Greek gods and goddesses. Zeus Zeus is the king of the gods.
Zeus: home of the heavies
-
Upload
objective-capital-conferences -
Category
Economy & Finance
-
view
1.196 -
download
0
description
Transcript of Zeus: home of the heavies
RARE EARTHS, SPECIALITY& STRATEGIC METALSINVESTMENT SUMMIT
IRONMONGERS’ HALL, CITY OF LONDON ● TUESDAY-WEDNESDAY 13-14 MARCH 2012
www.ObjectiveCapitalConferences.com
Zeus: home of the heaviesCaroline Wilson – Director Business Relations, Matamec
The Kipawa HREE-Y-Zr Deposit
March, 2012
This document contains “forward-looking information” including without limitation statements relating to mineral reserve estimates, mineral resource estimates, realization or mineral reserve and resource estimates, capital and operating costs estimates, the timing and amount of future production, costs of production, success of mining operations, the ranking of the project in terms of cash cost and production, permitting, economic return estimates, potential upsides, and the future price and supply and demand for rare earths. Readers should not place undue reliance on forward-looking statements.
Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Corporation to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. The preliminary economic assessment study results are estimates only, are preliminary in nature and are based on a number of assumptions, any of which, if incorrect could materially change the projected outcome. Until a positive feasibility study has been completed, and even with the completion of a positive feasibility study, there are no assurances that Kipawa will be placed into production. Factors that could affect the outcome include, among others: the actual results of development activities; project delays; inability to raise the funds necessary to complete development; general business, economic, competitive, political and social uncertainties; future prices; alternative rare earth sources or substitutes; actual rare earth recovery; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; accidents, labour disputes and other risks of the mining industry, political instability, terrorism, insurrection or war; delays in obtaining governmental approvals, necessary permitting or in the completion or development or construction activities.
Although the corporation has attempted to identify important factors that could cause actual actions, events or results to differ materially for those described in forward-looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward-looking statements contained herein are made as of the date of this presentation and the Corporation disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws.
NI 43-101 ComplianceThe technical information pertaining to the Kipawa HREE Project in this presentation is based on the news release entitled “ Matamec PEA Study Shows Robust Economics for the Kipawa HREE Project” published on January 30th, 2012 that describes the results of the Kipawa HREE Project Preliminary Economic Assessment (“PEA”) study and was prepared in accordance with Canadian regulatory requirements by, or under the supervision of Guy Saucier, ing. of Roche Ltd.
3
Cautionary Statement Concerning Forward-Looking Statements
4
Market Summary (TSXV:MAT)
Shareholder Base Research Coverage
Institutional ownership 30% Byron Capital Markets Dr. Jon Hykawy
Insider ownership 2% Cormark Securities Edward Otto
Pinetree Capital, Mineralfields ~20% Jacob Securities Luisa Moreno
Source: Capital IQ, Bloomberg and company.Data as of March 5, 2012.
COMPANY STATISTICSCurrent share price $0.3152 week range $0.20 to $0.70Basic shares 120 millionFully diluted shares 138 millionMarket capitalization $37 millionEntreprise value $33 millionCash & cash equivalents $4 million
CAPITAL STRUCTUREIssue and outstanding 120 millionWarrants 11 million
Weighted average exercise price $0.41Options 7 million
Weighted average exercise price $0.221 Weighted average exercise price 0.0
1.0
2.0
3.0
4.0
5.0
6.0
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
3/3/2011 4/3/2011 5/3/2011 6/3/2011 7/3/2011 8/3/2011 9/3/2011 10/3/2011 11/3/2011 12/3/2011 1/3/2012 2/3/2012 3/3/2012
Vol
ume
(MM
)
Pric
e ($
CA
D p
er s
hare
)
Properties: Main Focus - Kipawa Deposit
5
• Located in the Témiscamingue region of Quebec, some 160 km south of Rouyn-Noranda and 50 km east of the town of Témiscaming
• Accessed by a nearby network of logging roads, railway, electric grid and airport• Use of Hydro-Quebec’s power grid at the mine site instead of diesel power• High capacity of rail freight service by CN-CP-OVR-ON
REE: 5 Critical Elements for 4 Clean Energy TechnologiesLa Ce Pr Nd Sm Eu Gd Tb Dy Ho Er Tm Yb Lu Y
6
HV electric motor & generator・ Neodymium ・ Praseodymium ・ Terbium・ Dysprosium
Source: U.S. Department of Energy, “Critical Materials Strategy”, Dec. 2011.
Rare Earths are Not Commodities!
The Needs of the End User must be Met
•They are customer-specific chemicals, produced to precise chemical and physical specifications.
•The customer needs are continually evolving.
•It requires the suppliers to become an integral link in the supply chain. Source: Dudley Kingsnorth (IMCOA), March 2010.
7
8
Developing a Rare Earth Project
Must develop 3 aspects simultaneously:
•Drill off a NI43-101 resource
•Define mineralogy and extraction process
•Find an end user
9
Company Overview• Focused on developing the Kipawa deposit, 100% owned
property located in Quebec - One of the top 5 HREE assets outside of China
• Signed an MoU with a high profile end-user, Toyota Tsusho Corp. (“TTC”), as a strategic partner
– TTC will provide an off-take agreement for 100% of production at market prices and CAPEX financing
• Experienced management team and directors• Fast tracking to production
– Mining lease application and environmental permitting to be filed by Q1 2012
– Hydrometallurgical pilot plants to be completed by Q2 2012
– Feasibility study by Q1 2013
– Environment and permitting by Q2 2014
– First production as early as Q2 2016 (Able to accelerate production by mid 2015 with help of TTC)
Strong project economics Before tax NPV8% of $606 million (36.9% IRR)
Robust production profile
Average annual production of 5,072 tonnes of mixed TREO concentrate with at least 200 tonnes of dysprosium
Low projected cash costs $16.97/kg mixed TREO concentrate
Simple metallurgy
Straightforward mineralogy, ideal deposit geometry, simple processing flow-sheet, most infrastructure in place
Upside potential
Significant upside potential from several by-products and deposit expansion drilling
10
Sudbury
MontréalOttawa
Val d’Or
Témiscaming
Rouyn-Noranda
Kipawa HREE Project: Location and Infrastructure
Kipawa Deposit
11
Mining services are found in Sudbury, Rouyn-Noranda and Val d’Or
North Bay
Mining – open pit, low strip ratio, small op
Mineral Resource
Deposit Open Laterally and at Depth
SW NE
Eudialyte Zone
TREO Enriched Zones
Zi
rcon
ium
Zon
e
Schematic Cross-Section with TREO enriched envelopes
12
2011 discovery
• Indicated resources represent 79.8% of the total resource• Mineral concentrate grade of 1.11% TREO; overall REE recovery of 81%• Heavy rare earth oxides and yttrium combine for an average of 36% TREOs totaling 22,940 tonnes of indicated and 6,300
tonnes of inferred HREO + Y2O3
Cut-off Grade Category TonnageGrade (%) Tonnes
ZrO2
Y2O
3 HREO1 TREO2 (H+Y)3/TREO HREO Dy
2O
3Y
2O
3Tb
2O
3Eu
2O
3Nd
2O
3
0.2% TREOIndicated 17,645,000 0.909 0.097 0.060 0.435 36% 1,58,700 2,823 17,116 423 300 10,234
Inferred 6,805,000 0.866 0.080 0.051 0.371 35% 347,055 885 5,444 136 95 3,403
0.3% TREOIndicated 12,472,000 0.913 0.114 0.070 0.512 36% 873,040 2,245 14,218 349 249 8,481
Inferred 3,842,000 0.912 0.101 0.063 0.463 35% 242,046 653 3,880 100 69 2,420
1 Sum of all heavy rare earths in oxides (terbium to lutetium)2 Sum of all rare earths in oxides plus yttrium in oxide; TREO = LREO + HREO + Y
2O
33 HREO plus Y
2O
3
In-Pit Mineral Resources* Tonnes Grade (%)
Indicated (79.8% of the deposit) 15,161,000 0.434
Inferred (20.2% of the deposit) 3,843,000 0.403
Total 19,004,000 0.428
Resource Update
Open pit design at Kipawa HREE Project mine site
13
Kipawa Deposit: Simple Mineralogy
14
-Main bearing-REE mineral is Eudialyte, contains 70% of TREO of the deposit
-Simple mineralogy: medium grained, well-crystallized and not intergrown- can eliminate 65% of ore through magnetic concentration with 90% recoveries= less ore to heat and leach = less cost
15
Low Cost Ore Processing with Simple Mineralogy3 steps for low-cost chemical extraction for a competitive edge vs. current producers
90 % of TREO in 35% of Original Mass Recovered in
Step 1
88% of TREORecovered in Step 2
Up to Purification / Precipitation
79% of TREO Recovered inSteps 1& 2 to the liquor
stage
Step 3
Rare Earth Separation
Individual REE Oxide
Mixed TREO Concentrate
Step 1
Crushing
Grinding
Physical Concentration
Mineral Concentrate
Ore from Open Pit (0.42%)
Step 2
Regrind
Leaching
Solid/Liquid Separation
Liquor
Heat: Room temp.Acid: 150 kg/tTime: 2 hours
+ Water
Solid Tailings Stabilization
Purification/Precipitation
Mineral Concentrate (1.11%)
Mixed TREO Concentrate
16
17
OPEXOPEX Items Annual
Cost(Million $/y)
Cost Per kg of Mixed TREO concentrate
($/kg)General & Administration
8.841 1.682
Mining(including Mine Manpower)
16.619 3.161
Total Process 58.350 11.099Tailings 0.240 0.046Transportation 5.160 0.982
Total 89.210 16.970
CAPEX Items Initial Cost (million CAD)
Kipawa site 100.778
Temiscaming site 85.999
Other Infrastructure 10.730
Total Direct Cost 197.507
Total Indirect Cost 55.103
Contingency (25%) 63.153
Total 315.763
CAPEX
•Kipawa deposit: Mining and mineral pre-concentration Plant•Temiscaming: Hydrometallurical processing Plant
PEA Highlights (January 30, 2012)
Financial Analysis - Assumptions
18
Technical Assumptions
Item Unit Base Case Value
Total Ore Mined M tonnes 19.0
Processing Rate Tonnes / year1,500,000
Life of Mine years12.9
Average Combined Process Recovery
%81.0
Average Mining Cost ($ / tonne mined) 4.67
Average Processing Cost ($ / tonne milled)38.90
Average General & Administration Costs
($ / tonne milled)5.90
Concentrate Transport between Process Plants
($ / tonne concentrate)8.00
Mixed TREO Transport to Asia
($ / tonne concentrate)183.00
Refining Charges $ /Kg 18.34
Economic Assumptions
REOs Price deckMarket Prices (US $/ Kg)
Ce2O3 5
La2O3 10
Nd2O3 75
Pr2O3 75
Sm2O3 9
Eu2O3 500
Gd2O3 30
Tb2O3 1 500
Dy2O3 750
Ho2O3 65
Er2O3 40
Lu2O3 320
Y2O3 20Exchange Rate(CAD $/US $) 1.00
Discount Rate (%) 8.0
Ce0.02
La0.02
Nd0.16
Pr0.05
Sm0.00
Eu0.03
Gd0.01
Tb0.14
Dy0.44
Ho0.01
Er0.02 Lu
0.02Y
0.07
Revenue
Ce0.291
La0.148
Nd0.132
Pr0.038
Sm0.030
Eu0.004
Gd0.030
Tb0.006
Dy0.036
Ho0.008
Er0.025
Tm0.004
Yb0.023
Lu0.003
Y0.223
Production
19
Base Case(million CAD)
Total At-mine Revenue 2,822.1Pre-production Capital Expenditures
315.8
Sustaining Capital Expenditures 38.3
Initial Working Capital Requirement
9.9
Mine Reclamation Costs 7.5
Total Operating Cost 1,142.5
Total Before-tax Cash Flow 1,679.6
Before-tax NPV @ 8% 606
Before-tax NPV @ 5% 811
Before-tax NPV @ 10% 500
Before-tax IRR (%) 36.9
Before-tax Payback Period (years) 2.4
5 Critical Elements (DOE)
Financial Analysis
Management and Technical TeamBoard of Directors 6 members
Officers
President and CEO Andre Gauthier (2003)
VP Exploration Aline Leclerc (2003)
VP Project development and construction Bertho Caron (2012)
Director of metallurgy Paul Blatter (2012)
Director of environment Hiring in progress
20
Kipawa Deposit – Main Project Tasks Schedule
21
2011 2012 2013 2014 2015 2016
PEA 43-101
Feasibility Study
Environment & Permitting
EPCM & Construction
Mining Pre-Prod. And Tailing Facilities Const.
A Strategic Partner: Toyota Tsusho Corp.
22
Source: TTC-Annual Report 2011
MoU with Toyota Tsusho Corp. (December 7, 2011)
• Signed a MoU with Toyota Tsusho Corp. (“TTC”), a trading company of Toyota Motor Group, in order to secure a HREE supply for the production and marketing of hybrid and electric vehicles
– Mutual collaboration to accelerate the development of the Kipawa Deposit
– Technical assistance will be provided in association with TTC’s chain of suppliers
• MoU is divided into three stages with a final decision at the end of the first two stages
• Expected definitive joint venture between TTC and Matamec (TTC: 49%/ Matamec: 51%) which covers 1,000 hectares on and around the Kipawa Deposit.
Stage 1) Due diligence period which may extend to the end of March 2012• Evaluation of PEA/ preparing joint venture and off-take agreements
Stage 2) If TTC decides to pursue further, TTC will reimburse Matamec $1.5 million for its historical metallurgical expenditures• Negotiate/receive internal approval for the joint venture, off-take agreement and other agreements
Stage 3) A definitive joint venture agreement would then be established for the Kipawa Deposit between TTC (49%) and Matamec (51%) with an off-take agreement• Contribution from TTC based on up to 49% of Matamec’s market capitalization for the 90-day period
ending on November 30, 2011 (~CAD$17.23 million)• Off-take agreement for 100% of the mixed rare earths concentrate to be sold at a price equal to 70% of
the fair market value of the processed form of such elements
Source: Capital IQ.
23
MOU - Matamec Gets:Mutual collaboration to accelerate the development of the
Kipawa Deposit• Feasibility study paid for• Access to TTC balance sheet (financing arranged for capex)• Technical expertise from TTC supply chain (huge intangible
value in terms of cost and time)• Accelerated development program (enables “first to market”
with HREE)• A buyer for 100% of the production• A mine not a story!
24
Zeus (HREE-Y-Zr) Property Upside PotentialTTC may negotiate in good faith to participate in the exploration and development of all other REE prospects found on the Zeus Property
Showing potential outside of Kipawa• Surprise REE-Nb-Ta (16 samples)
– Average of 3.2% TREO at 27% HREO+Y2O3
• Certitude REE-Y-Nb-Ta (13 samples)– 5.2% TREO at 36% HREO+Y2O3
Spring 2012 Follow-up ground exploration to define potential drill targets in the area Ground traverses, mechanical trenching, line cutting, ground geophysics and geochemical surveys
25
REE Deposit Comparables
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
$0
$300
$600
$900
$1,200
$1,500
$1,800
$2,100
$2,400
HR
EO
/TR
EO
%
Mar
ket C
apita
lizat
ion
(US
$ M
illio
n)
Source: Capital IQ, Technology Metals Research LLC and company filings.1 Byron Capital Markets Research Department.* The economic assumption for Y2O3 is based on the cash flow model used in the PEA.
2016E 2017E 2018E 2019E 2020E$0
$100
$200
$300
$400
$500
$600
$700
$800
$900
$1,000
Price Projections for Key REOs
HREE (Eu, Tb, Dy, Y*)
LREE (La, Ce, Pr, Nd)
First year of expected
production by Matamec
26
HREE Company ComparablesDeposit
TypeCompany (Project)
Mine Type*
TREOIn-situGrade(%)
HREO/TREO(%)
OPEX/kg TREO($)
Required CAPEX ($ MM)
Pre-Tax NPV ($ MM)
IRR (%)
Full CAPEX Financing Partner
LREE
Frontier Rare Earth (Zankopsdrift)
OP 3.2% 7.8% $13.1 910 $4,340 at 11% (PEA)
57.6% KORES
Great Western Minerals (Steenkampskraal)
UG 17% 7.8% N/A N/A N/A N/A
Rare Element Resources (Bear Lodge)
OP 3.75% 3.3% $4.6 446 $1,300at 10% (PFS)
44.9%
Avalon Rare Metals (Nechalacho)
UG 1.35% 15.5% $5.5 1,200 $1,770 at 10% (PFS)
39.0%
HREE
Matamec Explorations (Kipawa)
OP 0.42% 36.9% $16.9 315 $606 at 8% (PEA)
36.9% Toyota
Quest Rare Minerals (Strange Lake)
OP 1.3% 43.2% $16.0 560 $1,826 at 10% (PEA)
36.4%
Ucore Rare Metals (Bokan Mountain)
UG 0.75% 39% N/A N/A N/A N/A
Source: Technology Metals Research LLC and company filings.* OP = Open-pit; UG = Underground
27
1010 Sherbrooke West, Suite 200Montreal, QuebecCanada H3A 2R7
Tel (514) 844 5252Fax (514) 844 0550
Email [email protected] www.matamec.com
28