WP 2Information Exchange on national incentives and status of Geothermal Energy
Pavel Ramšak / Gerdi BreembroekNetherlands Enterprise Agency
Geothermal ERA NET
Final Meeting – Moravske Toplice (SLO)
13 october 2016
2
WP2 Information exchange on national incentives and status of geothermal energylead partner: RVO (Netherlands Enterprise Agency)
Objectives
To exchange information on the status of geothermal energy utilization, including national support schemes and research, development and deployment (RD&D) activities.
Another objective is the identification of gaps and recommend measures to strengthen European geothermal development in order to meet short-term targets according to the National Renewable Energy Action Plans and future contributions to renewable energy supply.
The scope will range from application of geothermal energy for direct heating to higher enthalpy resources and their corresponding use, and include technical as well as non-technical issues.
Pavel Ramšak 13/10/2016
3
NL
EU member states and their geothermal ambitions
Source: http://www.ecn.nl/nreap - 28 November 2011
H
D
I
F
NREAP 2020: Geothermal Heat / capita
SVK
SLO
Pavel Ramšak 13/10/2016
4
Organisational structure / work packages
Pavel Ramšak 13/10/2016
5
WP2 Information exchange on national incentives and status of geothermal energylead partner: RVO (Netherlands Enterprise Agency)
Planning
Start month 1
End month 54 deliverables ready in M30milestone reached in M30
Pavel Ramšak 13/10/2016
6
WP2 Information exchange (RVO)
Task 2.1 Initial information exchange (RVO/ OS)
• Collect information on existing support and funding schemes in partner countries.
• Collect information on most relevant research, development and demonstration projects and initiatives in partner countries.
• Record information of all participating and other programmes, covering characteristics of programme design and implementation: objectives, target groups, instrument types, eligibility, conditions, budgets, evaluation procedures, etc.
• Record information on evaluation, monitoring and dissemination processes in use for both programmes and projects
• Common formats (templates, questionnaires) and tools for an easy, comprehensive way of data exchange/processing will be proposed in order to prepare the final task report.
Task 2.2 Barriers, gaps & required actions (RVO)
• Identify and analyse technical and non-technical barriers and opportunities for geothermal development (CNR/RVO)
• Map the need for future RD&D (Jülich/RVO)
• Propose actions to bridge gaps, overcome barriers and promote the use of geothermal energy in Europe (RVO)
• (If appropriate) more intensified information exchange on specific topics (running until M54=end project)
Pavel Ramšak 13/10/2016
7
WP2 Information exchangeDescription of deliverables and milestones
Task 2.1 Initial information exchange (RVO/OS)
D2.1 Report with an inventory of existing support and funding schemes
D2.2 Report with an inventory of RD&D projects highlights
Task 2.2 Barriers, gaps & required actions (RVO)
D2.3 Report on technical & non-technical barriers (CNR/RVO)
D2.4 Report on future RD&D needs (Jülich/RVO)
D2.5 Report on required actions (RVO)
MS7 Propose actions to promote the use of geothermal energy in Europe
Pavel Ramšak 13/10/2016
8
WP2 Information exchange (RVO)
Task 2.1 Initial information exchange (RVO/ OS)
• Collect information on existing support and funding schemes in partner countries.
• Collect information on most relevant research, development and demonstration projects and initiatives in partner countries.
• Record information of all participating and other programmes, covering characteristics of programme design and implementation: objectives, target groups, instrument types, eligibility, conditions, budgets, evaluation procedures, etc.
• Record information on evaluation, monitoring and dissemination processes in use for both programmes and projects
• Common formats (templates, questionnaires) and tools for an easy, comprehensive way of data exchange/processing will be proposed in order to prepare the final task report.
Task 2.2 Barriers, gaps & required actions (RVO)
• Identify and analyse technical and non-technical barriers and opportunities for geothermal development (CNR/RVO)
• Map the need for future RD&D (Jülich/RVO)
• Propose actions to bridge gaps, overcome barriers and promote the use of geothermal energy in Europe (RVO)
• (If appropriate) more intensified information exchange on specific topics (running until M54=end project)
Pavel Ramšak 13/10/2016
9
WP2 Information exchangeDescription of deliverables and milestones > task 2.1
Task 2.1 Initial information exchange (RVO/OS)
D2.1 Report with an inventory of existing support and funding schemes
D2.2 Report with an inventory of RD&D projects highlights
Task 2.2 Barriers, gaps & required actions (RVO)
D2.3 Report on technical & non-technical barriers (CNR/RVO)
D2.4 Report on future RD&D needs (Jülich/RVO)
D2.5 Report on required actions (RVO)
MS7 Propose actions to promote the use of geothermal energy in Europe
Pavel Ramšak 13/10/2016
Task 2.1 Initial Information Exchange
10
D2.1reportDecember
2013
D2.2reportOctober
2013
Pavel Ramšak 13/10/2016
11
WP2 Information exchange (RVO)
Task 2.1 Initial information exchange (RVO/ OS)
• Collect information on existing support and funding schemes in partner countries.
• Collect information on most relevant research, development and demonstration projects and initiatives in partner countries.
• Record information of all participating and other programmes, covering characteristics of programme design and implementation: objectives, target groups, instrument types, eligibility, conditions, budgets, evaluation procedures, etc.
• Record information on evaluation, monitoring and dissemination processes in use for both programmes and projects
• Common formats (templates, questionnaires) and tools for an easy, comprehensive way of data exchange/processing will be proposed in order to prepare the final task report.
Task 2.2 Barriers, gaps & required actions (RVO)
• Identify and analyse technical and non-technical barriers and opportunities for geothermal development (CNR/RVO)
• Map the need for future RD&D (Jülich/RVO)
• Propose actions to bridge gaps, overcome barriers and promote the use of geothermal energy in Europe (RVO)
• (If appropriate) more intensified information exchange on specific topics (running until M54=end project)
Pavel Ramšak 13/10/2016
12
WP2 Information exchangeDescription of deliverables and milestones > task 2.2
Task 2.1 Initial information exchange (RVO/OS)
D2.1 Report with an inventory of existing support and funding schemes
D2.2 Report with an inventory of RD&D projects highlights
Task 2.2 Barriers, gaps & required actions (RVO)
D2.3 Report on technical & non-technical barriers (CNR/RVO)
D2.4 Report on future RD&D needs (Jülich/RVO)
D2.5 Report on required actions (RVO)
MS7 Propose actions to promote the use of geothermal energy in Europe
Pavel Ramšak 13/10/2016
13
Technical & non-technical barriers & opportunities (task 2.2a CNR/RVO)
New application concepts
B O
Innovative concepts
Renewableheating and
cooling/Under-ground storage/
Heat pumps
New conceptsfor geothermal
energy use(cascade etc)
Innovative applications
Horticulture and fish farming
Living lab for geothermal
research and Utilisation
Bio technics
Lighthouseprojects
Multi-sourcesystems for
heatproduction
Innovative concepts
Technology
Well recoveryfrom other
operations (i.enat. gas)
Exploitationof off-shore
sources
Innovative drilling and operation
Power distribution
and transmission
Enlargingexploited
geothermal resources
New technology
developmentfor power
production
Chemical industries
connected to geothermal gas
exhaust
Broadening the knowledge base (international /
related technologies)
BAT
10-bullet lists (per country)
clustering workshop
Report(barriers & opportunities)
Pavel Ramšak 13/10/2016
14
Technical/non-tech. barriers & opportunities
A1 Regulations
A2 Economics & risk-
mitigation
a investment
b operational support
c risk mitigation
A3 New/innovative
concepts and applications
A4 Operational issues
A5 Sub-surface
knowledge/data
A6 Structuring the
geothermal sector
A7 Public and education a public acceptance
b visibility & dissemination
c education and training
7 B&O clusters
D2.3reportSeptember
2014
Pavel Ramšak 13/10/2016
15
Future RD&D needs for geothermal development (task 2.2b PTJ/RVO)
10-bullet lists (per country)
clustering workshop
report
Pavel Ramšak 13/10/2016
16
RD&D needs
RD&D clusters
B1 Reservoirs A reservoirs (general)
B reservoir modelling
C reservoir exploration
B2 Operation A operational issues
B injection issues
C pumps & components
B3 PR & data A dissemination
B acceptance
C reporting code/statistics
B4 New concepts A innovative concepts
B heat
C power cycle
B5 Anthropogenic influence A reservoir creation
B seismicity
B6 Drilling
D2.4reportSeptember
2014
Pavel Ramšak 13/10/2016
17
Common Challenges in Geothermal EraNet countries
9 clusters
1.Regulations (A1)
2.Economics & Risk-mitigation (A2)
3.New/innovative concepts & applications (A3/B4)
4.Operation (A4/B2)
5.Subsurface/reservoir knowledge (A5/B1)
6.Structuring the geothermal sector (A6)
7.Public & Education (A7/B3)
8.Anthropogenic Influence (B5)
9.Drilling (B6)
Barriers & Opportunities clusters RD&D needs clusters
A1 Regulations ...
A2 Economics &
risk-mitigation
...
A3
New/innovative
concepts and
applications
B4 New concepts
A4 Operational
issues
B2 Operation
A5 Sub-surface
knowledge/data
B1 Reservoirs
A6 Structuring
the geothermal
sector
…
A7 Public and
education
B3 PR & data
... B5
Anthropogenic
influence... B6 Drilling
All clusters are relevant for the progression of geothermal energy in Europe
Pavel Ramšak 13/10/2016
How to collaborate?
JA1 Information
exchange (groups)
regularmeetings, workshops, visits, ideafactories, etc.:
JA2 Joint work
Joint assignment:detailed studyon specificissue
JA3 Joint call
Jointlydevelopingnew insights, new systems
• Appropriate (and feasible) JA-type should be chosen for a specific challenge• JA’s can evolve from JA1 > JA2 > JA3• Effectiveness/Impact more important than amount of €’s
Pavel Ramšak 13/10/201618
19
How to start/organise joint activities ?
•Bottom-up
•Bi- or multilateral
•Based on countries preferences (within the clusters)
At least two countries to take the initiative
The Geothermal Era Network as a continuing vehicle to launch JA’s
also after the project period !
Pavel Ramšak 13/10/2016
20
Actions to bridge gaps, overcome barriers and promote the use of geothermal energy in Europe(task 2.2c RVO)
Basis for WP4: development of joint activities
D2.5reportNovember
2014
Pavel Ramšak 13/10/2016
7 Joint Activities
NWWOpERA
PRGeo
EGIP
GeoStatReSus
New Concepts
21 Pavel Ramšak 13/10/2016
22
more intensified information exchange (running until M54=end project)
Some examples:
• public Geothermal Risk-mitigation schemes (NL, F, CH) - Cully 29 jan 2016
trilateral meeting
• NL-SLO Information Exchange – Ljubljana 19 feb 2016
workshop, attendance SLO State Secretary for Energy
• exchange with ETIP Deep Geothermal – Brussels 6 april 2016, and onwards
presentation at inaugural meeting and representation of Geothermal EraNet at ETIP-DG
• exchange with EERA-JPGE - Trieste 2014, Bergen 2015, Utrecht march 2016 , Strasbourg sep 2016
presentations and exchange at EERA general meetings presentation and exchange at joint geothermal meeting (R&D project coordinators)
• input to Declaration of Intent for Deep Geothermal (SET-plan/EC) – Q2/Q3 2016
endorsed 14 sep 2016
• linked to joint activities e.g. New Concepts, OpERAe.g. subcontracting of Plinius Consult/Dario Frigo in support joint of joint activities/in-depth information exchange regarding Operational Issues of Geothermal Installations in Europe
Pavel Ramšak 13/10/2016
23
New Concepts workshop 30 okt 2015Genève, Switzerland (CH)OpERA workshop 1+2 okt 2015Vaals, Dutch Mountains (NL/D)
OpERA Magna Carta
24
Actions to bridge gaps, overcome barriers and promote the use of geothermal energy in Europe(task 2.2c RVO)
Basis for WP4: development of joint activities
D2.5reportNovember
2014
Pavel Ramšak 13/10/2016
25
Hvala lepa !