Your partner for customised control solutions for gas turbine packages
Customised control solutions for existing gas turbine packages
Optimum control system solutions for existing turbines, reciprocating engines and related equipment is
what Holland-Controls offers to its customers. Our challenge is to offer dedicated solutions using
off-the-shelf components where possible from renowned manufacturers. This offers our customers,
international companies in the oil and gas or utilities, the benefit of focused knowledge, great
experience and application oriented independent solutions.
Why Holland-Controls
Customised engineering
Support of various control platforms
Experienced and dedicated team
Compliancy with CE, ATEX and SIL
Excellent documentation and support
ISO 9001 and SSC* certified by TÜV
A high level of expertise in control systems
Gas turbine control
Reciprocating engine control
Gas station control
Electric power management
DMEnergy (Generation Service) Tel.: +7 (499) 992-09-90 E-mail: [email protected] Web: www.dm.energy
Experience in solutions for equipment of all brands and types
RB211 / RB211-DLE
Avon / Avon-DLE
Olympus
501-KC5
501-KB5 (WLE) Mars / Saturn
Centaur
Taurus – SoLoNOx
TA1750
Frame 5 FT4 Heron H1 OP16-3A
OP16-3B (DLE)
Engineering, hardware and software design
Design specification: the result of contractual
requirements and a site survey in daily language
and an engineering database.
Hardware design: using the engineering
database as a basis, the PC and field terminal
layout is determined and a schematic drawing is
constructed.
Software design: parallel with the hardware
design, the functional design specification is used
to define the software setup in the form of an
alarm&trip matrix and a logic flow diagram.
Production and testing
The control panel is built according to the
hardware design and specifications.
The procurement and construction takes place
under ISO-9001-2008 procedures with the aid of
an ERP software package.
Extensive documented testing and FAT is carried
out prior to shipping to site.
Work at site and closing out
The installation of the new system is carried out
and mechanical changes to the unit (if
necessary) are realised. After handover of the
installation a training session can be held,
provided by the lead engineer. The installation is
followed by a commissioning period, which
consists of loop checking, functional testing and
an integrated start-up test.
Further info
Detailed brochures are available upon request.
Gas turbine control systems at in-house test facility.
Holland-Controls B.V.
Adam Smithstraat 6
7550 SW Hengelo
The Netherlands
Tel: +31 (0)74-3030 300
Fax: +31 (0)74-3030 333
E-mail: [email protected]