inition &W'S or P'S and%or# pac#age(%or# tas# details)

    *. Detailed schedules %ith milestones+. Project udget and cost accounts

    . -ualit! plan

  • 7/25/2019 2. Planning Fundamentals

    3/50

    Elements of Project Plan

    . /is# plan0. Wor# reie% plan

    1. esting plan

    11. Change control plan12. Documentation plan

    13. Procurement plan

    1$. 4mplementation plan5lement 2 has alread! een discussed.

    his chapter "ocuses on elements 1,3,$, and aspects o" * and 13.

    he remaining elements are addressed in later chapters.

  • 7/25/2019 2. Planning Fundamentals

    4/50

    Scope, Charter, and SOW

    Scope, charter, or SOW6 is the "irst item on

    project master plan. 7ariations on same theme

    Purpose proide road description o" master plan(project to

    sta#eholders

    directed at core project team, project organization,primar! sta#eholders

  • 7/25/2019 2. Planning Fundamentals

    5/50

    Scope Descries 8readth o" project,9 areas to e coered

    ! project and delierales : areas not coered.

    4ncludes6

    Ojecties o" project "rom perspectie o" contractor

    /equirements

    Delierales

    ;ilestones

  • 7/25/2019 2. Planning Fundamentals

    6/50

    SOW

    SOW, Statement o" Wor#, is the scope

    document "or contractedprojects

    >ppears in /?P, proposal, contract, as %ell as

    master plan

  • 7/25/2019 2. Planning Fundamentals

    7/50

    Dening the SOW1. ?or contracted project %or#

    Contractor and customer agree on de"inition o" %or#required, %or# proposed, and asis "or costs,schedules, and related matters.

    here are t%o SOWs, SOW in master plan

    SOW in contract&CSOW)

    SOW in contractor@s project plan must contain same

    in"ormation and requirements as stated in CSOW. Contractor@s SOW and CSOW might e %orded

    di""erentl!, ut oth should hae e=act sameinterpretation in terms o" %or# and end results

  • 7/25/2019 2. Planning Fundamentals

    8/50

    Dening the SOW2. Suggestions

    5nsure that SOW and W'S correspond to each other.

    'oth must e clearA neither contractor nor customer

    question %hat has to e done.

    /equirements "or eer! endBitem, tas#, and report must

    e clear enough so parties responsible%ill e ale tosignBo"" acceptance o" results.

    eer speci"! tas#s using 8as necessar!9 or 8as required9.

    Where judgments must e made, speci"! who%ill

    ma#e them,procedures"or ma#ing them, and

    potential impact o" judgments on cost and schedule

    escalation.

  • 7/25/2019 2. Planning Fundamentals

    9/50

    Issues in Dening SOW

    2. Suggestions &cont.)6

    Speci"! requirements using actie terminolog!

    &8shall9 or 8%ill9)

    eer use passie terminolog! &8should9 or 8tr! to9).

    8shall9 must do

    8%ill9 desirale to do

  • 7/25/2019 2. Planning Fundamentals

    10/50

    Issues in Dening SOW

    2. Suggestions &cont.)6

    Categorize speci"ications applicale to entire

    project separatel! "rom those applicale to onl!

    parts o" project.

    Eold meetings %ith customers and technical

    specialists to reie% clarit! and completeness

    SOW and W'S.

  • 7/25/2019 2. Planning Fundamentals

    11/50

    Charter Charter is the scope document internalprojects

    ;a! include eer!thing in Scope Statement plus

    ris# limits

    customer needs spending limits

    #e! pla!ers on project team.

    4ssued ! senior management to legitimize project

    Fies project manager authorit! to initiate %or#

    and appl! resources to project.

  • 7/25/2019 2. Planning Fundamentals

    12/50

    Charter Contents 'ac#ground Project Ojecties Scope or SOW Delierales

    >ssumptions Constraints >pproach

    Schedule Project eam /is# ;anagement Plan

  • 7/25/2019 2. Planning Fundamentals

    13/50

    Work Denition Start %ith the SOW and requirements &the

    8%hat9 o" the project)

    >s# 8ho%9 %ill the SOW and requirements emet6 %hat is the actual %or# to e per"ormed

    to meet the requirementsG Sudiide the project into small, %ell de"ined

    %or# pac#ages

    Hse the Wor# 'rea#do%n Structure, W'S&a.#.a. Project 'rea#do%n Structure, P'S)

  • 7/25/2019 2. Planning Fundamentals

    14/50

    WS

    Diide project into 8%ellBde"ined9 tas#s

    WellBde"ined tas#s6 the asis "or project schedule,

    udget, resource requirements, responsiilit!assignments, and ris# management

  • 7/25/2019 2. Planning Fundamentals

    15/50

    WS E!ample for "ouse

    - Heating- Plastering

    - Plumbing-Wiring-Carpentry-Painting

    HOUSE

    SITE GARAGE OVERHEADAD!I"ISTRATIO"

    #ASE!E"TSTRUCTURE I"TERIOR

    $%OOR ROO$ WA%%S

    - Sur&ey- St'rm (rains- Gra(ing- Wal)s* (ri&e

    - %an(s+aping

    - E,+a&ati'n- $'un(ati'n

    - Plumbing- $l''r- Carpentry

    - $rame- Subl''r* l''r- Insulati'n

    - $rame- R''ing- Insulati'n- Gutters

    - $rame- #ri+)s- R'ug. Wiring- /

    %IVI"G U"IT

    ----

    ---

    -

    /equirements6 I

    -

    ---

  • 7/25/2019 2. Planning Fundamentals

    16/50

    WS Procedure Start %ith SOW and requirements

    >s# 8%hat *B1 high leel actiities %ould !ield

    intended resultsG9

    ?or each highBleel actiit! as# 8What is inoled

    here, %hat is requiredG9

    -uestions that are di""icult to ans%er require the

    actiit! to e "urther ro#en do%n

    Continue rea#ing do%n actiities until all

    actiities at ottom o" W'S are well-defined

  • 7/25/2019 2. Planning Fundamentals

    17/50

    WS Procedure

    What is %ellBde"inedG

    WellBde"ined actiit! is called a 8%or# pac#age9and "eatures the "ollo%ing elements6 SOW and requirements Clear de"inition o" %or# and all sutas#s

    ime estimates or deadlines Cost estimates /esponsiilit! 4mmediate predecessors, preconditions, inputs

    Delierales /esources /is# assessment

  • 7/25/2019 2. Planning Fundamentals

    18/50

    Work Package DenitionWhile going through W'S, as# "ollo%ing questions aout each %or# pac#age6

    1. Do you need better estimates of duration and cost of the work package?

    2. Can you identify who will be responsible for work the package?3. Is the sie of work package too large to track and control?

    !. "re acti#ities within work package independent of each other?

    $. Do some acti#ities within work package ha#e different immediatepredecessors?

    %. "re risky and non-risky acti#ities combined in the same work package?&. Does the work package contain many different kinds of

    resources?

    4" ans%er is !es to an! o" questions, decompose the %or# pac#age intosmaller %or# pac#ages.

    4" ans%er is no to all o" them, the %or# pac#age proal! does not need toe sudiided.

    'he purpose here really is to decouple any elements that put together couldmean trouble(

  • 7/25/2019 2. Planning Fundamentals

    19/50

    Creating WS

    Project team

    'rainstorm

    Past e=perience

    emplates

    ;ultiple teams

    5=perts

  • 7/25/2019 2. Planning Fundamentals

    20/50

    #pproaches

    SDSys+'m Dri&es

    Pr'0e+t

    SD 1Planning System

    SD2C'ntr'l System

    SD 3Oi+e A((iti'n

    SD 141System Engineering

    SD 142Har(5are

    SD 143S't5are

    SD 241System Engineering

    SD 242S't5are

    SD 243!aterials

    SD 24341C'ntr'llers

    SD 24342Pr'+ess'rs

    SD 341Design

    SD 342$'un(ati'n

    SD 343Stru+ture

    SD 346E,teri'r

    SD 347!e+.ani+al Systems

    SD 348Interi'r Detail

    End-item Sub-systems Approach

    Start %ith E5 endBitem s!stem,sudiide it "irst into sus!stems,

    then into components, then parts

  • 7/25/2019 2. Planning Fundamentals

    21/50

    #pproaches

    5ndBitem SuBs!stems >pproach e=ample

  • 7/25/2019 2. Planning Fundamentals

    22/50

    #pproaches

    S't5are (e&el'pmentpr'0e+t

    Analysis Design C'nstru+t

    Deine userintera+e

    R'll'utTest

    De&el'p te+.ni+al(esign

    Establis. 9ualityre9uirements

    De&el'p (etaile((esign

    Deine appli+ati'nar+.ite+ture

    Deine pr'+essingl'5

    Design l'gi+alDatabase stru+ture

    Design systemintera+es

    Delierales o" PhaseTe+.ni+al Design D'+ument Appli+ati'n ar+.ite+ture Appli+ati'n l'5 Database (esign En( user intera+e (esign

    W'r)l'5 (iagramUser ('+umentati'n 'utline

    1

  • 7/25/2019 2. Planning Fundamentals

    23/50

    WS Formats

    ree Structure

    4ndented

    Structure

    SDSys+'m Dri&es

    Pr'0e+t

    SD 1Planning System

    SD2C'ntr'l System

    SD 3Oi+e A((iti'n

    SD 141System Engineering

    SD 142Har(5are

    SD 143S't5are

    SD 241System Engineering

    SD 242S't5are

    SD 243!aterials

    SD 24341C'ntr'llers

    SD 24342Pr'+ess'rs

    SD 341Design

    SD 342$'un(ati'n

    SD 343Stru+ture

    SD 346E,teri'r

    SD 347!e+.ani+alSystems

    SD 348Interi'r Detail

    SD S!stem Dries and Spaces

    SD1 Planning S!stem

    SD1.1 S!stem 5ngineering

    SD 1.1.1 Control requirements

    SD 1.1.2 Controller speci"ications

    SD 1.1.3 Controller "unctions

    SD1.2 ;aterials

    SD1.2.1 Controller deices

    SD1.2.2 Controller inter"aces

    SD2 Control S!stem

    S!stem

    Sus!stem

    Component Part

  • 7/25/2019 2. Planning Fundamentals

    24/50

    oston$s ig Dig

  • 7/25/2019 2. Planning Fundamentals

    25/50

    'igBDig %or#pac#ages ased

    on contracts

    Contracts ased ona rea#do%n o"project intoph!sical sectionsand components

    Charles River

    DowntownBoston

    LoganAirport

    BostonHarbor

    5ndBitem SuBs!stems >pproach

    Cambridge

  • 7/25/2019 2. Planning Fundamentals

    26/50

    Hse same identi"iers on all project documentsJSchedules

    J'udgets

    J/esponsiilit! matri=

    JChange requests, etc.

    SDSys+'m Dri&esPr'0e+t

    SD 1Planning System

    SD2C'ntr'l System

    SD 3Oi+e A((iti'n

    SD 141System Engineering

    SD 142Har(5are

    SD 143S't5are

    SD 241System Engineering

    SD 242S't5are

    SD 243!aterials

    SD 24341C'ntr'llers

    SD 24342Pr'+ess'rs

    SD 341Design

    SD 342$'un(ati'n

    SD 343Stru+ture

    SD 346E,teri'r

    SD 347!e+.ani+alSystems

    SD 348Interi'r Detail

    E%er& task or 'ork package hasa uni(ue identier

  • 7/25/2019 2. Planning Fundamentals

    27/50

    WS and Integrated Planningand Controlhe W'S process and %or# pac#ages proide integrated plan andcontrol6

    1. ?unctional managers, sucontractors, and others responsile "or the

    %or# are identi"ied and ecome inoled during the W'S process.

    2. Wor# pac#ages in each phase are logicall! and ph!sicall! related to

    those in earlier and later phasesA predecessor requirements are met and

    no steps oerloo#ed.

    3. Wor# pac#ages are the asis "or udgets and schedules. he project

    udget is the sum o" the udgets "or all the %or# pac#ages plus project

    oerhead and indirect e=penses. he project schedule is the composite

    o" the schedules o" all the %or# pac#ages.

    $. he project organization is "ormed around %or# pac#ages. /esources

    are assemled "or and management responsiilit! delegated to

    indiiduals in each %or# pac#age.

    *. he project is directed ! directing people %or#ing in indiidual %or#

    pac#ages.

    +. Project control is e=ercised through control o" %or# pac#ages.

    >n inte rated ro ect lan is a s stems a roach to mana ement

  • 7/25/2019 2. Planning Fundamentals

    28/50

    Project )esponsi*ilit&

    While creating W'S, the questions 8%ho is needed to do

    this9 and 8%ho %ill e responsile9 are addressed "or

    each pac#age

    >ns%ers result in responsiilit! assignments "or all areaso" project

    People responsile "or areas o" project, and details o"

    that responsiilit!, are documented and communicated in

    /esponsiilit! ;atri=

  • 7/25/2019 2. Planning Fundamentals

    29/50

    )esponsi*ilit& +atri!

    ?or each tas#, sho% %ho is responsile ?or each person, sho% #ind o" responsiilit!A e.g.

    P6 primar! or lead

    One, and onl! one, P per tas#

    S6 secondar!

    6 noti"ication required

    >6 approal required

  • 7/25/2019 2. Planning Fundamentals

    30/50

    )esponsi*ilit& +atri!

  • 7/25/2019 2. Planning Fundamentals

    31/50

    )esponsi*ilit& +atri!

  • 7/25/2019 2. Planning Fundamentals

    32/50

    )esponsi*ilit& +atri!

    5er! tas# accounted "orA nothing "alls through crac#s

    5ach responsiilit! represents mutual agreement

  • 7/25/2019 2. Planning Fundamentals

    33/50

    Scheduling asics W'S proides in"ormation necessar! to

    create a schedule

    4ncludes

  • 7/25/2019 2. Planning Fundamentals

    34/50

    ogical Se(uencing of -asks Predecessor6 > tas# that must e completed e"ore

    another can e started 4" tas# C depends upon as#s > and ',

    then as#s > and ' are 8predecessors9 "or as# C.

    A

    #

    C

    as# C is the 8successor9 o" as#s > and '

  • 7/25/2019 2. Planning Fundamentals

    35/50

    .antt Chart Simple, common scheduling tool

    5as! to create and understand

    Deeloped ! Eenr! Fantt,

    a consultant o" ?rederic# a!lor.

    From Wikipedia

    Henry Laurence Gantt, A.., !.E.&1+1B1010) %as a mechanical engineer and management consultant %ho

    is most "amous "or deeloping the Fantt chart in the 101s. hese Fantt charts %ere emplo!ed on major

    in"rastructure projects including the Eooer Damand 4nterstate high%a!s!stem and still are an important tool

    in project management.

    H.Gannt

    http://en.wikipedia.org/wiki/Hoover_Damhttp://en.wikipedia.org/wiki/Interstate_highwayhttp://en.wikipedia.org/wiki/Interstate_highwayhttp://en.wikipedia.org/wiki/Hoover_Dam
  • 7/25/2019 2. Planning Fundamentals

    36/50

    .antt Chart

    5=ample

    >ctiit! 4mmediate

    Predecessors

    ime

    > BB 1

    ' > 2

    C ' 3

    D ' 1

    5 C, D 2

    ? 5 3

  • 7/25/2019 2. Planning Fundamentals

    37/50

    .antt Chart

    ote6

    5 starts at time + ecause then

    oth C and D are completed.D is completed at time $, ut Cis not until time +. Eence, Cmust %ait until time +.

    >ctiit! 4mmediate

    Predecessors

    ime

    > BB 1' > 2

    C ' 3

    D ' 1

    5 C, D 2

    ? 5 3

    A

    #

    CD

    E

    $

    11:8631

    Time

  • 7/25/2019 2. Planning Fundamentals

    38/50

    .antt Chart >nother 5=ample

    >ctiit! 4mmediate

    Predecessors

    ime

    > BB 1

    ' BB 3C > 2

    D >

    5 ', C, D 2

    ? ', C, D 3F 5 +

    E ? 1

    >ctiit! 4mmediate ime

  • 7/25/2019 2. Planning Fundamentals

    39/50

    .antt ChartPredecessors

    > BB 1

    ' BB 3

    C > 2

    D >

    5 ', C, D 2

    ? ', C, D 3

    F 5 +

    E ? 1

    A#

    C

    D

    E

    $

    H

    G

    1812111;:31

    Time

    Tas)s

  • 7/25/2019 2. Planning Fundamentals

    40/50

  • 7/25/2019 2. Planning Fundamentals

    41/50

  • 7/25/2019 2. Planning Fundamentals

    42/50

    e%el of Detail

  • 7/25/2019 2. Planning Fundamentals

    43/50

    e%el of Detail

  • 7/25/2019 2. Planning Fundamentals

    44/50

  • 7/25/2019 2. Planning Fundamentals

    45/50

  • 7/25/2019 2. Planning Fundamentals

    46/50

    .antt Chart/ Pro and Con

    With simple Fantt charts, such questions are notal%a!s eas! to ans%er.

    Ket !ou need the ans%ers to plan the project and

    create realistic schedules Fantt charts are good "or displa!ing schedules,

    et%or#s, descried in the ne=t chapter, are etter "or

    creating them

  • 7/25/2019 2. Planning Fundamentals

    47/50

    Procurement +anagement

    Procurement management

    he planning, udgeting, scheduling, and control o"procured"oods, work, or ser#ices $GWS%.

    Hsuall!, goods are ra% materials or produced items,%or# is contracted laor, and serices is consulting

  • 7/25/2019 2. Planning Fundamentals

    48/50

    Procurement +anagement4ncludes

    Equipment, materials, or componentsdesigned and proided !endors speci"icall! "or the project. Could e6

    portions o" %or# pac#ages or entire %or# pac#ages &e.g., design %or#,enironmental impact stud!, soil anal!sis)

    major portions o" the project %holl! &8turn#e!96 sucontractors "ull!design, uild, and install equipment or components "or the project endB

    item). Off-the-shelf (OTS) equipment and componentssupplied ! endors.

    &Products readil! aailale and not speci"icall! produced "or the project.)

    Bulk materials&cement, metal tuing or "raming, %ire, stone, piping, etc.)

    Consumales&nails, olts, riets, "uel) or loose tools used "or construction

    or "arication Equipment not alread! o"ned! the contractorA e.g., includes cranes,

    supports, sca""olding, and equipment "or machineBshops, %elding, andtesting.

    #dministrati$e equipment not alread! o"ned! contractorA e.g.,computers, project o""ice "acilities and o""ice equipment.

  • 7/25/2019 2. Planning Fundamentals

    49/50

    Procurement +anagement4ndenti"!ing FWS items to e procured 4noles decision aout %hich items are to e

    designed(uilt( proided inBhouse and %hich to eprocured &purchased or acquired)

    Eappens during the W'S process or design process

    %hen the needed materials and resources are "irstidenti"ied.

  • 7/25/2019 2. Planning Fundamentals

    50/50

    Procurement +anagement4noles

    Contracting%ith suppliers or sucontractors, o"tenthrough the "ormal /?P(proposal process.

    %ntegrating procured &'S itemsinto the project li"e

    c!cle and project plan &i.e., schedule, responsiilit!

    matri=, udget, qualit!, and ris#, etc.) ogistics

    ransport and storage o" materials "or the project.

    loading, unloading, transportation, inspection,

    clearances and approals, and storage o" materials cane major issues.

    Procured materials must arrie %hen needed according to

    project schedules.