XARIS ENERGY (PTY) LTD
Transcript of XARIS ENERGY (PTY) LTD
XARIS ENERGY (PTY) LTD
SPECIALIST STUDY: Noise Impact
PREPARED BY: Dr. Brett Williams
ENVIRONMENTAL NOISE IMPACT STUDY
FOR THE PROPOSED XARIS ENERGY FSRU AND POWER
GENERATION PROJECT – WALVIS BAY NAMIBIA
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
i
COPYRIGHT:
PROJECT NAME Xaris Energy Walvis Bay Power Plant and Gas Supply
Facility
STAGE OF REPORT Final Noise Impact Study
CLIENT Xaris Energy (Pty) Ltd
SPECIALIST CONSULTANT Brett Williams
DATE OF RELEASE 10th April 2015 (Version 4)
CONTRIBUTORS TO THE REPORT -
CONTACT [email protected]
+27 (0)41 3656846
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
ii
DECLARATION
I hereby declare that I do:
(a) have knowledge of and experience in conducting specialist assessments, including
knowledge of the Environmental Management Act (Act 7 of 2007)and the
Regulations and Guidelines that have relevance to the proposed activity;
(b) perform the work relating to the application in an objective manner, even if this
results in views and findings that are not favourable to the applicant;
(c) comply with the abovementioned Act, its Regulations, Guidelines and other
applicable laws.
I also declare that there is, to my knowledge, no information in my possession that
reasonably has or may have the potential of influencing –
(i) any decision to be taken with respect to the application in terms of the Act and its
Regulations; or
(ii) the objectivity of this report, plan or document prepared in terms of the Act and its
Regulations.
Dr Brett Williams
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
iii
EXECUTIVE SUMMARY
Safetech were requested to conduct a noise impact assessment for the construction
and operation of the proposed Xaris Energy FSRU and Power Generation Facility in
Walvis Bay, Namibia.
The following conclusions can be drawn from the results of the study:
There will be a short-term increase in noise in the vicinity of the site during
construction, as the ambient level will be exceeded in areas very close to the
two construction sites. The impact will however not be significant due to the short
duration;
The noise impact from the Power Plant and FSRU will be minimal due to the
distance from the nearest noise sensitive human receptors;
The noise impacts from the decommissioning and rehabilitation of the site will be
of short term nature and the will be similar to the construction phase.
The IFC Environmental Noise Guidelines require a residential daytime limit of 55dB(A)
and a night time limit of 45 dB(A) for industrial projects. The night and daytime limit is
not exceeded.
The SANS 10103:2008 “Rural” noise limits are more stringent limits than the IFC noise
emission limits used in the study in the absence of Namibian noise limits. The SANS
daytime of limit of 45dB(A) and a night time limit of 35 dB(A) was applied for the
FSRU due to the FSRU being located closer to residents than the Power Plant. The
predicted FSRU operations met the SANS10103:2008 limits at the closest human
receptors. The SANS 10103:2008 “Industrial” limits were met at the Power Plant. No
noise sensitive receptors were identified within close proximity to the proposed
Power Plant.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
iv
TABLE OF CONTENTS
EXECUTIVE SUMMARY .............................................................................................................. iii
TABLE OF CONTENTS ............................................................................................................... iv
ABBREVIATIONS AND ACRONYMS ........................................................................................ vi
1 BACKGROUND ................................................................................................................... 8
1.1 Introduction ................................................................................................................. 8
1.2 Specialist Study Leader .............................................................................................. 8
1.3 Terms Of Reference .................................................................................................... 8
1.4 Methodology ............................................................................................................... 9
1.4.1 Desktop study methodology .............................................................................. 9
1.4.2 Field Study ............................................................................................................. 9
1.5 Assumptions And Limitations ................................................................................... 12
2 PROJECT DESCRIPTION .................................................................................................... 13
2.1 POWER PLANT ............................................................................................................ 13
2.2 FSRU............................................................................................................................. 13
3 LEGAL AND REGULATORY REQUIREMENTS ................................................................... 13
4 THE RECEIVING ENVIRONMENT ...................................................................................... 15
4.1 Sensitive Receptors ................................................................................................... 15
4.1.1 Human Sensitive Receptors .............................................................................. 15
4.1.2 Natural Environment Receptors ....................................................................... 16
4.2 Results of the field study ........................................................................................... 17
4.3 Environmental Vulnerability ..................................................................................... 17
5 NOISE IMPACT ASSESSMENT ............................................................................................ 19
5.1 Noise Impact during the Construction Phase ....................................................... 19
5.1.1 Conclusion - Construction Noise ..................................................................... 20
5.2 Noise Impact of the Gas Power Station ............................................................... 20
5.2.1 Conclusion – Power Plant ................................................................................. 25
5.2.2 Conclusion – FSRU .............................................................................................. 25
5.3 Assessment of Noise Impact.................................................................................... 26
5.3.1 Comparison to IFC Environmental Noise Guidelines ..................................... 27
5.3.2 Mitigation - Construction................................................................................... 27
5.3.3 Mitigation - Operation ....................................................................................... 27
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
v
5.3.4 Recommended Monitoring .............................................................................. 28
6 CONCLUSION ................................................................................................................... 28
7 REFERENCES ...................................................................................................................... 29
Appendix A – POWER PLANT LAYOUT ................................................................................. 30
Appendix B – Calibration Certificate .................................................................................. 31
Index of Tables
Table 1-1 - Meteorological parameters used in modelling ............................................... 9
Table 1-2 – Location of ambient measurement point ...................................................... 10
Table 3-1- Typical rating levels for noise in various types of districts ............................... 14
Table 4-1 Results of Field Study ............................................................................................ 17
Table 4-3 Vulnerability Rating Criteria ................................................................................. 18
Table 4-4 Vulnerability Rating .............................................................................................. 18
Table 5-1 Combining Different Construction Noise Sources – High Impacts (Worst
Case) ....................................................................................................................................... 19
Table 5-2 Combining Different Construction Noise Sources – Low Impacts ................. 19
Table 5-3 Attenuation by Distance for the construction phase (worst case) ............... 20
Table 5-4 Sound Power Levels used in the Modelling....................................................... 21
Table 5-5: Impact assessment of the proposed project ............................................... 26
Index of Figures
Figure 1-1- Locations of ambient measurement point – Power Plant ............................ 10
Figure 1-2- Locations of ambient measurement point – FSRU ......................................... 11
Figure 4-1- Location of Power Plant and FSRU ................................................................... 16
Figure 5-1 - Modelling Results – Power Plant ...................................................................... 22
Figure 5-2 - Modelling Results – FSRU .................................................................................. 23
Figure 5-3 - Modelling Results – Power Plant & FSRU ........................................................ 24
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
vi
ABBREVIATIONS AND ACRONYMS
Ambient noise
Totally encompassing sound in a given situation at a given time, and
usually composed of sound from many sources, both near and far.
Note: Ambient noise includes the noise from the noise source under
investigation.
Annoyance General negative reaction of the community or person to a condition
creating displeasure or interference with specific activities
A-weighted
sound pressure
level (LpA and
LAeq,T)
A-weighted sound level LpA which is the sound pressure level at specific
frequencies and is given using the following equation:
LpA = 10Log
OP
PA
2
Where:
PA = is the root-mean-square sound pressure, using the frequency
weighting network A
PO = is the reference sound pressure (PO = 20 μPa).
A-weighted sound pressure level is expressed in decibels dBA
Note: For clarity in this study LpA shall equal LAeq,T
dBA
The decibel is the unit used to measure sound pressure levels. The human
ear does not perceive all sound pressures equally at all frequencies. The
“A” weighted scale adjusts the measurement to approximate a human
ear response.
Equivalent
continuous
day/night rating
level (LR,dn)
Equivalent continuous A-weighted sound pressure level (LAeq,T) during a
reference time interval of 24 h, plus specified adjustments for tonal
character, impulsiveness of the sound and the time of day; and derived
from the following equation:
dB
Where:
LR,dn is the equivalent continuous day/night rating level;
d is the number of daytime hours;
LReq,d is the rating level for daytime;
LReq,n is the rating level for night-time;
Kn is the adjustment of 10 dB added to the night-time rating level.
High-energy
impulsive sound
Sound from one of the following categories of sound sources: quarry and
mining explosions, sonic booms, demolition and industrial processes that
use high explosives, explosive industrial circuit breakers, military ordnance
(e.g. armour, artillery, mortar fire, bombs, explosive ignition of rockets
and missiles), or any other explosive source where the equivalent mass of
TNT exceeds 25 g, or a sound with comparable characteristics and
degree of intrusiveness
Highly impulsive
sound
sound from one of the following categories of sound sources: small arms
fire, metal hammering, wood hammering, drop-hammer pile driver, drop
forging, pneumatic hammering, pavement breaking, or metal impacts
of rail yard shunting operations, or sound with comparable
characteristics and degree of intrusiveness
Impulsive sound Sound characterised by brief excursions of sound pressure (acoustic
impulses) that significantly exceed the residual noise
Low frequency
noise
Sound which predominantly contains sound energy at frequencies
below 100 Hz
Reference time
interval
Representative duration of time periods that are regarded as typical for
sound exposure of the community within a period of 24 h:
– Daytime: 06:00 to 22:00
– Night-time: 22:00 to 06:00
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
vii
Residual noise
Totally encompassing sound in a given situation at a given time, and
usually composed of sound from many sources, both near and far,
excluding the noise under investigation
Specific noise
Component of the ambient noise which can be specifically identified by
acoustical means and which may be associated with a specific source
Note: Complaints about noise usually arise as a result of one or more
specific noises.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
8
1 BACKGROUND
1.1 INTRODUCTION
Xaris Energy (Pty) Ltd has developed the Xaris Project to provide NamPower with
their required power needs of 250 MW Net Generation Capacity. The Power Project
consists of the following main elements:
A Gas Port consisting of:
o Floating Liquefied Natural Gas (LNG) Storage and Regasification – FSRU
o Sea Island – Offshore berth comprising loading platform, dolphins and
access trestle
o Gas receiving facilities and piping
Overland Natural Gas Pipelines to the Power Plant
A Power Plant using Aeroderivative Gas Turbine Technology (GE LM6000)
The planned project will impact on the environment in a number of ways and this
study only addresses the noise impact. The study was requested by the Enviro
Dynamics as part of the overall Environmental Impact Assessment for the project.
1.2 SPECIALIST STUDY LEADER
The noise impact baseline study was conducted by Dr Brett Williams who has also
conducted the following noise impact projects in Namibia:
Walvis Bay Container Terminal Extension on behalf of Namport.
Walvis Bay Desalination Plant project on behalf of Namwater.
The Sandpiper Marine Phosphate Project on behalf of Namibian Marine
Phosphate (Pty) Ltd
Gergurub Zinc Mine development by Skorpion Mining Company (Pty) Ltd
1.3 TERMS OF REFERENCE
The terms of reference for the noise impact baseline study are:
Provide a brief review of noise legislation and standards applicable in Namibia as
well as international standards and identify relevant protocols, legal and permit
requirements;
Measure the current ambient noise levels at the various component sites
comprising the project area as well.
Conduct a noise impact study of the future impact during construction of the
project infrastructure, and operation of the plant.
Assess the potential impacts of the project, and provide management actions to
avoid/reduce negative impacts or enhance benefits, as well as associated
monitoring requirements.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
9
1.4 METHODOLOGY
The methodology used in the study consisted of two approaches to determine the
noise impact from the proposed plant and associated infrastructure:
A desktop study to model the likely noise emissions from the site; and
Field measurements of the existing ambient noise at different locations in the
vicinity of the proposed mine.
1.4.1 Desktop study methodology
The desktop study was conducted using the available literature on noise impacts as
well as numerical calculations using the method described in SANS 10357:2004
version 2.1 (The calculation of sound propagation by the Concawe method). The
numerical results were then used to produce a noise map that visually indicates the
extent of the noise emissions from the site.
Two wind directions were used in the study, the prevailing wind from the west south-
east and an north-west wind. The summer and winter conditions that were used in
the modelling are presented in Table 1. These parameters were chosen for the
modelling data set and are thus approximations of the site conditions.
Table 1-1 - Meteorological parameters used in modelling
TEMPERATURE RELATIVE
HUMIDITY WIND DIRECTION
Summer
Conditions 20
0C 50% NE
Winter
Conditions 10
0C 80% WSW
1.4.2 Field Study
The methodology used consisted of field measurements of the existing ambient
noise at different locations in the vicinity of the proposed Gas Port and Power Plant
facility.
A field study was conducted on the 17th March 2015. The location of the ambient
measurement position is listed in Table 1-2 and shown in Figures 1-1
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
10
Table 1-2 – Location of ambient measurement point
TEST POINT # POSITION DESCRIPTION
TP 1 22°55'24.80"S
14°31'49.39"E
Ambient test in the closest
community in proximity to the
FSRU and Gas Pipeline Servitude.
TP 2
22°57'39.85"S
14°36'10.84"E
14°36'10.84"E
Ambient test point at Dune 7
close to the Power Plant
Figure 1-1- Locations of ambient measurement point – Power Plant
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
11
Figure 1-2- Locations of ambient measurement point – FSRU
A number of measurements were taken by placing the noise meter on a tripod and
ensuring that it was at least 1.2 m from ground level and 3.5 m from any large flat
reflecting surface.
All measurement periods were at least 10 minutes, except where indicated. The
noise meter was calibrated before and after the survey. At no time was the
difference more than one decibel (If the difference is more than 1 decibel the meter
is not calibrated properly and the measurement is discarded).
The weighting used was on the A scale and the meter placed on impulse correction,
which is the preferred method as per Section 5 of SANS 10103:2008. No tonal
correction was added to the data. Measurements were taken during the day and
night-time. The meter was fitted with a windscreen, which is supplied by the
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
12
manufacturer. The screen is designed so as to reduce wind noise around the
microphone and not bias the measurements.
The test environment contained the following noise sources:
Vehicular traffic that included trucks and cars;
Birds;
wind noise;
The instrumentation used to conduct the study was:
Rion Precision Sound Level Meter (NL32) with 1/3 Octave Band Analyzer Serial No.
00151075;
Microphone (UC-53A) Serial No. 307806;
Preamplifier (NH-21) Serial No. 13814; and
All equipment was calibrated (see Appendix).
1.5 ASSUMPTIONS AND LIMITATIONS
The following assumptions and limitations are applicable to the interpretation of the
report:
The infrastructure layout was supplied by the client.
The operational parameters were supplied by the client.
The project will operate for 24 hours per day.
The site layout details used in the modelling is not final and the positions are thus
approximations. The effect on the results will however be negligible due to the
remoteness of the Power Plant site to the nearest receptors, and the anticipated
small changes to the equipment positions if these are moved.
The lack of detailed noise emission data and information on the FSRU operation.
The engineering details of the final equipment have not been finalised.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
13
2 PROJECT DESCRIPTION
Xaris Energy Namibia (Pty) Ltd proposes to import liquefied natural gas (LNG) into
the Walvis Bay area to be re-gasified for use at a power plant that will be
constructed approximately 10 km east of Walvis Bay. The development will consist of
the following components:
Floating Storage Regasification Unit (FSRU).
Light trestle and overland pipelines for transporting the gas to the plant.
An open cycle gas turbine power plant using gas turbines at a heavy
industrial zone close to the Walvis Bay airport and Dune 7 recreational area.
2.1 POWER PLANT
The power plant will operate six General Electric LM 6000 turbines. The LM6000 is a 2-
shaft gas turbine engine equipped with a low-pressure compressor, high pressure
compressor, combustor, high-pressure turbine, and low-pressure turbine. The
dominant noise source at the plant will be the turbines. Other pumps and associated
equipment are ignored for this study as the exact design details of these are not
available yet.
2.2 FSRU
A Liquid Natural Gas (LNG) tanker will offload periodically into the FSRU which will be
permanently moored approximately 3.3km from the nearest residents of Walvis Bay.
The FSRU will pump the gas to the Power Plant via a pipeline trestle.
3 LEGAL AND REGULATORY REQUIREMENTS
Namibia does not have any directly applicable noise legislation or standards that
could be applied to the project. The draft scoping report has identified that the
applicable environmental legislation places a general onus on the developer to
ensure that the environment is not affected negatively by any development.
In view of the absence of specific noise legislation the following standards have
been used to aid the study and guide the decision making process with regards
noise pollution:
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
14
South Africa - GNR.154 of January 1992: Noise control regulations in terms of
section 25 of the Environment Conservation Act (ECA), 1989 (Act No. 73 of 1989).
South Africa - GNR.155 of 10 January 1992: Application of noise control
regulations made under section 25 of the Environment Conservation Act, 1989
(Act No. 73 of 1989).
South Africa - SANS 10103:2008 Version 6 - The measurement and rating of
environmental noise with respect to annoyance and to speech communication.
South Africa - SANS 10210:2004 Edition 2.2 – Calculating and predicting road
traffic noise.
South Africa - SANS 10357:2004 Version 2.1 - The calculation of sound
propagation by the Concawe method.
International Finance Corporation – 2007 General EHS Guidelines: Environmental
Noise.
SANS 10103:2008 provides typical rating levels for noise in various types of districts, as
described in Table 8 below.
Table 3-1- Typical rating levels for noise in various types of districts
Type of District
Equivalent Continuous Rating Level, LReq.T for Noise
Outdoors (dB(A)) Indoors, with open windows (dB(A))
Day-night Daytime Night-time
Day-night Daytime Night-time
Rural districts 45 45 35 35 35 25
Suburban districts with
little road traffic 50 50 40 40 40 30
Urban districts 55 55 45 45 45 35
Urban districts with one
or more of the
following: Workshops;
business premises and
main roads
60 60 50 50 50 40
Central business districts 65 65 55 55 55 45
Industrial districts 70 70 60 60 60 50
SANS 10103:2008 defines Daytime as 06:00 to 22:00 hours and night time as 22:00 to
06:00 hours. The applicable rating limits that were chosen for this project is the
“Industrial” limit for the power plant and “Rural” limit for the FSRU as this is the most
stringent limit.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
15
The rating levels in Table 3-1 above indicate that in rural districts the ambient noise
should not exceed 35 dB(A) at night and 45 dB(A) during the day. These levels can
thus be seen as the target levels for any noise emissions from an industrial operation.
Furthermore the South African noise control regulations describe a disturbing noise
as any noise that exceeds the ambient noise by more than 7dB. This difference is
usually measured at the complainants location should a noise complaint arise.
Therefore if a new noise source is introduced into the environment, irrespective of
the current noise levels, and the new source is louder than the existing ambient
environment by more than 7dB, the complainant will have a legitimate complaint.
The Noise Management guidelines in the IFC EHS Guidelines provide ambient noise
level guidelines for an area that can be classified as residential, institutional or
educational. The community areas around the mine can be classified as residential
areas. These guidelines state the equivalent one hour LAeq rating for noise should not
be greater than 55dBA during the day (07:00 – 22:00) and 45dBA during the night
(22:00 – 07:00) outdoors. Due to the sensitivity of the operations at the FSRU, the IFC
guidelines have not been used, as the South African limits are stricter.
4 THE RECEIVING ENVIRONMENT
The potential sensitive receptors are discussed below. The main noise sensitive
receptors that could be impacted by noise pollution are the terrestrial animals, the
avifauna and human receptors.
4.1 SENSITIVE RECEPTORS
4.1.1 Human Sensitive Receptors
The proposed Power Plant is located to the west of Walvis Bay in an area that has
been designated as a heavy industrial zone. There are no sensitive noise receptors
within 5km of the site. The airport is to the east and several mines to the south. The
outskirts of Walvis Bay is about 6km to the west. There are large dunes (including
Dune 7) bewteen the proposed site for the power plant and Walvis Bay
The FSRU berth is to north east of the shore line. The berth is approximately 3.5km
from the northern suburbs of Walvis Bay.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
16
Figure 4-1- Location of Power Plant and FSRU
4.1.2 Natural Environment Receptors
There are sensitive and proclaimed protected areas such as the Dorob National Park
in close proximity to the Power Plant site, which could be impacted upon by noise
pollution.
The FSRU is situated in a part of the bay known for marine mammal life and avifauna.
The noise impact on the marine mammals and avifauna has not been assessed as
this is beyond the area of speciality of this study.
N
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
17
4.2 RESULTS OF THE FIELD STUDY
A field study was conducted on the 17th March 2015. The results are shown in Table
4-1 below.
Table 4-1 Results of Field Study
TEST POINT START
TIME
SANS
10103
GUIDELINE
NOISE
RATING
LIMIT
L90
dB(A)
LREQ.T
dB(A) COMMENTS
TP 1
Northern suburb in
close proximity to
the pipeline
servitude and the
FSRU
18:25 45 43.8 47.0 Wind @ 3.1m/s
22:10 35 38.1 39.6 Wind @ 1.9m/s
TP 2 Power Plant
14:15 70 37.9 39.3 3 trucks and 4 cars on
D1984.
23:15 60 37.9 38.4 1 truck and 1 car on
D1984.
4.3 Environmental Vulnerability
The vulnerability of the surrounding environment was scored using the vulnerability
rating in the table below. Vulnerability refers to the susceptibility of an environmental
feature to suffer harm or its inability to withstand the effects of a hostile environment
before potential impacts are taken into account.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
18
Table 4-2 Vulnerability Rating Criteria
VULNERABILITY
RATING CRITERIA
LOW
The environmental feature will be negligibly affected by the
potential impact and has the ability to withstand negative effects
without being adversely affected.
MEDIUM
The environmental feature will be moderately susceptible to suffer
harm and will therefore be negatively affected by the activity
albeit not adversely.
HIGH
The environmental feature will be severely affected by the
potential impact as it is highly susceptible to suffer harm and lacks
the ability to withstand the negative effects of the activity.
Table 4-3 Vulnerability Rating
COMPONENT SENSITIVITY VULNERABILITY POTENTIAL IMPACT
Surrounding
communities and
the natural
environment to
noise emissions from
the plant during
Construction
Surrounding communities
and the natural
environment could be
disturbed by the noise
Medium Noise disturbance and
annoyance
Surrounding
communities and
the natural
environment to
noise emissions from
the plant during
Operation
Surrounding communities
and the natural
environment could be
disturbed by the noise
Medium Noise disturbance and
annoyance
Surrounding
communities and
the natural
environment to
noise emissions from
the plant during
Decommissioning
Surrounding communities
and the natural
environment could be
disturbed by the noise
Medium Noise disturbance and
annoyance
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
19
5 NOISE IMPACT ASSESSMENT
The data collected during the site visit and subsequent communication with the
client was used to model the future noise impact on the receiving environment.
5.1 Noise Impact during the Construction Phase
The impact of the construction noise that can be expected at the proposed site can
be used from previous projects that the author has conducted. As an example, if a
number of pieces of equipment are used simultaneously, the noise levels can be
added logarithmically and then calculated at various distances from the site to
determine the distance at which the ambient level will be reached.
Table 5-1 Combining Different Construction Noise Sources – High Impacts (Worst Case)
DESCRIPTION
TYPICAL
SOUND
POWER
LEVEL (DB)
Mobile cranes 109
Front end loaders 100
Excavators 108
Bulldozer 111
Total* 114.4
*The total is a logarithmic total and not a sum of the values.
Table 5-2 Combining Different Construction Noise Sources – Low Impacts
DESCRIPTION
TYPICAL
SOUND
POWER
LEVEL (DB)
Front end loaders 100
Excavators 108
Truck 95
Total 111.8
The information in the above tables can now be used to calculate the attenuation
by distance. Noise will also be attenuated by topography and atmospheric
conditions such as temperature, humidity, wind speed and direction etc. but this is
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
20
ignored for this purpose. Therefore, the distance calculated below would be
representative of maximum distances to reach ambient noise levels.
The table below gives an illustration of attenuation by distance from a noise of 114dB
(Sound Power) measured at the source.
Table 5-3 Attenuation by Distance for the construction phase (worst case)
DISTANCE FROM
NOISE SOURCE (METRES)
NOISE LEVEL
DB(A)
10 86
20 80
40 74
80 68
160 61
320 54
640 47
1280 37
What can be inferred from the above table is that if the ambient noise level is at 38
dBA as measured at Test Point Number 2, the construction noise will be similar to the
ambient level at approximately 1280m from the noise source, if the noise
characteristics are similar. Beyond this distance, the noise level will be below the
ambient noise and will therefore have little or no impact. Due to the absence of
sensitive human noise receptors in close proximity to the Power Plant and FSRU, the
construction noise impact will be negligible.
5.1.1 Conclusion - Construction Noise
The predicted noise from the construction activities is unlikely to affect the residents
of Walvis Bay.
5.2 Noise Impact of the Gas Power Station
The predicted noise levels emissions were calcualted using Sound Power levels that
were provided by the client. This was to provide an estimation of the noise energy
produced by the equipment.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
21
The following values were used to predict the noise impact. The list below is not
exhaustive as only the major noise producing equipment was modelled based on
the limited information available.
Table 5-4 Sound Power Levels used in the Modelling
SOURCE
# DESCRIPTION
TYPICAL SOUND POWER
LEVEL (dB)
S1 LM6000 Gas Turbine Units – Six units all
operational and acoustic enclosures
fitted to each unit.
106
S2 FSRU - FSRU docked and performing
normal regasification and offloading
operations.
118
The above data was then used to calculate the noise impacts from the Power Plant
and the FSRU. The noise impacts from the operations at the Power Plant and FSRU
are shown in the figures below.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
22
Figure 5-1 - Modelling Results – Power Plant
Key: Green = <30 dB(A) ; Yellow = >30 dB(A); Orange = >35 dB(A); Red = >45 dB(A)
N
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
23
Figure 5-2 - Modelling Results – FSRU
Key: Green = <30 dB(A) ; Yellow = >30 dB(A); Orange = >35 dB(A); Red = >45 dB(A)
N
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
24
Figure 5-3 - Modelling Results – Power Plant & FSRU
Key: Green = <30 dB(A) ; Yellow = >30 dB(A); Orange = >35 dB(A); Red = >45 dB(A)
N
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
25
Figure 5-4 - Modelling Results close-up of FSRU
Key: Green = <30 dB(A) ; Yellow = >30 dB(A); Orange = >35 dB(A); Red = >45 dB(A)
5.2.1 Conclusion – Power Plant
The predicted noise from the Power Plant is unlikely to have any adverse effect on
Walvis Bay due to the distance (approximately 6.5 km) from the noise source.
5.2.2 Conclusion – FSRU
The predicted noise from the FSRU is unlikely to have any adverse effect on Walvis
Bay due to the distance (approximately 3.5 km) from the noise source. As can be
seen in Figure 5-4 it may be possible to hear the noise from the FSRU under light wind
and sea conditions on the shoreline. Beyond the shoreline the ambient noise will
have a masking effect and be below the predicted 35dB(A) limit.
N
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
26
5.3 ASSESSMENT OF NOISE IMPACT
The noise impact summary rating of the various key issues is presented below.
Table 5-5: Impact assessment of the proposed project
POTENTIAL
IMPACT
STATUS/
NATURE EXTENT DURATION INTENSITY PROBABILITY
DEGREE OF
CONFIDENCE
SIGNIFICANCE
PRE-
MITIGATION
MITIGATION/
ENHANCEMENT
POST-
MITIGATION
CONSTRUCTION PHASE
Construction
Noise Impact Negative Local Temporary Low Improbable High Low Noise Monitoring Low
OPERATIONAL PHASE
Operational
Noise Impact
(Power Plant)
Negative Local Long Term Low Improbable High Low Noise Monitoring Low
Operational
Noise Impact
(FSRU)
Negative Local Long Term Low Improbable High Low Noise Monitoring Low
DECOMMISSIONING PHASE
Decommissioning
Noise Impact Negative Local Temporary Low Improbable High Low Noise Monitoring Low
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
27
5.3.1 Comparison to IFC Environmental Noise Guidelines
Power Plant
The IFC Environmental Noise Guidelines require a daytime limit of 55dB(A) and a
night time limit of 45 dB(A). The daytime limit is not exceeded further than
approximately 200m from the Power Plant and the night time limit further than
approximately 580m from the Power Plant. No noise sensitive receptors were
identified within these distances to the plant.
FSRU
The IFC 55dB(A) daytime limit is not exceeded further than approximately 800m
from the FSRU and the IFC 45dB(A) night time limit further than approximately 1300m
from the Power Plant. No noise sensitive human receptors were identified within
these distances to the FSRU.
5.3.2 Mitigation - Construction
a) It is recommended that vehicles with low noise emissions be used during
construction and that these vehicles at least comply with the Namibian Road
Traffic Regulations for noise level emissions.
b) Blasting should only occur if there are no signs of marine mammals or avifauna in
the immediate vicinity of the blast area.
c) All construction personnel should be given noise pollution sensitivity training.
d) Noise emissions should be monitored during construction.
5.3.3 Mitigation - Operation
Given that it is not possible to eliminate all noise during the operational phase, the
following general recommendations are made:
a) The International Finance Corporation guidelines for noise reduction in new
developments should be implemented. These include:
Selecting equipment with lower sound power levels;
Installing suitable mufflers on engine exhausts and compressor components;
and
Where possible, installing acoustic enclosures for equipment to stop noise at
source. This is especially important on the FSRU. The intake air ducts and
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
28
exhaust ducts as well as the gas turbine units at the Power Plant should be
attenuated.
5.3.4 Recommended Monitoring
The following noise monitoring is recommended:
a) Noise monitoring during the construction phase along the shoreline at Walvis Bay
as well as the Power Plant site boundary; and
b) Noise monitoring during the operational phase at the nearest Walvis Bay
communities to the FSRU and Power Plant.
6 CONCLUSION
The following conclusions can be drawn from the results of the study:
There will be a short term increase in noise in the vicinity of the FSRU berth and
Power Plant during construction as the ambient level will be exceeded in areas
very close to the construction sites. The impact will however not be significant
due to the short duration.
The noise impact from the Power Plant and FSRU during operations will be
minimal due to the distance from the nearest noise sensitive receptors;
The noise impacts from the decommissioning and rehabilitation of the site will be
of short term nature and the will be similar to the construction phase.
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
29
7 REFERENCES
International Finance Corporation – 2007 General EHS Guidelines: Environmental
Noise.
South Africa - GNR.154 of January 1992: Noise control regulations in terms of section
25 of the Environment Conservation Act (ECA), 1989 (Act No. 73 of 1989)
South Africa - GNR.155 of 10 January 1992: Application of noise control regulations
made under section 25 of the Environment Conservation Act, 1989 (Act No. 73 of
1989)
South Africa - SANS 10210:2004 Edition 2.2 – Calculating and predicting road traffic
noise
South Africa - SANS 10357:2004 Version 2.1 - The calculation of sound propagation by
the Concawe method)
South Africa - SANS 10103:2008 Version 6 - The measurement and rating of
environmental noise with respect to annoyance and to speech communication.
---------------------------
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
30
APPENDIX A – POWER PLANT LAYOUT
ESIA FOR THE PROPOSED DEVELOPMENT OF THE XARIS ENEREGY WALVIS BAY POWER PLANT PROJECT
ENVIRO DYNAMICS CC
10TH APRIL 2015
31
APPENDIX B – CALIBRATION CERTIFICATE