World Bank Documentdocuments.worldbank.org/curated/en/910931468094771638/...Specialist and...
Transcript of World Bank Documentdocuments.worldbank.org/curated/en/910931468094771638/...Specialist and...
Document of
The World Bank
Report No: 78735-PH
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
PH - CHILLER ENERGY EFFICIENCY PROJECT
GLOBAL ENVIRONMENT FACILITY TF095991
OZONE TRUST FUND TF096093
{BOARD APPROVAL DATE: JUNE 3, 2010}
TO THE
REPUBLIC OF THE PHILIPPINES
June 24, 2013
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ii
ABBREVIATIONS AND ACRONYMS
CDM Clean Development Mechanism
CFC Chlorofluorocarbon
CoA Commission on Audits
DENR Department of Environment and Natural Resources
EMB Environmental Management Bureau
ERPA Emissions Reduction Purchase Agreement
FASPO Foreign Assisted and Special Projects Office
FM Financial Management
GEF Global Environment Facility
GWh Gigawatt hour
IAS Internal Audit Service
IFR Interim Financial Report
KfW Kreditanstalt fur Wiederaufbau
MIS Management Information Systems
MMV Measurement, Monitoring and Verification
MW Megawatt
MWh Megawatt-hour
ODP Ozone Depleting Potential
OTF Ozone Trust Fund
PCEEP Philippine Chiller Energy Efficiency Project
PDO Project Development Objectives
PMC Project Management Contractor
PMU Project Management Unit
RF Results Framework
SGA Sub-grant Agreement
TTL Task Team Leader
TORs Terms of Reference
Regional Vice President: Axel von Trotsenburg
Country Director: Motoo Konishi
Sector Manager / Director: Ousmane Dione/John Roome
Task Team Leader: Viraj Vithoontien
iii
PHILIPPINES
PH - CHILLER ENERGY EFFICIENCY PROJECT
P114119
CONTENTS
Page
A. BACKGROUD UMMARY ........................................................................................ 1
B. PROJECT STATUS.................................................................................................... 2
C. PROPOSED CHANGES ............................................................................................ 2
Project Development Objective .................................................................................. 2
Results Indicators ........................................................................................................ 2
Revised Eligibility Criteria ......................................................................................... 4
Components ................................................................................................................ 4
Safeguards ................................................................................................................... 5
Institutional Arrangements.......................................................................................... 5
Financing..................................................................................................................... 6
Financial Management ................................................................................................ 7
Revised Disbursement Estimates ................................................................................ 8
Procurement ................................................................................................................ 8
Mid-Term Review ....................................................................................................... 8
Closing Date................................................................................................................ 8
Implementation Schedule ............................................................................................ 9
ANNEX 1: Results Framework And Monitoring ............................................................. 10
ANNEX 2: Revised Eligibility Criteria ........................................................................... 12
ANNEX 3: Chiller Replacement And Procurement Plan ....................................................... 13
1
PH - CHILLER ENERGY EFFICIENCY PROJECT
RESTRUCTURING PAPER
A. BACKGROUND SUMMARY
1. The Philippine Chiller Energy Efficiency Project (PCEEP) is financed by a grant
from the Global Environment Facility (GEF) ($2.6M) and the Ozone Trust Fund (OTF)
($1.0M). The Project was approved on June 3, 2010 and declared effective on January 5,
2011.
2. The project seeks to reduce greenhouse gas emissions by replacing inefficient
chillers, including both old chlorofluorocarbon (CFC)-based chillers and non-CFC-based
chillers. The GEF grant will provide the initial subsidy to the first batch of chiller
replacements. The Emission Reduction Purchase Agreement (ERPA) between
Department of Environment and Natural Resources (DENR) and Kreditanstalt fur
Wiederaufbau (KfW) would scale up the investment in the replacement of chillers
through carbon credits earned from the newly replaced chillers. However, the delay in
the validation process, the mutually agreed termination of the contract between DENR
and the Project Management Contractor (PMC) and more importantly, the depressed
carbon market caused KfW and DENR to mutually agree to terminate the ERPA. The
absence of this additional revenue stream would require downscaling the original results
indicators for the project.
3. In addition to the change in indicators, the proposed restructuring will: (a) change
the Project Management Contractor (PMC) from a firm to individual consultants given
the simpler nature of the project due to the removal of the Clean Development
Mechanism (CDM) revenue; (b) modify the project cost, procurement plan, financing
plan and disbursement estimate; (c) clarify the project description for Component 1 and
refine the monitoring indicators; (d) revise eligibility criteria; (e) amend Sub-grant
Agreement templates; (f) eliminate the requirement for a mid-term review in lieu of the
restructuring and the comprehensive review undertaken in its preparation; and (f)
retroactively eliminate the semestral internal audit review for the project as a requirement
under the Grant Agreement but rather include the internal audit review as part of the
overall Financial Management arrangement.
4. The Closing Date for the GEF TF is January 1, 2015 while the OTF TF Closing
Date is January 1, 2017. At this time the Closing Date of the GEF TF will not be
extended and any extension will only be considered after sufficient and sustained
progress has been made in the chiller replacement program and is disbursing. The
implementation progress will be reviewed during CY14.
5. There will be no proposed change in the project development objectives and
safeguards category for the project.
2
B. PROJECT STATUS
6. The project has been rated moderately unsatisfactory for progress towards
achievement of project development objectives (PDO) and implementation progress.
Limited progress has been made prior to the last supervision mission in February 2013.
However, several activities critical to the achievement of the PDO including staffing of
the Project Management Unit (PMU) and firming up pipelines of potential chillers for
replacement have been undertaken during the last six months.
7. Implementation progress was impeded by the mutually agreed termination of the
ERPA between KfW and DENR. Since effectiveness, the project was focused on
completing the CDM registration process and was in the final stages of the process. The
endorsement of the Designated National Authority (DNA) had been obtained but the
process had to be suspended due to the termination of the ERPA.
8. Another factor which contributed to the delay in project implementation was that
the contract between DENR and the PMC was not completed as originally planned and
was subsequently mutually terminated. Under the original implementation
arrangements, the PMC was responsible for undertaking the day-to-day operations of the
project and reported to the PMU, which ensured the effective and timely implementation
of the project. Due to the termination of the contract with the PMC, the PMU now
undertakes the roles and responsibilities previously assigned to the PMC and is overseen
by Foreign Assisted and Special Projects Office (FASPO). The PMU has contracted
three individual consultants (Carbon Specialist cum Task Team Leader (TTL), Chiller
Specialist and Measurement, Monitoring and Verification (MMV) Specialists) and
Financial and Administrative Assistants in October 2012. The hiring of the Financial
Management Specialist, whose main responsibility will be to analyze the financial
viability of chiller replacements, remains pending but is expected to be hired by end June.
9. Under the project, one chiller has been replaced in 2012 and the financial
incentive paid to the chiller owner in May this year. Two additional SGAs have been
signed for the replacement of five chillers. A firm pipeline of 53 chillers has been
established and additional SGAs are expected to be signed for the replacement of 16
additional chillers in CY13 and the remaining replacements are scheduled in CY14.
10. To date, about $US$277,000 has been disbursed from the OTF grant while
$532,000 has been disbursed from the GEFTF.
C. PROPOSED CHANGES
11. Project’s Development Objectives. The Project’s Development and Global
Environment Objectives remain valid despite the proposed changes.
12. Results/indicators. With the absence of additional source of funding as
originally envisioned for scaling up investment in the replacement of chillers, the results
indicators for the project need to be revisited. As part of the restructuring, the indicators
were also reviewed to reconfirm their validity in terms of measuring the project’s
3
progress towards the PDO. All indicators will remain the same with the exception of the
Outcome Indicator of 195 inefficient Chiller Replacements. It is proposed to change this
indicator to Cooling Capacity addressed by the Project because this indicator would be
more appropriate and closely linked to measuring Ozone Depleting Potential (ODP)
consumption and energy savings. In addition, the size of the chillers to be replaced under
the project may vary in terms of capacity from 300 ton of refrigeration (TR) to 1000 TR.
However the project will prioritize large capacity chillers because of the economies of
scale and greater climate benefits. The proposed outcome /results indicators and targets
are:
Indicators Unit Old Target New
Target
Outcome Indicators
New: Cooling Capacity Addressed by
the Project (to replace old indicator of
No. of Chiller Replacements)
TR (new) 30,649 TR
ODP Consumption Phaseout due to
replacement of Chillers
Ton ODP 22 5.7
Cumulative Carbon Emission
Reduction as Direct Benefits from the
Project
K tCO2 560
62.4
MWh savings and MW demand
reduction
GWh;
MW
341 GWh/y
over 20 years;
59 MW
124.7
GWh/yr
Intermediate Results Indicators
Component One: Number of Sub-grant Agreements
signed
Number of new energy efficient
chillers installed
new
Number
(old)
375
20
53
Component Two: Data MIS for VER
claims
% 100 35
Component Three: Number of chiller
owners participating in the recognition
program
Number of training/workshops
Number 50
15
38
12
13. In addition to this change, the original period (which took into account the
expected revenue from the carbon credits) during which the target value will be achieved
has to be reduced from 10 years to the life of the GEF grant. The Grant Agreement will
no longer contain the Results Framework (RF) but will refer to the Operations Manual
which contains the RF. See Annex 1 for details.
4
14. Revised Eligibility Criteria. With the cancellation of the ERPA, the eligibility
criteria will be revised under the proposed restructuring. The eligibility criteria for
chiller replacements will be simplified to remove the stringent requirements that were
needed in order for the beneficiaries to receive credits from their reduced carbon
emission as part of the cancelled ERPA. The eligibility criteria for the baseline and new
chillers can be found in Annex 2.
15. Components. The project has four components: (a) investment in chiller
replacement; (b) measurement, monitoring and verification; (c) performance standards
and technical assistance; and (d) project management.
16. The component that was impacted most by the cancellation of the ERPA is
Component 1 which provides financial incentives (15% of the new chiller cost) to
accelerate the replacement of inefficient chillers. The initial phase of the project was to
be funded by GEF funds and the carbon credits earned from the new chillers will be used
to scale up the investment. Originally, chiller owners were provided two options in terms
of financial incentives under the project: (a) 15 % of the ex-works price of the new chiller
or the normative cost whichever is lower; or (b) future carbon finance or deferred
revenues. With the cancellation of the ERPA, the second financial incentive option is no
longer available. The Sub-Grant Agreement templates between DENR and the chiller
owners have been amended to reflect this change. The project will be delinked from the
CDM and investment in chiller replacement will be funded solely from GEF funds. As a
result, the scale of the investment will be significantly reduced resulting in a simpler
project design.
17. There are no changes in the activities for Components 2 and 3 aside from the
scale of activities. Under Component 2, the project would measure energy consumption
of baseline and new equipment; monitor performance of new chillers by collecting
performance parameters of new chillers; and analyze the data collected during the
lifetime of the project. Under this component, verification of emission reduction as
required by the CDM process would be undertaken. With the removal of the CDM
element, the project would continue to support the verification of emission reduction to
build capacity in DENR for registering the carbon credits in the voluntary (Variable
Carbon Standard or Gold Standard) rather than the compliance (CDM) market. The
activity will be smaller in scale and will be undertaken, when the situation of the carbon
market improves in the future, as a pilot for possible replication in future energy
efficiency initiatives to be undertaken in the Philippines.
18. Component 3 would provide targeted technical assistance in order to build
capacity in the PMU and the chiller owners/technicians to ensure that even after the
project is completed that they will be equipped to undertake the operations and
maintenance of the new chillers. Under this component, public awareness activities
highlighting the benefits of converting to energy efficient chillers will be intensified in
order to motivate other chiller owners to undertake the conversion either under the
project or on their own.
5
19. For Component 4, the responsibility for the day to day operations of the project
will be overseen by the PMU. However, instead of hiring a private firm as the Project
Management Contractor (PMC), qualified individual consultants were hired on an interim
basis in order for project activities to continue pending approval of the proposed
restructuring which will make this a permanent arrangement.
20. Safeguards. There are no changes to Safeguards. The same safeguards
instrument will apply for the Restructured Project.
21. Institutional Arrangements. Primary responsibility for implementation remains
with DENR with the Foreign Assisted and Special Projects Office (FASPO) acting as the
Oversight Agency. The Environmental Management Bureau (EMB) established the
Project Management Unit (PMU) which oversees the day to day activities of the project.
Previously, responsibility for day to day operations was under the Project Management
Contractor. However, the contract did not proceed as planned and DENR and the PMC
mutually agreed to terminate the contract. Under the Project’s Grant Agreement, the
PMC is defined as a firm. Under the proposed restructuring the PMU will take over the
responsibility for day to day operations for the project.
22. With the simplification of the project, FASPO will now act as the Oversight office
for the project. In addition, DENR proposed to replace the PMC with the PMU to be
staffed with qualified individual consultants to handle the technical, financial and
administrative aspects of the project. The individual consultants will report to the PMU.
On an interim basis prior to the approval of the proposed restructuring, individual
consultants were engaged to undertake the day to day activities of the project. The
restructuring seeks to make this a permanent arrangement for project management. The
revised organizational chart below reflects the proposed institutional arrangements after
the restructuring.
Secretary WB
Chiller Supplier
DENR FMS
VER Buyer EMB Director
Undersecretary
FASPO
PMU including ICs
Support Staffs
Chiller
Owner/ESCOs
PSC
TWG
6
23. Below is a brief description of the role and responsibilities of these consultants:
Carbon Specialist cum TTL – will assist the PMU in the overall management,
monitoring and evaluation procedures and systems for PCEEP implementation
and other monitoring activities of the PMU; take the lead in exploring new
carbon mechanism and provide TA in determining CER and energy efficiency
to be generated through the replacement of the chillers.
Financial Management Specialist – to assist PMU in the financial aspects of
the PCEEP implementation such as project financial management and
investment analysis; prepare financial documents/reports/analysis for the
project and provide assistance to the FASPO and DENR FMS on the required
financial reports/documentation.
Chiller/MMV Specialist – To assist the PMU in the overall monitoring and
evaluation procedures and systems for the PCEEP implementation and other
monitoring activities of the PMU and to provide expertise in installation and
management of chiller replacement;
Management Information Systems (MIS) Specialist – To assist the PMU in
ensuring that the data from the beneficiaries’ chiller (funded by the project)
would be transmitted on a regular basis from its location to the PMU database;
development of an information management system that will be used to
monitor the performance of the project-funded chillers and a receptacle and
storage for the transmitted data as well as data with respect to the project and
beneficiaries, troubleshooting, assurance of data security; and technical
support for the PMU regarding information management of the gathered data
are done effectively and efficiently.
Technical Assistant – assist PMU in the overall monitoring and evaluation
procedures and systems for the PCEEP implementation and other monitoring
activities of the PMU; and prepare required reports for the activities of the
PMU.
Administrative Assistant-assist the PMU in carrying out its functions in the
financial and administrative management aspects of the project; and to assist
the PMU in preparing the required financial reports/documents, in cooperation
with the PMC.
24. All consultants with the exception of the FMS are already on board.
25. Financing
Project Costs. The diminished resources available for the project are reflected in
the table below.
7
Project Costs (US$M)
Components/Activities Current1 Proposed
1. Investment in Chiller Replacement 43.845 17.000
2. Measurement, Monitoring and Verification 1.821 .205
3. Performance Standards and Technical
Assistance
0.204 .432
4. Project Management 1.816 .738
5. Contingency .214
Total 47.900 18.375
Financing Plan. The financing plan will be revised as follows:
Financier Current
(US$M)
Proposed
(US$M)
Borrower/Recipient .320 .325
Private Commercial Sources 36.620 14.400
Global Environment Facility (GEF) 2.600 2.600
Montreal Protocol Investment Fund 1.000 1.000
Germany: Kreditanstalt fur
Wiederaufbau (KfW)
7.310 0.0
US Environment Protection Agency 0.05 .05
Total 47.900 18.375
Disbursement arrangements. There is no change in the disbursement
arrangements.
Reallocations. A reallocation is proposed between components 2, 3 and 4 due
to the savings from the monitoring and verification activities related to the
cancelled CDM component of the project.
Cancellations. There is no proposed cancellation.
26. Financial Management. The current financial covenants under the project
require the PMU to submit the following reports:
(a) Unaudited interim financial reports (IFRs) within 45 days after the end of each
calendar quarter;
(b) Annual audited project financial statements; to be submitted 6 months after
the end of each fiscal year; and
(c) Internal audit review report to be submitted 90 working days after the end of
each semester.
1 If the project has had a previous restructuring, the current should reflect the latest approved costs.
8
27. There are no pending IFRs due to date and timeliness of submission has improved
over time. The IFR covering the period ending March 31, 2013 has been received by the
Bank. We have received the 2011 audited project financial statements prepared by the
Commission on Audit (COA). COA rendered an unqualified opinion, stating that the
financial statements are free of material misstatements and are in conformity with
generally accepted accounting principles. The 2012 audited financial statement is due by
June 30, 2013.
28. The restructuring of the project would result in a simpler project design with the
elimination of the need to account for the reflows of the carbon credits simplifying the
FM design for the project. The improved FM reporting (e.g. timely submission of IFRs
and unqualified opinion on the financial reports) further provides justification for the
proposal to remove the internal audit review on a semestral basis as required in the grant
agreement. No internal audit review for 2011 and 2012 were conducted due to the
limited physical and financial progress of the project. It was agreed that the Internal
Audit Service (IAS) review requirement be eliminated from the Grant Agreement. The
internal audit work program will be conducted for the project so as to obtain significant
coverage when there is better physical accomplishment as part of the overall FM
arrangement of the project. This will allow more flexibility in conducting a useful risk-
based approach to the project rather than a mandatory review even with limited physical
progress.
29. Revised Disbursement Estimates. Based on the proposed changes and the
revised procurement plan, we have prepared a revised disbursement estimate:
FY12
(Actual) FY13 FY14 FY15 Y16 Total
GEF 531,683 1,768,185 300,132 2,600,000
MLF 260,152.6 208,720 193,527 187,244 150,357 1,000,000
Total 791,836 208,720 1,961,712 487,376 150,357 3,600,000
30. Procurement. Based on the pipeline of chiller replacements, the procurement
plan for the GEF TF was modified. Furthermore, the term “commercial practice
acceptable to the Bank” was defined as it relates to Component 1 to ensure that there is a
common understanding of the term. This is reflected in the revised SGA templates for
the project.
31. Mid Term Review. In view of the comprehensive review and changes to be
undertaken as a result of the restructuring, it was agreed to eliminate the mid-term review
requirement.
32. Closing Date. Project implementation has been hampered by the cancellation of
the ERPA with KfW and further impeded by the unsatisfactory performance of the PMC
and the subsequent termination of their contract.
33. Given the changes in the project and as part of the proposed restructuring, the
PMU revised their marketing, procurement and chiller replacement plans providing
details and an adjusted schedule of project activities. In addition, the Operational Manual
9
has been revised to take into account the proposed changes in the restructuring. The
Bank has reviewed these documents and found them acceptable.
34. The extension of closing date will not be part of the restructuring at this time.
Any extension of the Closing Date will be considered once sufficient implementation
progress has been made and both TFs are disbursing.
35. Implementation Schedule. A revised chiller replacement plan has been agreed
and is attached as Annex 2. The schedule shows a plan towards completion of the project
activities by the proposed revised closing date. The pipeline for CY13 has been firmed
up and the PMU is working on firming up its CY14 pipeline based on the expression of
interest received from chiller owners.
10
Annex 1: Results Framework and Monitoring
PHILIPPINES: CHILLER ENERGY EFFICIENCY PROJECT (P114119)
Project Development Objective (PDO): The project development objective (PDO) is to reduce greenhouse gas emissions by replacing inefficient chillers, including both old CFC-based chillers
and non-CFC based chillers.
Revised Project Development Objective: N/A
PDO Level Results
Indicators* Co
re
D=Dropped
C=Continue
N= New
R=Revised Unit of
Measure
Base
line
Cumulative Target Values**
Frequency Data Source/
Methodology
Responsibility for Data
Collection YR1
(2013)
YR 2
(2014)
YR 3
(2015)
YR4
(2016)
YR5
(2017)
Indicator One Cooling
Capacity Addressed by the
Project
R
Number of
TRs
0
14,422
22,954
30,649
30,649
30,649
Annual
Verification
Reports and
MM&V MIS
DENR
Indicator Two: ODP
Consumption Phase-out due to
replacement of Chillers
R
ODP ton
0
2.7
3.3
4.8
5.2
5.7*
Annual
Verification
Reports and
MM&V MIS
DENR
Indicator Three: Cumulative
Carbon emission reduction as
direct benefits from the project
R
k tCO2
0
7.2
17.8
32.7
47.5
62.4**
Annual
Verification
Reports and
MM&V MIS
DENR
Indicator Four: GWh savings
and MW demand reduction
R
GWh
0
14.4
21.2
29.7
29.7
29.7
Annual
Verification
Reports and
MM&V MIS
DENR
INTERMEDIATE RESULTS
Intermediate Result (Component One): Investments to Chiller Replacement
Revised Intermediate Result (Component One):
Intermediate Result indicator
One: No. of Sub –Grant
Agreements Signed
N
Number
0
10
20
20
20
20
Annual
SGAs
DENR
Intermediate Result Indicator
Two: Number of new energy
efficient chillers installed
R Number of
units
replaced
0 22 39 53 53 53 Annual MM & V MIS DENR
11
Intermediate Result (Component Two): Measurement, Monitoring and Verification (MMV)
Revised Intermediate Result (Component Two):
Intermediate Result Indicator
One: Data MIS for VER
Claims
R % of Units
providing
data
0 9 23 35 35 35 Every six
months
Verification
Reports and
MM & V MIS
DENR
Intermediate Result (Component Three): Performance Standards and Technical Assistance
Revised Intermediate Result (Component Three):
Intermediate Result indicator
One: Number of recipients
participating in the recognition
program
R Number of
participants
0 9 14 15 15 15 Annual Progress Reports and MM&V MIS
DENR
Intermediate Result Indicator
Two: Number of training and
workshops
R Number of
training
0 4 8 12 12 12 Annual Reports DENR
*.
12
Annex 2. Revised Eligibility Criteria
Revised Eligibility Criteria: Old Chillers Criteria Eligibility
Age The old chiller must be operating not more than 15 years. The age of
the chiller will be based on the historical operating hours.
Chiller Type All chillers that conform to CDM methodology are eligible.
Power Source and Compression The chiller should be electrically powered and of the vapor
compression type.
Efficiency Old chillers shall have an energy efficiency at least 0.8 kW/TR.
Cooling Capacity In size or in terms of cooling capacity, the old chiller proposed for
replacement must be at least 300 tons of refrigeration (TR) or above
with priority given to larger capacity chillers.
Operating Hours The old chiller must have operating on a regular basis.
Refrigerant Type The old chiller uses CFC or non-CFC refrigerants.
Use and Location The chiller must be currently in use and located in the Philippines.
Proof of Ownership or Legal Rights to
Possess and Operate
The chiller operator is the owner, or has the legal right to possess
and operate the existing chiller. The chiller operator shall show
proof of ownership or legal rights to possess and operate.
Revised Eligibility Criteria (New Chillers) Criteria Eligibility
Starting Date To be eligible, the new replacement chillers should have been
installed on or after January 1, 2012 but before December 31, 2014.
Chiller Process The new chiller generates chilled water or a water/antifreeze mixture
(e.g, water and glycol) for process cooling or air conditioning
Power Source and Compression The replacement chiller should be electrically powered and of the
vapor compression type.
Efficiency Energy consumption ratio of the new chiller should be equal to or
lower than 0.63 kW/TR and a difference of at least 0.3 kW/TR
between the efficiency of old and new chiller.
Cooling Capacity The rated cooling capacity of the new chiller must be within + 10%
of the rated cooling capacity of the existing chiller to be replaced.
Operating Hours New chiller must operate to ensure investment payback period of
less than four (4) years
Refrigerant Type The new chiller must use non-CFC based refrigerant.
Data Measuring Device The new chiller is fitted with data measuring device that would
measure compression motor kWh (energy efficiency), temperature of
in and out chilled water, chilled water flow rate based on flow meter
or pressure drop.
Installation The new chiller is installed in the applicant’s facility where the old
chiller was located. New chiller location need not be in the exact
same place of the old chiller, as long as it is serving the same
facility/building.
13
Annex 3 Procurement and Chiller Replacement Plan
Date of Forwarding
of Budget Request
& Submission of
Justification Report
for Direct
Contracting
Date of
Evaluation
& Awarding
Of Contract
Date of
Purchase
Order
Date of
Submission
of Letter Of
Credit
Date of
Arrival Of
New Chiller
Date of
Installation
Of New
Chiller
Date of
Commissioning
of New Chiller
Date of
Recovery of
Refrigerant
Date of
Destruction of
Compressor of
Old Chiller
Date of
Payment
Of Subsidy
7 Calendar Days 7 Calendar
Days
1 Calendar
Day
#1 Peninsula Manila Hotel 2012 18-May-12 19-Jun-12 20-Jun-12 4-Sep-12 4-Jan-13 10-Jan-13 Mar-13 Based on CO's Procurement Plan
#2 SM City Iloilo (1) 2013 Apr-13 Oct-13 Oct-13 Nov-13 Nov-13 Nov-13 Nov-13 Mar-14 Estimated
#3 SM City Iloilo (2) 2013 Apr-13 Oct-13 Oct-13 Nov-13 Nov-13 Nov-13 Nov-13 Mar-14 Estimated
#4 SM City Bacoor 2014 Sep-13 Oct-13 Oct-13 Oct-13 Jan-14 Feb-14 Feb-14 Feb-14 Feb-14 May-14 Estimated
#5 SM Iloilo 2014 Sep-13 Oct-13 Oct-13 Oct-13 Jan-14 Feb-14 Feb-14 Feb-14 Feb-14 May-14 Estimated
#6 SM Southmall 2014 Sep-13 Oct-13 Oct-13 Oct-13 Jan-14 Feb-14 Feb-14 Feb-14 Feb-14 May-14 Estimated
Item
No.Chiller Owner
Replace
ment
Year
Total # of
Days
DEPARTMENT OF ENVIRONMENT
AND NATURAL RESOURCES
PHILIPPINE CHILLER ENERGY EFFICIENCY PROJECT
PROCUREMENT PLAN FOR DIRECT CONTRACTING
Date of
Preparation
Of Bid
Documents
Date of
Publication Of
Bid
Documents
Date of
Submission
Of Bid
Documents
Date of
Evaluation Of
Bid
Documents
Date of
Awarding Of
Bid
Date of
Contract
Date of
Notice to
Proceed
Date of
Submission
of Letter
Of Credit
Date of
Arrival Of
New
Chiller
Date of
Installation
Of New
Chiller
Date of
Commission
ing of New
Chiller
Date of
Recovery of
Refrigerant
Date of
Destruction of
Compressor of
Old Chiller
Date of
Payment Of
Subsidy
2 Weeks30 Calendar
Days1 Day
14 Calendar
Days
7 Calendar
Days
10
Calendar
Days
14
Calendar
Days
1
Mactan Cebu International Airport Authority
(MCIAA) Used in RTI. 2013 Replacement. 2013 Oct-12 Nov-12 1-Dec Jan-13 Jan-13 Jan-13 Jan-13 Jan-13 May-13 Jun-13 Jun-13 Jun-13 Jun-13 Aug-13 Based on CO's Procurement Plan
2 Bank of the Philippine Islands (BPI) Buendia (1) New. 2013 Replacement 2013 Sep-12 Sep-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Feb-13 Jul-13 Aug-13 Aug-13 Aug-13 Nov-13 Estimated
3 Bank of the Philippine Islands (BPI) Buendia (2) New. 2013 Replacement 2013 Sep-12 Sep-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Feb-13 Jul-13 Aug-13 Aug-13 Aug-13 Nov-13 Estimated
4 Bank of the Philippine Islands (BPI) Buendia (3) New. 2013 Replacement 2013 Sep-12 Sep-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Oct-12 Feb-13 Jul-13 Aug-13 Aug-13 Aug-13 Nov-13 Estimated
5 Cultural Center of the Philippines (CCP)
SGA signing in 2013. 2014
Replacement 2014 11-Feb-14 18-Feb-14 4-Mar-14 11-Mar-14 18-Mar-14 ######## 8-Apr-14 22-Apr-14 4-Jun-14 12-Jun-14 17-Jun-14 24-Jun-14 27-Jun-14 10-Jul-14 149 Based on CO's Procurement Plan
6 Bangko Sentral ng Pilipinas (BSP)
SGA signing in 2013. 2014
Replacement 2014 Nov-13 Nov-13 Jan-14 Jan-14 Feb-14 Feb-14 Mar-14 Mar-14 Jul-14 Jul-14 Aug-14 Aug-14 Aug-14 Oct-14 Based on CO's Procurement Plan
7 Social Security System (SSS) (1)
SGA signing in 2013. 2014
Replacement 2014 Feb-14 Mar-14 Apr-14 May-14 May-14 Jun-14 Jul-14 Aug-14 Nov-14 Nov-14 Dec-14 Nov-14 Jan-15 Apr-15 Based on CO's Procurement Plan
8 Social Security System (SSS) (2)
SGA signing in 2013. 2014
Replacement 2014 Feb-14 Mar-14 Apr-14 May-14 May-14 Jun-14 Jul-14 Aug-14 Nov-14 Nov-14 Dec-14 Nov-14 Jan-15 Apr-15 Based on CO's Procurement Plan
9 National Kidney & Transplant Institute (NKTI)
SGA signing in 2013. 2014
Replacement 2014 Apr-13 May-13 Jan-14 Jan-14 Aug-14 Aug-14 Aug-14 Aug-14 Oct-14 Nov-14 Nov-14 Dec-14 Dec-14 Feb-15 Based on CO's Procurement Plan
10 Social Security System (SSS) (3) Used in RTI. 2015 Replacement 2015 Feb-15 Mar-15 Apr-15 May-15 May-15 Jun-15 Jul-15 Aug-15 Nov-15 Nov-15 Dec-15 Nov-15 Jan-16 Apr-16 Estimated
11 Social Security System (SSS) (4) Used in RTI. 2015 Replacement 2015 Feb-15 Mar-15 Apr-15 May-15 May-15 Jun-15 Jul-15 Aug-15 Nov-15 Nov-15 Dec-15 Nov-15 Jan-16 Apr-16 Estimated
12 NAIA Terminal 1 (1) Used in RTI. 2013 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
13 NAIA Terminal 1 (2) Used in RTI. 2013 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
14 NAIA Terminal 2 (1) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
15 NAIA Terminal 2 (2) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
16 NAIA Terminal 2 (3) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
17 NAIA Terminal 2 (4) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
18 NAIA Terminal 2 (5) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
19 NAIA Terminal 2 (6) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
20 NAIA Terminal 2 (7) Used in RTI. 2014 Jan-15 Feb-15 Mar-15 Apr-15 Apr-15 May-15 May-15 May-15 Sep-15 Sep-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
REPLACE
MENT
YEAR
Total #
of Days
PROCUREMENT PLAN FOR COMPETITIVE BIDDING
Item No. Chiller Owner
Notes
(RTI is Results/Target Indicators
calculated by DENR and WB)
14
Date of
Submission
of Request
For
Quotation
(RFQ)
Date of
Evaluation
of Request
For
Quotation
(RFQ)
Date of
Awarding
of Request
For
Quotation
(RFQ)
Date of
Purchase
Order
Date of
Submission of
Letter Of
Credit
Date of
Arrival Of
New Chiller
Date of
Installation
Of New
Chiller
Date of
Commissioning
of New Chiller
Date of
Recovery of
Refrigerant
Date of
Destruction of
Compressor of
Old Chiller
Date of
Payment
Of Subsidy
1 Calendar
Day
14
Calendar
Days
7 Calendar
Days
1 Calendar
Day#1 Marco Polo used in RTI. 2013 replacement 2013 Feb-13 Feb-13 Mar-13 Mar-13 Mar-13 Aug-13 Aug-13 Sep-13 Aug-13 Aug-13 Oct-13 Based on CO's Procurement Plan
#2 Waterfront Hotels & Casinos - Lahug (1) used in RTI. 2013 replacement 2013 Mar-13 Mar-13 Mar-13 Apr-13 Apr-13 Aug-13 Aug-13 Aug-13 Sep-13 Sep-13 Nov-13 Based on CO's Procurement Plan
#3 Waterfront Hotels & Casinos - Lahug (2) used in RTI. 2013 replacement 2013 Mar-13 Mar-13 Mar-13 Apr-13 Apr-13 Aug-13 Aug-13 Aug-13 Sep-13 Sep-13 Nov-13 Based on CO's Procurement Plan
#4 Waterfront Hotels & Casinos - Lahug (3) used in RTI. 2013 replacement 2013 Mar-13 Mar-13 Mar-13 Apr-13 Apr-13 Aug-13 Aug-13 Aug-13 Sep-13 Sep-13 Nov-13 Based on CO's Procurement Plan
#5 Waterfront Hotels & Casinos - Lahug (46) used in RTI. 2013 replacement 2013 Mar-13 Mar-13 Mar-13 Apr-13 Apr-13 Aug-13 Aug-13 Aug-13 Sep-13 Sep-13 Nov-13 Based on CO's Procurement Plan
#6 Manila Pavilion (1) used in RTI. 2013 replacement 2013 Apr-13 Apr-13 Apr-13 May-13 May-13 Sep-13 Sep-13 Sep-13 Oct-13 Oct-13 Dec-13 Based on CO's Procurement Plan
#7 Manila Pavilion (2) used in RTI. 2013 replacement 2013 Apr-13 Apr-13 Apr-13 May-13 May-13 Sep-13 Sep-13 Sep-13 Oct-13 Oct-13 Dec-13 Based on CO's Procurement Plan
#8 Trinoma (1) used in RTI. 2013 replacement 2013 Jun-13 Jun-13 Jun-13 Jun-13 Jul-13 Nov-13 Dec-13 Dec-13 Dec-13 Dec-13 Feb-14 Based on CO's Procurement Plan
#9 Trinoma (2) used in RTI. 2013 replacement 2013 Jun-13 Jun-13 Jun-13 Jun-13 Jul-13 Nov-13 Dec-13 Dec-13 Dec-13 Dec-13 Feb-14 Based on CO's Procurement Plan
#10 Trinoma (3) used in RTI. 2013 replacement 2013 Jun-13 Jun-13 Jun-13 Jun-13 Jul-13 Nov-13 Dec-13 Dec-13 Dec-13 Dec-13 Feb-14 Based on CO's Procurement Plan
#11 Trinoma (4) used in RTI. 2013 replacement 2013 Jun-13 Jun-13 Jun-13 Jun-13 Jul-13 Nov-13 Dec-13 Dec-13 Dec-13 Dec-13 Feb-14 Based on CO's Procurement Plan
#12 Trinoma (5) used in RTI. 2013 replacement 2013 Jun-13 Jun-13 Jun-13 Jun-13 Jul-13 Nov-13 Dec-13 Dec-13 Dec-13 Dec-13 Feb-14 Based on CO's Procurement Plan
#13 Philippine National Bank (1) used in RTI. 2013 replacement 2013 Mar-13 Mar-13 Apr-13 Apr-13 Apr-13 Oct-13 Oct-13 Oct-13 Oct-13 Oct-13 Dec-14 Based on CO's Procurement Plan
#14 Philippine National Bank (2)
SGA singing in 2013. 2014
Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Based on CO's Procurement Plan
#15 Tower One & Exchange Plaza (1) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#16 Tower One & Exchange Plaza (2) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#17 Tower One & Exchange Plaza (3) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#18 6750 Office Building (1) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#19 6750 Office Building (2) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#20 6750 Office Building (3) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#21 6750 Office Building (4) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#22 FGU Makati (1) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#23 FGU Makati (2) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#24 Greenbelt 5 (1) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#25 Greenbelt 5 (2) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#26 Greenbelt 5 (3) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#27 Greenbelt 5 (4) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#28 Greenbelt 1 (1) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#29 Greenbelt 1 (2) Used in RTI. 2014 Replacement 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#30 GMA Network Inc. Used in RTI. SGA signing in 2014. 2014 Mar-14 Mar-14 Apr-14 Apr-14 Apr-14 Oct-14 Oct-14 Oct-14 Oct-14 Oct-14 Dec-14 Estimated
#31 Festival Supermall Used in RTI. May replace in 2013 2013 Jun-13 Jun-13 Jul-13 Apr-15 Apr-15 Oct-15 Oct-15 Oct-15 Oct-15 Oct-15 Dec-15 Estimated
#32 Philippine National Bank (3) Used in RTI. 2015 Replacement. 2015 Mar-15 Mar-15 Apr-15 Apr-15 Apr-15 Oct-15 Oct-15 Oct-15 Oct-15 Oct-15 Dec-15 Based on CO's Procurement Plan
Replace
ment
Year
Total #
of Days
PROCUREMENT PLAN FOR SHOPPING
Item
No.Chiller Owner
Notes
(RTI is Results/Target Indicators
computed by DENR and WB)