Www.see-grid-sci.eu SEE-GRID-SCI Ognjen Prnjat, Project Coordinator GRNET NA1: Project...
-
Upload
ellen-sullivan -
Category
Documents
-
view
219 -
download
1
Transcript of Www.see-grid-sci.eu SEE-GRID-SCI Ognjen Prnjat, Project Coordinator GRNET NA1: Project...
www.see-grid-sci.eu
SEE-GRID-SCI
Ognjen Prnjat, Project CoordinatorGRNET
NA1: Project Administrative and Technical Management
PSC07 Meeting, Zabljak, 22-23 February 2010
The SEE-GRID-SCI initiative is co-funded by the European Commission under the FP7 Research Infrastructures contract no. 211338
NA1 Objectives
Ensure the consistency of the overall resources used and the work performed.Control the progress of the work so the results of the project adhere to the grant agreement.Organise and co-ordinate the production of deliverables, meetings, workshops.Resolve any project internal conflicts and build accountability into the project's work.Report on project progress to the EC and to potential project sponsors.
PSC07 meeting, Zabljak, 22-23/02/10
NA1 Activities
NA1.1 - Organize meetingsNA1.2 - Establish and maintain project management information systemNA1.3 - Establish and maintain “grant agreement” relationshipsNA1.4 - Prepare 3-monthly, yearly and final progress reportsNA1.5 - Prepare cost statements and transfer interim paymentsNA1.6 - Assess the project deliverables and conformance to requirements
Lead: GRNET; A1.6 UoM
PSC07 meeting, Zabljak, 22-23/02/10
NA1 Deliverables and Milestones
DNA1.1 - Project management information system and “grant agreement” relationships - M01 - GRNETProject notebook
+ 6 Quarterly reports and 1st year reports
MNA1.1 Kick-off meetingMNA1.2 Successful completion of first year reviewMNA1.3 Successful completion of project - final project audit
PSC07 meeting, Zabljak, 22-23/02/10
NA1.1: Organization of meetings
PSC01 Athens 05/08; SEE-GRID-2 reviewPSC02 Belgrade 09/08EVO1 11/08PSC03 Bucharest 01/09; meteorology workshopPSC04 Sofia 05/09; environmental workshopPSC05 09/09 DubrovnikPSC06 12/09 + User Forum (regional dissemination) + Regional users training– IstanbulPSC07 22-23/03/09 – Zabljak, ME - to coincide with conference
Project review: 24th June, Athens. Attendance: Activity leaders and PO only. Costs claimable to the project.
PSC07 meeting, Zabljak, 22-23/02/10
NA1.2: Establish and maintain project management information system
Notebook is an effective and living document; a set of spreadsheets with full project management information
Activity NameActivity
ID: 1A4
Planned start dateActual start dateResponsibleParticipants GRNET CERN IPP ICI TUBITAK SZTAKI ASA-INIMA UoBL UKIM UOB UOM RENAM RBI TOTAL
Planned person-months 0,40 0,30 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,70
To: SEE-GRID-2 consortium
From:
Investigate additional sources of funding and cooperation
Disseminate Project results & get feedback
Project brochure,Project presentation,Project workshops,Project website
Obtain additional sources of funding & cooperation
From: SEE-GRID-2 consortium
Input Objectives OutputProject Notebook Provide expert opinion on technical matters & help seeking
additional supportEstablish Industrial Advisory Board
From: SEE-GRID-2 consortium To: SEE-GRID-2 consortium
Ognjen Prnjat GRNET
1/5/2006 Actual end date Actual duration
Participate in liaison activities with other projects
1/5/2006 Planned end date 30/4/2008 Planned duration 24 months
From:
PSC07 meeting, Zabljak, 22-23/02/10
NA1.3: Establish and maintain “grant agreement” relationships and other
agreements
Contract amendment now finalized, payments from EC will happen ASAP, but first partners must insert form C data!
Consortium Agreement
MoUs: EELA2; Belief; EGEE3; GENESI-DR; EDGES
PSC07 meeting, Zabljak, 22-23/02/10
NA1.4: Prepare 3-monthly, yearly, final progress reports
This task will coordinate the preparation of interim (quarterly) and periodic (yearly) progress reports covering the status of project major achievements, Activity progress (including any deviations and corrective actions taken), use and dissemination of project results, monitoring of milestones, ongoing tasks and resource consumption. Quarterly Reports 7th QR input deadline Friday 19th February, don’t delay.
PSC07 meeting, Zabljak, 22-23/02/10
NA1.4: Resource Consumption
Travel consumption is lower (Use you budget for travel)
PSC07 meeting, Zabljak, 22-23/02/10
NA1.4: Main problems identified & corrective actions
AL application
PSC07 meeting, Zabljak, 22-23/02/10
NA1.5: Prepare costs statements and transfer advance/interim payments
Total EC pre-financing is up to 90% of maximum EC contributionThe remaining 10% will be paid after the approval of final reports plus the 5% guarantee fund which was withheld from 1st EC prepayment As a result we expect to receive 250K euro now that Forms C are submitted in NEF and approvedThis is hardly enough to cover the 6Q expenses that were not being paid in the previous pre-financing and 7Q expensesAll partners should afford to pay their last Q expenses with their own funds until final reports are sent and approved by EC
Organisation short name
EC maximum contribution for
the entire project
Budget allocation from total advance
payment received
*Revised* 2Q planned
prefinancing
*Revised* 3Q planned
prefinancing
112.016 56.008 0,00 € 4.842,00 €
103.985 51.992 14.135,00 € 15.363,00 €
210.529 105.265 39.372,00 € 32.367,00 €
80.075 40.038 3.904,00 € 0,00 €
259.501 29.750 6.448,00 € 8.276,00 €
112.558 56.279 15.798,00 € 7.681,00 €
69.016 34.508 4.000,00 € 10.000,00 €
72.210 36.105 3.814,00 € 6.464,00 €
UoBL
RBI
UOB
IIAP NAS RA
UOM
RENAM
UKIM
GRENA
PSC07 meeting, Zabljak, 22-23/02/10
NA1.6: Assess the project deliverables and conformance to requirements
Lead: UoMExternal reviewer of project deliverablesImplement and perform appropriate quality control on project deliverables in order to ensure that they conform to the high quality and standards of the project goals QC effectively helps to double-check the quality of the work of the projectPerformed on all deliverables
DELIVERABLE DELAYS ISSUE
PSC07 meeting, Zabljak, 22-23/02/10
Review Recommendations
DJRA1.5 suggested ToC and content.
JRA1 leader and the responsible deliverable editor ICI / Gabriel should consider this recommendation carefully.
PSC07 meeting, Zabljak, 22-23/02/10
Review Recommendations
"In the second year of the project, the partners will need to place more emphasis on dissemination of the scientific outputs from the project".
Travel funds available, and publications should be made in refereed conferences and journals, with an emphasis to conferences in scientific field of interest.Also NA4 leader and DNA4.4 editor RBI-Davor should consider this recommendation carefully.
PSC07 meeting, Zabljak, 22-23/02/10
Review Recommendations
For all activity leaders: "Based on the tools and applications being developed, in the 2nd year of the project the consortium should attempt to get additional users and stakeholders from outside the project involved." The external collaboration has to be intensified, specifically: JRA1 should promote OTs and ASsNA4 the applications should be advertised in wider communitySA1 tools and procedures should be presented to other projects.
PSC07 meeting, Zabljak, 22-23/02/10
NA1 risk & issues
Personnel and skills in Albania, Moldova Applications
Deliverables timeline for release not followed
PSC07 meeting, Zabljak, 22-23/02/10
NA1 actions
Grant agreement: amendment being finalized by ECPartners must enter data in NEFPayments to partners
BSI MoU: collaboration exists despite they MoU: closed
DJRA1 deliverable to be carefully writtenMore publicationsJRA1 should promote OTs and AssNA4 the applications should be advertised in wider communitySA1 tools and procedures should be presented to other projects.
PSC07 meeting, Zabljak, 22-23/02/10