XIV Paper 38

download XIV Paper 38

of 11

Transcript of XIV Paper 38

  • 7/24/2019 XIV Paper 38

    1/11

    1CHSME SYMPOSIUM SERIES NO. 144

    T HE U S E OF R IS K B A S E D A S S E S S M E N T T E C HN IQU E S T O OP T IMIS E

    IN S P E C T ION R E GIME S

    G R Bennett, M L Middleton, P Topalis

    Det Norske Veritas. Stockport Technical Consultancy, Highbank House. Exchange Street,

    Stockport, SK3 OET.

    Regulators and insurance companies now recognise the acceptability

    of a risk based approach to the optimisation of inspection and

    maintenance intervals. Qualitative approaches to Risk Based

    Inspection (RBI) have been developed for general use and more

    detailed quantitative methods exist for activities with major loss

    potential or large preventive expenditure requirem ents. DN V

    pioneered the use of RBI in the chemical process industry in 1992 and

    has produced a resource document for the API (API 581). DNV

    subseque ntly further develo ped Quantified RBI software. A number

    of case studies and client projects have been conducted and the RBI

    techniques and software are becoming valuable tools for the oil and

    chemical industry.

    Keyw ords: Risk Based Inspection, Inspection Planning ,

    Consequence, Likelihood, Corrosion

    WHY CONSIDER RISK IN INSPECTION PLANNING ?

    The first duty of business is to survive and the guiding principle of business econom ics is

    not the maxim isation of profit, it is the avoidance of loss

    (P e te r Dru c k e r )

    All industrial organisations use people, equipment and property to add value to a

    commodity and thus generate a return on their investments. If the returns are in excess of

    the costs, the com pany is in profit, if they are less, a loss occ urs and if the losses co ntin ue

    to be sustained, the organisation will ultimately fail.

    People and equipment are not infallible. People do make m istakes and equipment does

    fail. All mistakes and failures have consequences, some sm all and others large. The

    magnitude of those consequences influences the ability of the organisation to achieve a

    sustained profit and thus survive . It is therefore good business prac tice to consider the

    consequences of failures and how likely they are to occur, i.e. to systematically consider

    the risks arising from failures.

    All forward thinking organisations practice some form of loss avoidance policy.

    Equipment maintenance, inspection and testing, and the training of personnel are all

    undertaken to avoid failures and red uce or m itigate their associated losses

  • 7/24/2019 XIV Paper 38

    2/11

    CKEMO S' MFOSrt'M SERIES N'

    How many organisations however, know in detail how effective their investment in

    loss prevention activity is ? Does the extent and frequency of inspection reflect the

    mag nitude of the conseq uen ces of an undesired failure ? Is the inspection activity likely to

    identify the degradation mechanisms that exist ? Do the planned maintenance routines

    actually influence the chance of the equipmen t breaking dow n ? Is mo ney be ing spent on

    inspecting and maintaining equipment which, if it fails, has very little effect on the

    organisation ?

    An organisation's abili ty to consider these questions has traditionally been driven by

    legislative rather than business need. For exam ple, inspection of pressure retaining

    equipment or structures has been primarily calendar based, driven purely by legislative

    requiremen ts. This no longer needs to be the case. The new goal setting legislative

    environm ent provides the opportunity to plan loss avoidance activities by linking any

    increase in the level of activity, to the reduction in risk ach ieve d by that increased level

    of activity.

    Both regulators and insurance companies now recognise the acceptabili ty of a risk

    based approach to the optimisation of maintenance.

    R ISK B A SED I N SPEC TI O N MET H O D S

    Risk Based Inspection (RBI) techniques have been developed along two complementary

    routes. Qualitative approaches to RBI have been developed for general use and detailed

    quantitative methods have been developed and are being refined for activities with major

    loss potential or large preventive expend iture requirements. This paper will con centrate

    on recent developments in the quantitative assessment approach.

    QUALITATIVE RISK BASED INSPECTION

    Qualitative RBI is based on answering a series of questions regarding likelihood of failure

    and the consequen ces of failure and assigning notional levels ( High / Med ium / Low ) to

    the answers to place the item on a risk matrix, see Figure 1.

    The closer an item is to the top right corner of the matrix, the more critical the item is,

    and the greater the inspection activity warranted. It should be noted how ever, that chan ges

    to inspection regimes can only effect the frequency of an event, and not its consequences.

    Therefore if an item is in the high risk category primarily due to it 's consequences, then no

    amount of additional inspection will improve it , and design changes to the system may be

    required instead. Th is statemen t is equa lly true for qua ntitative assessm ent techn iques .

    Software packages are now available which allow a qualitative estimate of inspection

    frequency to be made. They vary in complexity, and in the degree of "engineering

    judgement" to be applied, but they can be used as an effective screening tool in order to

    determine w hich equipm ent should be subjected to a more detailed quantified assessment.

    An example screen shot from o ne of the DNV software p ackag es is shown in Figure 2.

    The software is driven simply by the selection of various options from drop down

    menus, which prompt the user to select the most appropriate category for equipment type.

    504

  • 7/24/2019 XIV Paper 38

    3/11

    SCHEME SYMPOSIUM SERIES NO.

    \44

    location, fluid type and inventory, business interruption consequence, and specific details

    relating to the material of construction of the equipment, and its susceptibility to various

    failure m ech anis ms . Based up on these inpu ts, the software then use s a set of pre-defined

    rule sets to calculate a risk ranking and a corresponding recommendation for the next

    inspection interval.

    THE QUANTIFIED RISK BASED INSPECTION METHOD

    The Quantified Risk Based Inspection philosophy and method has been endorsed and is

    being promoted by the American Petroleum Institute Committee on Refining Equipment.

    The group is comprised of representatives from the following com panie s:

    Amoco

    Aramco

    Arco

    Ashland

    BP

    Chevron

    Citgo

    Conoco

    Dow

    DNO Heather

    DSM

    Exxon

    Fina

    Koch

    Marathon

    Mobil

    Pennzoil

    Petro Canada

    Phillips

    Shell

    Sun

    Texaco

    Unocal

    DNV pioneered the use of RBI in the chem ical process industry in 1 992. In 1993 the

    API approach ed D NV with the reque st to join tly fund a larger dev elop me nt effort, aimed

    at producing a resource document for how to establish risk based inspection in the

    petroleum industry. DN V obliged, and in 1994 it produced the Base Resource Docum ent

    on Risk-Based Inspection. This document is now being promoted by API as a standard

    referred to as API 581, it will be followed shortly by API 580 which will become an API

    Recommended Practice.

    In 1995, the API commissioned DNV to develop software for i ts members to allow

    them to automate some of the processes required by API 581 . This software based system

    has now been used successfully on a number of studies conducted both by DNV, and the

    sponsor group mem bers. DNV d ecided to further develop the Quantified R isk Based

    Inspection Software in 1996. The new software, called OR BIT w as initially released in

    March 1998 and is available to the industry as part of an integrated package of Risk Based

    Inspection services. ORB IT provides a fast interpolation approac h for consequ ence

    analysis.

    The quantified RBI approach provides a methodology for determining the optimum

    combination of inspection method s and frequencies. Each available inspection method

    can be analysed and its relative effectiveness in reducing failure frequency can be

    estimated . Give n this information and the cost of each proce dur e, an optimisation

    program can be developed. The key to developing such a procedure is the abili ty to

  • 7/24/2019 XIV Paper 38

    4/11

    : - ' >SiUM SERIES NO. 44

    quantify the risk associated with each item of equipment and then to determine the most

    appropriate inspection techniques for that piece of equipment.

    SY STEMA TI C A PPR O A C H TO R ED U C I N G R I SK S

    A fully integrated Risk Based Inspection system should contain the steps shown in Figure

    3. The system includ es inspe ction activities, inspection data collection and updatin g, and

    continuous quality improv emen t of the system. Risk analysis is "state of kn ow ledg e"

    specific and, since processes and systems are changing with time, any risk study can only

    reflect the situation at the time the data were collected . Althou gh any syste m, whe n first

    established, may lack some needed data, the risk based inspection program can be

    established based on the available information, using conservative assumptions for

    unkno wns. A s know ledge is gained from inspection and testing prog ram s and the

    database imp rove s, unce rtainty in the analys is will be reduced. This results in reduced

    uncertainty in the calculated risks.

    The combination of elements required as inputs to a quantitative RBI analysis are

    shown in Figure 4.

    The two major elements of a quantitative RBI analysis, as with any risk based study are

    an assessment of the probability (or l ikelihood) of an event occurring, and its

    consequences should it occur.

    LIKELIHOOD ANALYSIS

    When considering the likelihood of a failure occurring, the RBI process utilises a series of

    technical modules, in order to establish a dam age rate for the equipment. Th e calculated

    dam age rate depends upon the item's material of construction, the process fluids it is

    exposed to, i ts external environment and the process conditions (pressure, temperature

    etc.).

    Details of the current technical mod ules are shown in Figure 5.

    It is also necessary to consider the current inspection regime, and to identify when the

    equipment was last inspected, how it was inspected, and what the results of those

    inspections were.

    For example, if an equipment is subject to damage by corrosion or erosion, and if no

    inspections have been performed, then the likelihood of failure may be high. If however,

    many inspections of sufficient quality have been performed ( and the equipment still meets

    its design intent ) then the likelihood of failure will be quite low, even if there has been

    significant corrosion, as the rate of corrosion will be well understood.

    Inspection activity is not however guaranteed to provide precise details of actual

    corrosion rates, each inspection h as an error band associated with the particular technique.

    These error bands can be established by trials and review of historical surve ys. Inspection

    activity does not change a corrosion rate, it reduces the error band and increases our

    confidence that we k now th e actual corrosion rate.

    506

  • 7/24/2019 XIV Paper 38

    5/11

    ICHE.VIE SYMPOSIUM SERIES NO. 144

    Statistical m ethods can be used to evaluate the likelihood that damage severe enoug h to

    cause a failure could exist given the am oun t of app ropria te inspection activity that has

    been performed. As the damage rate is t ime based, future inspection techniques and

    intervals can be planned based upon the amount of damage expected to be seen at some

    point in the future. A proper balance must be established between advancing damage and

    increased knowledge of the amount of damage, to ensure safe and economic operation.

    An exam ple of a screen shot of the equipmen t details from the equipmen t specification

    mo dule of the software is shown in Figu re 6. A screen shot of the likelihood m odu le is

    shown in Figure 7.

    C O N SEQ U EN C E A N A LY SI S

    The consequ ence analysis conducted w ithin the RBI software is based upon look-up tables

    calculated using the DNV software package

    PHAST .

    Conseq uences are calculated in

    terms of the area of equipment damage, and the areas within which personnel will be

    adversely affected by flames, explosions, or the toxic effects of the product concerned.

    Using the input data on process pressure and temperature, material properties, and

    inventories, the system determines the release rate for a range of representative hole siz es,

    and also determines the release type. After d etermining w hether a release is continu ous or

    instantaneous (as in a vessel rupture), the software calculates the final phase in the

    environm ent (liquid or gas) and then determines the toxic or flammable co nsequ ences. In

    evaluating the consequences, the software also allows modeling of account mitigating

    features such as isolation and shu tdown systems.

    An example of the Consequence data module can be seen in Figure 8.

    R I SK A SSESSMEN T

    Having evaluated both the likelihood of an event, and its consequences, the system then

    combines this data to produce the overall risk evaluation for each piece of equipment.

    This allows the assessment of the overall risk levels of the plant, and the identification of

    whe re the high risk items on the plant are. so that inspection effort can be focused initially

    on the high risk items. Various reports can be automatically g enerated to produ ce a w ide

    range of analyses. These reports include:

    Action damag e/mechan ism summary reports.

    Financ ial risks.

    Inspection planning.

    Risk rank ing.

    Graphs can also be produced for specific i tems of equipment showing the optimised

    number of inspections (cost of risk per number of inspections versus years of inspection)

    and the percentage of equipment versus the percentage of risk. An exam ple plot is

    illustrated in Figure 10. The curve demonstrates the general principle that 80-90% of the

    risk is contributed by only 10-20% of a plants fixed equipment.

    507

  • 7/24/2019 XIV Paper 38

    6/11

    EGHEME SYMPC5TUM 3 O. 144

    PLA N T EX PER I EN C E

    It should be clear from the forgoing that regardless of whether a qualitative or quantitative

    approach is followed, i t cannot be implemented without the active involvement of

    personnel familiar with the plant and its operation. Corrosion engineering experience is

    required to determine the damage mechanisms possible. Inspection management personnel

    are required to extract the knowledge of past inspection, and operations personnel are

    required to assist with establishing the safety and prod uction im plication s of failures. It

    must be a team effort, in order to be effective.

    CASE STUDIES

    DNV has now completed a number of botii pilot and full scale studies, in order to validate

    the data in the model, and to evaluate the usage of the technique. Results demo nstrate that

    the RBI techniques and software are becoming valuable tools for the oil and chemical

    industry.

    On one site, an RBI analysis of nearly 2,000 piping sections in an ethylene plant

    show ed that less than 10% fell into the high risk category. Failure of those items

    cons tituted a busines s interruption and asset dam age risk of SI 1.5 million per year. Th e

    application of improved inspection techniques reduced this risk to $4.1 million per year, a

    saving of S7.4 million per year. The re was of course a cost associated with this risk

    reduction, and the improved inspection technology utlised was estimated to cost $250,000

    per year. In this case the benefits clearly outw eigh ed the cos ts. On the other hand, a

    review of the bottom 10% of risk items showed that the application of the same inspection

    techniques could still result in a risk reduction from $12,000 per year, to $4,300 per year a

    saving of $7,700 per year. Ho wev er the costs of the improved inspection of those items

    would still cost $250,000, and this was clearly not cost effective.

    On another site. 10 vessels were removed from the annual inspection plan, at an annual

    cost saving of $25,000 per vessel, and some pipework materials were upgraded at a 20%

    increased cost of materials, but avoiding a possible $3 million loss in bu siness

    interruption.

    S U M M A R Y

    The RBI methodology and its supporting computer program has already gone a long way

    toward an integrated risk management program.

    The technology is sti l l being developed by DNV, and the author wishes to take this

    opportunity to thank the RBI sponsor group for their advice and support during the

    develo pm ent phase. The RBI philosophy and database has drawn upon the experience of

    both DNV and the project sponsors in order to evaluate failure mechanisms, corrosion

    rates,

    consequences etc.

    The author would also like to acknowledge the contribution of his colleagues Mark

    Middleton (DNV Stockport), Panos Topalis (DNV Software Products), Angus Lyon

    (DNV Aberdeen) and Gert Koppen (DNV Rotterdam) to the production of this paper.

    508

  • 7/24/2019 XIV Paper 38

    7/11

    LCHEME SYMPOSIUM SERIFSN

    Figure 1 Exam ple Risk Ma trix

    Increasing

    Likelihood 3

    2

    1

    ; MecJiium@l ' m

    w s . w

    : : -

    . .V... ,

    . ; . .

    i

    . - - . V .

    Mediun

    1 2

    3 4 5

    Increasing Consequence

    Figure Example of Qualitative RBI Software

    R~~

    z

    qipmenH den#co(Jon

    3

    C iM e* tao af

    C a ra a ue n C s t h e o r y f c ? ;R f c M & f e l M dH i g h R i t k

    -Irw&oCtcn RocomrandabcfT:

    &r

  • 7/24/2019 XIV Paper 38

    8/11

    ICHEME

    SYMPOSIUM SERIES NO. ^

    Fi gur e3 Risk Based Inspec t ion Pr og ram for In-Service Eq uip me nt

    -

    PLANT DATABASE

    RISK BASED PRIORITISATION

    INSPECTION PLANNING '

    r

    INSPECTION RESU LTS

    FITNESS FOR SERVICE

    I

    - . ' a

    a i - .

    -.

    INSPECTION UPDATING

    . - . . , ' . . .

    3

    SYSTEM AUDIT

    Fi gur e4 Overview of Risk Based Inspect ion

    125.vsd

    ; . - . . * .

    :

    . . . . . - . . .

    PROCESS SAFETY

    MANAGEMENT

    IMPROVEMENTS

    510

  • 7/24/2019 XIV Paper 38

    9/11

    SCHEME SYMPOSIUM SCRIES NO. 144

    Figure 5 RBI Technical Modules

    Thinning

    Modu le

    Corrosion

    U nder

    Insulla l ion

    Techn ica l M odu les

    Set -up

    Stress

    Corros ion

    Cracking

    High

    Temperature

    Hydrogen

    Attack

    Fatigue

    Brittle

    Fracture

    No

    Me ch a n isms

    App ly

    HCI

    HT Sulf idat ion

    HT H.S/H.

    H j S O ,

    HF

    Sour Water

    Amine

    HT Oxidat ion

    C U I

    Caustic H

    Amine

    Carbonate

    Sulphide

    HIC/SOHIC - H

    3

    S

    HSC/HF

    HIC/SOHIC - HF

    Fatigue

    Brittle

    Fracture

    Figure 6 General Equipment Module

    ' ; Fquipm ent Deta i l D ata

    Consequence

    e n e r a l

    Likelihood

    Results

    - Tempetatuie and Pressute -

    Op tempetature: J293

    Op pressuie:

    102000

    Design temperatuie: |263

    Design pressure:

    Miri.

    |263

    |99000

    Max.

    |323

    |103000

    K

    Pa

    T empetatuie and Pressure Check j

    -Add i t iona l Data

    Material ot ICarbon S teel

    Construction;

    PJID-

    ZJ

    100-1000 Re v

    1

    Equipment Dimensions-

    Wall Thickness: [5

    Tank Sha pe: |Verti

    Internal Length : ("

    Internal Diameter lg.0

    Internal Height |3.rj

    D a t e ;

    ]Current Service Starting Data

    11987-01 04 1

    ; Insulated fr-es) I~ PWHT [Vast [""

    ;

    Exterior Coating fTest 17 Notmalized

    [Yes):

    T j

    : Vessel Lining

    (Yes):

    l~" Impact Test (Yes ): F \

    3

    Help-1

    Notes

    5 1 1

  • 7/24/2019 XIV Paper 38

    10/11

    1CHEME SYMPOSIUM S5H;E5

    NO N

    Fi gur e7 Like l ihood Analys i s Module

    8

    E q u i p m e n t D e t a i l D a t a

    eneia l J L ik e l ih ood Consequence

    - D a m a g e - T y p e s

    Jhinnkig

    SCC

    I - Failure Freauency -

    U iiltfe Fracture

    r

    No M echanisms App(y

    3

    r

    Small

    Medium

    Large

    Rupture

    Leak Frequency

    (peiyeaf|

    4.00E-05

    1.00E-Q4

    100E-05

    200E-O5

    Cfosa

    Help

    Fi gur e8 Consequence Analys i s Module

    I t q u r p m e n t D e t a i l D a t a

    Senetal ] Lfcelihood Consequence]_ Results

    Chemical Name : |KER0SENE

    Look up Table Name: |Keiosene

    Inibal Fluid State: jLiquid Vesse l Type : [Pressurized Liquid

    Chemical.

    Vessel TypeandInitial Fluid Sta te

    Method: |

    Lookup Melhod 3

    Inventory -

  • 7/24/2019 XIV Paper 38

    11/11

    ECHEME SYMPOSIUM SERIES NO. 14^

    Figure 9 Results Module

    Eq u ip me n t De ta i l Da ta

    :

    U k d h o o d R esu K s

    Ukelhood Categoiy

    Consequence Resul t s

    Area Based Results

    3.81E-03 Events/yeaf

    i C o n s eq u en ce

    F a c t a

    3 6 8 . 0 0 1 s q .

    Categoiy ;

    2 2 4 1

    j Equipment Damage:

    FataU y:

    ToacAfea:

    1.13E*Q2

    | s q m

    |

    3.68E-02

    I sqm

    [

    O.O0E+OQ

    | sq m" j

    2241

    Inspection Plann ing Calculations

    Inspection Planning J

    .

    CJoae Help Notes

    F ig u re

    10

    Risk Results

    Percentage of Equipmentvs.Percentage o f Risk

    i

    I

    s,

    100

    o~

    80

    70

    m

    50

    4 0

    30

    20

    10

    0

    i j j

    P e r c e n t a g e o f E q u i p m e n t

    513