XTRP Hardware
Mike Kasten
University of Illinois
2/24/00
![Page 2: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/2.jpg)
Data board (x12)Clock/control board
Clock/control transition module
Data board transition module (x12)
CDF clock
Data boards (duplicates)
2 XFT linkers
L1 muon
L1 calorimetry
Level1 Request
132 ns + 33ns clocks
SVTL2 trigger
12 data boards
30° (2 wedges)
The core XTRP SystemXTRP I/O
Internal communication
Track Data
![Page 3: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/3.jpg)
XTRP Teststand #1: Pre-crate
• Custom Backplane
• Initial power-up
• Boot PROM
• VME emulation– Signals via Unidig Module
– C code
• Power measurement
U of Illinois
![Page 4: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/4.jpg)
XTRP Teststand #1: VME crate
• Successfully completed VME transactions– Write/Read registers
– Load extrapolation RAMs
• Benchtop accessibility & VME emulation were extremely helpful for initial debugging
• This teststand will provide initial testing infrastructure for new VME boards
![Page 5: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/5.jpg)
XTRP Teststand #2: VME crate
• VIPA-style Test Crate at U of Illinois
• VME access– Write/Read registers
– Load extrapolation RAMs
• Multi-board system– Controller / TestClock / Clock Control / Data
– Send clock signals from Clock Board to Data Board
– Step data through Data Board (slow clock)
• Software Development– DataBSim.java (Data Board simulator)
– XtrpExpertPanel.java (Test engine)
![Page 6: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/6.jpg)
XTRP Functional Clock Test
VME write(+Test Clock)
TestClock
Clock Board
132ns Clock
Data Board
132ns, 33ns, SyncSignals
CLOCK TEST
132ns, 33ns, SyncSignals
![Page 7: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/7.jpg)
• Set up Data Board & Clock Board
• Repeat N times:– Load XFT Simulation data into Data Board
– Increment Data Board clock via Clock Board
– Increment Simulator
• Compare Data Board versus Simulator
• Debug
Functional Data Test Procedure
![Page 8: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/8.jpg)
XTRP Functional Data Test
VME writeTest Clock
Clock Board Data Board
VME read &compare to Simulation
STEPPED132ns, 33ns, Sync
Signals
VME writeXFT Simulation Data
![Page 9: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/9.jpg)
XTRP Teststand #2: VME crate• Data Board II is necessary
– simple reroutes: ~100• power supply pins (64 identical ICs )• various
– Mechanical compliance– Improvements (JTAG & buffering)
• Data Board I lives on…– Completely Functional– Acceptable to use for B0 integration tests
• Clock Control Board is OK (so far)– Corrections do exist: ~25 total wires– Relayout not planned
![Page 10: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/10.jpg)
XTRP Teststand #3: Wilson Hall
• Multi-crate system– XFT CDF-style Crate
• Test Clock / Clock Splitter / Controller / TRACER
• LinkerTester
• Linker / Output Modules
– XTRP VIPA-style Crate• Controller / TRACER
• Data Board
• Clock Control Board
• Much much more Software Development
![Page 11: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/11.jpg)
XTRP Tests
VME write Linker(2) Output Formatters
Data BoardVME readfrom
Pipe FPGAs
Data transferred at full speed for 250 clocks
LinkertesterInput Fifos
INPUT TEST
VME read &compare to Simulation
CAL/MUON Data
DATA TEST
>100,000,000 clockserrors: x000000 to xFFFFFF
>1,000,000 clocks error free
![Page 12: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/12.jpg)
XTRP Tests
Linkertesters(2)
Output Fifos
Input Fifos
VME write
VME read &
compare toSimulation
Linkers (2)
Data Board
Data transferred at full speed
for 10k clocks
>10,000,000 clocks error free
![Page 13: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/13.jpg)
XTRP Tests
Linkertester
Output Fifos
Input Fifos
VME write
VME read &
compare toSimulation
Data BoardData transferred at full speed
for 10k clocks
Software under development
![Page 14: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/14.jpg)
XTRP Teststand #3: Wilson Hall
• Data Board I– No more layout errors found
• Data Board Transition Module - new board necessary– wiring corrections: ~5
– PCB footprint for Muon connector is wrong
• Clock Board– No more layout errors found
• Clock Board Transition Module - new board necessary– Errors found independent of testing
![Page 15: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/15.jpg)
Plan for New Hardware
• Data Board II– Quotes requested, waiting for responses
– Contract Assembler reviewing BOM
– Target date for 1st DBII: April 1, 2000
• Data Board Transition Module– Want to connect to Muon & Calorimetry systems first
– Target date for new TM: April 15, 2000
• Clock Board Transition Module – Need a new board for SVT & L2P integration
– Target date for new TM: May 1, 2000
![Page 16: XTRP Hardware Mike Kasten University of Illinois 2/24/00.](https://reader031.fdocuments.us/reader031/viewer/2022032313/56649e595503460f94b52620/html5/thumbnails/16.jpg)
Input Test Error
Linker(2) Output Formatters
x000000 to xFFFFFF
Data BoardData BoardTransition Module
3.3V LVDSReceiver
3.3V LVTHLatch
Backplane
xFFFFEF
xFFFFFF
Error seen on only1 out of 96 bits