Www.electranet.com.au Slide 1 Munno Para Substation and the role of ElectraNet Accessing Mining and...
-
Upload
trevin-turnock -
Category
Documents
-
view
214 -
download
0
Transcript of Www.electranet.com.au Slide 1 Munno Para Substation and the role of ElectraNet Accessing Mining and...
www.electranet.com.au
Slide 1
Munno Para Substation and the role of ElectraNet
Accessing Mining and Major Projects 2012May 2012
ElectraNet Slide 2
Presentation Outline
Industry Structure and the Role of ElectraNet
New Generation and Network Development
Munno Para
www.electranet.com.au
Slide 3
Industry Structure and Overview
ElectraNet Slide 4
About ElectraNet Private Transmission Infrastructure Company
Principal Transmission Network Service Provider (TNSP) in SA
ElectraNet owns and manages the SA transmission system in the National Electricity Market (NEM)
Comprises about 6,000 circuit kilometres of transmission line
88 substations
Asset value around $1.9bn
Turnover >$300m pa
Employs over 270 staff
Private Transmission Infrastructure Company
Principal Transmission Network Service Provider (TNSP) in SA
ElectraNet owns and manages the SA transmission system in the National Electricity Market (NEM)
Comprises about 6,000 circuit kilometres of transmission line
88 substations
Asset value around $1.9bn
Turnover >$300m pa
Employs over 270 staff
ElectraNet Slide 5
QLD
NSW
SNOWY
VIC
TAS
SA
400 MW
1000 MW
1900 MW
680 MW
677 MW
450 MW
1078 MW
1100 MW
3000MW
Existing Interconnector(export direction)
WA
NT
National Electricity Market (NEM) Grid
600 MW
Total Demand: 38,842 MW
National Electricity Market is
made up of five regions joined
by transmission interconnectorsQld
8,891 MW
NSW
14,289 MW
Vic
10,459 MW
SA
3,413 MW
Tas
1,790 MW
ElectraNet
Role of Transmission in the Market
Slide 6
Build, operate and maintain the electricity transmission ‘highways’ that transport electricity from generators and interconnectors to distribution networks and large direct connect industrial customers.
Supply competitive electricity transmission services and high levels of safety and reliability for the benefit of customers.
Competitive Regulated Monopolies Competitive
ElectraNet Slide 7
Network Service Provider (NSP)
Network Companies are common carriers of generators’ and/or retailers’ energy on a non-discriminatory basis, but are NOT responsible for:
– the generation of electricity– the trading or setting of Spot Price for electricity– the operation of the National Electricity Market
Networks provide:
– least cost transport for generators– reliable and secure power delivery for customers– access to competitive market for participants
ElectraNet
South Australian Energy Consumption by Source
Slide 8
Trends are:
• Coal from 35% to ≈ 30% - slow decline but relatively constant
• Gas from high of 55% to 45% - ramped up to replace interconnector then declined
• Wind from 5% to >20% - growing source, SA Govt target is 33% in 2010
• Net Interconnector from high of 18% to low of 0% to 5%
ElectraNet Slide 9
South Australian Emission Levels
South Australian electricity emissions are continuing to trend down and are nearly 20% down on 2004/05 peak
www.electranet.com.au
Slide 10
Role of ElectraNet
ElectraNet Slide 11
The Roles and Expectations on Transmission
Fundamental role – reliable delivery of bulk electricity supply to major load centres
The vast majority of ElectraNet’s five-year investment program is reliability driven: i.e. by the need to “keep the lights on” in the face of ever increasing demand
Investment is only just keeping pace with load growth – just-in-time is the credo
The reliability impacts of transmission failures can be severe (e.g. US and London blackouts)
ElectraNet Slide 12
The Roles and Expectations on Transmission
Additional role – delivering potentially lower prices by facilitating competition between generators both intra-state and inter-state
Competition can be lessened and consumers can be worse off if there is inadequate transmission transfer capacity
Unlike for reliability, outcomes to date have been sub-optimal – there have been high wholesale price events - focus has been more on developing a National Electricity Market than a National Electricity Grid – this is changing
ElectraNet 13
Investment and Reliability of Supply
“Figures around recent and projected price rises are regularly cited in media reports
What is less frequently mentioned are the costs to consumers and the costs to business from a lack of reliability because of underinvestment.
Lack of reliability in our electricity supply would threaten jobs, threaten business and undermine our economic prosperity.
This is why it is so important to get the balance right, why it is vital that we don’t stand in the way of required investment…”
“Energy networks play a crucial role in bringing reliable energy to households and businesses – they are the foundation of our modern economy”
Source: Martin Fergusson speaking at ENA Smart Networks Summit, 18 May 2011
www.electranet.com.au
Slide 14
New Generation and Network Development
ElectraNet
Renewable and Emergent Technology in SA
20102012
20122014
20142016
20162018
20182020
20202022
20222024
20242026
20262028
20282030
Coal to Liquids
Geothermal
Wind
Wave
Solar
Slide 15
Feasibility Studies Construction PilotDemonstrationCommercially available
Grid connection
An optimistic view of timelines …
Wind is presently the only mature technology; however, Solar thermal is improving and all should reach ‘Grid Parity’ by ≈2016
ElectraNet 16
Wind Generation Connection Outlook
South Australia has about half of the nation’s installed wind capacity
~1,200 MW operational and under construction
20% of annual energy requirements are now met by wind
Significant potential for further development (SA Govt target = 33% by 2020)
Capacity for total wind connections of approx. 2,300 MW
Beyond this requires significant transmission investment; e.g. Eyre Peninsula
ElectraNet
Wind Projects Summary 2011
Waterloo (111MW)
Clements Gap (57MW)
Snowtown S1 (99MW)
Starfish Hill ETSA (35MW)
Wattle Point (91MW)
Lake Bonney S1 (81MW)
Lake Bonney S2 (159MW)
Lake Bonney S3 (39MW)
Canunda (46MW)
Cathedral Rocks (66 MW)
Mount Millar (70MW)
Hallett S1 Brown Hill (95MW)
Hallett S4 North Brown Hill (132MW)
Hallett S2 Hallett Hill (71MW)
Hallett S5 The Bluff (53MW)
Willogoleche (50MW)
Hallett S3 Mt Bryan (99MW)
Robertstown (90MW)
Stony Gap (99MW)
Snowtown S2 (206MW)
Kongorong (120MW)
Allendale (69MW)
Mount Hill (80MW)
Barn Hill (124-186MW)
Kulpara (109MW)
Lincoln Gap (177MW)
Carmody’s Hill (140MW)
Robe (600MW)
Registered/Operating
Under Construction
Future Pipeline
Legend
Woakwine (300-600MW)
Keyneton (120MW)
Collaby Hill (150MW)
Yorke Peninsula (600MW)
ElectraNet Slide 18
Future Retail Electricity Prices
31% nominal increase over three years
76% of increase is related to wholesale energy and distribution costs
7% of increase is due to transmission costs
Source: AEMC Report, 30 Nov 2010.
Figures are representative for customers on standing offer contracts
ElectraNet Slide 19
Future Retail Electricity Prices
Network costs drivers…– increasing levels of capital
works to meet growing demand and replace ageing assets
– higher rates of return due to increase in debt premiums following GFC
– higher input costs as commodities market recovers from GFC
– Changes in reliability standards
Source: AEMC Report, 30 Nov 2010.
www.electranet.com.au
Munno Para Substation
Slide 20
ElectraNet Slide 21
Background
A substation is required in the Munno Para region. This facility will provide the bulk supply connection point between the 275 kV line delivered by ElectraNet and the 66 kV distribution supply required by ETSA Utilities.
This need was identified after examining supply issues for the northern suburbs 66 kV network. The identification process followed procedures established by the National Electricity Rules. The options considered were subjected to Regulatory Test
The process confirmed the necessity to construct the infrastructure in this region, with an energisation date of November 2014.
ElectraNet Slide 22
Background … continued
The preferred site was deemed to be must suitable because:
– It is located at the connection point between existing 275 kV and 66 kV transmission lines;
– It is a level undeveloped site;
– The land available is of suitable size;
– It has minimal residential development in the vicinity; and
– There is an established corridor of trees bordering the road frontages.
ElectraNet Slide 23
LMC:FutureResidential
Seagas Pipeline
Enet Transmission Line
Dwellings
Dwelling
Dwelling
ETS
A U
tiliti
es L
ine
CFS Depot
300 m
Proposed ETSA Utilities Site
Proposed substation site(Not to Scale)
Proposed DTEI Site
Munno Para Substation SiteLot 1000 DP 43447Acquisition Area 12.0 ha (subject to survey)
Note: Area required for the substation site is approximately 10Ha. This allows for current works, future upgrades, and an appropriate buffer zone.
ElectraNet boundary (indicative)
ETSA Utilities Boundary (indicative)
DTEI boundary (indicative)
Allotment Boundary
ElectraNet Slide 24
ETSA Utilities also requires land on which to construct their distribution infrastructure. ETSA will therefore also be a party to this development.
DPTI also have secured an adjoining site on which to construct infrastructure for the electrification of the Gawler railway line.
Acquisition Partners
ElectraNet Slide 25
Munno Para site – existing 275 kV transmission line.
ElectraNet
Development Timeline
Slide 26
Site secured
December 2011
Specifications Developed
Contracts awarded
Jan 2012
Detailed Design Jan
2013
Civil Works commence
Sep 2013
Substation Energised
November 2014
ElectraNet Slide 27
Picture of visualisation
Visualisation of Munno Para Substation
View from Dalkeith Rd, CFS Depot in the foreground
www.electranet.com.au
Slide 28
Questions?