World Bank Documentdocuments.worldbank.org/curated/en/778331512661086878/pdf/ICR-P... · FEHIDRO...
Transcript of World Bank Documentdocuments.worldbank.org/curated/en/778331512661086878/pdf/ICR-P... · FEHIDRO...
The World Bank Brazil São Paulo Water Recovery Project (P106703)
Document of
The World Bank
Report No: ICR00003902
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IBRD-78700)
ON A
LOAN
IN THE AMOUNT OF US$64.50 MILLION
EQUIVALENT
TO THE
GOVERNMENT OF THE STATE OF SÃO PAULO (GESP)
FOR THE
BRAZIL - SÃO PAULO WATER RECOVERY PROJECT - REAGUA
November 29, 2017
Water Global Practice
Latin America and Caribbean Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
The World Bank Brazil São Paulo Water Recovery Project (P106703)
CURRENCY EQUIVALENTS
Currency Unit = Real (R$)
R$ 1.75 = US$1.00
US$1.00 = R$ 0.57
(Project Board Approval – January 12, 2010)
R$ 3.26 = US$1.00
US$1.00 = R$ 0.31
(Project Closing Date – May 30, 2017)
FISCAL YEAR January 1 - December 31
ABBREVIATIONS AND ACRONYMS
ANA National Water Agency (Agência Nacional de Águas)
CBA Cost Benefit Analysis
CEF Caixa Econômica Federal
CFP Call for Proposal
CPS Country Partnership Strategy
EMP Environmental Management Plan
ESF Environmental Social Framework
FEHIDRO São Paulo State Water Resources Funds (Fundo Estadual de Recursos Hídricos)
GESP Government of the State of São Paulo
GPOBA Global Partnership on Output Based Aid
IBRD International Bank for Reconstruction and Development
ICR Implementation Completion and Results Report
IFR Interim Financial Report
ILI Infrastructure Leakage Index
IRR
M&E
Internal Rate of Return
Monitoring and Evaluation
MTR Mid-Term Review
MRSP Metropolitan Region of São Paulo
OBA Output-based Aid
OBD Output-based Disbursement
PAC Growth Acceleration Program (Programa de Aceleração do Crescimento)
PAD Project Appraisal Document
PDO Project Development Objective
PMU Project Management Unit
PPA Project and Performance Agreement
PRODES Water Basin Pollution Control Program (Programa de Despoluição de Bacias
Hidrográficas)
QER Quality Enhancement Review
SAAE Autonomous Water and Sanitation Service Provider (Serviço Autônomo de Água e
Esgoto)
The World Bank Brazil São Paulo Water Recovery Project (P106703)
SABESP State Water and Sanitation Autonomous Utility (Saneamento Básico Do Estado De São
Paulo)
SANASA Municipality of Campinas water and sanitation company (Sociedade de Abastecimento
de Água e Saneamento S.A.)
SNIS National Information System on Water Supply, Sanitation and Solid Waste
SSE State Secretariat for Water Supply, Sanitation and Energy
SSRH State Secretariat for Water, Sanitation, and Water Resources (Secretaria de Saneamento
e Recursos Hídricos)
VA Verification Agent
WRM Water Resources Management
WSS
WWTP
Water Supply and Sanitation
Wastewater Treatment Plant
Vice President: Jorge Familiar Calderon
Country Director: Martin Raiser
Senior Global Practice Director: Guang Zhe Chen
Practice Manager: Rita E. Cestti
Project Team Leaders: Oscar Alvarado / Juliana Garrido
ICR Team Leaders: Oscar Alvarado / Juliana Garrido
The World Bank Brazil São Paulo Water Recovery Project (P106703)
BRAZIL
SÃO PAULO WATER RECOVERY PROJECT (REAGUA)
CONTENTS
A. Basic Information.................................................................................................................... i
B. Key Dates ................................................................................................................................ i
C. Ratings Summary .................................................................................................................... i
D. Sector and Theme Codes ....................................................................................................... ii
E. Bank Staff ............................................................................................................................... ii
F. Results Framework Analysis ................................................................................................. iii
G. Ratings of Project Performance in ISRs ................................................................................ v
H. Restructuring ......................................................................................................................... vi
I. Disbursement Profile ............................................................................................................. vii
1. Project Context, Development Objectives and Design ........................................................... 1
2. Key Factors Affecting Implementation and Outcomes........................................................... 4
3. Assessment of Outcomes ...................................................................................................... 13
4. Assessment of Risk to Development Outcome .................................................................... 20
5. Assessment of Bank and Borrower Performance ................................................................. 21
6. Lessons Learned ................................................................................................................... 23
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ....................... 24
Annex 1. Project Costs and Financing ...................................................................................... 26
Annex 2. Outputs by Component ............................................................................................. 28
Annex 3. Economic and Financial Analysis ............................................................................. 35
Annex 4. Bank Lending and Implementation Support/Supervision Processes ......................... 38
Annex 5. Beneficiary Survey Results ....................................................................................... 40
Annex 6. Stakeholder Workshop Report and Results ............................................................... 41
Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ................................. 42
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ................................... 44
Annex 9. List of Supporting Documents .................................................................................. 45
Annex 10. Maps .................................................................................................................... 46
The World Bank Brazil São Paulo Water Recovery Project (P106703)
i
DATASHEET
A. BASIC INFORMATION
Country: Brazil Project Name:
BR Sao Paulo Water
Recovery Project -
REAGUA
Project ID: P106703 L/C/TF Number(s): IBRD-78700
ICR Date: 10/08/2017 ICR Type: Core ICR
Financing Instrument: SIL Borrower: STATE OF SAO PAULO
Original Total
Commitment: USD 64.50 million Disbursed Amount: USD 37.74 million
Revised Amount: USD 64.50 million
Environmental Category: B
Implementing Agencies:
State Secretary for Water Resources and Sanitation (SSRH)
Cofinanciers and Other External Partners: N/A
B. KEY DATES
Process Date Process Original Date Revised / Actual Date(s)
Concept Review: 09/18/2008 Effectiveness: 12/27/2010 12/08/2010
Appraisal: 04/22/2009 Restructuring(s): 11/28/2015
Approval: 05/04/2010 Mid-term Review: 09/17/2012 10/28/2013
Closing: 11/30/2015 05/30/2017
C. RATINGS SUMMARY
C.1 Performance Rating by ICR
Outcomes: Moderately Unsatisfactory
Risk to Development Outcome: Moderate
Bank Performance: Moderately Unsatisfactory
Borrower Performance: Moderately Unsatisfactory
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Unsatisfactory Government: Moderately Unsatisfactory
Quality of Supervision: Moderately Unsatisfactory Implementing
Agency/Agencies: Moderately Unsatisfactory
Overall Bank
Performance: Moderately Unsatisfactory
Overall Borrower
Performance:
Moderately Unsatisfactory
The World Bank Brazil São Paulo Water Recovery Project (P106703)
ii
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments (if
any) Rating
Potential Problem Project at
any time (Yes/No): No Quality at Entry (QEA): None
Problem Project at any time
(Yes/No): Yes
Quality of Supervision
(QSA): None
DO rating before
Closing/Inactive status: Moderately Unsatisfactory
D. SECTOR AND THEME CODES
Original Actual
Major Sector/Sector
Public Administration
Public administration - Water, sanitation and flood
protection 4 4
Water, Sanitation and Waste Management
Water Supply 31 31
Sanitation 65 65
Major Theme/Theme/Sub Theme
Environment and Natural Resource Management
Environmental Health and Pollution Management 66 66
Air quality management 22 22
Soil Pollution 22 22
Water Pollution 22 22
Water Resource Management 33 33
Water Institutions, Policies and Reform 33 33
E. BANK STAFF
Positions At ICR At Approval
Regional Vice President: Jorge Familiar Calderon Pamela Cox
Country Director: Martin Raiser Makhtar Diop
Practice Manager: Rita E. Cestti Guang Zhe Chen
Task Team Leader(s): Oscar E. Alvarado
Juliana Menezes Garrido Carlos E. Velez
ICR Team Leader (s): Oscar E. Alvarado
Juliana Menezes Garrido
ICR Primary Author: Paula Pini
The World Bank Brazil São Paulo Water Recovery Project (P106703)
iii
F. RESULTS FRAMEWORK ANLYSIS Project Development Objectives (from Project Appraisal Document)
The Project Development Objective is to increase clean water availability in the critical watersheds in the State of Sao
Paulo.
Revised Project Development Objectives (as approved by original approving authority)
Not Applicable.
(a) PDO Indicator(s)
Indicator Baseline Value Original Target
Value (from
approval
documents)
Formally Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1: Cubic meters of recovered water (cubic meters (m3), Custom)
Value quantitative or
qualitative -- 30,106,311 47,966,660 47,127,718
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
Comments
(incl. % achievement)
Target was almost achieved reaching 94 percent. Target was revised in the November 2015
restructuring to reflect expected outcomes by ongoing subprojects (components 1 and 2) and
contributions from the new component 4.
Indicator 2: Direct Project beneficiaries (number)
Value quantitative or
qualitative 0 -- 289,686 97,373
Date achieved 12/31/2009 12/31/2014 11/27/2015 05/30/2017
Comments
(incl. % achievement)
Target was not achieved reaching 11 percent. Indicator was added in the November 2015
restructuring. It was designed to reflect the achievements of component 2 and 4 added in the
November 2015 restructuring.
Indicator 3: Female beneficiaries (percentage, custom, supplement)
Value quantitative or
qualitative 51% -- 51% 51%
Date achieved 12/31/2009 12/31/2014 11/27/2015 05/30/2017
Comments
(incl. % achievement)
Target was fully achieved reaching 100 percent. Indicator was added in the November 2015
restructuring.
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value Original Target
Value (from
approval
documents)
Formally Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1: Volume of recovered water per year from reduction in water losses (m3).
Value quantitative or
qualitative -- 9,275,156 30,572,331 43,713,975
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
The World Bank Brazil São Paulo Water Recovery Project (P106703)
iv
Comments
(incl. % achievement)
Target was surpassed reaching 142 percent. The wording and target were revised in the
November 2015 restructuring. The original wording was: Volume of m3 of recovered
water per year from reduction in water losses.
Indicator 2: Cubic meters of reduced water consumption per year in selected public schools.
Value quantitative
or
qualitative
-- 98,915 147,338 335,080
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
Comments
(incl. %
achievement)
Target was surpassed reaching 227 percent. The wording and target were revised in the
November 2015 restructuring. The original wording was: Volume of reduced water
consumption per year in selected public schools.
Indicator 3: Volume of m3 of wastewater reused per year in selected activities.
Value quantitative
or
qualitative
-- 938,727 Dropped
Date achieved 12/31/2009 12/31/2014 11/27/2015
Comments
(incl. %
achievement)
Dropped. This indicator was dropped in the November 2015 restructuring given that no
contract was signed to implement reuse activities under the Project.
Indicator 4: Number of new active connections to the collection network of participating services
provider.
Value quantitative
or
qualitative
0 4,748 2,346 330
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
Comments
(incl. %
achievement)
Target was not achieved reaching 14 percent. The target for this indicator was revised
during the November 2015 restructuring to a smaller number to reflect the actual number
of contracts signed associated with activities that would contribute to the indicator.
Indicator 5: Volume of wastewater transported to and treated in a wastewater treatment plant.
Value quantitative
or
qualitative
-- 19,793,513 13,172,267 3,078,633
Date achieved 12/31/2009 12/31/2014 11/27/2015 05/30/2017
Comments
(incl. %
achievement)
Target was not achieved reaching 23 percent. Wording and target revised during the
Novermber 2015 restructuring. The original wording was: Volume of water that is
returned to selected watersheds in conformity with environmental standards, as measured
by the increase in population equivalent that is served by wastewater treatment plant.
Indicator 6: Impact evaluation study ready.
Value quantitative
or
qualitative
-- Completed Dropped --
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
The World Bank Brazil São Paulo Water Recovery Project (P106703)
v
Comments
(incl. %
achievement)
This indicator was dropped during the November 2015 restructuring given technical
difficulties (lack of similar Projects to compare to) that impedes carrying out the study. A
results evaluation study was carried out as part of the ICR preparation.
Indicator 7: Number of water utilities that the Project is supporting.
Value quantitative
or
qualitative
-- 8 8 8
Date achieved 12/31/2014 12/31/2014 11/27/2015
Comments
(incl. %
achievement)
Target was fully achieved reaching 100 percent. The original indicator was changed in the
November 2015 restructuring. The original wording was: Increasing number of service
providers receiving technical assistance, capacity building and training.
Indicator 8: Wastewater volume transported and treated in the treatment plant and returned to the basin
in accordance with environmental legislation. (m3)
Value quantitative
or
qualitative
-- -- 3,513,600 0
Date achieved 12/31/2009 12/31/2014 11/27/2015 05/30/2017
Comments
(incl. %
achievement)
Target was not achieved. New indicator included as part of the November 2015
restructuring associated with the inclusion of component 4.
Indicator 9: Volume of reduced water consumption per year in housing units of social interest.
Value quantitative
or
qualitative
-- -- 700,800 0
Date achieved 12/31/2009 12/31/2014 11/30/2015 05/30/2017
Comments
(incl. %
achievement)
Target was not achieved. New indicator included as part of the November 2015
restructuring associated with the inclusion of component 4.
Indicator 10: Number of people in urban areas provided with access to improved sanitation under the
Project.
Value quantitative
or
qualitative
0 20,000 Dropped --
Date achieved 12/31/2009 11/30/2015 11/30/2015 05/30/2017
Comments
(incl. %
achievement)
Dropped. This indicator was dropped as part of the November 2015 restructuring as the
number of beneficiaries was already included as a PDO level indicator.
G. RATINGS OF PROJECT PERFORMANCE IN ISRs
No. Date ISR
Archived DO IP
Actual Disbursements
(USD millions)
1 06/08/2010 Satisfactory Satisfactory 0.00
2 11/30/2010 Satisfactory Satisfactory 0.00
3 06/25/2011 Satisfactory Moderately
Satisfactory 0.00
The World Bank Brazil São Paulo Water Recovery Project (P106703)
vi
4 03/03/2012 Satisfactory Moderately
Satisfactory 0.00
5 11/17/2012 Satisfactory Moderately
Satisfactory 0.25
6 07/10/2013 Moderately Satisfactory Moderately
Unsatisfactory 1.22
7 02/24/2014 Moderately Satisfactory Moderately
Unsatisfactory 3.27
8 10/20/2014 Moderately Unsatisfactory Moderately
Unsatisfactory 6.75
9 04/17/2015 Moderately Unsatisfactory Moderately
Unsatisfactory 16.67
10 10/29/2015 Moderately Unsatisfactory Moderately
Unsatisfactory 23.87
11 04/15/2016 Moderately Unsatisfactory Moderately
Unsatisfactory 27.26
12 11/27/2016 Moderately Unsatisfactory Moderately
Unsatisfactory 29.43
13 05/30/2017 Moderately Unsatisfactory Moderately
Unsatisfactory 35.94
H. RESTRUCTURING (IF ANY)
Restructuring
Date(s)
Board
Approved
PDO
Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
Millions
Reason for Restructuring & Key
Changes Made DO IP
11/28/2015 MU MU 25.66
The restructuring was to: (i)
extend the Project closing date
by 18 months to 05/30/2017; (ii)
introduce a new component 4;
(iii) incorporate changes to the
implementing agency,
safeguards, implementation
schedule, reallocation of funds;
and (iv) modify the results
framework, disbursement and
cost estimates.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
1
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. The challenge of water scarcity in the State of São Paulo1. With 95 percent of its 41 million
people living in urban areas, the State of São Paulo is one of the world’s most urbanized areas and
emblematic of the urban challenges facing Brazil. At Project appraisal, the Metropolitan Region of São
Paulo (MRSP), with its 20 million inhabitants, was the seventh largest city in the world. Among its most
pressing problems, water scarcity and environmental degradation were extremely critical constraints on
economic growth and competitiveness, as well as on social and environmental sustainability. MRSP’s per
capita water availability was so low that it was comparable to that prevailing in the driest areas of the
Brazilian Northeast.
2. The problem of water quality. The State of São Paulo has not only faced the problem of critical
water scarcity, but also suffers from the deterioration of its water quality. At the time of Project
preparation, although 49 percent of collected wastewater received treatment, there was still approximately
15.7 million people living in the State with wastewater collection but no treatment. Dumping untreated
wastewater directly into the water bodies further exacerbated the already critical problem of water
scarcity.
3. Other dimensions of water scarcity. The relatively high level of water losses and the lack of
treated wastewater reuse compounded the problem of water scarcity. Water losses can be physical (or
real) through leakages, commercial (or apparent), through theft or metering inaccuracies, or unbilled
authorized consumption. According to the National Information System on Water Supply, Sanitation and
Solid Waste (SNIS) statistics for 2007, of the 477 municipalities in São Paulo reporting to SNIS (out of
645 municipalities in the State), 16 percent had real water losses above 50 percent, 44 percent had real
water losses above 30 percent, and only 14 percent had real water losses below 20 percent. This lack of
homogeneity reflected huge variations between utilities, with real water losses averaging 28 percent for
SABESP, 58 percent for the autonomous service provider (autarquia) in Guarulhos, and 24 percent for
SANASA2 in Campinas.
4. The poor are the most vulnerable to the effects of low water availability. The scarcity of
potable water and the deficit of wastewater collection and treatment were more common in poor
neighborhoods, and particularly severe in slums. This was the case of São Paulo, where about 54 percent
of the poor lived in areas of critical water deficit and 59 percent lacked proper sanitation.
5. State interest in results-based operations. In an example of the evolving and dynamic
relationship between the Bank and the Government of State of Sao Paulo (GESP) in the water sector, the
State Secretariat for Water Supply, Sanitation and Energy (SSE)3 expressed interest in executing part of
1 Brazil: Inputs for a Strategy for Cities: A Contribution with a Focus on Cities and Municipalities, World Bank
Report No. 35749 (June 2006). 2 Sociedade de Abastecimento de Água e Saneamento S.A (Municipality of Campinas water and sanitation
company) 3 Later on named State Secretariat for Water, Sanitation, and Water Resources (Secretaria de Saneamento e
Recursos Hídricos, SSRH).
The World Bank Brazil São Paulo Water Recovery Project (P106703)
2
its programmatic commitment through a pilot Project using an output-based financing mechanism. SSE’s
objective was to satisfy water supply and sanitation (WSS) investment needs, while providing
transparency in the management of resources, better application of funds, and improved service quality
within a reasonable timeframe. In response to GESP’s request, the proposed Project designed an Output-
Based Disbursement (OBD) financing mechanism to encourage investment in activities aimed at
improving the efficiency of WSS assets. Under the results-based scheme, Project funds would be
disbursed to incumbent providers of water services (state or municipal-owned) against agreed and
independently verified outputs.
1.2 Original Project Development Objectives (PDO) and Key Indicators (as approved)
6. The Project Development Objective (PDO) in the loan agreement is stated as follows: “To
increase clean water availability in the critical watersheds.” The PDO in the Project Appraisal Document
(PAD) also mentions “…in the State of São Paulo.” In addition, the PAD defines “clean water” as
additional potable water available for consumption or additional treated wastewater discharged to a water
body in conformity with environmental legislation. The Project had one PDO indicator: The number of
cubic meters of clean water made available.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and
reasons/justification
7. The PDO was not revised. The PDO indicator target was changed during the November 2015
restructuring from 30,106,311 cubic meters (m3) to 47,966,660 m3. The increase reflected the expected
outcomes from the ongoing activities under both Components 1 and 2, and contributions from the newly
included Component 4. In addition, the November 2015 restructuring introduced two new PDO
indicators: (i) Direct Project Beneficiaries, with a target of 289,000 people; and (ii) Female Beneficiaries,
with a target of 51 percent of the Direct Project Beneficiaries.
1.4 Main Beneficiaries
8. The Project beneficiaries were identified in the PAD4 (page 76 and paragraph 10), as the water
and sanitation service providers located within the selected five critical watersheds5 of the State of São
Paulo. Furthermore, only three types of service providers were eligible for financing: autonomous
services providers, municipal companies, and state/regional companies. The November 2015 restructuring
estimated that the Project aimed to directly benefit approximately 289,000 people; out of which 51
percent were expected to be female.
1.5 Original Components (as approved)
9. The Project comprised three original components.
10. Component One: Increase Water Availability (cost at appraisal, US$30.68 million). This
4 Report No. 53620-BR.
5 The five critical watersheds were: Piracicaba/Capivari/Jundiaí; Alto Tietê; Sapucaí Mirim/Grande; Mogi-Guaçu;
and Sorocaba/Médio Tietê. These were the five most critical watersheds in the State, with water demand/availability
ratio of above 80 percent.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
3
component was designed to finance activities aimed at increasing the quantity of available water by
controlling and reducing real water losses, promoting the rational use of water in public schools and
reusing treated wastewater. It was 100 percent OBD financed, with payments to the service providers tied
to the delivery of clearly specified outputs with a final payment made upon reaching agreed targets and
sustainability conditions. It included three sub-components: (i) Control and reduction of real water losses
(US$22.88 million); (ii) Rational use of water (US$3.05 million); and (iii) Reuse of treated wastewater
(US$4.75 million).
11. Component Two: Enhance Water Quality (cost at appraisal, US$64.80 million). This
component was designed to finance activities aimed at improving the quality of water by: (i) building new
wastewater connections to new or existing networks; (ii) installing pipes and pumps to transport
wastewater to new or existing treatment plants; and (iii) constructing new or upgrading existing
wastewater treatment plants (WWTPs). It was 100 percent OBD financed. It included three sub-
components: (i) Wastewater collection networks (US$4.00 million); (ii) Wastewater transport systems
(US$27.10 million); and (iii) Upgrading existing and constructing new WWTPs (US$33.70 million).
12. Component Three: Project Management and Development of Institutional and Technical
Capabilities (cost at appraisal, US$8.16 million). This component was designed to finance activities to
increase the efficiency of the State’s WSS sector. It included: (i) the carrying out of an impact evaluation
study on the output-based financing scheme financed by the loan vis-à-vis the traditional input-based
financing approach, specifically on impact of the output-based approach on the construction time period
and costs and sustainability; and (ii) the provision of technical assistance, capacity building, and training
to water and sanitation service providers. In addition, it aimed at providing support for project
management, supervision and auditing, including provision of experts for the strengthening of the Project
Management Unit (PMU) in the management of the Project and in the verification of outputs and the
Project and performance indicators under the Project and Performance Agreement (PPA). This
component was to disburse based on inputs.
1.6 Revised Components
13. During the November 2015 restructuring, the components descriptions were slightly revised to
reflect the activities that were dropped; and included activities in response to the severe drought faced by
the State that affected the MRSP water supply services dramatically:
14. Component One: Increase Water Availability (revised cost, US$31.67 million). The reuse of
treated wastewater sub-component was dropped. The budget of the other two components was adjusted as
follows: (i) Control and reduction of real water losses (US$29.47 million); and (ii) Rational use of water
(US$2.20 million). This component continued to disburse based on results.
15. Component Two: Enhance Water Quality (revised cost, US$27.68 million). The budget of the
sub-components was adjusted as follows: (i) Wastewater collection network (S$1.12 million); (ii)
Wastewater transport system (US$6.90 million); and (iii) Upgrading existing and building new WWTPs
(US$19.66 million). This component continued to disburse based on results.
16. Component Three: Project Management and Development of Institutional and Technical
Capacity (revised cost, US$5.75 million). The following activities were dropped: (i) impact evaluation
studies; and (ii) technical assistance to municipalities; and municipal and regional service providers. The
total cost amount increased for the following activities: (i) project management; (ii) financial audit; and
(iii) Independent Verification Agent. This component continued to disburse based on inputs.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
4
17. Component Four: Emergency Works for Water Supply Sources (estimated cost, US$30.65
million). This component was added to help minimize the (2013 – 2015) drought’s impact on the MRSP
water production sources6. The component included: (i) the execution of environmental sanitation works
to minimize the impact of the crisis that undermined the two main water sources for the MRSP (the
Cantareira and the Alto Tietê systems), including upgrading or construction of wastewater collection
networks, transport system, and/or treatment plants; and (ii) a water demand management program,
including the implementation of measures to increase the rational use of water in low-income housing
complexes in key neighborhoods of the MRSP, located preferably in the catchment area of key water
production systems. This component was input-based financed, rather than output-based.
1.7 Other significant changes
18. Other changes introduced during the November 15 restructuring included: (i) 18-month extension
of the original closing date from November 30, 2015 to May 30, 2017; (ii) changes in the implementation
schedule; (iii) modifications in the results framework, including indicators and targets; and (iv)
disbursement estimates.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
19. The financing mechanism. Project preparation started7 in late 2008, following the 2007 request
submitted by GESP to the Federal Government and the Bank. The São Paulo Water and Sanitation and
Water Resources Secretariat (SSRH)8 was the executing agency. The Project was appraised 9 months
later. During this short period, the Project concept and design evolved significantly: from a broader to a
narrower focus on selected water and sanitation activities and areas/basins for interventions; and, from a
general to a tailored results-based payment approach, fine-tuned to the technical specifications of the
activities financed, as well as to adjust to the Bank financing requirements. The Project preparation was
supported by a US$180,000 GPOBA grant9 signed in early 2008. The Project was the first Bank-financed
operation in the water supply and sanitation sector to implement a comprehensive results-based scheme.
Between the Bank and GESP, this scheme was an OBD, while between the GESP and the beneficiaries
(WSS providers), it was an Output-Based Aid (OBA), therefore, a grant.
6 Extremely low rainfall over the past two years before the 2015 Restructuring led to a severe water supply crisis in
the state of São Paulo and in the MRSP in particular. The reservoir system that supplies the metropolis was at risk of
depletion, with potential dire social and economic consequences. Despite institutional gaps in water resources
management at higher levels of government, SABESP managed to avoid the collapse of the system. Nevertheless,
risks remained and there was uncertainty about the immediate future and recovery of the accumulation level of the
reservoirs. Of particular concern was the Cantareira reservoir system, which supplied to about half of the
metropolitan 20 million people but by the 2015 Restructuring its supply capacity was reduced to only 25% of the
metropolitan inhabitants. 7 The Project Concept Review Meeting (PCN) took place on September 18, 2008, the Decision Meeting was held 9
months later, on May 07, 2009. 8 During Project preparation and early implementation, the SSRH was named SSE.
9 GPOBA grant (P114151): Design of innovative OBD schemes for water supply and sanitation Projects in two
Brazilian states (Pernambuco and São Paulo).
The World Bank Brazil São Paulo Water Recovery Project (P106703)
5
20. Lessons incorporated. The Project assimilated lessons from: (i) the Bank supported
OBA approach, in particular from the Mexico Decentralization Infrastructure Reform and
Development Project solutions with respect to unit costs definition; (ii) the Brazilian Water
Basin Pollution Control (PRODES) Program, a federal program sponsored by the National Water
Agency (ANA), which had produced significant experience with results-based financing
mechanisms that partially subsidized construction of WWTPs; (iii) the SABESP investment
programs in reducing water losses, as well as from10 addressing rational water use in public
facilities through performance-based contracts; and (iv) the findings from the International Water
Association’s Water Loss Task Force.
21. Testing OBD effectiveness. The PAD11
highlights that the Project envisaged to properly test in a
wider context the effectiveness of the results-based mechanisms in terms of: (i) encouraging investments
in activities aimed at increasing water quantity and improving water quality in the most seriously
compromised watersheds in the State of São Paulo; (ii) promoting transparency and efficiency; (iii)
improving access to services by the poor; (iv) demonstrating potential for scale up and replication; (v)
providing solutions to the difficulty faced by municipalities and utilities in putting up funds in advance to
finance Projects; (vi) supporting weaker municipalities and service providers so they would be capable of
competing for the funds and implementing the activities; (vii) ensuring a better application of funds and
improved services within a reasonable timeframe; and (viii) shifting performance risk from GESP to
selected service providers.
22. Key inputs that shaped the Project design. Early during Project preparation, the SSRH
launched the Projects’ first Call for Proposals (CFP)12
. The Project results-based financing specifications
were still under development, but it was already defined that the Project-targeted territory would
encompass the five most critical watersheds13
in the São Paulo state. The SSRH received 165 proposals
with a total value of US$259.38 million14
. The significant response indicated demand for the Project
results-based approach, and provided guidance on the distribution of the Project funds amongst its
components.
23. Pioneering legal and technical tools, as well as decision chain. The Projects’ innovative nature
required the development of several new technical and legal tools consisting of: (i) the CFP procedures
aimed at the participants selection; (ii) the set of six normative presenting in detail the methodology and
unit costs; (iii) the PPA model, which set forth the obligations in the implementation of the activities and
constituting the legal contract15
to be signed by the service providers and the SSRH; (iv) the Verification
Agent (VA) procedures to verify that the agreed outputs have been produced in accordance the signed
PPA; (v) the Implementation and Targets Plan providing the baseline information; and (vi) the overall
detailed procedures for the preparation, implementation, and monitoring of each activity.
10 SABESP’s Programa Uso Rational da Água (PURA) intervenes in public facilities such as schools, health centers
and hospitals, as well as prisons. 11
Project PAD dated March 26, 2010. See paragraphs 11 and 15 in pages 5 and 6 respectively. 12
The Project first Call for Proposals was launched in November 27, 2008. 13
The five most critical watersheds encompassed: 40,000 km2; 30M people; and 191 municipalities. 14
REAGUA Project - QER Meeting Minutes, dated March 30, 2009. Page 2. 15
PPA/contract as designated by the SSRH: Contract for Concession of a Financing Stimulus to the Water Recovery
Activity. REAGUA Project Operational Manual, Vol. 1, page 23.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
6
24. Readiness of required implementation tools: By the completion of Project preparation
activities, the degree of readiness of the required implementation tools was uneven. The most advanced in
preparation was the set of normative. This was essentially conceived and developed in the few months of
the preparation phase, benefiting from ANA’s PRODES and SABESP’s performance-based contracts
tested implementation tools. However, the other several technical and legal required instruments were left
in very preliminary stages. The development of the PPA — the legal contractual document — proved to
be one of the most difficult to achieve. It generated broad, long and complex discussions, triggering
numerous unexpected and challenging technical and legal issues. One of those referred to the legal
implications associated with GESP providing a grant to SABESP, given that GESP held 51 percent of
SABESP’s shares, while the remaining was held by the private sector. During the preparation phase, no
conclusion was reached regarding the results-based PPA contract template. In addition, the development
of other critical technical tools and procedures pertinent to Project implementation, such as the
specification for the VA activity, was left to be resolved at the implementation phase of the Project. The
lack of readiness of these key technical tools significantly undermined and delayed the Project
implementation.
25. Implementation arrangements. At appraisal, the Project aimed to operate through PPA
contracts between the State and the operators, which were selected by a demand and merit approach. The
SSRH staff were expected to ensure Project oversight, while two private consulting companies were
expected to be selected, one to support the overall Project implementation activities and, the other, to
carry out the VA attributions. The arrangements were consistent with those prevailing in most of the
lending operations in the country.
26. Other relevant elements. Other elements that impacting on quality at entry related: (i) The
reference unit price: The definition of the reference unit price was one of the most complex activities
undertaken during preparation. It involved a detailed study tn the construction costs of water and
sanitation infrastructure practiced both in the State of São Paulo and at national level, as well as
developing a cost model for the typical activity under each subcomponent. These were used in calculating
and establishing the payments that would be received when complying with the implementation and
sustainability conditions; (ii) The two-phased payment: The results-based approach considered two
payment phases (implementation and sustainability). The payments during implementation sought to help
the provider to overcome, at least partially, the lack of funds for executing the activity. They were
disbursed against partial results or execution stages achieved. The sustainability payments were disbursed,
after the subprojects were operational, against achievement of agreed targets and sustainability conditions.
Partial compliance resulted in partial payments. The ratio for control of water losses activities was 60/40,
while it was 70/30 for the other subcomponents; (iii) The total cost: The Project was not informed on the
expected or actual costs of the activities it supported. Payments were calculated assuming counterpart
funds were necessary and were expected to be significantly larger than the Project financial incentive,
especially for the construction of WWTPs; and (iv) The financing: The activities supported by financing
were also eligible under the Project, excluding those supported by a grant, since the Project also provided
grants.
2.2 Implementation
27. Slow implementation takeoff. The Project faced severe delays over the first two- years (2011
and 2012) to get actual implementation off the ground. The following reasons can be ascribed to the slow
takeoff:
The World Bank Brazil São Paulo Water Recovery Project (P106703)
7
(a) Lack of an approved PPA template. The final version of the PPA fell under the GESP
juridical department responsibility, beyond the SSRH institutional scope and control.
(b) Delays in contracting both the management and the Verification Agent (VA) teams. It was
only accomplished by the end of the Projects’ second implementation year.
(c) Fine-tuning the operational procedures. Once the two consulting companies were finally on
board, it became evident that the overall operational procedures, as well as the VA protocol,
needed further detailing, updating and a reality check.
(d) Learning-by-doing. Both the Project management and the VA teams underwent a learning-
by-doing process, developing while also implementing and revising the measuring and
evaluation tools.
(e) Tailored technical assistance. It became increasingly evident that technical support was
needed. Two Bank consultants that played a fundamental role in the preparation phase
provided intense tailored clarification and training.
28. Substantial demand drop. During the Project life cycle, three CFPs were launched to attract
demand in meeting the Project financing availability. The first CFP resulted in a demand almost three
times the Project total funds; the two others generated enough demand to commit all the remaining
available funds. However, as the process evolved (i.e., selection, signing of contract, and implementation),
the drop in participants and funds commitment was substantial16
. The reasons for the drop included:
(a) Given the long period of 4 years between the first CFP launch (early in the Project
preparation) and the subsequent selection and contract signing, many providers declined from
participating in the Project.
(b) Many of the proposals from the first CFP had inconsistencies with the results-based approach
since the set of normative was not ready, thus were not disclosed.
(c) Lack of upfront own or other financing, in disagreement with the CFP requirements.
(d) Provider declined to participate considering that committing to the Project was too complex
and not financially rewarding.
(e) PPA template limitations, such as no reference unit price adjustments during the contract
duration and no retroactive financing (several proposals from the first CFP were already
under implementation when signing a contract with the Project was proposed).
(f) Provider obtained a Federal grant. which would offer better financial incentives and then
became ineligible.
(g) Long delays faced by the SSRH in obtaining internal clearances, in particular from the legal
department, to allow the signing of contracts, triggered more dropouts.
(h) No payment for results could be made until the VA had been hired17
and was performing the
evaluations activities, thus severely affecting the proposals under the first CFP, launched 4
years earlier.
(i) Proposal implementation timeline no longer compatible with the Project implementation
period.
(j) Proposal was already under implementation when there were changes in the designs, thus the
proposal submitted to the Project was no longer valid.
16 First CFP:165 proposals received, 19 contracts signed, and 11 implemented. Second CFP: 26 proposals received,
14 contracts signed, and 7 implemented. Third CFP: 10 proposals received, 9 contracts signed, and 8 implemented. 17
The VA contract was signed in August 2012, as well as contract with the consulting company to perform the
Project management activities. The gap period between the first Call for Proposal and the VA contract signing was
approximately 4 years.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
8
(k) Proposal submitted by a municipality in which the water and sanitation services were
delivered by a private service provider, or the selection process to concede the concession to
a private company was ongoing were not eligible.
29. Issues that significantly changed Project commitments and disbursement projections. At
each CFP, the results achieved in terms of number and costs of the proposals submitted led to the
conclusion that the Project funds were fully committed. However, as the processing progressed, several
downward adjustments were necessary. Finally, by Project closure just about 42 percent of the total
Project funds were disbursed. The main reasons included the following:
(a) Impact of the Brazilian currency depreciation. Significant appreciation of the dollar vis-à-vis
the Real (43 percent increase from April 2009 to May 2017) increased uncommitted and
undisbursed loan proceeds.
(b) Water and financial crisis. The unprecedented drought from 2014 to 2016 in São Paulo
significantly affected investments prioritization by the service providers particularly
regarding those contracts that were meant to carry out sanitation investments. Most of these
investments were put on hold while all efforts were focused on activities to increase water
supply. Also, given the severe drought affecting the state of São Paulo, water losses in places
where there was rationing (about 6 cases), caused difficulties in establishing the baseline and
results measurements, brought about by the intermittent supply of the water service.
(c) New Component 4 added during restructuring. In the November 2015 restructuring, the
added component addressing emergency works for water supply was expected to absorb the
uncommitted loan proceeds. However, its implementation was not initiated given GESP fiscal
and financial crisis that hit the State in early 201impacting on counterpart funds availability.
30. Mid-Term Review (MTR). The MTR mission took place in September 2013. Despite the low
disbursements, the PPA commitments at that time were evaluated as sufficient to achieve the PDO and
able to absorb all remaining Project funds by the Project closing date. In addition, the operational process
was analyzed and some opportunities for improvement were identified, such as revising the PPAs to
reduce the time of the last payments and increasing the incentive payments. However, these were deemed
to only bring marginal acceleration and were not pursued given the expected difficulties with amending
these contracts in Sao Paulo. However, after the MTR, several simultaneous and unexpected unfavorable
events took place, such as the eventual dropping of various contracts mostly due to the financial crisis
and/or legal issues (the three largest contracts valued at a combined US$26 million failed), as well as the
dollar appreciation peak of about 80 percent in the following 2 years. These again, led to a commitment
lag, which was at the time addressed by the third CFP. In retrospect, the MTR may have missed the
opportunity to improve the PPA’s financial rewards. Improvements on this front would have accelerated
Project implementation by reducing the requirement of counterpart funds and likely preventing some
drop-outs.
31. The Project restructuring. The Project restructuring and the original closing date coincided. At
restructuring, the total loan proceeds disbursed and total estimated commitments were 25 and 58 percent,
respectively18
. The restructuring responded to GESP request to help in addressing the then ongoing
18 REAGUA Project ISRs # 9 and # 10.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
9
drought crisis in the State of São Paulo19
and among other changes, reallocated funds from other
components to finance complex activities under the new Component 4. In retrospect, the planned
timeframe (18 months) to implement the new component was over-optimistic.
32. Technical assistance, capacity building and training. While the Project was supposed to
provide technical assistance, capacity building and training to support the service providers in the design,
operation, and maintenance of programs and facilities associated with the implementation of Components
1 and 2, these activities were not implemented. Based on ongoing implementation learning, the
government and Bank team agreed that tailored assistance would provide greater benefits. The two Bank
consultants who were pivotal in developing the project results-based approach delivered it. Finally, it was
also foreseen to finance an impact evaluation study on the OBD financing scheme vis-à-vis the traditional
input-based financing approach. This study was canceled in the November 2015 restructuring given the
difficulties associated with the methodology.
33. Project success in implementing non-intensive capital investments activities. In summary, the
Project results-based approach was very successful in financing non-intensive capital investment
activities (such as the control of water losses, and rational water use). In contrast, it was less successful in
supporting capital-intensive activities (such as waste water treatment facilities). Regarding the control of
water losses and rational water use (in particular those selected through the third CFP), the Project results-
based approach was able to: (i) influence the technical solutions; (ii) provide a meaningful financial
incentive; and, (iii) contribute to a reasonable implementation timeframe. With respect to the sewerage
investments, the Project results-based approach did not achieve the expected results. Table 2 provides key
information on the contracts implemented.
34. Selected providers. The Project supported 23 results-based contracts, which were implemented
by 8 providers20
. Four21
of those responded to 95 percent of the total Project funds allocated to the results-
based financing. Some of these providers were rated amongst the best performing ones in the State of São
Paulo22
.
35. Results of testing OBA effectiveness. Project implementation generated a wealth of information
on the effectiveness of the results-based approach tested in a very wide range of conditions. The most
relevant are summarized below:
(a) Demonstrating potential for scale up and replication. The results indicate that the results-
based approach was an appropriate mechanism to support activities that do not require
intensive capital investments. It was successful in shifting the focus from implementation to
the results, promoting changes in the providers’ management culture and promoting the
adoption of new technologies. This also gave autonomy and flexibility to the provider’s
technical teams involved, resulting in greater agility and efficiency in using the financial
incentive offered by the Project. However, the results-based approach did not promote
19 The proposed 2015 restructuring of the REAGUA Project, along with the restructuring of the Mananciais Program,
also carried out in 2015, allowed the Bank to provide critical and timely technical and financial support to GESP and
SABESP in facing unprecedented water supply crisis affecting the MRSP. 20
SABESP; SANASA, Campinas; SAAE, Guarulhos; SAAE, Indaiatuba; CODEN, Nova Odessa; SAAE, Santo
André; SAAE, Sorocaba; and DAEV, Valinhos. 21
SABESP, 50 percent; SAAE Indaiatuba, Guarulhos, and SANASA, 15 percent each. 22
Ranking of WSS in Brazil (Ranking do Saneamento no Brasil, 2015); Instituto Trata Brasil and GO Associados.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
10
changes in the water and sanitation capital intensive investments. Their designs, execution
procedures, timetable23
, and costs remained unchanged. Moreover, it was emphasized that all
sanitation investments financed by the Project received simultaneous support from input-
based financing, since no utility committed to such investments otherwise.
(b) Providing solutions to address the difficulty faced by utilities in putting up funds in advance
to finance sub-projects. Greater support through the implementation phase, coupled with
higher reference unit costs, could have triggered more favorable implementation of the
activities under the Project24
.
(c) Shifting performance risk from GESP to selected service operator. According to statements
from the mid-size utilities representatives, the payment for results-based approach actually
induced the transfer of risks to the technical team in charge of implementing the intervention,
generating anxiety and defensive attitudes. The technical team saw advantages in the results-
based approach and took the initiative to sell it to the company, but faced doubts particularly
from the financial department, which claimed that the risk of not accessing the full incentive
support was high. In large-size utilities, such dialogue concerning the results-based financial
support was not under debated. Committing to the Project was a high-level decision aligned
with government initiatives.
36. Risks. There were two risks not considered during Project preparation. Underestimated: (i) the
high dependency on traditional input-based financing for sanitation investments; and (ii) the unforeseen
execution timeline for these investments in order to comply with regulations applying to technical,
institution and environmental rules.
37. The VA contract designs. The VA contract was the first of such contracts in Brazil. Its
implementation successfully met the expected results, providing sound indications that the contract as
conceived was appropriate and constituted a solid contribution from the Project for future similar
operations. Nevertheless, in order to fully understand their tasks, as well as the Project results-based
approach, the VA team required significant training provided by the Bank consultants. Still, the VA team
undertook all activities under its contract, providing the required information for issuing the Project
results-based payments. No complaint against the VA was registered and no amendment to the VA
contract was required. Moreover, the providers supported by the Project were soon able to clearly
distinguish the roles performed by the VA and those undertaken by the Project management team.
38. Low disbursement (51 percent) but Project achieved 98 percent of the PDO indicator target
value. At Project closure, the target value of the PDO indicator “cubic meters of recovered water” was 98
percent achieved, although only 51 percent of the Project total funds were disbursed. Moreover, 92
percent of the PDO indicator target value achievement resulted from the implementation of just one sub-
23 Information provided by Project stakeholders that also participated in the ANA’s PRODES Program, the
implementation timetable of the WWTPs that received incentive from PRODES ranged from 10 to 16 years.
However, as the PRODES financial incentive was deposited in a special escrow account which benefited from
interest rate returns, when it was allowed to be withdrawn (by the agreed results verification), the amount in the
account had increased at least accordingly with inflation. 24
The activities addressing reduction and control of real water losses were also supported by different input-based
financing such as from the São Paulo State’s water resources funds (FEHIDRO) and the Institutional Development
financing lines financed by the Federal Bank (CEF). They had the support of own source revenues and/or labor
resources. Interventions implemented by SABESP were, in some cases, complemented by the company’s large
losses control performance-based program.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
11
component — control of water losses. The Third CFP, which targeted only water losses, focused on sub-
projects with ongoing water losses programs, which required modest investments but yielded high
volumes of recovered water.
39. The strong depreciation of the Brazilian currency to the dollar. The Brazilian currency
experienced a 43 percent depreciation against the dollar during the Project disbursement period but
peaked to nearly 80 percent depreciation from September 2013 to December 2015. While this
significantly increased the undisbursed loan proceeds, it did not affect the implementation of the signed
contracts and the achievement of the targets associated with them.
40. Uneven Project achievements. Component 1 largely exceeded in achieving the associated
indicators’ targeted values, almost entirely supported by the subcomponent “water losses control”. The
latter exceeded its target by 143 percent that had been increased at the 2015 restructuring, which was, in
turn, 333 percent larger than the target set at appraisal. However, this remarkable achievement was
supported by an increase of just 33 percent of funds (from the appraisal estimates to the actuals at the
Project closure). Component 2 contribution to the achievement of the PDO level indicator was minimal
— only 6 percent, while Component 4 did not contribute since it was not implemented.
41. Final and verified results larger than Providers’ estimates. The implementation of the results-
based approach and subsequent verification process revealed that the providers supported by the Project
made a downward estimate of the volume of water to be recovered in order to avoid eventual Project
financial penalties and criticism from other departments.
42. Realism in Project design. With the benefit of hindsight, the Project could have been able to
achieve its targets with a more realistic design and restructuring.
43. The control of water losses approach constitutes an exceptional contribution to the sector. Nevertheless, despite of the shortcomings mentioned above, the Project results-based approach addressing
control of water losses achieved remarkable success acknowledged by all the Project stakeholders. They
stated that the approach, beyond achieving the results pursued, established a practical and innovative
solution to one of the most complex and difficult challenges in the water industry worldwide.
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
44. The M&E design. The M&E system was well defined. It was able to translate the Project
objectives and components into just a single simple indicator – cubic meters of water recovered. In
addition, the information provided under the “use of Project outcome information” column of the PAD,
Annex 3, constituted a clear guidance regarding the underlined message conveyed by the PDO and
Intermediate Outcome indicators. The intermediate results indicators were aligned with the Project
components and the systematic collection of data and periodic results tracking was an integral part of
Project implementation. The PMU capacity to undertake the M&E system requirements was appropriate
and was further strengthened by the VA procedures.
45. The M&E implementation and utilization. Implementation was straightforward given the
simplification allowed by the adoption of a single PDO indicator. Also, the combined contributions from
the management firm and the VA contributed to a smooth follow-up of the Project goals throughout
implementation, including timely and meaningful Project implementation reports. A study on the impact
evaluation part of the Project design was dropped in the November 2015 restructuring given the
difficulties associated with technical specifications embedded in the study, including finding a control
The World Bank Brazil São Paulo Water Recovery Project (P106703)
12
group. The study findings were expected to provide significant inputs to evaluating the Project against not
only its objective, but also against the numerous assumptions raised in the PAD. In the restructuring, two
new PDO indicator were added. In all, the M&E system was utilized as a tool to register the PDO and
Intermediate targets values and to guide managerial and operational decisions, in particular the inclusion
of two additional subproject selection processes and the new Component 4.
2.4 Safeguards and Fiduciary Compliance
Safeguards
46. Safeguards compliance. During implementation, the safeguards performance evolved from
Moderately Unsatisfactory, to Moderately Satisfactory, and finally to Satisfactory. The Project was an
Environmental Category B. It triggered the following safeguard policies: OP 4.01 Environmental
Assessment; OP 4.04 Natural Environment; OP 4.11 Physical Cultural Resources; and OP 4.12
Involuntary Resettlement. An Environmental Safeguards Framework defining criteria and procedures the
selected water and sanitation providers needed to observe when developing and implementing the
activities. In addition, a Resettlement Management Framework was prepared, although the activities
triggering the Resettlement policy were not eligible for participation in the Project. Both frameworks
were incorporated in the Project operational manual. The environmental procedures in place were
reviewed and few adjustments were made. In the November 2015 restructuring, Component 4 was added
to the Project. The detailed designs available for the activities incorporated under the new component
allowed for a detailed screening concerning the safeguards triggered. All designs complied with the
safeguard policies, including the resettlement policy. Nevertheless, as indicated before, none of the
activities under the new component were implemented.
47. OP 4.01 Environmental Assessment. In agreement with the Environmental Framework, the
activities selected for financing by the Project presented, as part of the mandatory documentation, an
environmental screening sheet. During the activity implementation, the procedures described in the
Construction Manual included in the Project operational manual were followed.
48. OP 4.04 Natural Habitat. This OP was triggered because there were environmental protected
and conservation areas within the five headwaters targeted by the Project. The activities financed by the
Project were screened to ascertain if any impact on these areas could occur. It was confirmed that none of
the activities the Project financed had impacts on these areas.
49. OP 4.11 Physical Cultural Resources. The Project was not expected to affect areas of historical
and cultural relevance. Nevertheless, the Environmental Framework incorporated chance-finding
procedures.
50. OP 4.12 Involuntary Resettlement. The activities triggering the Resettlement Policy were not
eligible for Project financing. Nevertheless, a Resettlement Framework was prepared and incorporated in
the mandatory documentation the selected activity had to comply with.
Financial Management
51. During implementation, financial management was rated as Satisfactory or Moderately
Satisfactory. Initially, there were delays in adjusting the State’s Administrative System to generate
Interim Financial Reports (IFRs) and the need to strengthen the internal control arrangements further.
These aspects improved during implementation. The PMU and the Management firm’s experience were
The World Bank Brazil São Paulo Water Recovery Project (P106703)
13
also important factors to ensure acceptable financial management arrangements throughout Project
implementation. Agreed action plans were generally implemented, but were not sufficient, to improve
disbursement, especially during the last years of the Project, as a result of the devaluation of the Brazilian
Real since 2015 and fiscal constraints. The financial management risk rating was considered Moderate
throughout the Project’s life. Audit reports were generally received on time (with the exception of the
2014 and 2016 reports). All audit reports expressed unqualified/unmodified audit opinions (with the
exception of the 2015 report, as the IFRs did not reconcile the opening balances). Although some IFRs
were received with delays, they were all considered acceptable. There were no instances of ineligible
expenditures identified.
Procurement
52. During implementation, procurement was rated Satisfactory or Moderately Satisfactory.
Procurement under the project was implemented at two levels. The PMU established within the SSRH
was responsible for procurement under Component 3, while water and sanitation service providers,
selected by the SSRH through the procedures informed by the launched CFP, were responsible for
procurement under Components 1 and 2 (following applicable Federal Law 8,666/93 with procedures
acceptable to the Bank). However, during Project preparation, both the Bank and the government teams
faced severe difficulties in agreeing upon appropriate legal and technical documents that were also
acceptable by eligible providers identified at that phase. Although it happened almost 10 years ago, the
teams involved still cannot forget the numerous and very difficult issues that had to be resolved to agree
on the final version of these documents. During Project implementation, the quality of the procurement
processes varied: while in some cases, the processes were well prepared and quickly implemented, in
other cases, they were very confused and slow. Clearly the quality of the procurement processes depended
on technical and political issues. The critical drought the State of São Paulo faced during Project
implementation contributed to the mixed performance. The Project team lacked previous experience with
Bank's procurement to select consulting services. This was a major issue at the start of Project
implementation (specially for Component 3). Gradually, it evolved to difficulties associated with
government administrative aspects and quality of technical documents. For the activities implemented
under Components 1 and 2, the selected providers had solid experience in addressing the national
procurement legislation requirements, and no remarkable issues had to be surmounted to increase the
provider’s capacity to comply with the procedures acceptable to the Bank. Despite these minor issues,
from a procurement point of view, the quality of the procedures followed by the Project was acceptable.
No major issue such as a mis-procurement or ineligible expenditure was declared or found.
2.5 Post-completion Operation/Next Phase
53. The Project results-based approach underpinned sustainability. Sustainability of the activities
under the subcomponent ‘control of water losses’ was verified by the VA, who confirmed that the agreed
targets and sustainability conditions had been met triggering the authorization for the last payment tranche.
Payments under the other two subcomponents addressing increasing water quantity as well as the three
subcomponents addressing water quality were scheduled as follow: 70 percent of total contract amount
paid during implementation, and 30 percent paid once compliance with sustainability targets was met.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation (Pre- and Post-restructuring)
The World Bank Brazil São Paulo Water Recovery Project (P106703)
14
54. The relevance of objective is rated Substantial. The objective of Project was consistent with
the development priorities and circumstances at the time of Project preparation and implementation. The
FY08-FY11 Country Partnership Strategy (CPS), dated May 1, 2008, laid out a program of continued
support to Brazil through four pillars of engagement: equity, sustainability, competitiveness, and sound
macroeconomic management. The CPS asserted that Brazil continued to falter in the area of
environmental sustainability, and that water scarcity and environmental degradation were urgent problems
hindering the country’s sustainable growth. The FY12-FY15 CPS 25
, valid by Project closure, was also
structured around four strategic objectives: (i) increase the efficiency of public and private investments;
(ii) improve quality and expand provision of public services for low-income households; (iii) promote
regional economic development through strategic investments and policies; and (iv) and improve
sustainable natural resources management and climate resilience. The third and fourth strategic objectives
were highly relevant to the Project’s rational and objectives. The results areas under these strategic
objectives were also closely aligned with the programmatic engagement with the State of São Paulo;
namely, improved policy coordination at territorial level, expanded access to improved basic sanitation,
integrated water resources management, and improved environmental management.
55. In addition, the Program objective’s relevance to the current situation of the country still remains
high. It is consistent with FY18-FY23 Country Partnership Framework (CPF).26
The third priority area
identified in the CPF focuses on inclusive and sustainable development with the objective, among others,
to increase urban resilience and provide more sustainable and inclusive urban services. Promoting the
improvement of the quality of urban infrastructure, improving the efficiency of service delivery, and
building resilience of populations against the variability of water supply are among the key activities
proposed. In conclusion, the Project objective is still closely aligned with the CPS in place by the Project
closure and the CPF valid for the coming years. Also, the SSRH during a workshop carried out by
Project closure indicated that it intends to continue to apply the Project’s results-based approach as a
financing method for future sector programs. This was also confirmed in the client’s letter included in
Annex 7.
56. The relevance of design and implementation is rated Modest. The Project design and
implementation proved to be relevant, as well as timely, particularly in adapting innovative tools to
address water recovery through several activities including water loss and wastewater treatment. The
Project developed and tested these tools, which constitute a major contribution to the water sector
worldwide. Additional positive aspects include: (i) the choice of priority basins that were prone to
drought; (ii) the incorporation of lessons learned; and (iii) the focus on both implementation and
sustainability aspects. As discussed earlier in Section 2, there were some shortcomings during
implementation including: (i) limited appropriateness of the results-based approach for supporting capital
intensive activities such as large sewerage system investments; (ii) limited state of readiness; and, (iii) the
ambitious timeframe.
3.2 Achievement of Project Development Objectives
57. The Project’s PDO remained unchanged over the life of the Project. However, the PDO indicator
target was amended during the November 2015 restructuring and new PDO indicators were added. Still,
25 CPS report number 89498 - BR, FY2012—2015.In 2016, the World Bank launched the Brazil Systematic Country
Diagnostic (SCD) to inform the preparation of a new Country Partnership Framework (CPF). 26
In June 2017, the Board approved the Brazil’s CPF for FY2018-2023 —report number 113259-BR.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
15
as the PDO indicator target value was not reduced but increased, a split evaluation was not considered
relevant.
58. PDO objective: To increase clean water availability in the State of São Paulo’s critical
watersheds. Rating: Modest
59. Achieving the PDO Objective — Pre-restructuring. Prior to the 2015 restructuring, the
achievement of the PDO Objective was measured by a single PDO-level indicator: Cubic meters of
recovered water. The original appraisal target was 30,1106,311 m3, which was expected to be achieved
through the implementation of the six subcomponents included under Components 1 and 2. By the fifth
year of implementation, the Project had achieved approximately 90 percent27
of the target. Though, this
achievement was met through the implementation of just one of the six-subcomponents, the
subcomponent that addressed control and reduction of real water losses, which responded for 97 percent
of the PDO-level indicator achievement. The implementation of the activities under the other
subcomponents contributed to only 3 percent.
60. Achieving the PDO Objectives — Post-restructuring. In the 2015 restructuring, the original
PDO-level indicator (cubic meters of water recovered) was retained, although its target was increased by
159 percent to 47,966,660 m3. Also, two new PDO-level indicators were added: direct project
beneficiaries, targeting 289,686 people; and female beneficiaries, targeting 51percent of direct project
beneficiaries.
(a) Regarding the original PDO-level indicator, the Project helped to recover 47,127,718 m3
against the revised target of 47,966,660 m3. The revised target was expected to be achieved
through the implementation of the five remaining28
subcomponents under Components 1 and
2, although the expected weight given to the subcomponent that addressed control and
reduction of real water losses increased from 30 percent to 63 percent. Nevertheless, by the
Project closure, once again this subcomponent largely responded to achieving the PDO-level
indicator by 96 percent.
(b) Regarding the direct Project beneficiaries, the Project directly benefited 97,373 people
against a target of 289,686 people (33 percent). The low achievement is explained by the
difficulties faced by the components tied29
to this PDO-level indicator.
(c) Regarding female beneficiaries, 51 percent of the direct Project beneficiaries were female.
Thus, the target was fully achieved.
61. With respect to the ‘clean’ water aspect of the PDO, the Project achieved 96 percent of the
revised target since the additional water recovered is also potable. In addition, Component 2 regarding
‘enhancing wastewater quality’ was also supposed to contribute to the ‘clean’ aspect. There is a strong
likelihood of achieving the results associated with Component 2 on ‘Enhancing Water Quality’. The
27 By the Project original closing date, November 30, 2015, the achievement of the PDO-level objective “Volume of
recovery water” target (30,106,311 m3) was 90 percent. The implementation of the activities under subcomponent
“Control and reduction of real water losses” had produced 26,569,790 m3 of recovered water, thus responding for 97
percent of the achievement concerning the PDO-level indicator. 28
The subcomponent on Reuse of Treated Wastewater was dropped during the November 2015 restructuring given
the lack of signed contracts under this subcomponent. 29
In the November 2015 restructuring, when the PDO-level indicator “Direct project beneficiaries” was added, it
was defined that the target would be achieved through the implementation of the activities under Component 2 and 4.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
16
implementation of six subprojects under Component 2 continued after the Project closure, with five
having active contracts with the State. The five ongoing subprojects expect to result in 4.4 million m3 of
water recovered per year and are considered likely to be completed between 2018 and 2019. The
remaining subproject without a contract so far, a big WWTP in Campinas, is expected to result in 3.9
million m3 of water recovered per year, but its date of conclusion is uncertain at this point. Assuming that
these 6 subprojects are completed, the total result for Component 2 would reach 86 percent of the overall
goal in enhancing water quality.
3.3 Efficiency
62. The efficiency of the Project is rated Substantial. The ex-post economic analysis carried out,
which was based on a sample of subprojects, indicates that the Project had a positive return and positive
impacts. Nonetheless, the most positive results derived from the high performance of activities under
Component 1, Subcomponent 1.1 on Control and Reduction of Water Losses, which was responsible for
93 percent achievement of the PDO goal. Results for Subcomponent 1.2 on Rational Use of Water was
modest. The results for activities under Component 2 on Enhance Water Quality were also modest and
were heavily influenced by the opportunity cost of avoiding government-imposed fines for non-action.
63. At appraisal, a Cost-Benefit Analysis (CBA) was carried out using a sample of proposed and or
similar subprojects in representation of each subcomponent. A total of six cases were analyzed. The CBA
analysis conducted for the above set resulted in positive returns and an overall economic Internal Rate of
Return (IRR) of 65 percent. None of the initially evaluated subprojects eventually participated in the
Project.
64. Summarizing Project results at closure. A total of 23 subprojects were implemented and their
results verified (refer to Table 1 in Annex 2). In terms of results, subcomponent 1.1 outperformed the
other subcomponents with a 93 percent contribution to the PDO results indicator while receiving only 37
percent of the total Project payments.
65. The ex-post analysis of the Project followed the appraisal evaluation concept, and comprised the
analysis of a new set of representative sample subprojects for Components 1 and 2 that had been carried
out to full completion (including sustainability period) as shown in Table 1 below.
Table 1: Sample Subprojects Analyzed
Brief Description of activities Verified water
recovered
results (m3/year)
% of total
Project
Component
Component 1 Water losses
SANASA First and
Second Batches for
Campinas
Infrastructure replacement,
sectorization, pressure management,
active leakage control in Campinas
3,578,490 8
Component 1 Rational
Use of Water in SANASA
Environmental education, equipment
and works carried out in 200 schools.
240,244 70
Component 2 Wastewater
Transport and Treatment
Boituva
Wastewater transport and treatment
serving a target of about 25 percent of
the city
409,968 13
Total Verified Results 4,228,702
The World Bank Brazil São Paulo Water Recovery Project (P106703)
17
66. Costs for Component 1 were approximate, particularly for the SANASA rational water use
subproject, as several SANASA personnel were significantly involved throughout the subproject timeline
and their salaries were not accounted for. The amount of additional water recovered under Component 1
through water losses and rational use of water subprojects was valued at marginal cost (US$1.8/m3)
..
Benefits for wastewater transport and treatment in Boituva under Component 2 included: (i) the volume
of BOD and COD pollution loads removed; (ii) the beneficiaries value of improved sanitation; and (iii)
the burden of disease avoided. Other environmental benefits, like nitrogen and phosphorus removal were
not included. In addition, an opportunity cost, derived from fines to be imposed by the Public Ministry for
non-action for curving pollution, was used as a proxy for minimum benefits.
67. Table 2 below shows the results of the analysis. Since none of the initially evaluated subprojects
eventually participated in the Project, the economic IRRs at appraisal and completion are not comparable.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
18
Table 2: Cost-Benefit Analysis Results
Subcomponent Benefits (NPV) Costs (NPV)
Results
IRR
(%)
B/C at 10%
Discount
Rate
Water Losses
SANASA
Life period 10 years
Measured as water
recovered at marginal
cost
Investment costs plus
coordination costs
63 5.6
Efficient Use of
water
SANASA
Life period 20 years
Measured as water
recovered at marginal
cost
Investment costs plus
SANASA coordination
and operational costs
14 1.37
Waste Water Boituva
Life period 25 years
Pollution Loads
removed
Beneficiaries valuation
Burden disease avoided
Opportunity cost
Actual investment costs 22 2.49
Wastewater with
opportunity cost
alone
Opportunity cost Actual investment
costs
16
68. The high return of the SANASA water losses subprojects is consistent with the sector experience
with these types of activities, and particularly, in this case the zones intervened had reasonably good
infrastructure and therefore getting the results required measures such as pressure management, leakage
control, and other activities that required moderate investments. Additional benefits not quantified derive
from the fact that there was a learning experience with new methodologies, and the establishment of
improved leakage control programs to the recipients, which are expected to increase and become
permanent.
69. Results of the water school programs were also positive. The analysis of benefits focused on the
water recovery aspect of the subproject and excluded those related to the environmental education part.
The training of students in efficient use of water represented a very successful program. Furthermore, the
program is currently expanding within Campinas and is expected to bring important benefits associated
with a long term rational use of water by the students and their families. In the case of SANASA,
efficiency was impacted by significant amount of internal manpower used, both for the establishment and
coordination and implementation of the Program. Future programs should benefit from this initial
learning curve and be more efficient.
70. The case of Boituva, costs included investments as well as operation and maintenance. An
additional analysis included benefits associated with the opportunity cost derived from high fines the
municipality would have been subjected to given a decree of the Public Ministry requesting the operators
to treat their pollution loads. By adding this benefit, the economic IRR increased from 16 percent to 22
percent. While the benefits were conservatively estimated, the relatively modest returns are not atypical in
these cases of WWTPs serving relatively small cities.
71. The Project was extended by 18 months to help respond to GESP request to help in addressing
the then ongoing and unprecedently drought crisis in the State of São Paulo. Despite all efforts from the
Bank and PMU teams, Component 4 was not implemented as expected due to fiscal and legal issues. The
The World Bank Brazil São Paulo Water Recovery Project (P106703)
19
extension period was important, though, to finalize ongoing Project activities and measure the
sustainability of completed subprojects.
72. The original Project cost was estimated at US$107.49 million. During restructuring, the Project
cost was reduced to US$95.91million, mainly due to: (i) the depreciation of the Real, which was BRL 2.0
per US$ in 2011 and BRL 4.0 per US$ in 2015, doubling the undisbursed loan portion; and (ii) the
cancellation of six contracts (out of 40 contracts) mostly due to the reduced financial capacity of many
operators unable to bear the Project’s financially demanding results-based disbursement mechanism.
73. At time of Project restructuring, good results of the water loss subprojects resulted in the increase
of the cost of Component 1 (even with the cancellation of the subcomponent related to water reuse) to
US$31.67 million (additional US$1 million). On the other hand, the cost of Component 2 faced a big
reduction due to number of delays in implementation, as: (i) many of the initial subprojects were dropped
from the Project as they were financed by other Federal programs; (ii) these investments take longer to be
implemented and to achieve results; and (iii) difficult financial conditions of the service providers have
impacted their capacity to invest. Resources allocated to Component 2 (US$37.12 million) were in
general, reallocated to Component 4 (US$30.65 million). The cost of Component 3 was also increased by
US$2.89 million due to the need to extend the contracts of the management firm and VA to monitor
Project implementation during the additional 18 months. Contingency funds in the amount of US$3.21
million were cancelled.
74. At time of Project closure, however, total Project cost went further down to US$47.40 million (a
reduction of US$48.51million) due to the limited progress on Component 2 (uncommitted funds
US$19.35 million) and nonexecution of Component 4 (US$30.65 million). On the positive note,
Component 1 progressed more than expected (additional US$1.33 million).
3.4 Justification of Overall Outcome Rating Rating: Moderately Unsatisfactory
Table 3. Evaluation Summary
Dimension Rating
Relevance
Relevance of objectives Substantial
Relevance of design and implementation Modest
Efficacy
PDO: Increase the water availability in the
State of São Paulo’s critical watersheds.
Modest
Efficiency Substantial
Rating Moderately Unsatisfactory
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
75. The Project has almost entirely achieved its PDO target value, which was the recovery of
approximately 45 million m3 of water. This total water amount of water recovered corresponds to the
consumption of around 800,000 people per year. Thus, its contribution to social development is relevant,
given the restrictions in water availability faced by MRSP. The impact on poverty was not measured
given the Project focus on water recovery. Moreover, to benefit low-income population, it was concluded
that the results-based scheme must include technical specifications and reference unit prices appropriate
to design solutions suitable to the low-income areas.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
20
(b) Institutional Change/Strengthening
76. The Project has significantly contributed to knowledge creation by testing a methodology to
finance the water and sanitation sector. It was highly successful in developing a methodology to address
water losses, as the financial incentive offered was attractive to the market and, moreover, induced the
selected water and sanitation providers to adopt a technical methodology leading to sound and sustainable
solutions. As such, it contributed to disseminate a practical and innovative solution to one of the most
complex and difficult challenges in the water industry worldwide.
(c) Other Unintended Outcomes and Impacts (positive or negative)
77. None.
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
78. A Stakeholder Workshop, part of the Project ICR preparation, was held in May 2017. In total, 25
participants attended the workshop, including representatives from SSRH, SABESP and SANASA. The
strengths and weaknesses of Project preparation and implementation and key recommendations identified
by the participants are presented below.
79. Project preparation and implementation. The strengths identified by the participants were: (i)
adopting the results-based approach; (ii) focusing on the priority basins; (iii) requiring a sustainability
period; (iv) flexibility given to providers to select solutions leading to agreed results; and (v) the
payments to providers did not require a heavy bureaucracy. The weaknesses in turn included: (i) reference
unit prices not well calibrated; (ii) long delays in selecting and signing contracts with providers; (iii)
difficulties faced in formulating the set of normative; (iv) huge technical differences between activities
under Components 1 and 2, creating difficulties to be handled under the management arrangement; (v)
risks associated with the results-based approach transferred to the technical team; (v) the value of the
reference unit prices was too low and did not include adjustment to inflation; and (vi) it was difficult to
understand the Project operational procedures.
80. Recommendations. Main recommendations for improving performance identified by the
workshop participants included: (i) developing the results-based set of normative was an intense learning
process; (ii) applying the normative addressing control of water losses required prior training; (iii) the
normative addressing sewerage systems needed simplification; (iv) the normative addressing rational
water use was quite appropriate; (v) the water crisis resulting from the drought boosted the control of
losses activities and reduced the investments in sewerage; (vi) the Project implementation generated an
important database that can be used to improve the set of normative; (vii) getting the Project
implementation started was a very difficult task because many indispensable elements were not ready,
such as the contract template, the VA and the management team; and (viii) the less efficient service
providers required prior and more intense capacity building.
4. Assessment of Risk to Development Outcome Rating: Moderate
81. The risk to development outcomes is rated Moderate taking into account that the subcomponent
“Control of water losses” responds to almost 96 percent of the achieved PDO indicator target value. The
adopted methodology for the implementation of this subcomponent was widely acknowledged by the
The World Bank Brazil São Paulo Water Recovery Project (P106703)
21
Project stakeholders as a major success. Moreover, the Project results-based approach included a
sustainability period to ensure the results achieved were sustainable. In addition, some of the water and
sanitation providers that implemented the subcomponent activities have been ranked amongst the most
efficient in the State of São Paulo.30
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry Rating: Moderately Unsatisfactory
82. The Project was well anchored strategically; its preparation was supported by quality technical
work. The Project incorporated the lessons learned from pervious interventions. The Project’s objective
was well aligned with the Government’s sector priorities. The Project envisaged to properly test in a
wider context the effectiveness of the results-based mechanisms. However, the innovative results-based
approach the Project adopted required numerous new key tools indispensable for implementation. During
preparation, one of these tools (the set of normative) was developed, consisting of an exceptional
technical contribution to the sector. Other key tools, such as the contract template including its legal and
technical foundations and required clearances, and the VA and the Project management team, were only
available at the end of the second year of Project implementation. As described in Section 2, there was
limited readiness for implementation when the Project was approved. Also, the Project results-based
approach was based on various technical assumptions. Some of them could be questioned even with the
information available during preparation, such as the feasibility of implementing large investments on
sewerage systems supported by results-based financing and within the Project timeframe. The Project
implementation timeframe (4 years) as presented in the PAD including the sustainability period was
unrealistic. Furthermore, the complexity of the results-based approach was not perceived during
preparation. This was a recurrent issue raised by stakeholders during the Project-closing workshop.
(b) Quality of Supervision Rating: Moderately Unsatisfactory
83. The challenges facing supervision and how these were or were not addressed also emerged from
Section 2, as in the previous paragraph. The lack of readiness for implementation was most likely the
major issue the supervision team faced, and had no option but to follow all the mandatory and complex
technical, juridical and bureaucratic steps in order to have the needed implementation tools ready to start
Project implementation. The first two-implementation years were mostly dedicated to get the Project off
the ground. From concept to the first disbursement, it took the Project almost 50 months, largely longer
that the average 30 months faced by Projects in Brazil. During this phase, the supervision team provided
significant support to the client implementation team, by financing two Bank consultants, who had a
major role in developing the results-based approach during preparation. Their support to the client
implementation team was critical in overcoming technical difficulties emerging as the legal and
contractual aspects were being addressed. In addition, the Bank team held regular supervision missions
and constant additional teleconferences. There was candor in the ISR reporting and the fiduciary aspects
were managed well by the team.
30Ranking of WSS in Brazil (Ranking do Saneamento no Brasil, 2015); Instituto Trata Brasil and GO Associados.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
22
84. The supervision team was less successful in achieving solutions for key aspects that delayed
Project implementation, such as the lack of an inflation correction mechanism in the contract template,
and ensuring that the Project funds were fully committed. During preparation (the first CFP) and three
times during implementation (second and third CFPs as well as in the November 2015 restructuring), the
Project funds were deemed fully committed. The Projections were not correct as the results show – by
Project closure only 58.52 percent of the loan proceeds were disbursed. Nevertheless, it must be noted
that events beyond the Project control such as the drought, alternative competing financing mechanisms,
financial constraints by providers, and fiscal limitation at the State level, were largely responsible for the
Projections failure. Also, the decision made of including an input-based financed component at
restructuring, carried out late in Project implementation, was seemingly not based on sound realism given
the difficulties inherent to the implementation of the investments targeted. Moreover, the reduction of the
loan financing percentage also made during the November 2015 restructuring increased implementation
problems. Nevertheless, a very successful decision was made during implementation: launching the third
CFP tailored for control of water losses activities. The providers engaged had been trained in previous
contracts, the activities were properly designed and implementation was carried out in a timely and
efficient manner.
85. Component 4 was not implemented due to the lack of counterpart funding by the Government.
This was a result of the financial crisis that the country and particularly the state of Sao Paulo was
experiencing. While the Bank team considered partial cancellation of the loan, there was a collective
agreement to see if the financial challenges could be surmounted.
(c) Justification of Rating for Overall Bank Performance Rating: Moderately Unsatisfactory
86. The overall Bank performance is rated Moderately Unsatisfactory
5.2 Borrower Performance
(a) Government Performance Rating: Moderately Unsatisfactory
87. The Government initiative in asking for and supporting an innovative results-based Project was
noteworthy, as well as the support given during preparation when top quality technical knowledge
nationally available was brought to contribute in conceiving the Project results-based approach. Despite
the initial weaknesses with the counterparts, the government subsequently provided the support needed
for Project implementation. The support provided during the first two years of implementation was
particularly noteworthy. During this period, the Project-financed support was not yet available. The
government team responsible for the Project implementation was basically just one person, who managed
to resolve the highly complex issues that the Project preparation had left unresolved. The most significant
shortcoming by the government was the lack of counterpart funds for implementing Component 4 that
was added to the Project in the November 2015 restructuring. Despite the delay in complying with the
legal covenants: (i) Schedule II, Section B, Paragraph 1; and (ii) Schedule II, Section B, Paragraph 2,
overall, the covenants were largely complied with for the duration of Project implementation.
(b) Implementing Agency or Agencies Performance Rating: Moderately Unsatisfactory
88. The implementing agency played an outstanding role in getting the Project off the ground into
actual implementation. It included three different teams: the SSRH own team; a consulting company hired
to carry out the Project management activities; and another consulting company hired to carry out the
verification activities tied to the Projects’ results-based approach. Although the consulting companies
The World Bank Brazil São Paulo Water Recovery Project (P106703)
23
were on board by the end of the Projects’ second implementation year, both teams still had to get deeply
involved in concluding and correcting numerous details in the Project implementation tools. Their
dedication in moving the Project forward, as well as technical capacity was decisive. Nevertheless, they
went through quite a long learning curve and they acknowledged getting to fully understand the Project
along its implementation. They also acknowledged that there were aspects tied to the results-based
approach that were misunderstood during implementation, which required a painful redressing process.
Moreover, the Projections on funds disbursements developed by the Project management team were
recurrently rejected by reality.
(c) Justification of Rating for Overall Borrower Performance Rating: Moderately
Unsatisfactory
89. The overall Borrower performance is rated Moderately Unsatisfactory.
6. Lessons Learned
90. Results-based approach requires substantial effort during preparation. The formulation of
the Projects’ innovative results-based approach required a substantial effort in preparing the set of
normative in order to make them consistent and operational. Innovative financing schemes might trigger
legal aspects the legislation in place does not contemplate, requiring long and complex juridical approval
processes. Therefore, the preparation of a results-based operation must include the full development of
the set of legal and operative normative prior to project implementation
91. Results-based approach needs superior management and verification capacity as well as
technical assistance support to potential beneficiaries. The success of a WSS Project implemented
through results-based financing requires more complex preparation procedures and a superior
management and verification capacity. In addition, more than in a conventional Project, its success
depends on the management capacity of well-structured service providers. The implementation of a
results-based operation requires the support of a technical assistance component to assist the providers in
preparing proposals that will ensure consistency throughout the execution of the activity. The type of
technical assistance needed, depends on its technical, financial and managerial capacity. The Terms of
Reference, as well as the selection of documents to hire the VA must also be fully developed during the
preparation phase. The VA must be available to verify the baseline data that is required for signing the
results-based contract with the provider.
92. Results-based scheme to target the poor need suitable solutions. In order to benefit low-
income population, the results-based scheme must include technical specifications and reference unit
prices appropriate to the design solutions suitable to the targeted neighborhoods.
93. Simplification of verification tools and set of normative: According to statements from the
Project team and providers involved, the verification tools, as well as the set of normative needed to be
simplified. Also, the procedures undertaken by the VA needed to be provided with absolute clarity.
94. Timeframe is essential for results-based schemes to be attractive to providers. The results-
based proposal selection and contract signing must be fast. The long process discourages the operators
interested in participating and causes the proposals to become outdated. In order to speed up the
implementation of results-based activities, the selection process needs to prioritize proposals that
demonstrate more advanced implementation status from the engineering perspective, as well as regarding
compliance with the environmental legislation. It should also contemplate the availability of land, when
The World Bank Brazil São Paulo Water Recovery Project (P106703)
24
required, and seek the participation of well-structured providers complying with a defined management
capacity threshold. In addition, the results-based contract must include mechanisms adjusting the
reference unit prices to inflation, particularly, for those activities requiring long implementation periods.
The absence of rules that preserve the contract value might result in breaking the supporting financial
balance and its feasibility.
95. Complexity or long implementation interventions and sustainability conditions need to be
revisited in case replication of the Project is envisioned. Activities requiring long implementation and
complex compliance with the environmental legislation, such as the construction of WWTPs, are most
likely not good candidates for financing operations limited to a five-year implementation period because
the sustainability time might exceed the implementation period. In order to ensure solid sustainability
conditions, the sustainability period considered under the Project needed to be revised, in particular for
those activities that depended on deep cultural and institutional changes, as it is the case for the WWTPs.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
96. Annex 7 provides the comments by the São Paulo State Governor on the draft ICRR. In general,
the Borrower appreciates the final assessment of the Project and acknowledges to have no disagreement
with the challenges and shortcomings in Project design and implementation identified in the report.
Considering the pilot nature of the operation and the external factors that impacted its implementation
such as the unprecedented water crises in the state and the economic crises, the Borrower feels that the
report has underestimated some of the ratings.
97. It is the Government’s view that the situation was not as severe as stated in the report to justify
the Moderately Unsatisfactory ratings in several aspects of the Project. Key aspects to take into account
include:
(a) The innovative design which impacted on overall Project costs.
(b) The several changes to the Project scope and the preparation of technical and normative
documents to guide contracting and implementation, which took considerable time and
impacted the time for effective implementation of the Project.
(c) The water crisis of unprecedented proportions that posed great risks to the São Paulo
Metropolitan Region, considering its significant urban and economic importance.
(d) The introduction of the exceptional operational measures in the supply system and the
physical interventions designed and executed extremely quickly to increase water production
and flexibility to transfer water between different production systems led to the postponement
of investments in sewage systems, which, strongly affected SABESP's participation in the
Project.
(e) The intensity of the economic crisis, with an impact on the taxes collected by the public
sector, hindered progress under Component 4, which was the main focus of the November
2015 restructuring.
(f) The appreciation of the US dollar and the absence of inflation correction measures in the
amounts paid by the Project to the providers under the results-based contracts impacted
negatively on Project implementation and disbursement.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
25
98. The Borrower also acknowledges the excellent support provided by the Bank’s management and
technical supervision team. The letter highlights the openness of the supervision team to institutional and
technical innovations, the caliber and dedication of Bank staff, and the understanding and collaboration
shown during the water crisis faced by the state.
99. The Bank team has addressed the issues raised by the Borrower, and has provided clarifications
on the overall evaluation and ratings.
(b) Cofinanciers Not applicable.
(c) Other partners and stakeholders Not applicable.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
26
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD Million equivalent)
Components Appraisal
Estimate (USDM)
Disbursed by
11/30/15
restructuring
Restructuring
Estimate (USDM)
Actual (USDM)
Percentage
of Appraisal
Component 1: Increase water
availability 30.68 19.09 31.67 33.00 107
1.1: Controlling and reducing real
water losses 22.88 18.35 29.47 30.80 134
1.2: Rationalizing the use of
water 3.05 0.74 2.20 2.20 72
1.3: Reusing treated wastewater 4.75 — — — —
Component 2: Enhance water
quality 64.8 3.88 27.68 8.33 13
2.1: Building wastewater
collection networks 4.00 0.10 1.12 0.73 18
2.2: Building wastewater
transport systems 27.10 2.04 6.90 5.22 19
2.3: Upgrading/building new
wastewater treatment plants 33.70 1.74 19.66 2.38 7
Component 3: Develop
institutional and technical
capabilities
318.64 4.31 5.75 5.91 68
Component 4: Emergency
works for water supply — — 30.65 — —
Total Cost 104.12 27.28 95.75 47.24 45
Physical Contingencies 0.41 — — — —
Price Contingencies 2.80 — — — —
Total Project Costs 107.33 27.28 95.75 47.24 45
Front-end fee IBRD 0.16 0.16 0.16 0.16 100
Total Financing Required 107.49 27.44 95.91 47.40 45
(b) Financing
Source of Funds Appraisal
Estimate (USD M)
Disbursed by
11/30/2015
restructuring (USD M)
Restructuring
estimate (USD M)
Actual (USD M)
Percentage
of Appraisal
Borrower 42.99 4.84 31.41 9.66 22
International Bank for
Reconstruction and Development 64.49 22.60 64.49 37.74 58
31 Numbers in the PAD are distinct. On pages related to the project components description, the total cost for
Component 3 is presented as US$8.16 million. On Annex 5 of the PAD, Component 3 is presented with a total cost
of US$8.64 million.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
28
Annex 2. Outputs by Component
1. Summarizing Project results at closure. A total of 23 subprojects had been carried out to conclusion and
with their results verified. In terms of results, subcomponent 1.1 on water losses, outperformed the other
subcomponents with a 93 percent contribution to the PDO results indicator.
Table 1: Results per Component
Components # of
Subproj
ect
Verified Results
(m3/year)
% Results
Sustainability
perspective
Reagua
Payments
($R mill)
Component 1
1.1 Water losses
1.2 Efficient Use in
schools
13
4
43,713,974.63
335,080.39
93
1
Estimated to remain
constant throughout
project lifetime
98.30
6.44
Total Comp. 1 17 44,049,055.00 94 104.74
Component 2
All subcomponents*
6
3,078,663.00
6
Will increase as
ongoing projects
culminate and design
capacity constructed
facilities is reached
23.96
Total 23 47,127,718.00 100 128.70
* At Project closure 8 projects were ongoing with expected results of 8,336,471 m3/year
Table 2: Results per Activities
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
Component 1: Increase water availability
Subcomponent 1.1: Control and reduction of real water losses
1 CODEN - Nova
Odessa
Infrastructure
replacement,
sectorisation,
pressure management,
active leakage
control
2.01 2.01 May/2012
May/2017 417,633 1,703,794 Closed
Closing 5 months extension
to December
2016. Additional 5 months
extension to May
2017.
1 SAAE -
Indaiatuba 10.86 10.86
May/2012
Aug/2016 2,514,253 2,997,089 Closed
Closing 10
months extension
to June 2016. Additional 3
months closing
extension to September 2016.
1
SABESP -
Campo Limpo/Varzea
Paulista
10.59 10.59 May/2012 Sep/2015
2,439,111 3,179,313 Closed
1 SABESP –
Franca 2.58 2.52
May/2012
Dec/2016 572,221 543,538 Closed
Closing 18 months extension
to April 2017.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
29
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
1 SANASA -
Campinas 2.24 2.24
Dec/2011
Dec/2015 533,671 872,699 Closed
Closing 5 months extension
to November
2015.
3 SAAE -
Guarulhos
Sectorisation, pressure
management,
assets and leaks control
20.36 20.36 Jul/2014
Dec/2015 3,927,303 5,524,190 Closed
No amendment to
contract.
However, the payment was
delayed for 18
months until fiscal constraints
blocking the
provider financing were
cleared.
3 SABESP –
Botucatu 2.71 2.71
Jul/2014
Dec/2015 475,188 1,216,227 Closed
3
SABESP -
Francisco
Mourato
4.68 4.68 Jul/2014 Dec/2015
1,004,208 2,280,644 Closed
3 SABESP –
Itaquacetuba 10.87 10.87
Jul/2014
Dec/2015 2,216,376 2,167,087 Closed Paiement in 2016
3 SABESP –
Osasco 5.03 5.03
Jul/2014
Dec/2015 1,078,045 11,550,143 Closed Paiment in 2016
3 SABESP - São Bernardo do
Campo
Sectorisation,
pressure management,
assets and leaks
contro
11.22 11.22 Jul/2014
Dec/2015 2,405,047 8,241,641 Closed
3 SABESP – Tatuí 1.32 1.32 Jul/2014 Dec/2015
283,546 731,810 Closed
3 SANASA - Campinas
13.86 13.86 Jul/2014 Dec/2016
2,589,568 2,705,799 Closed
Subtotal subcomponent 1.1 98.33 98.27 20,456,170 43,713,975
Subcomponent 1.2 Rational water use
1 SANASA
Environmental
education, equipment and
works carried
out in 100 schools.
2.39 2.35 Dec/2011
Dec/2016 73,802 143,957 Closed
Closing 12 months extension
to August 2016.
Additional
closing 5 months
extension to
December 2016.
2 SANASA
Environmental education,
equipment and
works carried out in 100
schools.
2.48 2.39 Dec/2013
Dec/2016 53,722 96,287 Closed
Closing 12
months extension
to November 2016. Additional
6 months
extension to May 2017.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
30
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
2 SAAE -
Indaiatuba
Environmental education,
equipment and
works carried out in 25
schools.
1.13 1.12 Dec/2013
Aug/2016 19,814 32,163 Closed
Closing 6 months extension to June
2016. Additional
6 months extension to
December 2016.
2 SAAE -
Guarulhos
Environmental education,
equipment and
works carried out in 20
schools.
0.69 0.58 Dec/2013
Aug/2017 35,708 62,673 Ongoing
Closing 24 months extension
to December
2017 to allow verifying
sustainability
targets, once fiscal constraints
blocking the
provider to receive payments
have been
cleared. The remaining
payments will be
100 percent counter-part
funds.
Subtotal subcomponent 1.2 6.69 6.44 183,046 335,080
Total Component 1 105.04 104.71 20,639,216 44,049,055
Component 2: Enhance quality of water
Contracts listed below includes activities under Subcomponent 2.1 Wastewater collection network; Subcomponent 2.2 Wastewater transport
system; Subcomponent 2.3 Upgrading existing and constructing new wastewater treatment plants
Component 2: Enhance
quality of water
Subcomponent 2.1 Wastewater collection network
Subcomponent 2.2 Wastewater transport system
Subcomponent 2.3 Upgrading existing and constructing new wastewater treatment plants
1 SABESP –
Conchas
Subcomponent
2.1: Construction
works creating
89 new active connections
0.13 0.13
Jun/12
Dec/2014
89 new
active
connections
93 new active connections
Closed
Subcomponent
2.3 Build a wastewater
treatment plant
2.42 2.42 757,21 772,632
1 SABESP - Alumínio
Subcomponent
2.2: Wastewater pumping station,
forced
wastewater pipe and gravity
wastewater pipe
1.51 0.85 May/2012 May/2017
Treatment plant results accepted.
Closed
(operational)
Change in designs and closing 22
months closing
extension. Additional change
in design and
sustainability targets exclusion.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
31
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
Subcomponent
2.3: Wastewater
treatment plan
built.
1.74 1.22 581,587 -
Closing 22 months extension to May
2017 and design
change modifying the treatment
solution. Original
contract amount was R$5,25M.
Additional
amendment
eliminated
sustainability
phase.
1 SABESP –
Boituva
Subcomponent
2.2: Gravity wastewater pipe
0.28 0.28
Jun/12
Dec/2016
Treatment plant results
accepted.
Closed
Closing 16 months
extension to Nov
2016. Additional extension to June
2017.
Subcomponent
2.3: Wastewater
treatment plan built.
1.16 1.16 448,704 409,968
Closing 16 months extension
to Nov 2016.
Additional 6 months extension
to June 2017.
1 SABESP -
Anhembi
Subcomponent:
2.2: Wastewater
pumping station,
forced
wastewater and
gravity
wastewater pipe lines
0.56 0.56
Jun/12
Dec/2016
Treatment plant results
accepted.
Closed
Closing 24 months extension to June
2017.but
concluded in December 2016
Subcomponent
2.3 Wastewater treatment plan
built.
0.46 0.46 142,502 279,269
Closing 20 months
extension to June
2017.
1 SABESP –
Araçariguama
Subcomponent
2.1: Construction works creating
102 new active
connections
0.16 0.00
Jun/12
Jun/17
102 new active
connections
-
Closed
(WWTP not yet
operational)
Closing 24 months extension to June
2017. Change
contract scope to comply with
closing date.
Subcomponent
2.2: Wastewater
pumping station
and forced wastewater pipe
0.31 0.00
Closing 24 months
extension to June 2017.
Scope reduction
excluding sewerage
transportation.
Subcomponent
2.3: Wastewater treatment plan
built.
5.17 2.00 722,477 -
Closing 24 months extension to June
2017. Additional
amendment reduces scope;
eliminate
sustainability and equipment.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
32
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
1 SABESP –
Sarapuí
Subcomponent
2.1: Construction
works creating 0
(zero) new active connections
0.00 0.00
Jun/12 Jun/17
- -
Closed
(work not
operational)
Closing 24 months extension to June
2015, and
exclusion of 178 new connections.
Additional
amendment to close contract.
Subcomponent
2.2: Wastewater
pumping station, forced
wastewater pipe
and gravity wastewater pipe
4.45 2.48
Closed (not
operational)
Closing 24 months
extension and
scope reduction. Additional scope
change, including
eliminating monitoring
sustainability
targets and pumping stations.
Subcomponent
2.3: Wastewater
treatment plan built.
1.03 0.72 350,957
-
Closed
(WWTP not
yet operational)
Closing 20 months extension
to June 2017. Additional
amendment to
reduce scope eliminating the
sustainability
phase and
equipment install.
1 DAEV – Valinhos
Subcomponent
2.1: Construction
works creating
89 new active connections
0.03 0.02
Jan/14 Aug/2017
18 new
active
connections
14 new active connections
Closed
(works
operational)
Closing 20 months extension to May
2017. Additional
amendment to reduce contract
scope and cancel
sustainability targets.
Subcomponent
2.2: Gravity
wastewater pipe
0.16 0.11 110,108 - Closed (operational)
Closing 20 months
extension to May
2017. Second amendment to
reduce scope and
eliminate sustainability
phase.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
33
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
2
SAAE -
Indaiatuba
(Região Norte)
Subcomponent
2.1: Construction
works creating 89 new active
connections
2.40 1.65
Dec/2013 Dec/2017
1250 new
active connections
822 new
active connections
Ongoing (works
already
operational)
Closing 24 months
extension to June
2017. Additional extension to
December 2017
and new connections
reductions to 1250.
Achievement of
sustainability
targets will be
verified counting on counterpart
funds exclusively.
Subcomponent
2.2: Build 3 wastewater
pumping station,
forced wastewater pipe
and gravity
wastewater pipe
4.00 2.37 410,884 - Ongoing
(operational)
Closing 18
months extension
to June 2017. Additional 6
months extension
to December 2017 and scope
reduction.
Sustainability targets will be
verified with
counterpart funds
support.
2 SAAE - Indaiatuba
(Buruzinho)
Subcomponent
2.2: Build 1 wastewater
pumping station,
forced wastewater pipe
and gravity
wastewater pipe
9.26 6.35 Dec/2013
May/2017 2,177,280 636,396 Closed
Closing 12 months extension
to December 2016.
Additional extension to May
2017.
2 SAAE - Sorocaba
(Bom Jesus)
Subcomponent
2.1: Construction works creating
165 new active
connections
0.36 0.32
Dec/2013
May/2017
188 new active
connections
165 new active
connections
Closed
Closing 18 months extension to
September 2017.
Additional extension to
December 2017
Subcomponent
2.2: Gravity
wastewater pipe
0.02 0.02 46,656 46,656 Closed
Closing 10 months extension
to September
2016. Additional 13 months
extension.
2 SAAE - Sorocaba
(sorocabanos)
Subcomponent
2.1: Construction works creating
262 new active
connections
0.50 0.10 Dec/2013
May/2017
262 new active
connections
71 new active
connections Closed
Closing 11 months extension to
September 2016.
Additional 6 months closing
extension.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
34
Ca
ll f
or P
ro
po
sal
Service
Provider –
Municipality
Summary
contract scope
Contract
amount
(R$
millions)
Amount
paid
(R$
millions)
Contract’s
start and
end dates
Expected
results
(m3 water
recovered
per year)
Verified
results
(m³/ year)
Contract
status
Amendments to
contracts
Subcomponent
2.2: Gravity wastewater pipe
0.80 0.76 933,742 933,742 Closed
Closing 10 months
extension to September 2016.
Additional 18
months extension to December 2017.
Total Component 2 36.91 23.98 6.68 3.07
Total (Components 1 and 2) 141.95 128.69
The World Bank Brazil São Paulo Water Recovery Project (P106703)
35
Annex 3. Economic and Financial Analysis
1. During Project preparation, an ex-ante Cost-Benefit Analysis (CBA) was carried out mostly using a
sample of subprojects from an initial list of potential candidates that responded to a call for proposals. The
subprojects chosen represented the project subcomponents and included: two cases for subcomponent 1.1, Control
and Reduction of Water Losses; for subcomponent 1.2 – Rational use Water a sample of 348 schools for a similar
and at the time ongoing efficiency Program by SABESP; subcomponent 1.3 –Reuse of Treated Wastewater an
industrial activity which was using reuse; for Component 2 - Wastewater Collection and Treatment and two of the
potential candidate operators. A cost Benefit analysis was conducted for the above set together with a financial
and distributive analysis. All the individual cases turned out positive results with an overall an IRR of 65 percent
for the Project.
2. None of the initially evaluated projects eventually participated in the Project. Nonetheless, to approximate
the Project efficiency a similar approach was used at project completion now analyzing a new set of
representative sample projects that had been carried out to full completion (including sustainability period. Table
1 below depicts the results of the Project at closure, indicating that 23 subprojects had been carried out to
conclusion and with their results verified. In terms of results, subcomponent 1.1 – water losses, outperformed the
other subcomponents with a 93 percent contribution to the PDO results indicator.
Table 1: Results per Component
Components # of
Subproj
Verified
Results
(M3/yr)
% Results
Sustainability
perspective
REAGUA
Payments
($R mill)
Component 1
1.3 Water losses
1.4 Efficient Use in
schools
13
4
43,713,974.63
335,080.39
93
1
Estimated to remain
constant through project
lifetime
98.33
6.44
Total Comp. 1 17 44,049,055 94 104.74
Component 2
All subcomponents*
6
3,078,663
6
Will increase as
ongoing projects
culminate and design
capacity constructed
facilities is reached
23.96
Total 23 47,127,718 100 128.7
3. Table 1 above shows that the results were heavily influenced by the water losses subcomponent which
received 37 percent of the total Project payments. The table also suggests that the overall result was significant. A
quick assessment estimating one year benefits of subcomponent 1.1 at closure (valued at marginal cost of water
US$1.8/M3 would yield estimated benefits of US$78.7 million for just the first year, or almost twice as much as
the total project disbursements.
4. The ex-post analysis of the Project followed the appraisal evaluation concept, and comprised a Cost
Benefit Analysis of a sample of concluded subprojects that were chosen to represent Project Components 1 and 2
as shown in Table 2 below.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
36
Table 2: Sample Subprojects Analyzed
Subcomponent Brief Description of activities Verified water
recovered
results
(M3/year)
% of total
Project
Component
Component 1 Water losses
SANASA First and
Second Batches for
Campinas
Infrastructure replacement,
sectorization, pressure management,
active leakage control in Campinas
3,578,490 8
Component 1 Rational
Use of Water in SANASA
Environmental education, equipment
and works carried out in 200 schools.
240,244 70
Component 2 Wastewater
Transport and treatment
Boituva
wastewater transport and treatment
serving a target of about 25% of the
city
409,968 13
Total Verified Results 4,228,702
Results of the CBA
5. Table 3 presents the results for the three analyzed subprojects.
Table 3: Cost-Benefit Analysis Results Benefits (NPV) Costs (NPV) Results
Subcomponent IRR% B/C at 10%
discount
Water Losses
SANASA
Life period 10yrs
Measured as water
recovered at marginal
price
Investment costs +
coordination costs
63 5.6
Efficient Use of water
SANASA
Life period 20 years
Measured as water
recovered at marginal
price
Investment costs +
SANASA coordination
and operational Costs
14 1.4
Waste Water
Boituva
Life period 25 years
Pollution Loads removed
Beneficiaries valuation
Burden disease avoided
Opportunity Cost*
Actual investment costs 22 2.4
Waste Water with
opportunity cost alone
Opportunity Cost Actual Investment
Costs
16
6. Component 1: Water Losses and Rational Use of Water in Schools in Campinas. The CBA analysis
for the two subprojects for Component 1 used different periods of analysis: water losses - 10 years, Rational use
of water – 20 years, and typical life time of these interventions. Costs for Component 1 were approximate,
particularly for the Campinas Rational Use subproject, as several SANASA personnel were significantly involved
part time. As for the benefits, for component 1 both water losses and the amount of additional water recovered
was monetized at marginal cost (US$1.8/m3).
7. The high returns of the SANASA water losses subproject is consistent with the sector experience with
these types of activities. Moreover, in this case getting the results required no major infrastructure investments
and only measures such as pressure management, leakage control, and other activities that require only moderate
investments were carried out. Additional benefits not quantified derive from the fact that there was a learning
The World Bank Brazil São Paulo Water Recovery Project (P106703)
37
experience and the establishment of a formal and improved leakage control Program which is expected to
continue indefinitely.
8. Results of the water school program analyzed was modest but positive. The analysis focused on the water
recovery aspect of the subproject and excluded the environment education part. The training of students in
efficient use of water, represented a very elaborate program, that is expanding within the Campinas and is
expected to bring important long-term benefits associated with a rational use of water by the students and their
families in the future. In the case of SANASA, though, given its innovative nature a costly preparation phase and
efficiency was impacted by a significant amount of internal manpower used, both for the establishment,
coordination and implementation of the Program. Future programs should benefit from this learned curve and be
more efficient.
9. Component 2: Enhanced Water Quality Wastewater. The CBA was carried out for a 25 years’ period.
Benefits that were calculated and monetized include: (i) volume of BOD and COD pollution loads removed; (ii)
beneficiaries value of improved sanitation; and (iii) burden of disease avoided. Other environmental benefits, like
Nitrogen and Phosphorus removal were not included. In addition, an opportunity cost, derived from defined fines
to be imposed by the Public Ministry for non-action for curving pollution, was used as a proxy for minimum
benefits. Table 3 above shows the results of the analysis.
10. For the case of Boituva, costs included investment, as well as operation and maintenance. An additional
analysis included an opportunity cost, reflecting fines the municipality was subject to, by a decree of the Public
Ministry, requesting the treatment of pollution loads. This was also included in the original analysis carried out by
the Project. Adding this as a benefit to the IRR becomes positive and a similar situation was found with the case
of Conchas, another concluded subproject. While the benefits were conservatively estimated, the low returns are
not atypical in these cases with WWTP serving relatively small cities.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
38
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit Responsibility/
Specialty
Lending
Susana Amaral Financial Management Specialist GGODR Financial
Management
Martin P. Gambrill Lead Water and Sanitation Spec GWADR Water and Sanitation
Juliana Menezes Garrido Sr Water & Sanitation Spec. GWADR Water and Sanitation
Karina de Souza Marcelino Program Assistant LCC5C Operations Support
Jose Alexandre Monteiro Fortes Environmental Spec. Consultant LCSUW-HIS Environmental
Specialist
Pery Nazareth Water and Sanitation Engineer, consultant GWA04 Water and Sanitation
Engineer
Airton Sampaio Water Loss Consultant GWA04 Water Loss Engineer
Mauricio Ludovice Wastewater treatment Consultant GWA04 Wastewater
Treatment Engineer
Luz Maria Gonzalez Financial Economic Spec. Consultant GWA04 Economic analysis
Luiz Tineo Procurement Specialist GPOBA Procurement
Julia Tierney Junior Professional Associate GWA04 Analyst
Marta Elena Molares-Halberg Lead Counsel LEGES Lawyer
Luis R. Prada Villalobos Senior Procurement Specialist GGODR Procurement
Maria Angelica Sotomayor Araujo Lead Specialist GSURR
Carlos E. Velez Lead Economist LCSWS - HIS Task Team Leader
Adriana M.G.M. Weisman Operations Officer OPSPQ Operations
Supervision/ICR
Sinue Aliram Procurement Specialist GGODR Procurement
Etel Bereslawski Procurement Specialist GGO08 Procurement
Susana Amaral Financial Management Specialist GGODR Financial
Management
Lizmara Kirchner Sr Water & Sanitation Spec. GWADR Former co-Task
Team Leader
Soraya Melgaço Social Specialist consultant GSU01 Social Specialist
Jose Alexandre Monteiro Fortes Environmental Spec., consultant LCSUW-HIS Environmental
Specialist
Menahem Libhaber Water and Sanitation Engineer, consultant GEN04 Water and Sanitation
Pery Nazareth Water and Sanitation Engineer, consultant GWA04 Water and Sanitation
Airton Sampaio Water Loss Consultant GWA04 Water Loss
Oscar Alvarado Sr Water & Sanitation Spec. GWA04 Task Team Leader
Perla Virginia Castillo Miranda E T Temporary LCSUW-HIS ACS
Juliana Menezes Garrido Sr Water & Sanitation Spec. GWADR Current co-Task
Team Leader
The World Bank Brazil São Paulo Water Recovery Project (P106703)
39
Catarina Isabel Portelo Senior Counsel LEGLE Lawyer
Julia Tierney Junior Professional Associate LCSUW-HIS Analyst
(b) Staff Time and Cost
Stage of Project Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks USD Thousands (including travel
and consultant costs)
Lending
FY08 4.63 56,602.05
FY09 41.46 246,533.06
FY10 13.24 89,585.00
Total: 59.33 392,720.11
Supervision/ICR
FY10 1.25 5,055.48
FY11 18.6 126,861.17
FY12 16.66 96,881.52
FY13 6.36 56925.29
FY14 6.71 91,604.44
FY15 12.33 82,290.44
FY16 19.68 99,535.03
FY17 14.44 130,131.51
FY18 1.35 19,981.12
Total: 97.38 709,266.00
The World Bank Brazil São Paulo Water Recovery Project (P106703)
40
Annex 5. Beneficiary Survey Results
Not applicable.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
41
Annex 6. Stakeholder Workshop Report and Results
1. A Stakeholder Workshop was held in May 2017, as part of the Implementation Completion Report
preparation. In total, 25 participants attended the workshop, including representatives from SABESP and
SANASA. The workshop main findings are presented below. The Workshop Report is available in the Project
files.
2. Project preparation and implementation (a) Strengths: (i) adopting the results-based approach; (ii)
focusing on the priority basins; (iii) requiring a sustainability period; (iv) flexibility given to providers to select
solutions leading to agreed results; (v) the payments to providers did not require heavy bureaucracy; (b)
Weakness: (i) Reference unit prices were not well calibrated; (ii) long delays in selecting and signing contracts
with providers; (iii) Difficulties faced in formulating the set of normative; (iv) huge technical differences between
activities under component 1 and 2, creating difficulties to be handle under the management arrangement; (v)
risks associated with the results-based approach transferred to technical team; (v) the value of the reference unit
prices was too low and did not include adjustment to inflation; and (vi) it was difficult to understand the Project
operational procedures;
3. Main findings: (i) developing the results-based set of normative was an intense learning process; (ii)
applying the normative addressing control of water losses required prior training; (iii) the normative addressing
sewerage systems needed to be simplified; (iv) the normative addressing rational water use was quite appropriate;
(v) the water crisis resulting from the drought boosted the control of losses activities and reduced the investments
in sewerage; (vi) the Project implementation generated an important database that can be used to improve the set
of normative; (vii) getting Project implementation started was a very difficult task because many indispensable
elements were not ready, such as the contract template, the verification agent and the management team; and (viii)
the less efficient service providers needed prior and more intense capacity.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
42
Annex 7. Summary of Borrower's Comments on ICR
This Annex includes the comments by the Borrower on the draft Implementation Completion and Result Report.
It is a translation of the letter sent to the Country Director. The original letter is included in the Project files.
Comments by the State of São Paulo Governor on the Implementation Completion and Results Report of the Loan
7662-BR of the Reagua Program
Mr. Director of the World Bank:
Our technical team has examined the Final Report on the Reágua Project, object of Loan Agreement 7662-BR,
sent to this Secretariat by the World Bank. This last formal assessment of the Program is very significant, in that it
must lay out, realistically, the lessons derived from the set of actions carried out under the Project. These include
concepts, technical aspects of greater significance and the influences of externalities that have greatly interfered
with the program's execution. We hope that a balanced assessment will lay the groundwork for Reágua to inspire
similar initiatives in the future, after it has undergone the necessary adjustments. To us, this is not just desirable -
it is essential.
In general, we have no significant disagreements with the points presented in the Report, which accurately and
precisely depicts the characteristics and conditions of the Program's design and implementation. It duly mentions
the challenges faced by the program since its very inception, such as the enormous efforts required to conciliate
Reágua's innovative ideas with the limitations set forth by law; the restrictive conditions imposed by a water crisis
that has afflicted the State of São Paulo - especially its main metropolitan region - since late 2013; the virtual
impossibility of securing counterpart funds from the State Government since the first quarter of 2016, as a result
of the Brazilian macroeconomic crisis and its effects on public finances. The Report is also correct in noting the
significant success of Reágua's Component 1, involving actions to control losses and promote the rational use of
water in public schools. It is correct as well concerning the Component 2, focused on sewage, subpar performance.
As the report aptly states, the water crisis prompted sanitation companies to relocate investment funds to
emergency interventions meant to ensure water supply.
Our assessment, however, is that the situation was not as severe as stated in the report, which rates several Project
aspects as "moderately unsatisfactory". As we broadly agree with the general content of the arguments, however,
the following comments will refer to the significant difficulties faced by Reágua due to the Project's very nature
and the externalities affecting execution.
The Project faced the costs associated with innovation- the report mentions that this was the Bank's inaugural
operation in the water and sanitation sector based on a payment-for-results scheme. Reágua's scope was changed
several times since the Project was first conceived; there was a long-time gap between the time when the final
scope was set and the preparation of technical and normative documents to guide contracting and implementation;
as mentioned earlier, these new and positive ideas had to be expressed in a judicially-sound format, which took
considerable time. This Secretariat and the World Bank worked tirelessly to find adequate solutions - which they
eventually did; nevertheless, the effective time for implementing Reágua was shortened considerably.
As widely reported, we faced a water crisis of unprecedented proportions that posed great risks to the São Paulo
Metropolitan Region, considering its significant urban and economic importance. These risks were only
circumvented by the organized and rigorous actions carried out by Sabesp, which included financial measures
meant to reduce consumption, exceptional operational measures in the supply system and physical interventions
designed and executed extremely quickly to increase water production and afford greater flexibility to the
structures used to catch and transfer flows between different production systems. The allocation of funds to
The World Bank Brazil São Paulo Water Recovery Project (P106703)
43
interventions in water systems - including the timely agreement with the World Bank to change the scope of the
Mananciais Program and enable interconnection works between the Billings and Taiaçupeba dams, the expansion
of the Alto da Boa Vista Treatment Station and interventions to control losses in distribution networks - led, in
turn, to the postponement of investments in sewage systems, which, in turn, strongly affected Sabesp's
participation in the Reágua Project. A similar problem delayed the work schedule of the company in charge of
sanitation services in Campinas (Senasa), at its Boa Vista Treatment Station.
Finally, the intensity of the economic crisis, with an impact on the taxes collected by the public sector, hindered
the development of Reágua's Component 4, the object of the contract restructuring process carried out in late 2015.
This restructuring, another testament of the strong relationship between the State Government and the World
Bank - I am referring here to its Director in Brasilia and the technical staff involved in managing the Program -
was meant to take advantage of the funds made available under the Loan Agreement due to the cancellation of
Component 2 contracts, the appreciation of the US Dollar exchange rate, and the absence of inflation correction
measures in the amounts paid by Reágua to the providers under the results based contracts.
Together, these events and challenges greatly affected the Project's disbursements - however, given the nature of
the payment-for-results model, the Projects’ total budget was not expected to be fully disbursed. In our
assessment, the amounts disbursed would certainly have been very different under less-dramatic circumstances,
with better performances in Component 2 and, above all, Component 4. A better rating would seem to be in order,
considering these restrictive events.
We have brief observations about two points that, inter alia, will require attention if similar programs are
implemented in the future:
First, actions to control physical losses in water systems and in wastewater treatment investments are
quite particular and have very distinct needs when it comes to resource mobilization and contract terms,
making it difficult to include them all under the same project. Nevertheless, both actions deserve support
and are fully compatible with the payment-for-results system.
Second, regarding measures to control water losses: Reágua was developed in partnership with the best
operators in São Paulo, which contributed to its success in this area. Future projects must include strong
action to support operators as they advance towards higher management and operational standards.
We would like to take this opportunity to thank the World Bank, its management and technical team in charge of
supervising the Reágua Program, and underscore their openness to institutional and technical innovations, the
caliber and dedication of its professionals, and the understanding and firm cooperation shown by the staff at
decisive junctures in the water crisis we had to face.
Yours faithfully.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
44
Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders
Not applicable.
The World Bank Brazil São Paulo Water Recovery Project (P106703)
45
Annex 9. List of Supporting Documents
1. Project Appraisal Document (PAD), dated March 26, 2010.
2. Guidelines for Reviewing World Bank Implementation Completion and Results Report, Independent
Evaluation Group (IEG), November 12, 2013
3. Implementation Completion and Results Report, Guidelines, OPCS, updated on July 22, 2014
4. Stakeholders Workshop Report, May 2017
5. Implementation Supervision Reports (numbers 1 – 13)
6. Bank Supervision Aide Memoires
7. REAGUA Project – Concept Review Minutes
8. REAGUA Project – Quality Enhancement Review (QER) Minutes
9. REAGUA Project – Decision Meeting Review Minutes
10. REAGUA Project – November 2015 Restructuring Paper
11. REAGUA Project – Loan Agreement, dated September 27, 2010
12. REAGUA Project – Amendment to the Loan Agreement, dated November 30, 2015
13. REAGUA Project – Set of Normative supporting the Results-Based Approach
14. REAGUA Project – Progress Reports from Implementing Agency
15. Brazil: Inputs for a Strategy for Cities: A Contribution with a Focus on Cities and Municipalities, World
Bank Report No. 35749 (June 2006).