1
J&KCivil(WA)PtyLtd
Unit 1, 9 Brig Way
Bullsbrook 6084
Western Australia
Of�icePhone:(08) 9571 1881
Email:[email protected]
Website:www.jkcivilwa.com.au
2
OVERVIEW
J&K Civil (WA) Pty Ltd
Established in 2007, J&K Civil (JKC) is a Western Aus-
tralian owned and operated contrac"ng company
specialising in providing high quality civil construc"on
services to the WA Infrastructure, Mining and Re-
sources sectors.
Our willingness to provide innova"ve solu"ons, help
create cost and "me savings for our clients coupled
with a proven site management team,
experienced work force and reliable fleet of plant, JKC
are capable of undertaking your small to medium
sized projects with bulk earthworks, detailed earth-
works, roading, rail, drainage, piping and tailings dam
components.
At J&K Civil we pride ourselves on producing high
quality work, with a2en"on to detail, in a safe and
produc"ve environment.
With over 20 years experience in the construc-
"on and mining sector, Owner and Opera"ng
Director Jason Dow has taken his small con-
trac"ng business and developed it into a suc-
cessful company. Jason has experience super-
vising and managing a diverse range of civil pro-
jects in the Pilbara for BHP Billiton Iron Ore, For-
tescue Metals Group and Rio Tinto Iron Ore.
Key Management
Kim Gilchrist Director / Admin As a Director Kim specialises in contract admin-
istra"on and manages the Companies human
resources, procurement, accounts and payroll.
Steve Watkins Opera"ons Manager
Steve has over 12 years experience in civil con-
struc"on and project management. Prior to
joining J&K Civil Steve worked for designers
Opus Consultants and civil contractors NRW and
Viento Group.
Jason Dow Director / Superintendent
Alvin Lai Project Manager (BE Hons.)
With experience in both construc"on and as
designer/client in the Pilbara Alvin brings enthu-
siasm, technical exper"se and a drive to suc-
cessfully deliver any project he is involved with.
3
CONSTRUCTION SERVICES
J&K Civil specialise in providing civil construc"on services
to the mining and resources sector in the northwest of
Western Australia.
With a wealth of experience working on mining and min-
ing related projects, J&K Civil is commi2ed to deliver our
clients' projects on "me and within budget.
J&K Civil has a team of high quality experienced personnel
available to operate our fleet of mine specific equipment
on your project.
Our construc"on services include:
- Tailings Dam Earthworks and Piping
- Rail Embankment Construc"on
- Drainage, Culvert and Arch Construc"on.
- Road Pavements
- Road Sealing Works
- Signage and Pavement Markings.
- Pothole Repairs.
- Detailed Earthworks
- Camp Construc"on (Earthworks, Trenching, Electrical Pit
and Demountable Building Installa"ons).
- Fencing
J&K Civil owns and operates over 80 items of plant and
equipment.
J&K Civil have a commitment to provide an excellent
service and strive to minimise down"me by regularly
servicing and maintaining their plant and equipment.
With depots in both Tom Price and Karratha Industrial
Areas J&K Civil are well placed to service civil works
across the Pilbara.
- GPS Graders
- Smooth Drum Rollers
- Mul"-tyre Rollers
- Bobcats
- Plate Compactors
- Road/Street Sweepers
- Line Marking Machinery
- Poly Welders
- Loaders
- Excavators
- Water carts
- Padfoot Rollers
- Side and End Tippers
- Detailed Earthworks
Equipment
- Graders
- Screening Plant
4
PROJECTS
Tom Price Tailings Storage
Facility Project May 2017 - January 2018
Removal and disposal of exis"ng pipe and infrastruc-
ture, installa"on of temporary pipework's, to enable
con"nued deposi"on whilst 205,000m3 of bulk and
detailed earthworks for several embankment raises
is completed. Supply and Installa"on of 4km of new
deposi"on HDPE and 108no. Polyurethane lined
steel pipe work with valving. Pressure tes"ng and
commissioning of the new pipework. All completed
Design and Construc"on
Mesa A Evapora"on Ponds
January 2017 - July 2017
Early works consisted of the detailed design, site ge-
otechnical and services inves"ga"on and repor"ng
followed by a joint Client/Contractor design and
safety review. The twin evapora"on ponds construc-
"on included cut to fill earthworks, trench and sur-
face prepara"on, geotex"le and HDPE liner installa-
"on followed by security fencing of the site.
A new concrete drying slab was constructed along
with new pipework and valves for the inflow to the
ponds.
Tom Price Stormwater Re-
newal Project Nov 2017 - May 2018
Supply and installa"on of 1,300m of new RRJRC pipe
and 80no. concrete pits at various loca"ons through-
out the town of Tom Price as part of the Shire of Ash-
burton’s drainage renewals programme. Works in-
cluded public no"fica"on/liaison, service loca"ng
and protec"on, removal and disposal of the exis"ng
redundant infrastructure, installa"on of new storm-
water infrastructure and reinstatement of sealed
roads, concrete kerbing and residen"al verges.
5
PROJECTS
Marandoo Waste Fines
Storage Facility Stage 2 & 3 December 2014 - February 2016
Bulk and detailed earthworks consis"ng of downstream
embankment liGs of a tailings dam, modifica"ons, exten-
sions, dismantling and reinsta"ng of underdrainage
equipment, waste fines and decant pipework.
Approximately 1.5 million cubes of material shiGed in
total.
Rail Capacity Enhancement
Project - Cape Lambert
September 2013 - March 2015
Earthworks for new and exis"ng level crossings and
rail maintenance tracks including the supply installa-
"on of road furniture, sealing works and line mark-
ing. Supply and installa"on of passive level crossing
gates and rail forma"on works.
70 Gate installa"ons; 30 level crossings; 350,000
square metres of 2-coat seal.
Autohaul Earthworks May 2012 - April 2014
Detailed earthworks at 40+ sites alongside RTIO’s ac-
"ve rail network for future autonomous train infra-
structure including signal pads, radio base pads and
level crossings. Works required access to Brockman,
Marandoo, Hope Downs and Tom Price mine sites
and included conduit installa"on, seal prepara"on,
sealing works and line marking ac"vi"es.
Detailed earthworks at Bellbird and Rosella sidings in
prepara"on for autonomous signally installa"on in-
cluding installa"on of train driver change out pads
and rail ballast supply.