responsibility based on these electronic files or for any defective or incomplete copying, exerpting, scanning, faxing or downloading of the contract documents. As always, for the official paper versions of the bidders packages and non-bidder packages, including addenda write to the California Department of Transportation, Plans and Bid Documents, Room 0200, P.O. Box 942874, Sacramento, CA 94272-0001, telephone (916) 654-4490 or fax (916) 654-7028. Office hours are 7:30 a.m. to 4:15 p.m. When ordering bidder or non-bidder packages it is important that you include a telephone number and fax number, P.O. Box and street address so that you can receive addenda.
etric
Caltrans
STATE OF CALIFORNIA
DEPARTMENT OF TRANSPORTATION __________________________________________________________
NOTICE TO CONTRACTORS AND
SPECIAL PROVISIONS FOR CONSTRUCTION ON STATE HIGHWAY IN
IMPERIAL COUNTY AT ANDRADE
FROM MEXICO BORDER TO 0.6 KM NORTH OF MEXICO BORDER
DISTRICT 11, ROUTE 186
__________________________________________________________
For Use in Connection with Standard Specifications Dated JULY 1999, Standard Plans Dated JULY 2004 and Labor Surcharge and Equipment Rental Rates.
__________________________________________________________
CONTRACT NO. 11-267504
11-Imp-186-0.0/0.6
Federal Aid Project
HPD-P186(003)E
Bids Open: August 2, 2007 Dated: July 2, 2007
*************************************************************************************************
IMPORTANT SPECIAL NOTICES
*************************************************************************************************
Attention is directed to Section 3, "Award and Execution of Contract," of these special provisions regarding submittal of the documents identified in Section 3-1.025, "Insurance Policies," of the Standard Specifications.
Contract No. 11-267504 i
TABLE OF CONTENTS
NOTICE TO CONTRACTORS ...........................................................................................................................................1 COPY OF ENGINEER'S ESTIMATE .................................................................................................................................4 SPECIAL PROVISIONS......................................................................................................................................................6 SECTION 1. SPECIFICATIONS AND PLANS.................................................................................................................6 AMENDMENTS TO JULY 1999 STANDARD SPECIFICATIONS .................................................................................6 SECTION 2. PROPOSAL REQUIREMENTS AND CONDITIONS.............................................................................106
2-1.01 GENERAL ....................................................................................................................................................106 2-1.015 FEDERAL LOBBYING RESTRICTIONS ................................................................................................107 2-1.02 DISADVANTAGED BUSINESS ENTERPRISE (DBE).............................................................................107 2-1.03 TRIBAL EMPLOYMENT RIGHTS ORDINANCE (TERO) ......................................................................108
SECTION 3. AWARD AND EXECUTION OF CONTRACT.......................................................................................109 SECTION 4. BEGINNING OF WORK, TIME OF COMPLETION AND LIQUIDATED DAMAGES ......................109 SECTION 5. GENERAL.................................................................................................................................................109 SECTION 5-1. MISCELLANEOUS...............................................................................................................................109
5-1.01 PLANS AND WORKING DRAWINGS......................................................................................................109 5-1.013 LINES AND GRADES ...............................................................................................................................109 5-1.017 CONTRACT BONDS.................................................................................................................................110 5-1.018 GUARANTEE ............................................................................................................................................110 5-1.019 COST REDUCTION INCENTIVE.............................................................................................................111 5-1.02 LABOR NONDISCRIMINATION...............................................................................................................111 5-1.022 EXCLUSION OF RETENTION.................................................................................................................111 5-1.023 UNSATISFACTORY PROGRESS ............................................................................................................111 5-1.03 INTEREST ON PAYMENTS.......................................................................................................................111 5-1.04 PUBLIC SAFETY.........................................................................................................................................112 5-1.05 TESTING ......................................................................................................................................................113 5-1.06 REMOVAL OF ASBESTOS AND HAZARDOUS SUBSTANCES...........................................................113 5-1.065 SOLID WASTE DISPOSAL AND RECYCLING REPORT.....................................................................113 5-1.07 (BLANK) ......................................................................................................................................................114 5-1.075 BUY AMERICA REQUIREMENTS .........................................................................................................114 5-1.08 SUBCONTRACTOR AND DBE RECORDS ..............................................................................................114 5-1.083 DBE CERTIFICATION STATUS..............................................................................................................114 5-1.086 PERFORMANCE OF SUBCONTRACTORS............................................................................................114 5-1.09 SUBCONTRACTING...................................................................................................................................115 5-1.10 PROMPT PROGRESS PAYMENT TO SUBCONTRACTORS..................................................................115 5-1.103 RECORDS ..................................................................................................................................................115 5-1.104 INTERNET DAILY EXTRA WORK REPORT ........................................................................................115 5-1.105 ARCHAEOLOGICAL DISCOVERIES .....................................................................................................116 5-1.11 COMPENSATION ADJUSTMENTS FOR PRICE INDEX FLUCTUATIONS .........................................117 5-1.12 AREAS FOR CONTRACTOR'S USE..........................................................................................................118 5-1.13 PAYMENTS .................................................................................................................................................118 5-1.14 PROJECT INFORMATION .........................................................................................................................118 5-1.15 RELATIONS WITH CALIFORNIA REGIONAL WATER QUALITY CONTROL BOARD...................118
WITHHOLDS ....................................................................................................................................................119 5-1.16 ENVIRONMENTALLY SENSITIVE AREA ..............................................................................................119 5-1.17 PRESERVATION OF PROPERTY..............................................................................................................119
SECTION 6. (BLANK) ...................................................................................................................................................120 SECTION 7. (BLANK) ...................................................................................................................................................120 SECTION 8. MATERIALS.............................................................................................................................................120 SECTION 8-1. MISCELLANEOUS...............................................................................................................................120
8-1.01 SUBSTITUTION OF NON-METRIC MATERIALS AND PRODUCTS ...................................................120 8-1.02 PREQUALIFIED AND TESTED SIGNING AND DELINEATION MATERIALS...................................127 8-1.03 STATE-FURNISHED MATERIALS ...........................................................................................................132 8-1.04 SLAG AGGREGATE ............................................................................................