Smart Metering Portfolio DCC Day 1
Project Smart Metering Portfolio Focus GroupProject Update
Thursday 06th June 2013
2
Agenda
• Action Review
• Implications of the delay to Mass smart meter roll-out
• Xoserve Overview
• Shippers Overview
• Overview of Solution Options
• Shipper Design to meet UNC Modification 0430 Requirements
• Project Smart Metering Portfolio Focus Group to discuss & advise UKLC on the implementation date of UNC Mod 0430
• Agree how UKL Comm members should be engaged through the Project Smart Metering
Portfolio Focus Group
• Overview of next steps on Shipper Design & agree engagement at SPAA & UK Link
• iGT Update
3
Action Review
• Workshop actions:
Workshop actions
4
Background & Purpose
• On the 10th May 13 DECC announced the delay of mass smart meter roll-out by one year.
• Industry Trials are to commence April 2015 (assumption) and mass smart meter rollout to
start Autumn 2015.
• Information gained from DECC indicated that the delay is to ensure that the successful
DSP/CSP bidder and the Suppliers have sufficient time to prepare their systems and
processes.
• To date we have been working towards dates of April 2014 for Industry Trials and October
2014 for the start of mass smart meter rollout.
• Agreed that Shipper Design will be progressed in advance of the DCA delivery to keep
momentum gained in the project so far.
5
Background & Purpose
• What does this change mean for our current Smart Metering Portfolio?
• Foundation delivery is not impacted but becomes more important
• DCC Day 1 is impacted
• Develop and agree approach with stakeholders via the Project Smart Metering
Portfolio Focus group for the preferred approach
6
Stakeholder Responses
• Xoserve have considered the options internally.
• Xoserve have discussed the way forward with a number of members of Project
Smart Metering Portfolio Focus group.
• Consensus seems to be that development should proceed to the current plan.
• The actual date for deployment will be dictated by the outcome of the Detailed
Cost Assessment.
7
Xoserve View
1. Phased delivery approach for MOD430 and iGT MOD047 as per current
plans. Delivery of DSP gateway functionality in line with the availability of
detailed requirements once the successful bidder has been selected by
DECC.
8
Next Steps
• Seek Project Smart Metering Portfolio Focus Group Stakeholder support for our approach
• Review the plan with internal & external Stakeholders
• Delivery of DCA to GT’s
• Plan project delivery and engagement with respective parties (eg UKLC & SPAA)
9
Solution Options Overview
• See Attached File
Adobe Acrobat Document
10
Solution Options Overview - Impacted File Types – 1
Outgoing Existing File
Change Summary DCC Day 1 Data Items
NMRAdd new data items to the new record type under RT_S64_Offer_Details -> RT_S75_Meter_Point
13. SMS Operating Entity ID
14. SMS Operating Entity EFD
15 .DCC Service Flag
16. DCC Service Flag EFD
17. IHD Install Status
18. First SMETS Installation Date (derived)
19. UPRN
CFR(Confirmation Acceptance)
Add new data items to the new record type under RT_S07_Accepted_Confirmation -> RT_S75_Meter_Point
CFR(Withdrawal Notification)
Add new items to the new record type under RT_S10_SP_Withdrawal_Notice -> RT_S77_Withdrawal_Meter_Point
TRF(Transfer of Ownership)
Add new data items to the new record type under RT_S15_Transfer_of_Ownership -> RT_S75_Meter_Point
TRF(Ceased Responsibility
Notification)
Add data items to the new record type under RT_S88_Ceased_Responsability_Notice -> RT_K13_MPO_CEASE_OWN_DETS
MRI Add data items to the new record type under RT_U06_Meter_Read_Instructions
PAC Add data items to the new record type under RT_U06_Meter_Read_Instructions
11
Solution Options Overview - Impacted File Types – 2
Incoming Existing File
Change SummaryDCC Day 1 Data
Items
ONJOB
IHD Install Status to DATASET_GROUP_MTPNT
Unique Property Reference Number within DATASET_GROUP_ADDRS to capture UPRN
17. IHD Install Status
19. UPRN
ONUPD IHD Install Status to DATASET_GROUP_MTPNT
GEAMAM change process
SUN process including Supplier EFD
SUN (Supplier Update
Notification)Existing SUN file will be decommissioned
12
Shipper Design to meet UNC MOD 0430 Requirements
• Agree how UKL Comm members should be engaged through Project Smart Metering Portfolio Focus Group
• Project Smart Metering Portfolio Focus Group to discuss & advise on the implementation date of UNC MOD 0430
• Overview of next steps on Shipper Design & agree engagement at SPAA & UK Link groups
13
iGT’s Update
• Business Requirements Document Update
• Update funding discussions
• Communications method updates
• Agree any next steps/decisions to make