Introduction to Introduction to Value AnalysisValue Analysis
Caltrans Delivers Value
By Renee Hoekstra, CVS
RH & Associates, Inc.
for
Caltrans
22
Today’s ObjectiveToday’s Objective
What is Value Analysis (VA) all about?
Why Caltrans Uses VA?
Caltrans VA Policy
How to Effectively Apply VA
33
What is Value Analysis?What is Value Analysis?
Value Analysis (or Value Engineering) is a function-oriented, structured,
independent multi-disciplinary team approach to identify improvements
in a project, product or service.
44
Typical Caltrans VA Job PlanTypical Caltrans VA Job Plan
• Pre-Study
• Information*
• Function Analysis*
• Speculation*
• Evaluation*
• Development*
• Presentation*
• Implementation
* Also referred to as “Workshop”
8 Step Process:
55
What is This VA Stuff Any How?”What is This VA Stuff Any How?”
• It’s About Improving a Project, Process or Item of Work
• It’s Not Just About “Cutting Costs” or “Taking Away”
• It’s Not About a Poor Design
IT’S ABOUT ADDING VALUE!!
66
• Stakeholder Satisfaction– Building consensus among project stakeholders – Better understanding of a project’s goals and objectives– Developing a better understanding of an alternative concept’s
affect on project performance– Developing a deeper understanding of the relationship
between performance and cost in determining value– Using value as the basis for selecting the best project, design
concept or approach
How Do We Define Value?How Do We Define Value?
77
• Performance Improvements– Schedule and Delivery– Environmental impacts– R/W impacts – Constructability – Maintainability– Traffic Control– Others?
How Do We Define Value?How Do We Define Value?
88
Why Caltrans Uses VA?Why Caltrans Uses VA?
• Meeting Caltrans’ Goals
• Providing Better Projects to our Clients, the Traveling Public
• Being Fiscally Responsible
99
Why Caltrans Uses VA?Why Caltrans Uses VA?
It Makes Good Business Sense!• Use it to streamline the decision-making process• To resolve issues with project stakeholders• To find Innovative solutions to complex project issues• Typical savings is greater than 5%• Typical Return on Investment is over 100:1
1010
Why Caltrans Uses VA?Why Caltrans Uses VA?
1111
2009 VA Results2009 VA Results• 2009 reported results: 48 VA Studies
Saved $171 Million Dollars
• 5% project savings
• ROI in 2009: 79:1
• Implementation Rate in 2009: 68%
1212
Caltrans VA PolicyCaltrans VA Policy
Satisfying Requirements
Responsibilities
Caltrans Role
1313
Caltrans VA PolicyCaltrans VA Policy
• DD-92 Value Analysis Policy– All projects on the Federal-aid system (Interstate and the
National Highway System) with a total project cost (right of way, construction and support) of $25 million or more.
– All bridge projects totaling $20 million or more.
– Although the VA study is most effective in the early stages of project development, a VA study can be conducted at any phase of the project prior to the start of construction.
– Requirements apply regardless of the funding source, or whether the Department’s employees, local agencies, consultants, or others are accomplishing the work.
1414
VA Study ResponsibilitiesVA Study Responsibilities
Who pays for the VA Study?
Project Sponsors secure funding for projects and serve as project advocates.
– Team Leader cost– Team Member cost– Study cost (facility, equipment, paper, etc…)
1515
VA Study ResponsibilitiesVA Study ResponsibilitiesWho is responsible for performing the VA Study?
The Implementing Agency is the entity charged with the successful completion of each project component:
– Project Initiation Document– Completion of all permits and environmental studies.– Preparation of plans, specifications, and estimates.– The acquisition of right-of-ways, including, but not limited to, support activities. – Construction, construction management, and engineering; including surveys and
inspection.
- Caltrans DD-90 and 23
1616
Caltrans Involvement in VA StudyCaltrans Involvement in VA Study
Three Basic Levels of Involvement:
1. Hire Caltrans as the Implementing Agency to design the project and perform the VA Study.
2. Team Member Participation
3. Oversight Responsibility
1717
Caltrans Involvement in VA StudyCaltrans Involvement in VA Study
Team Member Participation vs Oversight
Team members are actively involved in the workshop as SME’s to create and develop viable alternatives to the baseline design.
This work would be considered as “reimbursable” work. Typical workshops are 40 hours, and Caltrans typical VA studies resource about 500 hours of staff time.
1818
Caltrans Involvement in VA StudyCaltrans Involvement in VA Study
Team Member Participation vs Oversight
Stakeholder and Decision Making Participation includes attending Pre and Post meetings (Kick-off and presentation phases), perform technical reviews on alternatives, review for federal compliance, and make recommendations for acceptance or rejection of alternatives.
This participation would be considered as a project’s Independent Quality Assurance (IQA) at no cost to the project.
1919
Satisfying Caltrans Satisfying Caltrans RequirementsRequirements
• Use Caltrans VA Process and Techniques• Establish Proper Timeframe for Study• Provide Sufficient Time to Perform the VA
Study• Use Independent Team and Team Leader
(CVS)
2020
Satisfying Caltrans Satisfying Caltrans RequirementsRequirements
• Involve Caltrans - HQ Reviewers in Technical Review
• Act on VA Alternatives– Implementation Meeting –Caltrans and Key
Stakeholders– Determine Disposition of Each Alternative– Follow Up when Final Decisions are Made
• Properly Document Results – VA Report Guide – Preliminary Reports – Final Reports (include Caltrans HQ VA Program)
2121
How to Effectively Apply VAHow to Effectively Apply VA
Study TimingStudy Length
Team MembersTeam Leaders
2222
VA Study Timing VA Study Timing Cost Savings / StudyCost Savings / Study
“The Earlier The Better”
All Following Charts Source: 286 Completed Caltrans Studies 2002-2009
2323
VA Study Timing VA Study Timing Return on Investments / StudyReturn on Investments / Study
2424
Typical Caltrans VA Job PlanTypical Caltrans VA Job Plan
• Pre-Study
• Information*
• Function Analysis*
• Speculation*
• Evaluation*
• Development*
• Presentation*
• Implementation
* Typical study is 6 days (40 hrs) divided into two weeks
8 Step Process:
2525
The Length of the WorkshopThe Length of the Workshop
• 6 DAYS, WHY DO WE NEED 6 DAYS!!– Scheduling adequate time to meet each of the steps
is critical– Allowing team members time to do their other job is
even more critical– Commitment by team members to stay engaged is
key to the study’s success– Each study is unique (maybe 5 days are enough)
2626
VA Study LengthVA Study Length
• 6 Day Caltrans Standard (40 hr workshop)– Ideally – two 3-day sessions– 5 Day acceptable for many smaller projects
• Exemption Process For Number of Days– See PDPM Chapter 19 for Process– Requests are being Denied by HQ
• 2 Days or Less are not acceptable– 3-4 days for minor improvements within
R/W
2727
Typical Study DurationTypical Study Duration
• Preparation 2-4 weeks• VA Study Segment 1 3 days• VA Study Segment 2 3 days• Implementation
– Prepare Draft Report 2 weeks– Review Report 2-6
weeks– Resolve Disposition 1 day
• Report – Prepare Final Report 3 weeks– Close out open items 3 months
2828
Typically 7-9 Cross Functional, Experienced Typically 7-9 Cross Functional, Experienced Team MembersTeam Members
• Design
• Construction
• Environmental
• Landscape
• Traffic Ops
• Maintenance
• Planning
• Right of Way
• Structures
It’s All About the Team!
Quality Team = Quality Results
2929
It’s All About the TeamIt’s All About the Team• Commitment of team members to
participate and engage is essential• Multi-disciplines are important to creativity• Removing personal and institutional
barriers aides in the creativity and evaluation process
3030
It’s All About the TeamIt’s All About the Team• Team Leaders should be trained in the
Value Engineering process and not meeting facilitation– Recommend Certified Value Specialist
(CVS) from Society of American Value Engineers (SAVE) International
3131
Caltrans VA Website: www.dot.ca.gov/hq/oppd/value/index.htm
FHWA VE Website: http://www.fhwa.dot.gov/ve/index.cfm
SAVE International Website: http://www.value-eng.org
Additional InformationAdditional Information
3232
Troy Tusup, HQ VA Program Manager
Richel Espinoza-Noss, HQ VA Program Administrator
Naghi Ghafari, North Region
Hamid Khorram & Binh Dang, District 4
Habib Sabzehzar, Central Region
Jamal El-Jamal & Duke Nguyen, District 7
Anthony Robinson & Jason Ahlswede, District 8
Chili Cilch, District 11
Christopher Le, District 12
Caltrans VA ChampionsCaltrans VA Champions
3333