The SEE-GRID-2 initiative is co-funded by the European Commission under the FP6 Research Infrastructures contract no. 031775
www.see-grid.eu
SEE-GRID-2
WP2 – Studies and Strategies for sustainable operational, organizational
and policy schemes
Progress Report – preliminary versionPSC06 Meeting
Gabriel NeaguWP2 Leader
National Institute for R&D in Informatics – ICI, [email protected], www.ici.ro
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 2
NGI Sustainability indicators for the 2-nd project year
General remarks on the Progress report content: It is focused on received contribution per country on NGI indicators
Partners not being able to provide their contributions before are invited to report during the meeting
Should be considered as un updated version of the report for the PSC05 meeting
Additional information reported for September – November period is presented in Italics for both achieved results and updates to the 2nd project year plan
This cumulative document is intended as the main input for the second version of D2.3 deliverable
Statistics are presented at the end on the addressed NGI Indicators from both planning and achieved results perspectives
The Further Work section of the report includes WP2 open positions in the AP Register
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 3
NGI Sustainability indicators for the 2-nd project year
NGI setup and recognition NGI organization and Consortium expansion NREN cooperation eInfrastructure national strategy National Policy documents eIRG plans National-level projects Other sources of funding in grid area including related projects Industrial cooperation Technical independence i.e. national-level services Expansion of national infrastructure Sites migrated to EGEE production Expansion to new applications and user communities
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 4
Albania
Plan for the 2-nd project year NGI setup and recognition
The launch of NGI is planned for September 2007 National-level projects
Several proposals would be submitted to Ministry of Education and Science, regarding both Grid infrastructure and applications
Other sources of funding in grid area including related projects The support is expected from bilateral and regional (SEE-ERA.NET)
projects Expansion of national infrastructure
Extension of existing sites (INIMA, FIE, FNS), and inclusion of new sites (FECO and universities of Elbasani and Shkodra)
Expansion to new applications and user communities Expansion into new domains, such as meteorology and seismology
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 5
Albania
Report on May-November 2007: NGI setup:
JRU signed between rectors of University of Tirana and Polytechnic University of Tirana
Plans to launch it in September delayed– Reorganization of INIMA– Plans for next PSC meeting in Sarajevo– Pre-election situation in universities
National projects One joint project-proposal was presented to Ministry in framework of
national programme for R&D in IT, focused on – Infrastructure improvement– Evaluation of future applications– Organization of local events
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 6
Albania
Other sources of funding Proposal to SEE-ERA was not accepted due to unclear causes
Expansion of national infrastructure New site in implementation at Faculty of Economy (FECO) Work in progress for improvement of the site at FIE Work in progress for implementation of the site at FNS New site deployed already at INIMA, but
– Sites of INIMA shut down for undetermined period due to moving out of the building.
Expansion to new applications and user communities Contacts with FECO and institutes of Seismology and Hydrometeorology
established, all included in the national project-proposal
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 7
Bosnia-Herzegovina
Plan for the 2-nd project year NGI setup and recognition
Improve the NGI organization and attempt the National level recognition. This could include recognition at various levels i.e. Ministries of Science / Technology / Education where applicable: state/entity/canton
NGI organization and Consortium expansion Planned inclusion of 3-5 new members
NREN cooperation NREN National recognition will be attempted
eInfrastructure national strategy If political issues allow
National-level policies If political issues allow
eIRG membership status If political issues allow
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 8
Bosnia-Herzegovina
Plan for the 2-nd project year (cont.): National-level projects
One long-term project is in preparation Other sources of funding in grid area including related projects
By SARNET and by individual universities. Technical independence i.e. national-level services
National CA is planned RB, BDII servers (or gLite counterparts)
Expansion of national infrastructure All sites are due for upgrade, 2 new sites will be introduced
Expansion to new applications and user communities Attempt the expansion into new domains: electromagnetics, fluid
dynamics, seismology, meteorology, biomed
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 9
Bosnia-Herzegovina
Report on May-November 2007:
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 10
Bulgaria
Plan for the 2-nd project year: NGI organization and Consortium expansion
BGGC expects new members eInfrastructure national strategy
eInfrastructure national strategy will be recognized on governmental level eIRG plans
contribution to eIRG workshops, participation at eIRG meetings regularly National-level projects
National-level projects are expected for expansion of infrastructure Other sources of funding in grid area including related projects
New bilateral and regional projects are expected to start Technical independence i.e. national-level services
Full technical independence in the production status will be achieved Expansion of national infrastructure
A total of more than 300 CPUs is expected to be achieved
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 11
Bulgaria
Report on May-November 2007: NGI organization and Consortium expansion
Agreement was signed with University of Ruse Interest was declared by one additional organization
National-level projects One big national project and two small projects were activated; it will
support configuration up-grades Expansion to new user communities
New members in SEE-GRID VO from computational mechanics and geographic
eIRG plans Participation in the Open Workshop on eInfrastructure, Lisbon, Portugal,
October 11-12, 2007 Participation in 12th e-IRG meeting, November 30, 2007, Lisbon, Portugal
(coming)
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 12
Croatia
Plan for the 2-nd project year: NGI organization
Establishment of CRO GRID 2 National Grid Infrastructure (CRO NGI) and Croatian [Hrvatska] National Grid Initiative (HNGI)
More formal internal organisation and decision-making mechanisms establisheds (Steering Commitee)
eInfrastructure national strategy e-Croatia (e-Hrvatska) strategy
National-level projects CRO GRID 2
Other sources of funding in grid area including related projects EGEE-II, SEE-GRID-2, EU funded CenVis (Centre for Scientific Visualisation) DARIAH bi-lateral and multi-lateral projects
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 13
Croatia
Plan for the 2-nd project year (cont): Industrial cooperation
Ericsson Nikola Tesla, CRO GRID related contracted relationship; IBM Hrvatska; interested industrial and other entities
Technical independence i.e. national-level services Improved Grid services at the national level Implementation of organisational mechanisms and production
infrastructure maintenance procedures Functionality and performance expansion and optimisation:
Expansion of national infrastructure The infrastructure will be expanded as the needs arise. Plans are being made to establish CRO GRID National Grid Infrastructure
in a similar way as by CARnet (no formal document, but strict rules).
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 14
Croatia
Report on May-November 2007: NGI organization
Establishment of Steering Committee for CRO NGI The Regulation act of CRO NGI and the Budget for the Croatian
eInfrastructure was adopted on the first meeting of the official CRO NGI board
Establishment of National Committee for NGI at Croatian Academy of Sciences and Arts
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 15
FYR of Macedonia
Plan for the 2-nd project year: NGI organization and Consortium expansion, NREN cooperation
Inclusion of new member (SEE University, Tetovo) eInfrastructure national strategy
National strategy for Electronic Communication with ICT, Ministry of Transport and Communications
Meeting with newly appointed Minister of Information Society The National Grid Strategy document will be presented to the ‘SS Cyril
and Methodius' University Council for approval. Depending of interest and inclusion of other Universities in NGI (from
Tetovo, Bitola) this document will be proposed for adoption to the Inter University Council.
National recognition of MARGI.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 16
FYR of Macedonia
Plan for the 2-nd project year (cont): Other sources of funding in grid area including related projects
SEE-ERA.NET call UNESCO initiative for new project: Improving Innovation Capacities in
the Universities Technical independence i.e. national-level services
CA accreditation planed to run in Jul/August 2007, CP/CPS document to be finished in March 2007; VOMS; RGMA; BDII.
Expansion of national infrastructure Inclusion of new site (Tetovo)
Expansion to new applications and user communities Large Scale Computations in Molecular Chemical Physics of Interacting
Systems Grid Enabled System for Mining, Gathering, Clustering and Retrieval
Images from the Web Mass Processing of Digital and Analog Seismological signals
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 17
FYR of Macedonia
Report on May-August 2007: NGI national-level recognition – In progress
Briefings with Minister of Information society of R. Macedonia, result UKIM/MARNet is recognized as the main coordinator of the Grid Initiative in Macedonia
JRU documents prepared as continuation of the previously signed MoA (2004-2006)
eInfrastructure national strategy On the request of the Minister of ICT
– Proposition of the MARNet budget 2008 year– Talks for possibilities of expansion of the backbone to all public
universities (Bitola, Tetovo, new univ. Shtip) NGI expansion. other sources of funding in grid area including
related project Preparation and dissemination activities (Linux installations) for the
preparation of the new grid site at South East Europe University
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 18
FYR of Macedonia
Report on May-November 2007 (cont): Industrial cooperation
Briefings with MB of MASIT Chamber of Commerce (result -presence of its president on Industrial day in Thessaloniki
Disemination event for policy makers at 5th SEEITA Conference and 4th MASIT Open Days under the track: Attracting FDI in Macedonia and SEE Region. Present were high Government officials, Minister for foreign investment, Minister for Information Society, Director of Agency for Foreign Investments, representatives of companies, USAID, GTZ
Expansion of national infrastructure Expansion of the MK1 cluster by 20 CPU-a Virtual machines, 1CPU on
3GHz and 512 MB RAM Expansion to new applications and user communities
Grid enabled system for mining, gathering, clustering and retrieval images from the web
Grid-based medical platform - analysis and enhancement of the algorithms for filtering of mammograms and segmentation).
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 19
FYR of Macedonia
Report on May-November 2007(cont): Technical independence i.e. national-level services
Preparing Linux machine and installation of CA software Participation in EUGRIDPMA meeting CPS finalized, site prepared, CA software, hardware and site installed
and configured Started the accreditation procedure scheduled for January 2008
Amsterdam meeting of EUGRID PMA. Participation in EUGRIDPMA meeting
---------- Doctorial virtual Studies
preparatory meeting and 1 month common work of Anastas Mishev with IPP BAS
1 month common work of Azir Aliu from SEE University with IPP BAS
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 20
FYR of Macedonia
Up-dated plan for the remaining period: NGI national-level recognition –
Adoption of the MARGI - Use Policy documents by MARNet Management Board. Preparing document for submission to the Inter University Council
National-level projects Preparation s for national Call
Other sources of funding in grid area including related projects Contributions to current FP7 projects preparations (SEE-GRID-SCI)
Technical independence i.e. national-level services Activate the national CA Improve the current level of deployment of national-level services
Expansion of national infrastructure Up-grade current sites, activate SEEU site
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 21
Greece
Plan for the 2-nd project year: National-level projects
Expansion of the HellasGrid infrastructure Other sources of funding in grid area including related projects
Participation in various Grid Related project proposals Industrial cooperation
Increase contacts with industrial partners Expansion of national infrastructure
Yes, via national project Expansion to new applications and user communities
On going effort via dissemination and participation to related projects
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 22
Greece
Report on May-November 2007:
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 23
Hungary
Plan for the 2-nd project year: Other sources of funding in grid area including related
projects Participation in various Grid Related project proposals
Industrial cooperation Increase contacts with industrial partners
Expansion of national infrastructure Further increase of HunGrid resources
Expansion to new applications and user communities Expand to new user communities in areas of data mining, drug
discovery, bioinformatics, climate modeling, B2B, geophysics, network modeling, etc
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 24
Hungary
Report on May-November 2007: NGI organization and Consortium expansion
Additional JRU established with 3 members in total: DEPARTMENT OF METEOROLOGY at ELU and SEISMOLOGICAL OBSERVATORY of GGRI
– The current JRU has been formed by two smaller application developer/user teams and one team that deals with grid development, operation, support, and training. This 'satellite' JRU will exploit the nationwide Grid resources (operated by the another HGCC JRU) together with other international resources for a specific purpose, namely for applications in the field of seismology and meteorology.
the Hungarian Grid Competence Center (HGCC), involving the key and most experienced Grid players from Hungary, has launched the National Grid Initiative and intends to become the national reference point.
– HGCC establish another JRU. SZTAKI is member in both JRUs
– The management of two separated JRUs with different objectives (instead of one heterogeneous JRU) and with different leaders seems to be more feasible.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 25
Hungary eIRG plans
Already eIRG member National-level projects
Same number of projects as before, working on the projects. Software and Services - National Technology Platform project initiated
and submitted (19. 11. 2007):– Hungarian Grid community (HGCC) supports and participate in the Grid related part of
the project (tight connection to NESSI - Networked European Software and Services Initiative)
Other sources of funding in Grid area including related projects SEE-GRID-SCI
Industrial cooperation Industrial collaboration was initiated with Oracle Hungary, first
negotiation was done beginning of May as an outcome of the HU-Hungarian Grid Induction and Application Development Training
Second negotiation was done at EGEE’07 in Budapest with Oracle EMEA
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 26
Hungary
Up-dated plan for the remaining period: NGI organization and Consortium expansion
HGCC and HunGrid will be expanded with the participation of new members.
National-level projects expected expansion of infrastructure with the new submitted projects. + Software and Services National Technology Platform project (SSNTP) + Biotech National Technology Platform project (BNTP)
Other sources of funding in Grid area including related projects Contributions to current FP7 projects preparations (EGEE III, SEE-GRID-
SCI, National Technology Platform project). Industrial cooperation
Meetings will be organized to strengthen the industrial and governmental collaboration of HunGrid.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 27
Hungary
Up-dated plan for the remaining period (cont): Expansion of national infrastructure
more storage + CPU Expansion to new applications and user communities
Supporting different research fields such as: Biotech/Bioinformatics and looking for multidisciplinary applications in the frame of Biotech National Technology Platform project.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 28
Moldova
Plan for the 2-nd project year: NGI setup and recognition
MD Grid NGI establishment in May 2007 NGI organization and Consortium expansion, NREN cooperation
Inclusion of State University of Moldova, Institute of Ecology and Geography, Faculty of Economical Cybernetics of AESM and the Institute of Applied Physics of the ASM.
eInfrastructure national strategy New strategy to be accepted in collaboration with MD Grid NGI
eIRG plans Application for Moldova membership to be prepared and sent.
National-level projects Adopting by Moldovan government of the Concept of National
Information System for Science and Innovation will include grid-related topics.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 29
Moldova
Plan for the 2-nd project year (cont): Other sources of funding in grid area including related projects
NATO Proposal for upgrading of NGI regional and global connectivity Industrial cooperation
Negotiations for new grid nodes and users involvement from MoldHidroMeteo State Enterprise and the Institute of Economics and Statistics of Moldova.
Technical independence i.e. national-level services Necessary resources for CA, VOMS, RB/WMS to be determined and
established. Expansion of national infrastructure
Inclusion of new sites Expansion to new applications and user communities
Creation of MD-Grid user communities, applications selection and gridification.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 30
Moldova
Report on May-November 2007: NGI setup and recognition
MD-Grid Kick-off meeting MD-Grid NGI Consortium Agreement signed by 6 NGI participants (May
10 2007):– Research and Educational Networking Association of Moldova – coordinator– Institute of Mathematics and Computer Science of the Academy of Sciences
of Moldova– Faulty of Radioelectronics and Telecommunications of the Technical
University of Moldova– Institute of Geology and Seismology of the Academy of Sciences of Moldova– State Hydrometeorological Service– School of Public Health, State University of Medicine and Pharmacy
“N.Testemitanu” NGI Recognized by: MID – Ministry of Information Development and
ASM
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 31
Moldova
Report on May-November 2007 (cont.): NGI organization and Consortium expansion, NREN cooperation
Negotiations of MoUs on joining MD-Grid NGI with potential partners from the State University of Moldova and the Academy of Economic Studies of Moldova have started
eIRG plans Letter of application sent. Answer gotten: Moldova cannot be member of
eIRG , observer only, but there is no policy at the moment Industrial cooperation
Negotiation of cooperation prospects with two domestic Companies that plan to be involved in GRID applications development
Technical independence i.e. national-level services CA building documents preparation continued Negotiation of the ability and possible procedure of National grid CA
creation with National PKI bodies was organized
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 32
Moldova
Report on May-November 2007 (cont.): Expansion of national infrastructure
Organization of the tender for purchasing of the equipment according to the MoUs with institutions
In September 2007 new equipment for two clusters deployment in RENAM node (MD-01-REN node cluster) and in RENAM - IMI node (MD-02-IMI node cluster) was purchased.
Expansion to new applications and user communities 1 application, nominated and gridification started
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 33
Moldova
Up-dated plan for the remaining period: NGI organization and Consortium expansion
State University of Moldova, the Academy of Economical Studies of Moldova
eInfrastructure national strategy new MD-Grid NG eInfrastructure to be determined
eIRG plans application for Moldova observer Membership to be prepared and sent
National-level projects Adopting by Moldovan government of the Concept of National
Information System for Science and Innovation will include grid-related topics.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 34
Moldova
Up-dated plan for the remaining period (cont): Other sources of funding in grid area including related projects
FP7, SEEGRID-SCI Industrial cooperation
negotiations for new grid nodes and users involvement from the Academy of Economical Studies of Moldova.
Technical independence i.e. national-level services necessary resources for CA, VOMS, RB/WMS to be determined and
established. Expansion of national infrastructure
negotiations for new grid nodes creation Expansion to new applications and user communities
creation of MD-Grid users communities, PRNNS application gridification and deployment.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 35
Montenegro
Plan for the 2-nd project year: NGI organization and Consortium expansion, NREN cooperation
Increase number of MGI members eInfrastructure national strategy
First draft of the national Grid strategy will be written and presented in for approval by the Ministry of Education and Science.
Promote the national Grid strategy and work on its implementation Other sources of funding in grid area including related projects
Search for additional sources of funding, especially from industry. Industrial cooperation
Dissemination of information about Grid technology among IT and other industry in Montenegro.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 36
Montenegro
Plan for the 2-nd project year (cont): Technical independence i.e. national-level services
Establish the National Grid CA (CP/CPS to be finished until May 2007 and completion is expected until end of 2007)
Expansion of national infrastructure Improve the Grid infrastructure by upgrading the existing site and
introducing new ones. Expansion to new applications and user communities
Increase the number of users and applications.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 37
Montenegro
Report on May-November 2007: NGI organization and Consortium expansion, NREN cooperation
MGI organization improved by signing of new MoU and forming of JRU Technical independence i.e. national-level services
CP/CPS documents were sent, waiting response and finish job. Expansion to new applications and user communities
Hydro-metrological institute of Montenegro signed JRU. HMI Montenegro use our cluster and adapting their application
Expansion of national infrastructure Established connection of HMI LAN with MREN
National-level projects Participation in the National Research Project Call from Ministry of
Education and Science (Project “Cluster improvement and promotion in Montenegro”, September 2007)
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 38
Romania
Plan the 2-nd project year: NGI organization and Consortium expansion
RoGrid expansion with one more institution during 2007 NREN cooperation
Cooperation with RoEduNet for NREGI development National-level projects
The new R&D Call for proposals at the National level Plan is scheduled for June-July 2007.
Other sources of funding in grid area including related projects Via international cooperation. Utilization of Structural Funds will be
attempted. Industrial cooperation
Activate cooperation with IT private high-tech companies
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 39
Romania
Plan for the 2-nd project year (cont): Technical independence i.e. national-level services
Activate the national CA Expansion of national infrastructure
It is planned to include 1-2 new sites Expansion to new applications and user communities
The expansion to the ESR, BioMed, and Simulation and Optimization fields will be attempted.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 40
Romania
Report on May-November 2007: NGI organization and Consortium expansion
Two new institutions have been included in the consortium: West University of Timisoara - Computer Science Department, and Technical University of Cluj-Napoca – Computer Science Department
National-level projects Participation in the National Research Programme Call 1 (June 2007) A proposal for NREGI development was submitted to the National
Committee for Research Infrastructures Three projects on Grid area were accepted for financing after the Call1
Other sources of funding in Grid area including related projects EGEE III, SEE-GRID-SCI, Structural funds.
Industrial cooperation IT private high-tech companies included in proposal consortia for the
NRP Call1
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 41
Romania
Report on May-November 2007 (cont): Technical independence i.e. national-level services
National CA accredited in July 2007 Romanian CA operational from October 2007 Current level of provided services improved as compared with previous
period Expansion of national infrastructure
Site of the new RoGrid comers Expansion to new applications and user communities
Modelling, simulation and optimization (MOSI) applications on Grid are under development (ICI, NCIT, WUT, TUCN, INCAS)
EQUSIM application was defined by NIPNE in cooperation with National Institute for Earth Science Bucharest
Aerospace research
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 42
Romania
Up-dated plan for the remaining period: National-level projects
Starting winning projects from NRP Call 1 Other sources of funding in grid area including related projects
Contributions to current FP7 projects preparations (EGEE III, SEE-GRID-SCI)
Technical independence i.e. national-level services Activate the national CA Improve the current level of deployment of national-level services
Expansion of national infrastructure Up-grade current sites
Expansion to new applications and user communities MOSI applications deployment and support
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 43
Serbia
Plan for the 2-nd project year: NGI organization and Consortium expansion, NREN cooperation
Improve AEGIS organization with signing of new MoU and forming JRU Maintain excellent relation with NREN
eInfrastructure national strategy Work towards eInfrastructure national strategy
eIRG plans Establish eIRG membership (in progress)
National-level projects Seek national funding from newly introduced Ministry of
Telecommunications and Information Society Other sources of funding in grid area including related projects
Obtain equipment grants from SNIP and IPA (in progress) Get further funding in grid area through participation in FP7 and
regional calls (e.g. see-era.net)
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 44
Serbia
Plan for the 2-nd project year (cont): Industrial cooperation
Expand industrial cooperation, by interacting with hi-tech SMEs (e.g. IRVAS, SEWA)
Technical independence i.e. national-level services Achieve full technical independence of national-level services, after
accreditation of CA Expansion of national infrastructure
Further expand AEGIS infrastructure by introducing new sites, and by upgrading existing ones
Expansion to new applications and user communities Expand to new applications and user communities such as Meteorology
and Archeology
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 45
Serbia
Report on May-November 2007: NGI organization and Consortium expansion, NREN cooperation
Annual AEGIS Assembly held on September 8 AEGIS organization improved by signing of new MoU and forming of JRU Excellent relation with NREN maintained – it is one of the founding
members of AEGIS Industrial cooperation
Industrial cooperation improved, two hi-tech SMEs (e.g. IRVAS, SEWA) are members of AEGIS
Technical independence i.e. national-level services Full technical independence of national-level services is achieved; AEGIS
CA accredited Expansion of national infrastructure
Upgrade of AEGIS01-PHY-SCL in progress, new sites will be added in 2007
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 46
Turkey
Plan for the 2-nd project year: NGI organization and Consortium expansion, NREN cooperation
TR-Grid will be expanded with the participation of new members from governmental departments and industry: Prime Ministry State Planning Organization, National Meteorology Service, Turkish Atomic Energy Authority, Kandilli Observatory and Earthquake Research Center , AGMLAB
JRU will be formed as a mechanism for NGI eInfrastructure national strategy
TR-Grid strategy and policy will be finalized. eIRG plans
TUBITAK expects to become a member of eIRG. Other sources of funding in grid area including related projects
All of the TR-Grid members are trying to participate in different projects from national and international level.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 47
Turkey
Plan for the 2-nd project year (cont): Industrial cooperation
Meetings will be organized to strengthen the industrial and governmental collaboration of TR-Grid.
Technical independence i.e. national-level services Full technical independence will be achieved.
Expansion of national infrastructure Increase in the number of CPUs to over 1000 cores is expected.
Expansion to new applications and user communities TR-Grid will support new grid applications from different research fields
and looking at multidisciplinary applications.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 48
Turkey
Report on May-November 2007: NGI organization and Consortium expansion
1 new member – Turkish Atomic Energy Authority (TAEA) TR-Grid JRU was formed in August 2007 with 9 members of NGI
eInfrastructure national strategy + policy documents TR-Grid Strategy, Site and User Policy documents were finalized and
announced to grid community in Turkey. As the decision policy maker TR-Grid NGI, “TR-Grid Advisory Board” was
initiated by Management Board of TUBITAK ULAKBIM. eIRG plans
The membership of TUBITAK to eIRG was approved. National-level projects
TR-Grid e-Infrastructure Project has been extended until the end of June 2007 and total project budget was increased to 800K Euro
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 49
Turkey
Report on May-November 2007 (cont): Other sources of funding in grid area including related projects
EUMEDGRID, EGEE-2 Industrial cooperation
The industrial collaboration was initiated with AGMLAB (SME) in the semantic and search engine areas. ULAKBIM and AGMLAB developed an academic research engine which will use TR-Grid infrastructure and grid services.
AGMLAB (SME specialized in the semantic and search engine areas) developer of “Academic Research Engine Application for Grid”
EDA Engineering and Analysis (SME specialized in Computational Fluid Dynamics)
ROKETSAN Missiles Industries Inc. (leading the national rocket and missile research and production programs)
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 50
Turkey
Report on May-November 2007 (cont): Expansion of national infrastructure
8 sites are operational. Minimum site configuration is 64 core and 1 Tbyte storage area. As total 1000 cores and 40 Tbyte storage.
The new HPC inifiniband 240 cores cluster with 12 Tbyte raw storage is also operational.
Sites migrated to EGEE production All of the 8 sites are part of EGEE infrastructure
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 51
Turkey
Up-dated plan for the remaining period: NGI organization and Consortium expansion, NRN cooperation
TR-Grid will be expanded with the participation of new members from governmental departments and industry:
– Prime Ministry State Planning Organization, National Meteorology Service, Kandilli Observatory and Earthquake Research Center
eIRG plans membership of eIRG
National-level projects expected expansion of infrastructure with the new submitted projects National funded grid project will be ended at the end of 2007.
Other sources of funding in grid area including related projects TR-Grid is involved in new Grid projects: EGEE-III, EUMEDGRID2, SEE-
GRID-SCI. Industrial cooperation
Meetings will be organized to strengthen the industrial and governmental collaboration of TR-Grid.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 52
Turkey
Up-dated plan for the remaining period (cont): Expansion of national infrastructure
more storage Expansion to new applications and user communities
TR-Grid supports new grid applications from different research fields and looking for multidisciplinary applications.
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 53
Addressed NGI Indicators: Planning NGI setup and recognition: AL, BA, MD / MK NGI organization and Consortium expansion: BA, BG, HR, MK, ME, RO, RS,
TR / MD, TR / HU NREN cooperation: RO, RS eInfrastructure national strategy: BG, HR, MK, MD, ME, RS, TR / MD National Policy documents: MD eIRG plans: BG, MD, RS, TR/ MD, TR National-level projects: AL, BA, BG, HR, GR, MD, RO, / MK, MD, RO, TR / HU Other sources of funding in grid area including related projects: AL, BA, BG,
HR, GR, MK, HU, MD, ME, RO, RS, TR/ MD, RO, TR / HU Industrial cooperation: HR, GR, HU, MD, ME, RO, RS, TR/ MD, TR / HU Technical independence i.e. national-level services: BA, BG, HR, MK, MD,
ME, RO, RS, TR/ MK, MD, RO Expansion of national infrastructure: AL, BA, BG, MK, GR, HU, MD, ME, RO,
RS, TR/ MK, MD, RO, RS, TR / HU Sites migrated to EGEE production: RO Expansion to new applications and user communities: AL, BA, MK, GR, HU,
MD, ME, RO, RS, TR/ MD, RO, TR / HU
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 54
Addressed NGI Indicators: Results NGI setup and recognition: MK,MD / AL NGI organization and Consortium expansion: BG,HR,MK,HU,MD,RO,RS,TR/
ME,RS NREN cooperation: RS eInfrastructure national strategy: MK,MD,TR / TR National Policy documents: TR / TR eIRG plans: HU,MD,TR / BG,TR National-level projects: BG,MK,HU,MD,RO,TR/ AL,HU,ME ,RO Other sources of funding in grid area including related projects: RO,TR Industrial cooperation: MK,HU,MD,RO,RS,TR / HU,MK,TR Technical independence i.e. national-level services: MK,MD,RO,RS /
ME,MK,RO Expansion of national infrastructure: MK,MD,RO,RS,TR / AL,ME,MK,TR Sites migrated to EGEE production: TR Expansion to new applications and user communities: BG,MK,MD,RO/
AL,BG,ME,MK,RO
SEEGRID PSC 06 Meeting – Sarajevo, 22.11.2007 55
Further work
Priority on Open Action lines: WP2 dissemination / open Produce a Guideline document based on D2.2 / open Detail WP2 metrics / open
We have a list of indicators for sustainability and a list of metrics in our 3M report
Finalize Policy documents / 30.11.2007 All partners to send me the policy documents implemented so far
Strength NGI in Albania and Bosnia-Herzegovina / 31.12.2007