OrganizationDatePresenters:• Mark Gaines, PE, WSDOT Bridge & Structures Engineer• Tim Moore, PE, SE, WSDOT Mega Project Bridge Manager• Jim Parkins, PE, Concrete Technology Corp
WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 Seattle Tunnel Precast Deck
August 22, 2019
![Page 2: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/2.jpg)
Building a new SR 99 Corridor
$3.2 B Replacement Program includes $1.4B Design-Build Tunnel 2
![Page 3: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/3.jpg)
This is a SAFETY project
The viaduct in 1953
The viaduct and neighboring seawall are vulnerable to earthquakes
3
![Page 4: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/4.jpg)
Meet Bertha, the SR 99 Tunnel Boring Machine
57’ – 4 ½” Overcut6700 tons10 bar pressure88M lbs thrust24ea by 750 hp drive motors 0-2 rpm24 Mw operating
4
![Page 5: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/5.jpg)
56’ DiameterTunnel DesignElectrical rooms
Equipment rooms
Egress corridor
Pump station
Utility corridor
Smoke extraction
duct
56’ Outside Diameter
5
![Page 6: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/6.jpg)
Construction Timeline2015 2016 2017 2018 2019
SR 99 Tunnel Project
Cast-in-Place NB Roadway Construction (Est)
Viaduct Demolition
Tunnel open to drivers (Feb. 4)
Mechanical, Electrical and Plumbing Systems
SB Portal Frame
NB Deck
Precast NB Deck
8 month Time Savings
Tunnel Boring, 1 yr
Tunnel Boring Machine Repair, 2 years
6
![Page 7: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/7.jpg)
Temporary Tunneling Elements
• Ventilation Duct
• Muck Conveyor
• Liner Panel Delivery Vehicle
7
![Page 8: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/8.jpg)
The tunnel behind Tunnel Boring Machine, TBM,
named Bertha, August 18, 2016
BUILDING THE HIGHWAYinside the tunnel
8
![Page 9: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/9.jpg)
BUILDING THE HIGHWAYinside the tunnel
Begin Precast Installation
9
![Page 10: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/10.jpg)
BUILDING THE HIGHWAYinside the tunnel
10
![Page 11: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/11.jpg)
BUILDING THE HIGHWAYinside the tunnel
Interior roadway construction
STP crews build the rebar cage for future roadway
walls
11
![Page 12: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/12.jpg)
• Panel Length 29’-9 1/2”• Panel Width 8’- 0”• Panel Depth 14 1/2”• Total # of Panels 1152 ea.• f’c = 7.0 ksi• Pre-Tensioned Transversely• Post-Tensioned Longitudinally• STP and HNTB Idea
NB Roadway Slab
Clear opening – 33’- 4” to deliver and rotate panel (3.5’ added clearance)
12
![Page 13: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/13.jpg)
Northbound Lower Roadway Pre-stressed Post-Tensioned Slab with O’Lay
BUILDING THE HIGHWAYinside the tunnel13
![Page 14: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/14.jpg)
Typical Unit of 25 panels – Length is 201’ (47 Units)
Middle panel is anchored to corbels with five – 5/8” threaded rods per each bearing.
PT Design Objective – Connect slab girders together to produce 250 psi compression after all losses per AASHTO 5.14.4.3 and prohibit tension cracking in the top surface that can be reflected through the overlay.
Direction of Traffic
14
![Page 15: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/15.jpg)
29’
Bearings
Bearings
Plan View – Finite Element Model
8’ Wide Panel
15
Traffic Direction
![Page 16: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/16.jpg)
16
![Page 17: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/17.jpg)
17
![Page 18: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/18.jpg)
PT Anchorage Slab
• Strut & Tie Model• Bursting & Splitting
Reinforcement within panel
18
![Page 19: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/19.jpg)
Panel Width Determination• Minimize total joints• Maximum allowable width for plant casting• Maximum weight for handling/rotation inside tunnel• Maximum weight for standard flatbed truck (cost and avoid travel curfew)• 8’ selected as optimized width
19
![Page 20: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/20.jpg)
Longitudinal Shear Key between PanelsMatch Cast vs. Standard• Standard key provides more tolerance• Standard key allows articulation along horizontal curve• Match cast has faster field installation• Match cast erecting sequence has little flexibility• Match cast will increase plant fabrication cost significantly
Match-cast Standard
20
![Page 21: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/21.jpg)
Tunnel Orientation vs. Casting Bed Layout
21
![Page 22: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/22.jpg)
• 7 pcs. on 250’ casting bed typical• 3 pcs. for slabs with PT anchor
22
![Page 23: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/23.jpg)
UTILITY COORDINATION- Contract drawings specify 4 total types of panels
23
![Page 24: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/24.jpg)
UTILITY COORDINATION- Contract drawings specify 4 total types of panels
24
![Page 25: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/25.jpg)
UTILITY COORDINATION- Contract drawings specify 4 total types of panels
25
![Page 26: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/26.jpg)
UTILITY COORDINATION- 4 mark numbers turned into 304
26
![Page 27: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/27.jpg)
Rules for Utility Coordination Developed• Prestressing strands treated
as immovable objects • Raised strand c.g.• Conventional rebar can be
adjusted• Standardize locations of
inserts as much as possible
27
![Page 28: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/28.jpg)
Why Mark Number Control is ImportantIncreased mark numbers increases costs for:• Drafting and project management• Yard stockpiling• Shipping sequence• Erection
28
![Page 29: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/29.jpg)
Other Production Considerations• Custom form sides for precision alignment of PT duct
29
![Page 30: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/30.jpg)
Concrete Properties• Release strength, f’ci = 5.6 ksi, achieved in 10 hour cure for daily turnover
• Type III cement• Low w/c ratio• Accelerated curing
• Release strength is a calculated value, not a ratio of service strength• Self-consolidating concrete used
30
![Page 31: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/31.jpg)
31
![Page 32: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/32.jpg)
Production Summary• 1,152 pieces total• Cast seven pieces per day typical, 5 days a week• Total duration of casting was 9 months
32
![Page 33: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/33.jpg)
Quality Control• CTC provided quality control;
• Fresh concrete testing; slump flow, j-ring, unit weight, air content, temperature
• Hardened concrete testing (compression cylinders)• Pre-pour inspection• Post-pour inspection• Documentation of non-conformances, re-work and completion of
repair• Raw material test reports from suppliers• Aforementioned compiled into certificate of conformance packet• Review and approved by STP
33
![Page 34: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/34.jpg)
Global Tolerance Mitigation• Three – 3’ long CIP closures provided at north end of tunnel to absorb
accumulated tolerances for fabrication and erection
Lessons Learned• Mark number control was acceptable, but could be improved by;
• Utilize longer “track type” inserts• Utilize inserts with greater flexibility fore/aft, and lateral• Utilize suspension system with greater flexibility
• Tradeoffs of increased cost for more flexible MEP solutions vs. higher plant production costs for increased mark numbers
Manufacturer Perspective• WSDOT and contractor engaged CTC early and often to optimize the
precast slab option, which provided great returns upon execution for all parties
34
![Page 35: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/35.jpg)
35
![Page 36: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/36.jpg)
36
![Page 37: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/37.jpg)
3” by 7’ long bearing consisting of two 1/8” Ultra High Molecular Weight, UHMW, Strip bonded to ¼” Neoprene Strip with thin layer of silicone grease between bearings. 37
![Page 38: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/38.jpg)
38
![Page 39: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/39.jpg)
MEP Prior to Setting Panels
39
![Page 40: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/40.jpg)
40
![Page 41: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/41.jpg)
41
![Page 42: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/42.jpg)
Mono-strand ram with curved jack chair fits in dual anchorage blockouts.
42
![Page 43: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/43.jpg)
PT Operation – 201’ Stressing Length 43
![Page 44: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/44.jpg)
Deck Preparation by Shotblasting –Roughen and Clean 44
![Page 45: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/45.jpg)
45
![Page 46: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/46.jpg)
Dow Corning 902 RCS Silicone Sealant Joint
46
![Page 47: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/47.jpg)
47
![Page 48: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/48.jpg)
Lessons Learned
• Tyne top surface of panels during panel casting
• Evaluate super-elevation transition areas for bearing flatness
• Expansion joint polymer header
48
![Page 49: WSDOT’s Alaskan Way Viaduct Replacement Project: SR-99 ... · 8/22/2019 · Global Tolerance Mitigation • Three long CIP closures provided at north end of tunnel to absorb –](https://reader034.fdocuments.us/reader034/viewer/2022051606/601dce940e19e941627dd38a/html5/thumbnails/49.jpg)
Questions?49