All Capacity*2011 6 monthsNew Plant 529 3,345Plant expansions 2,597 6,154Total 3,126 9,499
2010New Plant 3,221 7,794Plant expansions 5,847 12,256Total 9,068 20,050
2009New Plant 5,182 13,580Plant expansions 6,676 11,712Total 11,858 25,292
2008New Plant 3,263 11,849Plant expansions 5,590 8,904Total 8,852 20,753
2007New Plant 2,003 11,517Plant expansions 3,201 5,290Total 5,204 16,807
Shareholder-Owned Electric
Utilities
New Capacity by Fuel Type
U.S. Shareholder owned Electric Utilities Entire industry*
Fuel Type Online Online Online Online Online Online Online Online Online
2007 2008 2009 2010 2007 2008 2009 2010Coal 479 790 1,998 4,848 615 2,091 1,390 3,566 6,692Natural Gas 3,483 4,687 6,249 2,313 2,025 7,506 9,105 10,627 7,072Nuclear 0 422 245 154 164 1,199 454 245 154Wind 1,240 2,857 3,146 1,496 274 5,022 9,206 9,451 5,126Solar 40 100 47 70 288 229Other 2 96 180 157 0 989 528 1,115 777Total 5,204 8,852 11,858 9,068 3,125 16,807 20,753 25,292 20,050
* Includes all new capacity placed on the grid by investor-owned utilities, independent power producers, municipals, co-ops, government uthorities and corporations.Note: Other includes hydro, biomass, diesel/fuel oil, fuel cells, landfill gas, pet coke, solar/PV, waste heat, water, wood. Source: Ventyx, Inc., The Velocity Suite and EEI Finance Department
2007 Shareholder Entire Industr
2008 Shareholder
2011 6 months
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
2007 2008 2009 2010 20116 months
0
5,000
10,000
15,000
20,000
25,000
30,000
Other Wind Nuclear Natural Gas Coal
MW
Entire Industr2009 Shareholder
Entire Industr2010 Shareholder
Entire Industr
Shareholder Entire Industr
20116 months
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
Shar
ehol
der o
wne
d
Entir
e In
dust
ry
2007 2008 2009 2010 20116 months
0
5,000
10,000
15,000
20,000
25,000
30,000
Other Wind Nuclear Natural Gas Coal
MW
Entire industry*
Online
8355249 65%
1642782 20%
173296 18%
9,499
* Includes all new capacity placed on the grid by investor-owned utilities, independent power producers, municipals, co-ops, government uthorities and corporations.
Coal Natural Nuclear Wind Other479 3,483 0 1,240 2
2,091 7,506 1,199 5,022 989790 4,687 422 2,857 96
2011 6 months
1,390 8,946 434 8,319 5361,998 6,249 245 3,146 2203,566 10,627 245 9,451 1,4034,848 2,313 154 1,496 2576,692 7,072 154 5,126 1,006
615 2,025 164 274 47835 5,249 164 2,782 469
New vs. Cancelled Capacity by Fuel TypeU.S. Shareholder-Owned Electric Utilities
Fuel Type Online Canceled Online Canceled Online Canceled Online Canceled Online Canceled
2007 2007 2008 2008 2009 2009 2010 2010Coal 479 13,880 790 2,759 1,998 3,634 4,848 1,428 615 0 24.0%Natural Gas 3,483 2,177 4,687 1,810 6,249 4,508 2,313 3,290 2,025 500 29.8%Nuclear 0 0 422 0 245 6,100 154 1,600 164 0 40.3%Solar/Photovoltaics 0 0 0 0 40 0 100 46 47 0 0.0%Wind 1,240 390 2,857 262 3,146 889 1,496 827 274 1,050 5.9%Other 2 130 96 125 180 0 157 96 0 0 0.0%Total 5,204 16,577 8,852 4,956 11,858 15,131 9,068 7,287 3,125 1,550 100.0%
205%
Note: Totals may reflect rounding.Note: Data includes new plants and expansions of existing plants, including nuclear uprates. Source: Ventyx, Inc., The Velocity Suite and EEI Finance Department
20116 months
20116 months
New Capacity -- Regulated vs. CompetitiveU.S. Shareholder-Owned Elec
New capacity only
2007 2008 2009 2010Total Competiti 996 2,148 2,823 1,588 85Total Regulate 1,007 1,114 2,359 1,633 444Grand Total 2,003 3,263 5,182 3,221 529
*Notes: Plant category based on designated operating company owner. Data does not include expansions, only new plants. Totals may reflect rounding.
Source: Ventyx, Inc., The Velocity Suite and EEI Finance Department
20116 months
123450
5
10
15New
Plants Online by Category (MW) 2002-2007Shareholder-Owned Electric Utilities
2007 2008 2009 2010 20116 months
0
500
1,000
1,500
2,000
2,500
3,000Total Competitive Total Regulated
New Capacity -- Regulated vs. CompetitiveU.S. Shareholder-Owned Elec
All Capacity -- New & Expansions
2007 2008 2009 2010Total Competiti 1,612 3,558 4,320 3,233 246Total Regulate 3,592 5,294 7,538 5,835 2,880Grand Total 5,204 8,852 11,858 9,068 3,126
*Notes: Plant category based on designated operating company owner. Totals may reflect rounding.
Source: Ventyx, Inc., The Velocity Suite and EEI Finance Department
20116 months
2007 2008 2009 2010 20116 months
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000Total Competitive Total Regulated
New Capacity by RegionU.S. Shareh
Online Canceled Online Canceled Online Canceled Online
Region 2007 2007 2008 2008 2009 2009 2010ECARERCOT 551 6,575 1,095 729 2,589 3,935 1,229FRCC 2,040 2,977 4,117 20HCC 5 113MAACMAINMRO 561 1,050 2,531 300 1,060 504 351NPCC 690 92 8 124 3RFC 775 867 486 1,288 741SERC 84 2,217 1,134 567 4,131 1,770SPP 776 874 670 150 740 630 2,347WECC 1,192 2,194 2,556 2,910 2,287 4,519 2,495Total 5,204 16,577 8,852 4,956 11,858 15,131 9,068
Note: Data includes new plants and expansions of existing plants, including nuclear uprates. Note: Totals may reflect rounding.Note: Reliability First Corporation (RFC) began operations on 1/1/06 and includes ECAR, MAAC, and MAIN.
Source: Ventyx, Inc., The Velocity Suite and EEI Finance Department
U.S. Shareholder-Owned Electric Utilities
Canceled Online Canceled
2010
2,390
532 262 2001 2 350
3,175 875605 1,15080 33
504 804 1,0007,287 3,126 1,550
Note: Reliability First Corporation (RFC) began operations on 1/1/06 and includes ECAR, MAAC, and MAIN.
20116
months2011
6 months
New Capacity Announcements by Fuel TypeU.S. Sharehold
2007 2008 2009 2010Coal 2,462 630 565Natural Gas 5,988 3,670 4,308 2,083 8,839 86%Nuclear 11,277 1,793 1,939 641Wind 4,900 6,164 3,517 3,646 988Solar 1,134 1,226 121Hydro 2,409 138 84 300Other 322 401 682 4 0Total 24,949 15,065 12,283 7,684 10,248
Note: Other includes biomass, diesel/fuel oil, fuel cells, landfill gas, pet coke, solar/PV, waste heat, water, wood. Totals may reflect rounding.Source: Ventyx Inc., The Velocity Suite and EEI Finance Department
20116 months
Natural Gas; 8,839
Wind; 988
Solar; 121 Hydro; 300
Note: Other includes biomass, diesel/fuel oil, ultra-low sulfur fuel oil, hydro, solar, wood. Totals may reflect rounding.
Source: Ventyx, EEI Finance Department
Natural Gas; 8,839
Wind; 988
Solar; 121 Hydro; 300
Projected Capacity AdditionsU.S. Shareholder-Owned Electric Utilities
Actual Projected2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
Coal 479 790 1,998 4,848 1,440 3,531 16 432 0 0 0 500 0Natural Gas 3,483 4,687 6,249 2,313 5,073 7,627 15,158 1,404 3,482 1,066 0 0 0Nuclear 0 422 245 154 881 524 58 150 232 3,892 2,617 3,800 1,117Wind 1,240 2,857 3,146 1,496 3,414 3,716 1,994 499 460 0 200 0 0Solar 40 100 259 205 1,142 1,800 6,950 0 0 0 0Other 2 96 181 157 364 483 580 1,708 1,474 268 268 268 568Total 5,204 8,852 11,858 9,068 11,433 16,087 18,948 5,993 12,598 5,226 3,085 4,568 1,685
Notes: Data includes new plants and expansions of existing plants, including nuclear uprates. Data does not include projects with an expected online date beyond 2020.Other includes biomass, diesel/fuel oil, fuel cells, landfill gas, pet coke, solar/PV, waste heat, water, wood. Totals may reflect rounding.2007-2010 is actual plants brought online. 2012-2020 is projected based on projects announced as of 31/07/10. 2011 includes projets brought online and projects expected to come online during the yearSource: Ventyx Inc., The Velocity Suite, Nuclear Energy Institute, EEI Finance Department
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Actual Projected
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000Other Solar Wind Nuclear Natural Gas Coal
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Actual Projected
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000Other Solar Wind Nuclear Natural Gas Coal
Projected2020
00
6,17000
2686,438
Notes: Data includes new plants and expansions of existing plants, including nuclear uprates. Data does not include projects with an expected online date beyond 2020.
2007-2010 is actual plants brought online. 2012-2020 is projected based on projects announced as of 31/07/10. 2011 includes projets brought online and projects expected to come online during the year
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Actual Projected
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000Other Solar Wind Nuclear Natural Gas Coal
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020Actual Projected
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000Other Solar Wind Nuclear Natural Gas Coal
Stage of Projected Capacity AdditionsU.S. Shareholder-Owned Electric Utilities (based on projecfts announced as of 30/06/11)
by MWFuel Proposed Feasibilityation Pending Permitted Site PrepCoal 47 500 0 0 0Natural Gas 4,721 0 6,751 13,911 620Nuclear 2,180 3,000 22,210 352 2,234Wind 6,902 10 1,020 1,133 150Solar 2,222 0 6,379 1,355 100Other 711 2,296 109 2,746 2Total 16,783 5,806 36,469 19,496 3,106
Source: Ventyx Inc., The Velocity Suite, Nuclear Energy Institute, EEI Finance Department
Note: Other includes biomass, diesel/fuel oil, fuel cells, landfill gas, pet coke, solar/PV, waste heat, water, wood. Totals may reflect rounding.
Construction Testing Total4,954 0 5,5005,783 0 31,785
130 0 30,106645 150 10,010249 0 10,306384 0 6,248
12,144 150 93,955
Note: Other includes biomass, diesel/fuel oil, fuel cells, landfill gas, pet coke, solar/PV, waste heat, water, wood. Totals may reflect rounding.
Proposed New Nuclear PlantsU.S. Shareholder-Owned Electric Utilities
Company Site (State) Early Site PermitDTE Energy Co. Fermi (MI) TBD ESBWR (1) September 2008 1Dominion Resources Inc. North Anna (VA) Approved November 2007. ESBWR (1) November 2007 1Duke Energy Corp. William States Lee (SC) - AP1000 (2) December 2007 2Entergy Corp. River Bend (LA) - TBD September 2008Exelon Corp. Clinton (IL) Approved March 2007. TBD TBDExelon Corp. Victoria County (TX) Submitted March 2010 TBD TBDFlorida Power & Light Turkey Point (FL) TBD AP1000 (2) June 2009 2NuStart (Consortium) - TVA Site Bellefonte (AL) - AP1000 (2) October 2007NuStart (Consortium) -Entergy SiteGrand Gulf (MS) Approved April 2007. TBD February 2008PPL Corp. / Unistar Susquehanna, PA - EPR (1) October 2008 1Progress Energy Shearon Harris (NC) - AP1000 (2) February 2008 2Progress Energy Levy County (FL) - AP1000 (2) July 2008 2PSEG Lower Alloways Creek ( Submitted May 2010 TBD TBDSCANA Corp. V.C. Summer (SC) - AP1000 (2) March 2008 2Southern Co. Vogtle (GA) Approved August 2009 AP1000 (2) March 2008 2Southern Co. TBD TBD TBD TBDEnergy Future Holdings Inc. (LuminComanche Peak (TX) - APWR (2) September 2008 2UniStar (Constellation & Areva) Calvert Cliffs (MD) - EPR (1) July 2007 & March 2008 1UniStar (Constellation & Areva) Nine Mile Point (NY) - EPR (1) September 2008NRG Energy/STPNOC Matagorda (TX) ABWR 2) September 2007 2
Shareholder-Owned Electric UtilitiesSource: Nuclear Energy Institute, Nuclear Regulatory Commission, EEI
Legend: TBD: To Be DeterminedAP1000: Reactor designed by WestinghouseAPWR: Advanced Pressurized Water ReactorEPR: Pressurized Water Reactor designed by FramatomeESBWR: Economic Simplified Boiling Water Reactor
Italics = COL appplications have been submitted
Design (# of Units)
Expected Construction & Operating License
Submittal
Units under NRC
Review