World Bank Document · document of the world bank report no: icr00002771 implementation completion...
Transcript of World Bank Document · document of the world bank report no: icr00002771 implementation completion...
Document of
The World Bank
Report No: ICR00002771
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(IDA-39300 IDA-45710)
ON AN
IDA CREDIT (IDA-39300)
IN THE AMOUNT OF SDR 138.44 MILLION
(US$207 MILLION EQUIVALENT)
AND
IDA CREDIT (IDA-45710)
IN THE AMOUNT OF SDR 172.00 MILLION
(US$253 MILLION EQUIVALENT)
TO THE REPUBLIC OF KENYA
FOR THE
NORTHERN CORRIDOR TRANSPORT IMPROVEMENT PROJECT
June 29, 2016
Transport and ICT Global Practice
Africa Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
CURRENCY EQUIVALENTS
Currency Unit = Kenya Shilling (KSh)
(Exchange Rate Effective)
(February 29, 2004) (December 31, 2015)
US$1.00 = KSh 77.0 US$1.00 = KSh 102.4
SDR 1.00 = US$1.4952 SDR 1.00 = US$ 1.3857
FISCAL YEAR
July 1– June 30
ABBREVIATIONS AND ACRONYMS
AF Additional Financing
AFD French Development Agency (Agence Française de Développement)
AfDB African Development Bank
APRP Annual Public Road Programme
CAS Country Assistance Strategy
CAT1 Category 1
DCA
EASA
Development Credit Agreement
East African School of Aviation
EBK Engineering Board of Kenya
EIB European Investment Bank
EIRR Economic Internal Rate of Return
ERB Engineers’ Registration Board
ERSWE Economic Recovery Strategy for Wealth and Employment Creation
EU European Union
FAA United States Federal Aviation Administration
FM Financial Management
GNSS Global Navigation Satellite System
GoK Government of Kenya
GPS Global Positioning System
IA Implementing Agency
IASA International Aviation Safety Assessment
ICAO International Civil Aviation Organization
ICR Implementation Completion and Results Report
ICT Information and Communications Technologies
IDA International Development Association
INT
IRI
Department of Institutional Integrity
International Roughness Index
ISR Implementation Status and Results Report
JICA Japan International Cooperation Agency
JKIA Jomo Kenyatta International Airport
KAA Kenya Airports Authority
KCAA Kenya Civil Aviation Authority
KeNHA Kenya National Highways Authority
KeRRA Kenya Rural Roads Authority
KMA Kenya Maritime Authority
KRA Kenya Revenue Authority
KRB Kenya Roads Board
KTSSP Kenya Transport Sector Support Project
KURA Kenya Urban Roads Authority
M&E Monitoring and Evaluation
MoF Ministry of Finance
MoTC Ministry of Transport and Communications
MoTI Ministry of Transport and Infrastructure
MoRPWH Ministry of Road, Public Works and Housing
MTR Mid-Term Review
NCA National Construction Authority
NCTIP Northern Corridor Transport Improvement Project
NCTTA Northern Corridor Transit and Transport Agreement
NCTTCA Northern Corridor Transit and Transport Coordination Authority
NDF Nordic Development Fund
NGO Non-Governmental Organization
NMT Non-Motorized Transport
NPV Net Present Value
NTSA National Transport and Safety Authority
NUTRIP National Urban Transport Improvement Project
OPRC Output- and Performance-based Road Contract
PAD Project Appraisal Document
PDO Project Development Objective
POC Project Oversight Committee
PPP Public-Private Partnership
PTT Project Technical Team
RAP Resettlement Action Plan
RCCI Roadworks Construction Cost Index
RSGIAP Road Sector Governance and Integrity Action Plan
RSIP Road Sector Investment Program
TOR Terms of Reference
TSA Transport Security Administration of the United States
TTL Task Team Leader
UNES University of Nairobi Enterprises and Services Limited
VAT Value Added Tax
VCT Voluntary Consulting and Testing
VPD Vehicles per Day
Senior Global Practice Director: Pierre Guislain
Acting Practice Manager: Aurelio Menendez
Project Team Leader: Josphat O. Sasia
ICR Team Leader: Akiko Kishiue
Kenya
Northern Corridor Transport Improvement Project
CONTENTS
Data Sheet
A. Basic Information ............................................................................................................... i
B. Key Dates ............................................................................................................................ i
C. Ratings Summary ................................................................................................................ i
D. Sector and Theme Codes ................................................................................................... ii
E. Bank Staff ........................................................................................................................... ii
F. Results Framework Analysis ............................................................................................. iii
G. Ratings of Project Performance in ISRs ......................................................................... viii
H. Restructuring ..................................................................................................................... ix
I. Disbursement Graph ........................................................................................................... x
1. Project Context, Development Objectives and Design ............................................... 1
2. Key Factors Affecting Implementation and Outcomes ............................................... 6
3. Assessment of Outcomes .......................................................................................... 14
4. Assessment of Risk to Development Outcome ......................................................... 21
5. Assessment of Bank and Borrower Performance ...................................................... 22
6. Lessons Learned ........................................................................................................ 24
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners ........... 26
Annex 1. Project Costs and Financing .......................................................................... 27
Annex 2. Outputs by Component .................................................................................. 28
Annex 3. Economic and Financial Analysis ................................................................. 46
Annex 4. Bank Lending and Implementation Support/Supervision Processes ............. 52
Annex 5. Beneficiary Survey Results ........................................................................... 54
Annex 6. Stakeholder Workshop Report and Results ................................................... 55
Annex 7. Summary of Borrower’s ICR and Comments on Draft ICR .......................... 56
Annex 8. Comments of Co-Financiers and Other Partners/Stakeholders ..................... 68
Annex 9. List of Supporting Documents ....................................................................... 69
Annex 10. Road Sector Governance and Integrity Improvement Action Plan………..71
MAP .............................................................................................................................. 77
i
DATA Sheet
A. Basic Information
Country: Kenya Project Name:
Northern Corridor
Transport Improvement
Project
Project ID: P082615 L/C/TF Number(s): IDA-39300,IDA-45710
ICR Date: 06/27/2016 ICR Type: Core ICR
Lending Instrument: SIL Borrower: GOVERNMENT OF
KENYA
Original Total
Commitment: XDR 138.44M Disbursed Amount: XDR 310.21M
Revised Amount: XDR 310.44M
Environmental Category: B
Implementing Agencies:
Kenya Civil Aviation Authority
Kenya Airports Authority
Ministry of Transport and Infrastructure1
Kenya National Highways Authority
Cofinanciers and Other External Partners: Nordic Development Fund
Agence Francaise pour le Developpement (AFD)
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 06/30/2003 Effectiveness: 09/16/2004 09/16/2004
Appraisal: 02/09/2004 Restructuring(s):
12/14/2005
04/02/2009
12/27/2012
Approval: 06/17/2004 Mid-term Review: 05/04/2009
Closing: 12/31/2009 12/31/2015
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Satisfactory
Risk to Development Outcome: Low or Negligible
Bank Performance: Moderately Satisfactory
Borrower Performance: Moderately Satisfactory
1 Ministry of Roads, Public Works and Housing and Ministry of Transport and Communications merged and became
Ministry of Transport and Infrastructure. MOTI has State Department of Transport and State Department of Infrastructure.
ii
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Moderately Satisfactory Government: Moderately Satisfactory
Quality of Supervision: Moderately Satisfactory Implementing
Agency/Agencies: Moderately Satisfactory
Overall Bank
Performance: Moderately Satisfactory
Overall Borrower
Performance: Moderately Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments (if
any) Rating
Potential Problem Project
at any time (Yes/No): Yes
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): Yes
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status:
Moderately
Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
Aviation 15 9
Central government administration 10 7
Health 1 1
Other social services 2 2
Rural and Inter-Urban Roads and Highways 72 81
Theme Code (as % of total Bank financing)
Administrative and civil service reform 13 13
Infrastructure services for private sector development 25 25
Regional integration 13 13
Regulation and competition policy 24 24
Trade facilitation and market access 25 25
E. Bank Staff
Positions At ICR At Approval
Vice President: Makhtar Diop Callisto E. Madavo
Country Director: Diarietou Gaye Makhtar Diop
Practice
Manager/Manager: Aurelio Menendez C. Sanjivi Rajasingham
Project Team Leader: Josphat O. Sasia Anil S. Bhandari
ICR Team Leader: Akiko Kishiue
iii
ICR Primary Author: Akiko Kishiue
Team Assistant Damon C. Luciano/ Rosemary
Ngesa Otieno Rosemary Ngesa Otieno
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document)
The Development Credit Agreement (DCA) stated the project development objectives (PDO)
as follows: The objective of the Project is to enhance the efficiency and effectiveness of the
Borrower's transport sector through: (a) increasing the efficiency of road transport; (b)
enhancing aviation safety and security to meet international standards; and (c) promoting
private sector participation in the management, financing, and maintenance of road assets.
The Project Appraisal Document (PAD) worded the PDO slightly different but no significant
discrepancy. For the purposes of the Implementation Completion and Results Report (ICR),
in line with the guidance,2 the PDOs stated in the DCA will be used.
Revised Project Development Objectives (as approved by original approving authority) In April 2009, the original PDOs were revised by the addition of one more PDO to support
the implementation of the post-election recovery program. The revised PDOs in the Financing
Agreement which was amending and restating the original DCA were to enhance
the efficiency and effectiveness of the Recipient's transport sector through: (a) increasing the
efficiency of road transport; (b) enhancing aviation safety and security to meet international
standards; (c) promoting private sector participation in the management, financing, and
maintenance of road assets; and (d) restoring vital public infrastructure and assets damaged
as a result of the 2007 post-election crisis. The PDOs in the Additional Financing (AF) Project
Paper are worded slightly different without any significant discrepancy.
(a) PDO Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally Revised
Target Values
Actual Value
Achieved at
Completion or Target
Years
Indicator 1 : Freight and passenger travel time by road from Mombasa to Malaba and Busia
reduced by 25 percent.
Value
quantitative or
Qualitative)
Truck - 24 hours
Bus - 18 hours
Car - 14.5 hours
Truck - 18 hours
Bus - 13.5 hours
Car - 11 hours
Truck - 18 hours
Bus - 13.5 hours
Car - 11 hours
Truck - 21 hours (50%)
Bus - 15.5 hours (63%)
Car - 12 hours (71%)
Date achieved 04/30/2004 12/31/2009 12/31/2015 12/31/2015
Comments
(incl. %
achievement)
Indicator partially achieved (average 61%). A significant reduction in travel time
was achieved by 2013 but gains on some road sections later diminished due to
growing traffic volumes. Car travel time met the target in 2009 but later rebounded.
2 p16 Guideline for reviewing World Bank Implementation Completion and Results Reports, updated on August 1, 2014,
IEG, p 58 Implementation Completion Report Guidelines, OPCS, Aug 2006, last updated July 22, 2014
iv
Indicator 2 :
KCAA is cleared as category 1 (CAT1) safety status under the International
Aviation Safety Assessment (IASA) of the United States Federal Aviation
Administration (FAA).
Value
quantitative or
Qualitative)
None
FAA/IASA
CAT1 Clearance
obtained
FAA/IASA CAT1
Clearance
obtained
Clearance not obtained
Date achieved 04/30/2004 12/31/2007 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator not achieved (0%). Change in the regional security situation required
additional security measures. An ICAO security audit in 2015 scored KCAA and
KAA at 88% against a cutoff of 80% for CAT1 clearance.
Indicator 3 : Jomo Kenyatta International Airport (JKIA) in Nairobi is cleared by the TSA for
direct flights to/from U.S. airports.
Value
quantitative or
Qualitative)
None Direct flight
cleared. 100% Direct flight cleared.
Date achieved 04/30/2004 12/31/2007 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Clearance of direct flight to/from U.S. airports by the
TSA was obtained in April 2009.
Indicator 4 : One long-term performance-based road management and maintenance contract
awarded to the private sector and effectively under implementation.
Value
quantitative or
Qualitative)
None 100% 100% 39 long-term contracts
Date achieved 04/30/2004 12/31/2011 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). The concept and approach of OPRCs were well
adopted by KeNHA and KeNHA's capacity has been increased. In FY 2015/16, 39
OPRCs have been awarded and are under implementation.
Indicator 5 : Bids for concessioning of one section of road invited.
Value
quantitative or
Qualitative)
None 100% 100% 100%
Date achieved 04/30/2004 06/30/2007 12/31/2012 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Bids were invited for a proposed toll road and one bid
was received in 2005.Parliament approved the concession but it was cancelled after
a due diligence review raised integrity concerns about the procurement process.
Indicator 6 : Damaged public infrastructure assets are restored.
Value
quantitative or
Qualitative)
Restoration pending. 100% 100% 100%
Date achieved 03/05/2009 12/31/2010 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%) achieved. Renovation and reconstruction of the KeNHA
regional offices in Kisumu, Homa Bay, and Oygis towns have been completed. The
repair of the Kisian-Busia road was also carried out with the GoK internal
resources.
v
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Average roughness less than IRI 3.0 m/km on completed sections of the project
roads.
Value
(quantitative
or Qualitative)
Less than 20% of
project road length.
100% of project roads
have average
roughness of less than
IRI 3.0.
100% of project
roads have
average
roughness of
less than IRI 3.0.
100% of project roads
Date achieved 04/30/2004 12/31/2009 12/31/2015 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Average IRI of project roads is 2.2. Nyamasaria-
Kisumu airport-Kisian road has been handed over in the end of March 2016 and
data is not available yet.
Indicator 2 : Public Buildings restored and functional.
Value
(quantitative
or Qualitative)
0 3 3 4
Date achieved 03/05/2009 12/31/2010 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (133%). The renovation and reconstruction of KeNHA regional
offices in Kisumu (two offices), Homa Bay, and Oyugis towns have been
completed and the buildings are in use.
Indicator 3 : Term contracts awarded for disaster response readiness.
Value
(quantitative
or Qualitative)
0 3 3 0
Date achieved 03/05/2009 12/31/2010 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator not achieved (0%). The Road Disaster Management and Response Unit
has been established and functions as a committee composed of representatives
from road authorities. A term contract was never advertised due to limited financial
resources of MoTI.
Indicator 4 : At least three roadside stations and amenities constructed and functional as per
designs and serving road users and local communities.
Value
(quantitative
or Qualitative)
None 3 3
5 schools, 1 lorry
park, 1 market, 1
community center, 1 1
footbridge and 24.8
km of footpaths were
constructed.
Date achieved 04/30/2004 06/30/2009 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (more than 300%). A lorry park, a community center, a market,
and five schools were constructed. Footpaths and a footbridge as NMT facilities
have been constructed in the urban centers. A lorry park and a market are under
construction.
vi
Indicator 5 :
At least 70% of road users and local persons surveyed become aware or make use
of the Voluntary Counseling and Testing (VCT) and other facilities for HIV/AIDS
campaign along the Northern Corridor.
Value
(quantitative
or Qualitative)
None 70% 70% 100%
Date achieved 04/30/2004 12/31/2009 12/31/2015 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). By 2012, the level of HIV/AIDS awareness among the
corridor users and communities living along the corridors surveyed and use of VCT
and other facilities to mitigate the spread of the disease reached 100%.
Indicator 6 : Legislation enacted for private sector participation in roads.
Value
(quantitative
or Qualitative)
None Yes Yes Yes
Date achieved 04/30/2004 12/31/2012 12/31/2012 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Kenya Roads Act 2007 was enacted, stating the
encouragement of private sector participation in road construction, maintenance,
and management. The PPP Act was enacted in 2013 and a toll road is one of the
prioritized projects.
Indicator 7 : At least 10% reduction in road related fatalities per annum.
Value
(quantitative
or Qualitative)
3,000 2,700 2,700 3,057
Date achieved 04/30/2004 12/31/2009 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator not achieved (0%). The total number of road related fatalities was not
reduced. However, fatalities per 100,000people have been reduced by 23 % from
8.31 in 2008 to 6.4 in 2015.
Indicator 8 : Kenya National Highways Authority established and functional as evidenced by
annual reports.
Value
(quantitative
or Qualitative)
None 100% 100% 100%
Date achieved 04/30/2004 12/31/2009 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Through the enactment of Roads Act in 2007, Kenya
National Highways Authority, Kenya Urban Road Authority, and Kenya Rural
Road Authority have been established and all are functional.
Indicator 9 : All feasibility and design studies carried out satisfactorily.
Value
(quantitative
or Qualitative)
None 100% 100% 100%
Date achieved 04/30/2004 12/31/2009 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). All the selected feasibility and design studies have been
completed: (a) three sections on the Kenya-South Sudan road, (b) Kibwezi-Kitui-
Mwingi-Maua, (c) Narok-Northern Lakeside Tanzania, and (d) Mombasa Southern
Bypass.
Indicator 10 : Timely public disclosure of national program and business opportunities in the road
sector.
Value
(quantitative
or Qualitative)
Partial and late
release of road
investment program
Plans disclosed Plans disclosed Plans disclosed
vii
Date achieved 03/05/2009 12/31/2010 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Road Sector Investment Program (RSIP) and Annual
Public Road Programmes (APRPs) are disclosed on Kenya Roads Board (KRB)
website. (http://www.krb.go.ke/adverts-downloads) All road works were procured
under open tender.
Indicator 11 : The National Construction Authority (NCA) established and functional as
evidenced by annual reports.
Value
(quantitative
or Qualitative)
None NCA established NCA established NCA established and
functional
Date achieved 03/05/2009 12/31/2011 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). NCA was established in 2011 through the National
Construction Authority Act. NCA is executing all functions outlined under the Act.
Annual report 2013/14 has been disclosed and the 2014/15 report will be published
in June 2016.
Indicator 12 : Road Sector Governance and Integrity Action Plan (RSGIAP) implemented
satisfactorily.
Value
(quantitative
or Qualitative)
None 100% 100% Mostly achieved
Date achieved 03/05/2009 12/31/2012 12/31/2015 12/31/2015
Comments
(incl. %
achievement)
Indicator mostly achieved (cannot be measured in %). The RSGIAP was targeting
the entire transport sector, and some of the proposed actions were beyond the
project scope. Implementation status of the RSGIAP is presented in Annex 10.
Indicator 13 : User perception and satisfaction improved in the road sector
Value
(quantitative
or Qualitative)
None >75% of users
surveyed are satisfied
>75% of users
surveyed are
satisfied
n/a
Date achieved 03/05/2009 12/31/2011 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator not achieved (0%) A study to measure this indicator was planned with
funding from the Governance and Anti-Corruption unit of the Bank. However, the
fund was not allocated and the study was not conducted. No existing information
was available.
Indicator 14 : JKIA meets the ICAO and TSA CAT1 security requirements.
Value
(quantitative
or Qualitative)
Not meet 100% 100% 100%
Date achieved 04/30/2004 12/31/2007 12/31/2014 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). JKIA obtained TSA clearance in 2009. Although JKIA
has not obtained the CAT1 status, the ICAO security audit in 2015 scored KCAA,
and KAA at a rate of 88 percent, against a cutoff of 80 percent for CAT1
certification.
Indicator 15 : No. of Passengers handled at JKIA (million).
Value
(quantitative
or Qualitative)
4.7 6.4 6.4 6.4
Date achieved 12/31/2007 12/31/2012 12/31/2015 12/31/2014
Comments
(incl. %
achievement)
Indicator achieved (100%). Based on KAA statistics, the number of passenger
handled at JKIA in 2014 was 6.4million. The information for 2015 was not
available yet.
viii
Indicator 16 : Cargo handled at KJIA (tons).
Value
(quantitative
or Qualitative)
278,000 383,000 383,000 260,000
Date achieved 12/31/2007 12/31/2012 12/31/2015 12/31/2014
Comments
(incl. %
achievement)
Indicator not achieved (-6.5%). According to the statistics from the KAA, cargo
handled at JKIA had a peak of 290,000 ton in 2011 and decreased since 2012 due to
external factors.3. The information for 2015 was not available yet.
Indicator 17 : KCAA meets ICAO and US FAA Category 1 safety requirements.
Value
(quantitative
or Qualitative)
None 100% 100% 100%
Date achieved 04/30/2004 12/31/2007 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Following the revenue gains, KCAA increased the
number of airworthiness and flight operations inspectors from 3 to 18 and 1 to 16,
respectively. KCAA expected to obtain IASA category 1 in the next audit in 2016.
Indicator 18 : The International Maritime Organization (IMO) and the Northern Corridor Transit
and Transport Agreement (NCTTA) certify compliance with respective treaties.
Value
(quantitative
or Qualitative)
None 100% 100% 100%
Date achieved 04/30/2004 12/31/2007 12/31/2013 12/31/2015
Comments
(incl. %
achievement)
Indicator achieved (100%). Kenya is listed as a white list country for
implementation of the International Convention on Standards of Training,
Certification, and Watch keeping for Seafarers of 1995. Kenya is in compliance
with the NCTTA provisions.
Indicator 19 : Bridges repaired and functional.
Value
(quantitative
or Qualitative)
0 3 DROPPED n.a.
Date achieved 04/02/2009 12/31/2010 12/27/2012
Comments
(incl. %
achievement)
Indicator was dropped in the 2012 restructuring.
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived DO IP
Actual
Disbursements
(USD millions)
1 11/11/2004 Satisfactory Satisfactory 6.50
2 12/16/2004 Satisfactory Satisfactory 6.50
3 05/17/2005 Satisfactory Satisfactory 6.51
4 12/02/2005 Satisfactory Satisfactory 6.70
5 06/22/2006 Satisfactory Satisfactory 7.11
6 12/29/2006 Moderately Satisfactory Moderately Satisfactory 8.00
3 http://www.businessdailyafrica.com/Dimethoatel-ban-hits-vegetable-exports-to-the-EU-market--/-/539546/1694416/-
/tf5vd1z/-/index.html. External factors such as the strengthening of European Union regulations on prohibiting fresh
products with excess level of pesticide (Dimethoate) are considered the main reasons.
ix
7 06/27/2007 Satisfactory Satisfactory 26.25
8 12/18/2007 Satisfactory Satisfactory 41.52
9 06/26/2008 Moderately Satisfactory Moderately Satisfactory 64.10
10 12/23/2008 Satisfactory Satisfactory 93.59
11 06/22/2009 Satisfactory Satisfactory 111.87
12 12/29/2009 Satisfactory Satisfactory 141.66
13 06/28/2010 Satisfactory Satisfactory 163.98
14 03/07/2011 Satisfactory Satisfactory 169.09
15 07/27/2011 Satisfactory Satisfactory 199.12
16 03/11/2012 Satisfactory Moderately Satisfactory 219.32
17 10/29/2012 Satisfactory Moderately Satisfactory 243.25
18 05/15/2013 Satisfactory Moderately Unsatisfactory 277.08
19 11/29/2013 Satisfactory Moderately Unsatisfactory 314.30
20 05/04/2014 Satisfactory Moderately Satisfactory 375.18
21 09/07/2014 Satisfactory Moderately Satisfactory 408.12
22 04/17/2015 Satisfactory Moderately Satisfactory 447.12
23 11/19/2015 Moderately Satisfactory Moderately Unsatisfactory 468.57
H. Restructuring (if any)
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made DO IP
12/14/2005 N S S 6.72
Restructured to change the
expenditures to be financed by
IDA under Roads Components
from 75 percent to 67 percent
and restructured project
component, support to KAA:
Cancelled the renovation of Old
Embakasi Airport (Nairobi)
instead expanded the JKIA, by
building fourth terminal.
04/02/2009 Y S S 103.19
Additional Financing (AF) to
meet a financing gap to complete
the original activities and to
implement a new component for
the rehabilitation and
replacement of infrastructure and
public assets damaged as a result
of post-election violence.
The closing date was also
extended by three years from
December 31, 2009 to December
31, 2012.
12/27/2012 N S MS 246.27
Level II restructuring as an
exceptional extension of the
project closing date by 36
x
Restructuring
Date(s)
Board
Approved
PDO Change
ISR Ratings at
Restructuring
Amount
Disbursed at
Restructuring
in USD
millions
Reason for Restructuring &
Key Changes Made DO IP
months to complete the on-going
activities that were delayed
because of factors external to the
operation and outside of the
control of the borrower. The
closing date was also revised to
December 31, 2015.
Note: MU = Moderately Unsatisfactory; S = Satisfactory.
If PDO and/or Key Outcome Targets were formally revised (approved by the original approving
body) enter ratings below:
Outcome Ratings
Against Original PDO/Targets Satisfactory
Against Formally Revised PDO/Targets Satisfactory
Overall (weighted) rating Satisfactory
I. Disbursement Profile
1
1 Project Context, Development Objectives and Design
1.1 Context at Appraisal
1. When the Northern Corridor Transport Improvement Project (NCTIP) was under
preparation, the new government of Kenya (GoK), which was installed in December 2002,
launched its Economic Recovery Strategy for Wealth and Employment Creation (ERSWE)
for the period 2003–07 to respond to weakening economic growth, low productivity, and high
unemployment. The GoK’s main objectives in the transport sector were to encourage the
private sector to lead economic growth through reducing the cost of doing business in Kenya
and to increase its competitiveness in domestic, regional, and international markets. Provision
of reliable and least-cost infrastructure services, particularly roads, power, water, and
communication was a key component of the new strategy.
2. The GoK established the Road Maintenance Levy Fund in 1993 to secure resources
for maintenance of the road network and established the Kenya Roads Board (KRB) in 1999
to oversee the road network and coordinate its development, rehabilitation, and maintenance.
The GoK also attempted to control axle loads along major corridors. Despite the institutional
development, policy, and funding instruments for the road sub sector, development of the
transport sector as a whole still suffered from numerous constraints at the time of appraisal:
particularly, inadequate funds, institutional inefficiencies, weakness in the policy, legal and
regulatory environment, poor safety and security standards at the airport and port, and
inadequate institutional capacity and human resources.
3. The project was consistent with two key areas of the World Bank Country Assistance
Strategy (CAS) placed in 2004: (a) strengthening public sector management and
accountability; and (b) reducing the cost of doing business and improving the investment
climate. The project was also consistent with the Kenya Transport Sector Memorandum of
2003 which was a Bank-financed Analytical and Advisory Activity to build the outline of an
infrastructure strategy and policy direction. The Memorandum identified adequate routine
and periodic maintenance, cost effectiveness of civil works, and institutional reforms seeing
or all critical to Kenya’s economic development.
1.2 Original Project Development Objectives and Key Indicators
4. As stated in the data sheet, the Project Development Objectives (PDOs) in the original
Development Credit Agreement (DCA) were “to enhance the efficiency and effectiveness of
the Borrower’s transport sector through: (a) increasing the efficiency of road transport; (b)
enhancing aviation safety and security to meet international standards; and (c) promoting
private sector participation in the management, financing, and maintenance of road assets”.
These PDOs were formulated slightly different in the Project Appraisal Document (PAD)
without any significant discrepancy but providing relative weights: 60 percent for road
transport efficiency, 30 percent for civil aviation safety and security enhancement, and 10
percent for private sector promotion.
5. The PDO outcome indicators in the DCA were as stated in the data sheet with
marginal differences from those in PAD. As indicated in the Implementation Completion and
2
Results Report (ICR) guidelines4, the indicators in the DCA are used in the ICR. The key
performance indicators for each component of the project are detailed in section F of the data
sheet along with discussions in section 3.2.
1.3 Revised PDO and Key Indicators, and reasons/justification
6. Additional International Development Association (IDA) credit was approved in
April 2009. The original PDOs were revised by adding one more PDO: (d) restoring vital
public infrastructure and assets damaged as a result of the December 2007 post-election crisis
to respond to the government’s urgent appeal to IDA to support the implementation of the
post-election recovery program (adaptive restructuring). The other three original PDOs
remained unchanged though additional or expanded activities were included in Components
A, C, and E, and Component F was restructured. Relevant weight of 60 percent for road
transport efficiency has been modified to 58 percent and 2 percent weight was given to the
newly added PDO.
7. To measure achievement of the additional element of the PDO, the Additional
Financing (AF) added one additional PDO indicator: “Vital public infrastructure and assets
destroyed or damaged during the post-election crisis are restored and functional again”.
Similarly to the other PDO indicators, the Financing Agreement and the AF project paper
worded this indicator slightly differently.
1.4 Main Beneficiaries
8. The project papers do not have an explicit section to describe the main beneficiaries
of the project. However, the economic analysis of road sector in PAD and the AF identified
that the main benefit of the project is ‘savings made by road users’. In addition to the road
users, from the statement of PDOs, airport users, private sector, as well as institutions of road
and civil aviation sub-sectors are considered main beneficiaries of the project.
1.5 Original Components
9. The NCTIP had originally three funding sources. The IDA credit (39300-KE) of
US$207 million, the Nordic Development Fund (NDF) loan of US$15.23 million (€12
million), which was parallel financing, and the GoK’ s contribution of US$54.26 million,
totaling US$276.49 million.
A. Rehabilitation of the Northern Road Corridor. (IDA US$134.59 million, total
US$190.46 million)
10. Strengthening and rehabilitation of about 373 km of selected priority road sections
along the Northern Corridor; improvement of the North Airport Road connecting the
Mombasa Highway to the Old Embakasi Airport (about 8 km); and consultant services for
supervision works.
4 p16 Guideline for reviewing World Bank Implementation Completion and Results Reports, updated on August 1, 2014,
IEG and p58 Implementation Completion Report Guidelines, OPCS, Aug 2006, last updated July 22, 2014
3
B. Socio-economic Enhancement, Roadside Amenities and HIV/AIDS Mitigation. (IDA
US$3.62 million, total US$4.35 million)
11. Construction of proper bus and truck stops at key selected locations, and off-road
booths for sale of local produce, and specific interventions along the Northern Corridor to
mitigate HIV/AIDS, such as awareness campaigns, distribution of condoms, strengthening
of local health centers as needed, voluntary counseling and testing, and support and care for
affected persons.
C. Private Sector Participation in Road Management and Maintenance. (IDA US$8.68
million, total US$10.66 million)
12. Provision of technical assistance to (a) facilitate the concessioning of selected
sections of the Northern Corridor road link; and (b) implement a pilot program of long-term
output and performance based maintenance and management of a selected sub-network
(about 300 km) of lower volume roads.
D. Road Safety Improvement. (IDA US$ 4.82 million, total US$4.96 million)
13. Provision of consultant services to prepare and implement a program of specific
actions designed to reduce the number of road accidents and fatalities.
E. Institutional Strengthening in the Roads Sector and Technical Assistance. (IDA
US$8.24 million, total US$11.46 million)5
14. Provision of technical assistance and training to enhance institutional capacity and
support policy reforms in the road sector, including establishment of an autonomous
National Highways Authority. This component also includes provision of consultant
services for design, engineering and preparation of bid documents for selected road projects.
F. Support to the Kenya Airports Authority. (IDA US$34.82 million, total US$41.91
million)
15. Financing of civil works, consultant services, purchase of equipment, IT support and
training to improve the operations, search and rescue capacity, and the safety and security
standards at the Jomo Kenyatta International Airport (JKIA), Mombasa Moi International
Airport, Wilson Airport, Kisumu Airport and other selected minor airports.
G. Support to the Kenya Civil Aviation Authority. (IDA US$10.02 million, total US$10.21
million)
16. This includes: (a) technical assistance for safety inspection, training, implementation
of Global Navigation Satellite System/Global Positioning System (GNSS/GPS) for en route
and approach procedures at minor airports; and (b) support to the East African School of
Aviation (EASA) for training of trainers, purchase of training equipment for airworthiness,
air traffic control systems, and engineering services, as well as an air accident investigation
laboratory.
H. Support to the Ministry of Transport and Communication. (IDA US$2.20 million, total
US$2.48 million)
17. This includes strengthening of the Ministry of Transport and Communications
(MOTC) through purchase of equipment, support to Bandari College, technical assistance,
5 Cost includes project operation cost of MoTI, US$1.1 million.
4
and training, and sector studies related to maritime laws and regulations, implementation of
the new transport sector policy and regional trade and transport facilitation.
18. In the rehabilitation of roads, 98 percent of design and supervision was to be funded
by IDA, while civil works were to be co-funded by the GoK and IDA at 25 percent and 75
percent, respectively. For the airport expansion and facility improvement, 94 percent of
consultant services was to be financed by IDA, and the civil works were to be co-funded by
the GoK and IDA at 26 percent and 74 percent, respectively.
1.6 Revised Components
19. Change in Financing Parameter and the revision of Project Component. On
December 14, 2005, Office Memorandum for change in the financing parameter for Civil
Works (Roads Component) and revision of the Component to support the Kenya Airports
Authority (KAA) was approved. The PDOs remained same and the DCA was amended as
follows:
Cancel the renovation of Old Embakasi Airport (Nairobi) and Paragraph 1 in Part F
of Schedule 2 to the Agreement is amended to read “Rehabilitation and
reconfiguration of the main terminal at Jomo Kenyatta International Airport and
construction of a new terminal 4; with corresponding reallocation of the credit
proceeds; and
Increase in the government’s counterpart share of financing for road works from 25
percent to 33 percent, and reducing the IDA share from 75 percent to 67 percent.
20. Additional Financing. The Board approved an additional IDA credit of US$253
million (45710–KE) entirely toward the road sub-sector for unfunded road sections and
deepening the reforms and Governance and Anti-corruption Action plan that was agreed
between the GoK and the Bank. The NDF financing increased by €4 million, totaling €16
million, which was equivalent to US$19.19 million. Due to changing in the financing
proportions, counterpart funding increased by US$286.35 million, totaling of US$340.64
million. In addition, US$100 million from other sources6 was included in the financing plan
and the overall revised project coast was US$919.83 million. The Results Framework was
also revised with additional indicators.
21. The AF added the implementation of Road Sector Governance and Integrity Action
Plan (RSGIAP) as a requirement. The RSGIAP included new steps and measures to improve
transparency and accountability such as the introduction of new and additional clause in the
road works contracts permitting the GoK and/or the World Bank to terminate any of these
contracts in the event that the winning contractors were debarred by the Sanctions Board of
the World Bank Group. The early termination clause was and remains an exception to Bank
policy. As the result, the NCTIP expanded its target to tackle with full-scale road sub-sector
reform.
22. Revised components of the projects under the AF were as follows: (a) AF to cover
the shortfall in financing of three original components, Components A, C and E, including
the expanded or new activities within the components; and (b) restructuring of Component
6 Financiers under consideration included European Investment Bank and Kenya Local Banks
5
F without AF from IDA. The rest of the original components, Components B, D, G and H
remained unchanged. Details of the revision are described below:
Component A: Rehabilitation of Northern Corridor and Emergency Rehabilitation
(US$318.41 million cost increase; additional IDA financing of US$220.43 million)
23. The AF covers unfunded rehabilitation and improvement of three road sections: Mau
Summit-Kericho, Kericho-Nyamasaria, and Nyamasaria-Kisumu Airport-Kisian, totaling
158 km. In addition, a new sub-component was the repair and replacement of roads and
bridges damaged or destroyed by floods in late 2006 and early 2007, and restore other public
infrastructure assets including buildings, vehicles, and equipment damaged following the
general elections in December 2007.
Component C: Private Sector Participation in Road Management (US$12.70 million cost increase; additional IDA financing of US$8.82 million)
24. Additional cost has been allocated to the existing two sub-components.
Component E. Institutional Strengthening in the Roads Sector and Technical Assistance.
(US$24.24 million cost increase; additional IDA financing of US$23.75 million)
25. In addition to the existing studies, design studies for the Sudan Link road and the
Urban Public Transport Improvement study in Nairobi were added to this component. A new
sub-component, Strengthening Governance in the Road Construction Industry, was added
with the following activities: (a) establishing a road infrastructure disaster management and
response unit within the Kenya National Highways Authority (KeNHA); (b) establishing a
National Construction Authority (NCA) to promote and oversee professional and ethical
conduct in the construction industry; and (c) strengthening the Engineers’ Registration Board
(ERB) and its associated institutions, including the Institution of Engineers of Kenya.
Institutional strengthening within the existing component was also scaled up under the AF.
Component F. Support to the Kenya Airports Authority 26. Component F was restructured, without any AF from IDA, as follows:
(a) Cancel the rehabilitation of the Old Embakasi Airport;
(b) Introduction of new project activities for: (i) the expansion of JKIA, including
construction of a new passenger terminal building (unit 4), a car park, and
reconfiguration of terminals 1, 2, and 3, and (ii) the supervision of expansion works
at JKIA Units 1-4 and arrivals building;
(c) Reallocation of the following IDA funds to the expansion of JKIA: (i) terminal
construction and extension of the runway at Kisumu Airport, (ii) renovation of the
terminal and upgrading of security at Wilson Airport, and (iii) rehabilitation of the
Old Embakasi Airport;
(d) Reduction of IDA’s financing percentage for civil works at JKIA Unit 4 and car park
from 25 percent to 19 percent; and
(e) Consolidation of the subcomponents for security perimeter lighting, surveillance
system, and support to emergency centers into the subcomponent for security and
communications equipment and vehicles, and adjustment of funds for feasibility,
design, and supervision of Kisumu and Wilson Airport reconfiguration and training.
6
1.7 Other significant changes
27. Restructuring. In addition to the changes in financing parameter and the revision of
project component in 2005 and the AF, the project had a level II restructuring in December
2012. This was an exceptional request to extend the closing date of both original and
additional credits by 36 months to complete the on-going activities. Delays were partially
due to the implementation of RSGIAP. Since the sector wide reform was not anticipated
originally, due to the factors external to the operation and outside of the control of the
Borrower, extension was requested. Reallocation of funds among various categories of the
NCTIP was also included in the restructuring.
28. Parallel Financiers. The French Development Agency (Agence Française de
Développement, AFD) (new credit, US$93 million) and European Investment Bank (EIB)
(new credit, US$93 million equivalent) decided to provide parallel finance to the NCTIP,
which became effective in 2011. The AFD supported the construction of Unit 4 terminal
building and car parking garage of JKIA and the activity has completed successfully7. On
the other hand, the EIB was to finance the remodeling of JKIA terminals but decided to
cancel its finance due to considerable delays and the needs to retrofit the expansion plan at
JKIA following the fire tragedy in 2013 that destroyed part of the facilities which had been
earmarked for remodeling. Since the GoK has not made the final decision on the remodeling
of terminal 1-B, C and D, this activity has been on hold.
29. Government Restructuring. With the ratification of new Constitution in 2010,
transport sector under Ministry of Roads, Public Works and Housing and Ministry of
Transport and Communications were merged under one ministry, Ministry of Transport and
Infrastructure (MoTI). MoTI has State Department of Transport and State Department of
Infrastructure.
2 Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
30. The project quality at entry is rated Moderately Satisfactory. The project was
designed in a client-oriented manner, responding to the government’s priorities set in the
ERSWE and gaps identified by the ongoing transport sector reform task force, and aligned
with the support areas identified under the CAS (2004-2007) as well as the Transport Sector
Memorandum. The project embraced a holistic approach to support policy formulation and
project implementation in various transport subsectors, including regional security and
tourism perspectives and its impact on the economic development of the country. Significant
weight was given to strengthening the institutional structure in the road subsector.
31. Adequacy of government support on project preparation. The GoK had taken
numerous steps to reform the entire transport sector since the 1990s, such as establishment
of the Road Maintenance Fuel Levy Fund and KRB, improvement of axle load control,
setting up of a national taskforce, the enactment of the Civil Aviation Act to establish an
autonomous Kenya Civil Aviation Authority (KCAA), privatization of Kenya Airways, and
so on. At appraisal, the GoK had set up a high level task force to review the existing structure
7 Final financing shares for unit 4 terminal and car parking are: IDA (11 percent), AFD (71 percent), and GoK (18
percent).
7
of roads department.
32. Well selected project components. The Bank team had extensive discussions with
both the GoK and development partners to finalize project components and increase
coordination in the sector. Although the project covered various transport subsectors, which
could increase the risk of poor performance by increasing the project’s complexity, the Task
Team deemed it necessary to propose a holistic approach to the GoK based on their
assessment of the ongoing sector reform and government commitment. Importance was
given to Bank policies, specifically social and environmental safeguards (resettlement and
HIV/AIDS mitigation, roadside amenities, and so on), some of which were new to Kenya.
The financial management (FM) and procurement capacity of the implementing agencies
(IAs) was reviewed, and possible funds flow and disbursement regimes were identified and
agreed at the preparation stage. One component of the project concentrated on the
improvement of the road safety.
33. Built on the lessons learned from previous transport sector reforms in the Region.
The World Bank accumulated considerable knowledge and experience in transport sector
reform in the region through Sub-Saharan Africa Transport Policy Program. Specifically,
the framework developed under the Road Management Initiative would inform efforts to
improve the institutional and financial sustainability of road management. Based on
previous road sector projects, the project was designed to ensure ownership of the project,
emphasize capacity building, incorporate an “all-inclusive” Project Technical Team (PTT),
and include adequate and secured domestic funding in project-financed infrastructure
maintenance.
34. Assessment of project design and Results Framework. The PDOs of the project were
clear. Importance of project components to the PDOs was mostly evident but the causal
chain between Components B, D, E, and H and PDOs was vague (see section 2.3). Since the
project supported a transport sector reform in addition to the infrastructure development, the
original project life of five years underestimated the complexity of and necessary time for
sector reform to attain a sustainable level.
35. Assessment of risks and mitigation. Overall risk rating at appraisal was ‘Substantial’
with one element related to the PDO, and three elements related to component results rated
‘Modest’. Most of the potential risks were identified and mitigation measures were prepared,
but the following two potential risks were not identified: (a) institutional sustainability, and
(b) effective monitoring and evaluation (M&E) mechanisms. Because the project was to
support the establishment of a new highways authority, a strategic approach would be
required for the sustainability of such an authority in terms of funding and human resources.
In addition, the project was to set up an innovative approach in M&E, outsourcing the task
to a local academic institution that had no experience in M&E of large infrastructure
investment projects. Therefore, there was uncertainty about the quality of outputs and extra
attention was required in order to ensure adequate implementation. There was no potentially
controversial aspect identified at the appraisal stage of the project.
8
2.2 Implementation
36. The key issues affecting project implementation were the change of leadership, post-
election crisis, regional security deterioration, floods, cost increase, late release of payment,
inadequate counterpart funding, poor project management of civil works, the review of road
sector procurement, and RSGIAP. Between the start of the project in September 2004 and
July 2011, most Implementation Status and Results reports (ISRs) rated project performance
‘Satisfactory’. Project performance was rated ‘Moderately Satisfactory’ twice between 2006
and 2011, first when significant delays were noted due to changes in the project technical
team leadership (road subsector) in 2006 and second the post-election violence in 2007/8.
The Mid-Term Review (MTR) in 2009 noted the satisfactory project progress with
completions of Maji Ya Chumvi-Miritini road section and security fencing of JKIA, and
substantial completion of Lanet - Njoro Turn Off road section. The MTR explained the low
disbursement at the initial stage was attributed to prolonged delays in start-up activities.
Starting 2012 to the closing of the project, ISR rated the implementation ‘Modestly
Satisfactory’ or ‘Moderately Unsatisfactory’ mainly because of late release of payment and
lack of counterpart funding. This section will discuss both positive and negative factors that
affected the project implementation.
37. Government commitment to sector reform enabled the successful implementation of
this complex project with multi IAs from different transport sub-sectors and under three
different administrations over the project cycle. Enactment of the 2007 Kenya Roads Act
and creation of three road authorities in 2008 were realized one year before the revised
target. The KCAA and KAA also became financially independent through the structural
reform of agencies. The National Transport and Safety Authority (NTSA), NCA and the
Engineering Board of Kenya (EBK) were established in 2011/12 through the enactment of
designated acts. The Project Coordinating Team had quarterly meetings where IAs shared
and discussed progress and implementation issues. Quarterly meetings also contributed to
the enhancement of communication and coordination among IAs, providing a platform for
discussions, and boosted supports for an integrated transport approach in Kenya. The project
coordination was further improved after the MoTI assigned the current project coordinator.
38. The NCTIP suffered from unexpected negative factors, such as a sharp increase in
the price of key construction material in the international market, post-election violence in
2007/08 and deterioration of regional security due to terrorist attacks since late 2011. Soon
after the approval of the project, the prices of key construction materials in the international
market increased, particularly steel, fuel and bitumen resulting in high bid prices of the civil
works contracts. Post-election violence displaced about 350,000 people8 and led the NCTIP
to suspend operations in several locations due to temporal unavailability of labor. The
increased security risk in the region suspended the realization of direct flights to/from JKIA
and U.S. airports approved by the Transportation Security Administration of the United
States (TSA) in 2009 and required a higher level of security facilities at the major airports
in Kenya. The number of international passengers at JKIA that had increased steadily since
1998, decreased 5 percent in 2013, compared to a peak in 2011.
39. Prolonged project life was partially due to the detailed reviews in Kenya conducted
by the Department of Institutional Integrity (INT) and the introduction of the RSGIAP
8 https://wikileaks.org/wiki/Full_Kenyan_post_election_violence_report_2008
9
imposed by the AF. Concerns about integrity issues and to increase transparency and
accountability in the road sub sector led INT to conduct detailed implementation reviews of
on-going projects in Kenya, including the NCTIP during 2005-07. This review put on hold
the implementation of project activities. The INT also conducted reviews of some of the
bidders for three project road sections 9 in 2008, which caused further delays in the
processing of the AF and start-up of execution of road contracts. Implementation of RSGIAP
required both the Bank and the GoK to undertake additional due diligence, such as reviews
of the winner of bids. The full-scale sector reform necessitated more time than anticipated.
40. A unilateral change in the leadership of the PTT (road sector) in 2006 without
consulting the Bank also caused a delay in start-up activities of road construction work.
Changing the leadership without consulting the Bank was in contravention to the legal
agreement. After the protracted discussions with the GoK, the Ministry of Roads, Public
Works, and Housing (MoRPWH), Ministry of Finance (MoF), and the Bank signed the
Memorandum of Understanding on transitional arrangements for the proposed change in the
MoRPWH PTT, which provided the way forward.
41. Slow progress of civil works due to contractors’ poor project management and
inadequate deployment of resources had serious impact on the project implementation.
KeNHA issued warning letters to the contractor of road sections: Mau-Summit-Kericho,
Kericho- Nyamasaria, Sultan Hamud-Machakos Turn off, and Machakos Turn off-JKIA,
and requested a supervision engineer to intensify monitoring with preparation of a quarterly
work program including specific outputs for each month. At the same time, it was agreed
among KeNHA, the supervision consultant and the contractor to review the contract if the
progress remains slow.
42. KeNHA applied liquidated penalties for the section of Machakos Turn off-JKIA,
which took twice as much time than originally projected. Since the contractor contested this
action, this dispute was brought to the Permanent Court of Arbitration in The Hague. Based
on the recommendations from the Dispute Resolution Expert (appointed by the Court), both
sides agreed on an amicable settlement. Intensive monitoring after this dispute contributed
to the improvement of the progress of the construction work.
43. Insufficient counterpart funding and delays in payment processing were serious
challenges. Adequate and timely counterpart funding was reported during the first phase of
the project but after approval of the AF, securing the counterpart funding became a serious
and systemic issue, specifically in the last two years of the project. In addition, the slow and
duplicative payment procedures of the ministry delayed the settlement of payment
certificates. The delays in commencement of road sections of Mau-Summit-Kericho and
Kericho-Nyamasaria were caused by a lack of counterpart funding for the advance
payment. 10 The outstanding payment and uncertainty of future payments from the
counterpart resulted in the suspension of construction for the sections of Sultan Hamud-
Machakos Turn off and Machakos Turnoff-JKIA for some time. Payment of interest due to
the delays in payment was also a significant burden to the GoK. 11 Prioritization of
9 Mau Summit-Kericho; Kericho-Nyamasaria; and Nyamasaria-Kisumu-Kisian 10 It is recorded that no objection from the World Bank to award these contract was issued on October 2009, but the
construction commenced only in October 2010. 11 KSh 158.5 million in interest is recorded in December 2013.
10
implementing the New Constitution ratified in 2010 was another factor.
44. To cope with inadequate counterpart funds, the GoK requested the Bank to allow for
100 percent IDA financing for the road works contract starting FY 13/14 until the IDA fund
was exhausted. This contributed significantly to the improvement of disbursement and
progress of civil works. The Bank also recommended in 2014 that the National Treasury
issue clear guidelines on securing budgets of donor funded projects. The guidance was
finally issued in September 2015, and disbursement of funds and payments to contactors
resumed in December 2015. At the ICR mission in February 2016, there was KSh 2.9 billion
outstanding payments for the road works to be paid from counterpart funds by June 2016
and the National Treasury assured the availability of this budget.
45. The increase of cost let the GoK to request AF in 2008. The main causes of cost
overruns were due to: (a) significant escalation in input unit costs in the international market;
(b) higher traffic growth than expected, resulting in upgrading to the road design; (c)
significant deterioration in the project road sections, aggravated by the floods in 2006/07,
which resulted in greater than expected rehabilitation costs; and (d) additional costs incurred
for supporting post-election reconstruction. An assessment of unit construction costs in
neighboring countries, such as Uganda, Ethiopia, Tanzania, and Mozambique, undertaken
at the time of the AF found that unit cost increase under the project reflected regional and
global market movements and no abnormality was found.
46. As stated above, a rapid growth in traffic volumes on the corridor forced KeNHA to
increase the scope of the original intervention. The number of vehicles in the major cities
nearly doubled between 2003 and 2007, and the strong traffic growth continued throughout
the project life: The annual average daily traffic (AADT) on eight project road sections
varied from about 4,400 to 25,300 in 2014/15, compared to 2,000 to 12,000 in 2003 with an
average annual growth rate of 8.1 percent. 12 Between 2003 and 2014, the number of
registered vehicles in Kenya increased by about 1.56 million13 while the total number of
registered vehicle in Kenya in 2013 was 2.01 million.14
47. Based on the above discussions, the overall implementation of the project, including
the compliance with both the original credit and the AF is rated Moderately Satisfactory.
2.3 Monitoring and Evaluation Design, Implementation and Utilization
48. M&E design. As noted in section 2.1 the PDOs are clear, but slightly differed
between the PAD and DCA, and the indicators of several components did not reflect the
objectives directly. Attaining road sub sector reform was one of the important targets of the
project but there was no PDO indicator to address this challenge. The AF supported the
further expansion of JKIA and added intermediate outcomes as well as indicators to measure
the capacity expansion of JKIA, which was different from security and safety enhancement.
However, PDO2 for aviation remained unchanged, and the causal chain between the PDO
and the additional expected component outcome became unclear. In addition, measuring
methods for some indicators were not feasible, for example, ‘legislation enacted for private
12 KeNHA: NCTIP Project Completion Economic Analysis Summary, April 2016 13 Kenya Facts and Figures, Kenya National Bureau of Statistics. 14 WHO: Global Health Observatory data repository
11
sector participation in road’, and ‘compliance with respective treaties’, cannot be measured
as a percentage.
49. The Results Framework prepared under the NCTIP was designed to be monitored by
a team of experts from the University of Nairobi Enterprises and Services Limited (UNES),
and the baseline survey was completed in 2007. While responsible agencies were assigned
for data collection, UNES was to consolidate and analyze the data. The approach to utilize
a local academic institution was innovative, and positive impacts on the institutional
capacity were observed, supporting more than 50 post-graduate students and a PhD
candidate majoring in transport and setting up a transport data bank in the university. This
arrangement is currently adopted by ongoing Bank-supported transport projects in Kenya.
50. Due to rapid motorization during the project period, there is a high risk of worsening
traffic congestion in urban centers along the Northern Corridor. Since this risk directly
affects the total travel time, this should have been identified and reviewed at the AF or at
restructuring, including the travel time of individual road sections to the PDO indicator. The
distance between Mombasa and Malaba/Busia is about 930 km and to achieve the target
travel time, trucks, cars, and buses need to maintain an average speed of 52 km/h, 85 km/h,
and 69 km/h, respectively. Thus, this target travel time was rather ambitious with respect to
the speed limit within towns and for specific vehicles set by the Traffic Act of Kenya.15 This
aspect needed to be considered as the Bank is a leading institution for road safety.
51. M&E Implementation. In spite of the high sustainability of the M&E arrangement
with an institutionalized system, the following challenging were observed in M&E
implementation: (a) long delays in contracting the UNES (contract was signed in early 2006)
and amendment of contract duration; (b) delays in data collection and reports, specifically
starting 2011; and (c) quality of M&E reports. During the ICR mission, lack of
understanding of the tasks of the M&E consultant was observed and missing project
indicators in the M&E reports were addressed though it was confirmed that each IA has
collected accurate and relevant data. The issue was not the credibility of available data, but
the inefficient M&E process (collecting and analyzing data), which was also addressed by
the IAs and stakeholders. The ICR team therefore directly obtained most of the data from
IAs and stakeholders.
52. It is also noted that the monitoring of agreed indicators by the Bank team was
inconsistent and indicators different from the Results Framework were sometimes recorded
in the ISRs. Some indicators, such as reduction in road-related fatalities, implementation of
the RSGIAP, road user perception and satisfaction, and so on, have been hardly explained
in the ISRs or Aide Memoires. Achievement of the target of 25 percent reduction in travel
time, which is one of the outcome indicators, has been reported in ISRs and Aide Memoires
repeatedly but the data source was not confirmed under the ICR process. Likewise, apart
from the obtainment of the TSA security clearance, further details should have been
provided related to the United States Federal Aviation Administration (FAA)/International
Aviation Safety Assessment (IASA) Category 1 (CAT1), which was not achieved at the end
of the project, whereas it was also an important outcome indicator.
15 The Traffic Act of Kenya defined that the maximum speed of a vehicle in a town is 50 km/h. To travel from Mombasa
to Malaba (930 km) in 11 hours requires an average speed of 85 km/h.
12
53. M&E Utilization. During the implementation of NCTIP, utilization of M&E was
partial because of discrepancy of indicators, inadequate analysis on M&E, and delayed
submission of M&E reports. After the closing of the project, a workshop to present the
achievements and lessons learned of the NCTIP was held on March 13, 2016. It presented a
good opportunity for stakeholders to review the achievements of the project and utilize the
information collected. There were useful comments from stakeholders to improve the M&E
of the project. It was unfortunate that there was no other workshop during the
implementation of the NCTIP to discuss the project progress with the stakeholders based on
the Results Framework of the project.
54. M&E collaboration with the Northern Corridor Transit and Transport Coordination
Authority16 (NCTTCA) under the NCTIP was not as strong as the project aimed. The limited
resources and manpower of NCTTCA were noted at the entry, but the Authority currently
monitors 30 performance indicators along the corridor separately prepared under one of its
program areas and has established the Northern Corridor Transport Observatory on their
website which presents the monitoring results in a timely manner. Since their monitoring
coverage is getting wider and more comprehensive in recently years, it is expected that
performance of the corridor will continue to be monitored after the end of the project.
55. In conclusion, the Bank has raised concerns on the M&E implementation, but it
could have intervened in this matter more proactively, considering the importance of M&E.
Gaps observed in the project M&E design and implementation reflect enhanced M&E
quality and effectiveness as a lesson learned for future projects.
2.4 Safeguard and Fiduciary Compliance
56. Safeguard. Based on the project implementation review by the safeguard and natural
resource management specialists, the safeguard policies triggered during project preparation
were found adequately covering the impacts and risks of the implemented subprojects. The
NCTIP was designated as an Environment Category ‘B’ project-a partial assessment.
Environmental Assessment (OP/BP 4.01) and Involuntary Resettlement (OP/BP 4.12) were
triggered by the project. Resettlement Policy Framework was reviewed and cleared by the
Bank and disclosed to public (InfoShop) on January 14, 2004. Based on the Framework,
Resettlement Action Plans (RAP) were prepared for all road work contracts and in total
1,055 project affected people were compensated under the NCTIP. KeNHA carried out land
acquisition for five road sections between 2010 and 2015 with the total amount of KSh 946
million without experiencing any substantial delays in civil works.17 KeNHA assigned
environmental and social specialists to the project. KAA also carried out land acquisition
satisfactorily for upgrading Kisumu Airport except one landowner who refused to move.
The key safeguard challenges in the operation are summarized in the table 1.
57. Road-side amenities and social and economic enhancement component, including
HIV/AIDS mitigation has been successfully completed with positive impacts as discussed
in section 3.5. As the follow up matters, the RAP completion reports and rehabilitation of
16 The NCTTCA was established under the legal framework of the Northern Corridor Transit Agreement to co-ordinate
implementation of the Agreement and to carry out decisions and resolutions reached by policy organs of the Authority. 17 For the sections of Maji ya Chumvi-Miritini and Sultan Hamud-Machakos Turnoff, no specific issue of land acquisition
has been observed but the detailed information is not available in KeNHA since the constructions were undertaken by the
Ministry before the establishment of KeNHA.
13
borrow pits and stone quarries are required while close monitoring of the allocation of the
trading stalls or units in Awasi market upon the completion of construction is necessary.
Table 1. Safeguard policies triggered by the NCTIP and implementation challenges
Safeguard policy triggered
by NCTIP
Implementation challenges
OP/BP 4.01 Environmental
Assessment Construction related impacts;
Safety of construction sites (speed control);
Timely quarry rehabilitation and closure.
OP/BP 4.12 Involuntary
Resettlement Compensation of project affected people without legal rights,
e.g. open air market traders with make-shift structures;
No clear guidelines on livelihood restoration;
Most of the road reserves encroached upon;
Setting up of cut-off date due to difficulties of controlling the
influx of people;
Political interferences;
Speculative development along the project area;
No clear national policies on RAP;
Issues of land ownership and documentation (succession issues
leading to litigation);
Lack of adequate funds for timely RAP implementation.
Access to Information Policy n.a.
58. Financial management. The project complied with the financial covenants stipulated
in the Financing Agreement. All the quarterly unaudited and the annual audited financial
reports were received. Some of the clarifications requested by the audits were mainly related
to delays in project implementation and outstanding bills that attracted interest and penalties.
The main challenges during implementation were inadequate provision of budget against
the submitted annual estimates that in turn affected the releasing exchequer. Delays in fund
flows were also experienced especially by the parastatals. The delays could be traced either
at the National Treasury or at the line ministry. The weak capacity of staffing and frequent
transfer of accountants at the line ministry also affected the efficiency of project operation.
However, the IAs has built overall capacities in FM over the years.
59. Procurement. Overall procurement performance under the project was rated as
Satisfactory. At the initial stage of project implementation, slow and unsatisfactory
procurement process was noted in the road subsector due to the transferring of functions
from the ministry to the newly established KeNHA. However, KeNHA increased its
procurement capacity rapidly through institutional strengthening and technical assistance of
the NCTIP, and the procurement plan was back on track. KeNHA is currently fully
established and staffed with qualified and experienced technical and procurement staff
though procurement capacity under Bank financed operations is still relatively low, and
specifically, contract management needs to be strengthened. KCAA, KAA, and MoTI also
completed all the contracts earmarked for implementation under the project satisfactorily.
2.5 Post-completion Operation/Next Phase
60. At closure, most of the activities were either completed or close to completion. Status
of the remaining activities at the ICR submission are as follows: The Nyamasaria-Kisumu
14
Airport-Kisian section (total 21.9 km, 8.4 km of which is dual carriage way) was completed
and handed over to KeNHA in March 2016, except the Nyamasaria-Kismu-Kisian road
section including Kisumu Bypass in which street lighting, road furniture, landscaping, foot
bridges, and construction of drains remains to be completed by July 2016. The office
rehabilitation and construction of new office buildings were completed and handed over to
the GoK in March 2016. A lorry park at Nyamasaria and a market at Awasi are expected to
be completed by September 2016. The National Treasury acknowledged the outstanding
payments and assured (ICR mission in February 2016), smooth weekly disbursement of
funds to MoTI to complete the remaining payments.
61. As a positive impact of the NCTIP, some of the rehabilitated roads under the project
are currently being maintained under the output- and performance-based road contract
(OPRC). The NCTTCA is also monitoring the performance of the corridor including the
quality of roads and traffic volume.
62. Even after the project is closed, the GoK, KAA and the KCAA are taking further
steps towards the obtainment of the FAA CAT 1 recognition: the KAA and KCAA drastically
improved its compliance rates through follow-up on the eight critical elements identified by
the International Civil Aviation Organization (ICAO). They have met the requirements for
the CAT1 clearance and expect to obtain CAT 1 certification in 2016. The key challenge for
the KCAA is to retain its inspectors through an adequate staff loyalty policy, by offering,
among others, competitive salaries.
63. Feasibility studies carried out under the NCTIP facilitated the project preparation
and financing: Implementation of Mombasa Southern Bypass is financed by Japan
International Cooperation Agency (JICA), and the design of Lesseru-Nadapal/Nakodok
Road has accelerated the preparation of the Eastern Africa Regional Transport, Trade and
Development Facilitation Project (P148853). The project was approved by the Board in June
2015 and became effective in November 2015, before the closure of the NCTIP.
64. Continuous institutional capacity building activities are undertaken by on-going
projects: National Urban Transport Improvement Project (NUTRIP, P126321) and Kenya
Transport Sector Support Project (KTSSP, P124109) have institutional capacity building
supports for the NTSA, NCA, KRB, EBK and, KCAA. KTSSP also supports capacity
building of KAA.
65. Follow up on uncompleted activities is necessary: the GoK’s decisions are awaited
for the conclusion of the development of a 50-year transport master plan, the remodeling of
terminal 1-B, C and D, and the restructuring of KCAA.
3 Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
Rating: High
66. The project objectives and accomplishments remain highly relevant to the GoK’s
current development priorities. The GoK’s development strategy, “Vision 2030” recognizes
the transport sector as a key Pillar for development and identified the NCTIP as a flagship
project to promote trade in the East African region and enhance economic and social
integration. The PDOs remain highly consistent with the current Country Partnership
15
Strategy, contributing to two of the three focus areas: (a) “Competitiveness and
Sustainability - Growth to Eradicate Poverty”, of which a key objective is enhancing
infrastructure and logistics to promote growth, and (b) “Protection and Potential - Human
Resource Development for Shared Prosperity”.
67. The objective of improving aviation safety and security enhancement to meet
international standards remains highly relevant as travel and tourism are key elements to the
economy of Kenya 18 and East Africa, and full compliance with international aviation
standards is critical to the sustainability of Kenya’s civil aviation and tourism industries.
68. The relevance of project implementation is assessed as High. The Project Oversight
Committee (POC) and project coordinating team conducted quarterly meetings, and a
project coordinator was appointed to increase coordination among IAs. These efforts created
a platform for the sub sectors to learn from each other and for discussing the transport sector
in general. The Bank responded promptly to unexpected events such as post-election crisis,
cost increases, emerging demands for further expansion of JKIA and up-scaling the design
scope of road sections due to higher traffic growth, severe floods, and so on, by processing
the AF and restructuring the project activities and reallocating funds. Flexibility of accepting
100 percent financing from IDA allocation starting FY13 until the exhaustion of the funds
mitigated the risk arising from the lack of counterpart funding. These actions were highly
relevant as they allowed the successful completion of almost all project activities.
3.2 Achievement of Project Development Objectives
69. Overall attainment of original PDOs and revised PDOs are both considered
Substantial. The project involved the reform of the transport sector and covered multiple
subsectors of transport, including road, civil aviation, and maritime. The NCTIP introduced
an integrated approach to transport planning, which led to developing and adopting an
integrated transport policy in 2009. The project established a platform for the transport sector
through quarterly meetings to discuss transport issues in an inclusive and holistic manner.
The project has met the targets for four out of six PDO indicators, and met targets for 13 out
of 18 intermediate indicators. In addition to the outcome and intermediate indicators,
benefits associated to each PDO are considered in the assessment. The relevant importance
among four PDOs follows the order listed in legal agreements and weight given in project
papers. In summary, the NCTIP has largely achieved the PDOs. The assessment results of
each PDO are summarized below, and achievements by objective are detailed in annex 2.
Table 2. Summary of achievements of PDO indicators
Outcome Indicators Targets
Actual
Values
Percent
Achieved
Aggregate rating of Efficacy: Substantial
PDO1. Increase the efficiency of road transport (58 percent weight)
Travel time by road from Mombasa to Malaba and Busia
reduced by 25 percent
25% 15% 60%
PDO2. Enhance aviation safety and security to meet international standards (30 percent weight)
(a) KCAA is cleared as category 1 safety status under the
IASA of the US FAA
CAT 1
clearance
obtained
Not obtained
but met the
requirements
0%
18 The total contribution of Travel & Tourism to GDP was KSh561.8bn (10.5% of GDP) in 2014.
16
(b) JKIA in Nairobi is cleared by the US TSA for direct
flights to/from United States airports
Direct
flight
cleared
Direct flight
cleared
100%
PDO3. Promote private sector participation in the management, financing, and maintenance of road
assets (10 percent weight)
(c) One long term performance based road management
and maintenance contract awarded to the private sector
and is effectively under implementation
(d) One road segment along the Northern Corridor
offered for concession to the private sector
100%
100%
100%+
100%
100%+
100%
PDO4. Restore vital infrastructure and public assets damaged as a result of the 2007 post-election
crisis (2 percent weight)
Vital public infrastructure and assets destroyed or
damaged during the post-election crisis are restored and
functional again
100% 100% 100%
70. The classical aggregated evaluation is adopted for the NCTIP. Original PDOs and
outcome indicators were unchanged, and restated in the Financing Agreement of the AF.
Fourth PDO added at the AF was to respond to the post-election recovery program with an
outcome indicator specific to the PDO. In addition, low disbursement ratio at the AF (21
percent) implies that overall outcome rating would be largely affected by the attainment ratio
of all parameters after the AF. Therefore, split evaluation does not gain any merit in this ICR
to assess the achievements of PDOs.
PDO1. Increase the Efficiency of Road Transport - Rating: Substantial
71. The project has substantially achieved the first PDO by rehabilitating in total 419.3
km19 of the Northern Corridor satisfactorily, reducing travel time by 15 percent in spite of a
more than doubling of the traffic volume for the project road sections20, constructing road
side amenities, reducing road related fatalities, establishing and enhancing KeNHA, and
increasing transparency and accountability in the road sub-sector as detailed in table 3.
Table 3. Summary of Achievement by PDO1
<Rehabilitation of Roads>
Rehabilitating total 419.3 km of the Northern Corridor satisfactorily
Travel time Mombasa-Malaba/Busia has been reduced by 15 percent
Condition of project road has been improved with International Roughness Index score
less than 3.0
Constructing road side amenities more than targeted
100 percent road users and local persons surveyed are aware of HIV/AIDS or make use
of VCT
<Road Safety>
Reducing road related fatalities: while total number of road related fatalities has not been
reduced, fatalities per 100,000 people have been reduced by 23 percent from 8.31 in 2008
to 6.4 in 2015
Constructed and rehabilitated six road safety parks
19 Total rehabilitated and improved road length 419.3 km includes 41.4 km dual carriage (377.9 +41.4= 419.3 km) as per
Borrower’s report. 20 For 8 project road sections, the average growth in traffic volume between 2003 and 2014/15 was 265 percent, varying
from 154 percent for the Lanet-Njoro Turnoff section and 345 percent for the Nyamasaria-Kisumu Airport-Kisian section.
17
<Institutional l Enhancement>
Road Act was enacted in 2007 and amended in 2009 and 2012
KeNHA, Kenya Urban Roads Authority (KURA), Kenya Rural Roads Authority
(KeRRA) have been created and functional
KeNHA/MoTI completed all planned feasibility and detailed engineering design studies
Established NCA is executing all the functions outlined under the Act
KRB completed inventory/reclassification of 160,886 km of roads which was published
in the national gazette in January 2016
EBK has been established and approved 32 accredited engineering programs in six
universities in Kenya
National Road Safety Program has been prepared and NTSA has been established
<Transparency and Accountability>
Road Sector Investment Program and Annual Public Road Programs are disclosed for the
public
GoK implemented most of RSGIAP in a satisfactorily manner
All road works under Road Authorities were procured under open tender
Kenya became one of the compliant Member States on Northern Corridor Transit and
Transport Agreement provisions
<Project ownership and commitment >
GoK provided US$307.94 million to complete the road sector work against US$126.12
million as revised at AF.
PDO2. Enhance Aviation Safety and Security to meet International Standards
-Rating: Substantial
72. The second PDO was substantially achieved as presented in table 4. The CAT1
certification has not been obtained officially but it is expected to be obtained later in 2016
due to the considerable improvements in aviation safety and security.
Table 4. Summary of Achievement by PDO2
<Clearance of IASA Category 1>
KCAA is on track to meet the FAA CAT1 requirement, recruited key staff with the
required qualifications and in adequate numbers, especially in the area of safety
ICAO security audit in October 2015 scored Kenya, the KCAA and KAA a rate of 88
percent, against a cut off rate of 80 percent for CAT1 certification
< Clearance of Direct Flight to/from USA>
TSA cleared JKIA for direct flight to/from USA
<Expansion of JKIA and Kisumu Airport>
The number of passengers handled at JKIA has met the target of 6.4 million in 2014
The volume of cargo handled at JKIA has slightly decreased to 260,000 tons in 2014
Construction of a new terminal building (Terminal 1A, formerly Terminal 4)
Construction of a three-story car park at the airport, increasing its capacity to a total of
1,500 cars and grade parking for 400 cars
The expansion of the aircraft parking (apron) and taxiways at JKIA, which increased the
apron space by 50 percent through the creation of 13 new stands for aircrafts, a fuel
hydrant system, and two new taxiways
Kisumu airport has been upgraded into an international airport, which increased the
passenger capacity to 500,000
<Civil Aviation sub sector Reform and Institutional Development>
The creation of an airport security oversight unit which is responsible for monitoring
security issues and ensuring compliance with security regulations
KCAA and KAA became financially autonomous and retain the revenues generated from
their operations
18
The improved security monitoring at key airports through transferring the responsibility
for passenger, baggage and mail security screening from the police to the KAA
The adoption of harmonized aviation safety and security regulations by each member of
the East African Community
The continuation of the KCAA restructuring through the separation of its oversight
functions from service provision activities
EASA has been accredited by the ICAO as a regional training center of excellence, as
one of 16 training centers in the world
PDO3. Promote Private Sector Participation in the Management, Financing, and
Maintenance of Road Assets - Rating: High
73. The third PDO has been clearly achieved through mainstreaming OPRC, and
obtaining legal endorsement on private sector participation in management, financing, and
maintenance of road assets as summarized in table 5.
Table 5. Summary of Achievement by PDO3
<OPRC awarding>
The implementation of performance-based contracts is apparent in the increased level of
private sector participation in the management and maintenance of road assets over the
course of the project and this approach is mainstreamed
KeNHA and KURA are managing 18 and 21 OPRC contracts, respectively21, with a total
amount of KSh 794 million (US$7.4 million) in FY15 and FY16
<Concession22>
One road segment of the Northern Corridor was offered for concession
The Parliament approved the concession contract in 2009
This activity was further developed into a pipeline project with a total estimated cost of
US$960 million, which was supported by several donors: IDA partial risk guarantee
(US$120 million), Multilateral Investments Guarantee Agency (US$120 million),
International Finance Corporation (US$115 million), African Development Bank
(US$100 million), and IDA (US$100 million)
<Legislation >
Kenya Roads Act 2007 encourages private sector participation in road construction,
maintenance, and management
The GoK established a Public-Private Partnership (PPP) Unit under the National Treasury
through the PPP Act of 2013
Toll road projects for Nairobi Southern Bypass and the Nairobi-Nakuru Highway are
some of the pipeline projects
PDO4. Restore Vital Infrastructure and Assets Damaged as a result of the 2007 post-
election crisis -Rating: High
74. PDO 4 was assessed attained successfully with the achievement of a PDO4 outcome
indicator and one of two intermediate indicators: In total, four public buildings became
functional against the target of three buildings.
21 According to the information obtained from KRB. 22 Due to the unfavorable results of due diligence from the Bank group, the GoK decided to terminate the process in 2011.
19
3.3 Efficiency Rating: Substantial
75. Efficiency of the project is assessed Substantial mainly due to the prolonged project
life and cost overruns in spite of the convincing results of the economic analysis for both
road and civil aviation components.
76. The ex-post economic analysis has been undertaken for the rehabilitation of key road
sections of the Northern Corridor (Component A), and the expansion of JKIA under the
original credit and the AF (Component F). The road works, with a total length of 419.3 km,
and the civil aviation related works account for about 72 percent, and 21 percent of the total
project cost, respectively. The details of the analysis can be found in annex 3.
Rehabilitation of the Northern Corridor
77. The main benefits of the rehabilitation of the Northern Corridor are the savings of
the road users in terms of vehicle operating costs, maintenance costs, and travel time costs.
The benefits were measured using the Highway Development and Management Model
(HDM 4), the same method that was used at the appraisal stage as well as at the AF. The
result indicates that the overall investments for road transport were economically viable for
all road sections with an economic internal rate of return (EIRR) ranging from 13.3 percent
in the Nyamasaia-Kisumu-Kisian section to 56.4 percent in the Machakos Turn off-JKIA
section, in spite of the cost overruns. The overall EIRR for the rehabilitation of the Northern
Corridor is 39.1 percent. The net present value (NPV) of the rehabilitation of the Northern
Corridor at 12 percent discount rate was US$550 million, which is about 26 percent higher
than that of the AF. The higher results than anticipated at appraisal and the AF in both EIRR
and NPV are mainly supported by significant traffic growth in all project road sections
between 2003 and 2014/15. The summary of economic analysis is presented in table 6.
Table 6. NPV and EIRR of the NCTIP
At Entry At AF At Ex-post
373km Road sections
under original
credit (223 km)
Road sections
under AF (158
km)
380 km
PV of Benefit (US$M) 235 n.a 265 809
PV of Base Cost (US$M) 110 n.a 199 259
NPV (US$M) 125 372 66 550
EIRR % 27 34 20 39
78. The Northern Corridor is the main transport corridor linking the land locked
countries of Uganda, Rwanda, and Burundi with Kenya’s maritime port of Mombasa, and
also serves the Eastern part of the Democratic Republic of Congo, South Sudan, and
Northern Tanzania. About 76 percent of urban dwellers, which is equivalent to 8.7 million
people in Kenya, are living within 15 km of the corridor. Project contribution to the regional
integration and trade enhancement is considered significant since the project rehabilitated
about 40 percent of the Corridor located within Kenya. The NCTIP reduced the average IRI
score of project roads to 2.2m/km at closure, which was ranging between 3.2 and 6.6 m/km
in 2003, which permits the saving of travel time and reduced vehicle operation cost.
20
79. Non-quantifiable benefits associated with the improvement of the Corridor include
the enhancement of, and better access to, socio-economic activities through the construction
of lorry parks, markets, schools, and improved road safety, especially for non-motorized
transport (NMT) with the construction of footpaths and foot-bridges. Furthermore, the
establishment and enhanced capacity of KeNHA and improved transparency in the civil
works industry through the enhanced capacity of KRB and the establishment of NCA and
EBK are also significant benefits obtained from the road subsector reform.
Civil Aviation Component
80. While the financial analysis has not been redone for the ICR, this result was
predicated on demand forecasts that predicted 5.5 million passengers (domestic,
international and transit) and 353,000 tons of air-freight by 2015, and annual growth rate of
4.7 percent. Actual data received from KAA reveals that total passenger numbers through
JKIA reached 6.4 million in 2014, with an annual growth rate of 6.4 percent, and cargo
260,000 tons of air freight.
81. The actual growth in passenger numbers exceeded the demand forecasts in the high
scenario, despite the impact of the global economic slowdown, and the fire at JKIA. The
drop in air freight is at least partially down to the introduction of stricter regulations in the
European Union on the importation of fresh products with excess level of pesticide
(Dimethoate)23 since the European market accounts for up to 80 percent of Kenya’s fruit and
vegetable sales and 42 percent of flower exports.
82. While actual financial costs (US$270 million) exceeded estimated costs markedly,
the growth in passenger traffic, the increase in the Airport Passenger Service Charge, a levy
charged on each passenger to pay for the improvements, from US$20 to US$40, would be
expected to more than ensure the investment was financially viable.
83. Flexibility in the project implementation such as the restructuring and AF to respond
to the changed priorities of the GoK, and cost increase, and obtaining financing from other
donors to cover up the financing gap, minimized these negative impacts. Nonetheless,
negative impact of cost and time overruns on efficiency is considered significant.
3.4 Justification of Overall Outcome Rating Rating: Satisfactory
84. Since relevance is assessed High, efficacy and efficiency are rated Substantial, overall outcome rating of the NCTIP is Satisfactory. 3.5 Overarching Themes, Other outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
85. The roadworks under the project included socioeconomic enhancement elements.
The positive way in which the NCTIP altered the lives of ordinary Kenyans is encapsulated
in a documentary video (https://vimeo.com/116895967). Construction of roadside
amenities, such as lorry parks, a community center, and community market created a better
environment for truck drivers to rest and local residents to sell local products. Construction
23 Business Daily (2013) Chemical ban hits vegetable exports to the EU market, May 2013
21
of five schools has provided better educational facilities for 2,620 students. Footpaths
constructed in the urban centers of Kisumu and Nakuru, with a total length of 24.8 km also
provide better safety for pedestrians and cyclists, including children and women. The
HIV/AIDS mitigation activity under the project resulted in 100 percent level of awareness
and availability of VCT centers for the surveyed sample.
(b) Institutional Change/Strengthening
86. The project supported the transport sector reform and made remarkable contributions
to institutional strengthening as summarized in annex 2d. Particularly, the NCTIP’s support
on the enactment of the Kenya Roads Act 2007, establishment of three road authorities,
financial autonomy of the KAA and KCAA are the most outstanding ones.
87. Under the NCTIP, a total of 380 staff attended oversea and/or domestic training
programs between 2005 and 2015. In addition, 21 staff from PTT including technical,
financial and procurement staff participated in disbursement and procurement clinics
organized annually by the Bank and enhanced their knowledge on fiduciary issues.
(c) Other Unintended Outcomes and Impacts
88. No other unintended outcomes and impacts are observed.
4 Assessment of Risk to Development Outcome
Rating: Low
89. Risks to maintain the development outcomes are assessed Low as described below:
90. Road Maintenance. At appraisal, the Road Maintenance Fuel Levy Fund, which was
established in 1994, could generate about US$100 million annually. This amount was just
enough to cover the core network of strategic roads, which were in maintainable condition.
With the increase of the number of vehicles and cost of fuel levy from KSh 9/l to KSh 12/l,
it is expected that the fund generate about US$400 million in 2015/16.24 Steady traffic
growth will support the increase of revenue in the fund. While some of the roads
rehabilitated are already under the OPRC, the NCTTCA keeps monitoring and reporting the
condition of the roads of the whole corridor with their own performance indicators.
Therefore, the maintenance risk of the Northern Corridor is low.
91. Decentralization. Kenya is experiencing a devolution process under the 2010
Constitution, which provided for not only a major devolution of resources and functions, but
also creating a whole new layer of county governments. Due to the devolution, the roles and
responsibilities amongst national government and county governments are still under
discussion. A draft bill has been prepared and submitted to the Parliament to propose
merging KURA and KeRRA.
92. Institutional Strengthening and Sustainability. The NCTIP supported the
establishment of KeNHA, KURA, KeRRA, NCA, NTSA, and EBK, and the institutional
enhancement of MoTI, KAA, KCAA, and KRB. Their implementation capacities have been
24 Estimation calculated by KRB.
22
increased through a technical assistance program but continuous supports for further
institutional strengthening and sustainability are necessary. For example, the KCAA has not
reached a final agreement of institutional arrangement and is still facing a challenge of
retaining an adequate number of flight inspection officers at the internationally required
level. KeNHA, in coordination with the KRB, needs to develop and apply construction cost
index for road works to prepare more accurate cost estimations. The on-going KTSSP and
NUTRIP have activities to support these institutions but it is necessary to monitor any other
needs for their sustainability.
5 Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry Rating: Moderately Satisfactory
93. As noted in section 2.1, the project was designed in a client-oriented manner,
responding to the government’s priorities and aligned with the support areas identified under
the CAS (2004-07), after 10 years break in Bank financing in the transport. The project was
designed based on extensive discussions with both the GoK and development partners, being
part of the sector reform task force. The Bank ensured the setting up of an “all-inclusive”
PTT, and inclusion of adequate and secured domestic funding in the project financed
infrastructure maintenance. While the Bank policies, such as environmental and social
safeguards, were well respected, special attention was paid to road safety, which the Bank
was addressing as a key priority before the establishment of the Global Road Safety Facility
in 2006. In addition, efforts made for enacting the Road Act, establishing KeNHA, bringing
local academia on board for sustainable M&E system, are remarkable. To demonstrate the
GoK’s trust in the Bank, the project was launched by a well-organized workshop with
attendance by top managers of the transport sector.
94. In spite of numerous positive aspects observed in the Bank’s performance at entry,
the following shortcomings are observed: The PDOs were clear but the result chain from
outputs to intermediate outcomes and to final outcomes has not been well developed for
some components as noted in section 2.3. The significant cost overruns of road works were
mainly due to the factors beyond project control, but were also attributed partially to too
conservative cost estimates at entry. Thus, overall Bank performance at entry is rated
Moderately Satisfactory.
(b) Quality of Supervision
Rating: Moderately Satisfactory
95. The Bank team worked closely with the IAs and the GoK by providing technical
support. The Bank supervision team put appropriate fiduciary measures and safeguards in
place. Most of the team members were located in Nairobi, which allowed the team to provide
daily communication and support for the GoK. It was noted during the ICR mission that the
client respected the Bank and the relationship between the project management team and
IAs was solid, which enabled both sides to manage and conclude this complex project
successfully. Furthermore, the fact that anti-corruption measures introduced by the Bank
after the approval of project were mostly adopted and implemented successfully by the GoK
demonstrates strong commitment of the GoK to the Bank project. The Borrower’s ICR noted
23
that physical availability of the task team leader (TTL) at the country office made
consultation easier, which the GoK considers one of the reasons for the successful
implementation of the project.
96. The Bank was responsive and took necessary actions for emerging issues and
changing needs. While the AF and restructuring were undertaken to achieve the original
project target, adjustment of the financing arrangement was accepted to respond to
prolonged counterpart funding issues. These actions helped the project be concluded with
the completion of most activities, attaining the primary project objectives. The Bank’s
leadership among development partners in the transport sector was also noteworthy,
bringing other financiers on board, such as the NDF, EIB, and AFD to fill the financial gaps
and increase the coordination. Regular joint missions and joint ‘no objections’ organized
and issued with the AFD are noted as good examples of efficient coordinated supervision.
97. Nonetheless, the M&E implementation was rated Moderately Satisfactory. The Bank
should have been more proactive to improve the situation and ensure the quality of outputs,
understanding that this was the first attempt to utilize the university as an M&E consultant
in a large-scale investment project. Implementation of the RSGIAP was mostly carried out
but key monitoring indictors were not fully reported. As stated in section 2.3, inconsistency
in the monitoring of agreed indicators was also observed in ISRs and Aide Memoires.
98. Regardless of shortcomings in project design and the M&E, overall supervision,
which managed this complex and large-scale project to conclude successfully as discussed
in section 3.2, is rated Moderately Satisfactory on balance.
(c) Justification of Rating for Overall Bank Performance
99. As described above, overall Bank performance is rated Moderately Satisfactory.
5.2 Borrower Performance
(a) Government Performance
Rating: Moderately Satisfactory
100. The GoK was committed to the transport sector reform and supportive to the project
throughout the project life, including the AF and restructuring, and executed more than what
was envisaged at appraisal. To manage this complex project, the POC was established.
Regular quarterly joint meeting with the IAs and the appointment of a project coordinator
were key factors for successful project implementation. The GoK’s commitment to the
transport sector reform is demonstrated in the number of acts enacted, policies adopted, and
authorities newly established or reformed with the direct and indirect support from the
NCTIP. Despite the fact that the introduction of RSGIAP and other anti-corruption measures
were additional heavy tasks assigned to the GoK after the project approval, the GoK
implemented most of actions satisfactorily, resulting in increased and long term
transparency and accountability in the road sub-sector. All authorities established are
functional though some are still facing challenges in securing resources. Specifically,
establishment of KeNHA, making KAA and KCAA financially autonomous and the
institutional enhancement of these three IAs are notable.
24
101. Nonetheless, inadequate counterpart funding was a serious issue that adversely
affected the implementation of the project and increased the total project cost. Through a
number of discussions, the National Treasury issued guidelines on budgets of donor-funded
projects in September 2015, and the disbursement of funds and payments to contactors
resumed in December 2015. Although the NCTIP has already been closed, this action will
be a significant contribution to other ongoing and future projects to avoid unnecessary delays
and accrual of interest. The limited capacity of staffing and frequent transfer of accountants
at the line ministry also affected the efficiency of project operation.
(b) Implementing Agency or Agencies Performance
Rating: Moderately Satisfactory
102. PTT was set up in each IA and joint coordination meetings were organized regularly
to monitor the project progress. The MoTC, KAA, and KCAA did not have previous
experience in implementing Bank financed projects but they have learned the Bank
procedures during project implementation with support from the fiduciary team of the Bank.
For most part, compliance with environmental and social safeguards, as well as procurement
was largely satisfactory throughout project implementation. The immediate response of
KAA to the restoration of operations at JKIA in August 2013 after a major fire that destroyed
part of the airport, successful execution of 419.3 km of road rehabilitation and construction
at closure by the newly established KeNHA, and KCAA’s fulfillment of security
requirement for CAT1 are significant samples of demonstrating the positive results of
institutional enhancement and reform under the NCTIP. Coordination and communication
among the IAs were smooth, and each subsector had a better idea on the benefit of having
an integrated transport approach through the implementation of the NCTIP.
103. The change of the project leader of the PTT (road sub sector) without informing the
Bank was noted but the Legal Agreement was reconfirmed without such an issue recurring.
The road subsector encountered challenges such as cost overruns, poor performance of
contractors, and so on, which were partly the reason for the AF, restructuring, and extension
of the project closing date. The IAs’ coordination with the M&E consultant was not clear
though the IAs has monitored the progress and collected data of quality independently.
104. Completion of most activities of the NCTIP at closure, establishing new authorities,
experiencing organizational reforms, and coping with post-election violence, rate the
performance of IAs as Moderately Satisfactory
(c) Justification of Rating for Overall Borrower Performance
105. As detailed above, overall Borrower Performance is rated Moderately Satisfactory.
6 Lessons Learned
106. The approach of an integrated transport project with good partnership with
the government and a well-developed Results Framework can bring constructive
results. The GoK mentioned the following positive impacts of NCTIP: improved integration
of the transport system, enhanced coordination and inclusiveness of transport sub-sectors.
The National Treasury also strongly supports the integrated transport approach to boost
25
economic development.
107. Strong ownership of sector reform and institutional development enables
successful implementation of a complex project. The NCTIP was implemented in a period
that has seen three different government administrations but the GoK demonstrated a strong
commitment to the project and made considerable progress in sector reform and institutional
development, such as policy development and enactment of Road Act, establishment of road
authorities and a maritime authority, enhancement of road sector agencies, restructuring of
civil aviation authorities, and implementation of governance action plans.
108. A TTL assigned in the country office supports smooth implementation of
complex project and enhances coordination with the government counterparts. The
NCTIP was led by TTLs assigned in the country office, which allowed TTLs to deepen their
understanding of the transport sector in the country and enabled counterparts to
communicate and consult with the Bank team on a daily basis.
109. Close inter-agency coordination with a project coordinator concedes smooth
implementation of complicated project. The NCTIP was composed of multiple subsectors
of transport, but all implementation agencies commented that project coordination was
smooth. Quarterly inter-government project meetings and the project coordinator were
identified as the key factors of smooth coordination of this complex project.
110. A sound analysis to determine a realistic project duration is essential when the
project supports sector reform and institutional development. The NCTIP supported
large-scale infrastructure development but significant weight was also given to the transport
sector reform. To develop the sector reform to a sustainable level, the project needed
extensions through the AF and restructuring.
111. Securing the budget for the donor-funded projects by the National Treasury
helps smooth implementation. Inadequate counterpart funding was a serious challenge of
the NCTIP. With the issuance of a guidance note on donor-funded projects from the National
Treasury in September 2015, disbursement of funds and payments to contactors resumed in
December 2015. Therefore, for on-going and future projects, it is important for the GoK to
ensure the enforcement of the guidance note and for the Bank to monitor closely through
maintaining coordination with the National Treasury.
112. Sector-wide support by INT can bring long term transparency and
accountability in Transport sector. The NCTIP received numerous supports from INT and
implemented various activities to increase transparency and accountability in the road sub-
sector. As a result, annual/5-year road investment plans are disclosed to the public,
construction companies are registered, corruption-reporting system becomes available, all
road works under the Road Authorities are procured under open tender, and the number of
qualified bids has been increased with competitive offer, some of which are below the
engineers’ estimates.
26
7 Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/Implementing Agencies
113. The GoK has prepared the Borrower’s ICR and provided comments on the draft ICR,
both of which are found in annex 7.
(b) Co-Financiers - Not Applicable
(c) Other Partners and Stakeholders
114. The draft report was shared with the parallel financiers, NDF and AFD for their
comments. The NDF and AFD thanked the Bank for sharing the draft report and informed
that they had neither specific questions nor comments on the report. The AFD also expressed
their gratitude to the Bank’s project team for the quality of collaboration in the
implementation of Component F.
27
Annex 1. Project Costs and Financing
(a) Project Cost by Component (in USD million equivalent)
Note: *Project operating costs for Component A, B, C, D and E are available in an aggregated manner only.
** No AF from IDA. The cost includes parallel finance and GoK’s own contributions
*** Actual estimates for Component B and D are included under Component A.
(b) Financing
Note: *under appraisal,
**Others includes Kenya Local Bank and other financiers
Appraisal
Estimate
(US$
millions)
Additional
Finance
Estimate
(US$
millions)
Actual/
Latest
Estimate
(US$
millions)
Latest %
of
Appraisal
Latest %
of
Revised
Estimate Components
A. Rehabilitation of the Northern
Road Corridor 190.46 546.86 750.78 394 137
B. Socio-Economic Enhancement,
Roadside Amenities and HIV/AIDS
Mitigation.
4.35 3.78 0*** 0 0
C. Private Sector Participation in
Road Management and
Maintenance.
10.66 16.54 2.60 24 16
D. Road Safety Improvement 4.96 4.97 0*** 0 0
E. Institutional Strengthening in the
Roads Sector and Technical
Assistance
10.36 35.88 32.43 313 90
Project operating costs(MoTI)* 1.1 1.1 - - -
F. Support to the KAA 41.91 297.90** 246.27 588 121
G. Support to the KCAA 10.21 10.31 9.26 91 90
H. Support to the MoTI 2.48 2.49 2.36 95 95
Total Project Cost 276.49 919.83 1043.71 377 113
Source of
Funds
Type of
Funding
Appraisal
Estimate
(US$
millions)
Revised
Estimate
at the
AF (US$
millions)
Revised
Estimate at
Restructuring
(US$ million)
Actual/
Latest
Estimate
(US$
millions)
Latest %
of
Appraisal
Latest
% of
Revised
Estimate
Borrower Counterpart
Funding 54.26 340.64 225.00 430.76 794 191
IDA Credit 207.00 460.00 460.00 491.35 237 107
NDF Loan 15.23 19.19 19.00 28.93 190 152
EIB Loan 0.00 70.00* 93.00 0.00 n.a. 0
Others** Loan 0.00 30.00 30.00 0.00 n.a. 0
AFD Loan 0.00 0.00 93.00 92.67 n.a. 100
Total 276.49 919.83 920.00 1043.71 377 113
28
Annex 2. Outputs by Component
Annex 2a. Outputs of Project Components
Table 2.1. Summary of outputs by component
Component Description Outputs Achieved
Original Additional Financing Original Additional Financing
A. Rehabilitation of the Northern Corridor.
Rehabilitation of
infrastructure and provision of
services for the improvement
of approximately 373 km of
roads in selected sections
along the Northern Corridor,
including construction of
approximately 8 km of roads
connecting the old Embakasi
Airport terminal to Nairobi-
Mombasa highway.
Rehabilitation of infrastructure
and provision of services for the
improvement of approximately
383 km of roads in selected
sections along the Northern
Corridor.
The following road sections (total 419.3 km (including 41.4 km dual carriage)) have
been completed and handed over to the GoK: (a) Maji ya Chumvi - Miritini (35 km, (5
km of which is dual carriageway)); (b) Sultan Hamud-Machakos Turnoff (55 km); (c)
Machakos Turn off-JKIA (33 km (12 km of which dual carriageway)); (d) Lanet-Njoro
Turnoff (dual carriageway 16 km); (e) Njoro Turnoff-Timboroa (84 km); (f) Mau
Summit-Kericho (57 km); (g) Kericho-Nyamasaria (76 km); and (h) Nyamasaria-
Kisumu Airport-Kisian section (total 21.9 km (8.4 km of which dual carriage)).
Rehabilitation and repair of roads,
bridges, buildings, and other
public infrastructure damaged or
destroyed by floods or the events
of the December 2007 post-
election crisis.
The main buildings works at Oyugis office and two Homa Bay offices
are completed and in use while KeNHA regional office (new office
building) in Kisumu is also completed. Rehabilitation of KeNHA
regional office in Kisumu is completed and in use. Road and bridges at
Kisian-Busia road sections were also rehabilitated with the GoK fund.
Replacement of public equipment
and vehicles destroyed during the
December 2007 post-election
crisis.
Completed.
Implementation of the mitigation measures specified in the EIA and
provision of support to PAPs including provision of support for
resettlement activities and compensation.
For the most part, compliance with both environmental and social safeguards was
largely satisfactorily throughout the project implementation. KeNHA has not yet
prepared a RAP Completion Report.
29
B. Socio-Economic Enhancement, Roadside Amenities and HIV/AIDS Mitigation.
Construction of facilities to enhance the socio-economic impact on
local communities and improve safety of road users, including bus
and truck stops, parking areas, utilities, merchandise booths for use
by local communities, bicycle paths, and pedestrian sidewalks.
(a) Roadside Amenities: A lorry park at Sultan Hamud-Machakos Junction, a market at
Taru, a community center at Chepseon, and five schools in Taru, Mlolongo, and
Kisumu airport have been constructed under the project. Footpaths as Non-Motorized
Transport (NMT) Facilities have been constructed in the road sections in the urban
centers of Kisumu and Nakuru. (Total length of footpaths is 24.8 km). A lorry park at
Nyamasaria and a market at Awasi are currently under construction and expected to be
completed by the end of May 2016.
Development and implementation of measures to mitigate effects
of HIV/AIDS, including awareness and information dissemination,
distribution of condoms, strengthening of local health centers,
facilitation of voluntary testing and counseling including
construction of kiosks for these purposes, and provision of support
to infected and affected people.
(b) HIV/AIDS mitigation: Implementation of this activity involves two dimensions: (i)
measures aimed at project workers for whom the contracts provide such items as
condoms, educational pamphlet and awareness raising through experts to help
disseminate information; and (ii) a second tier intervention including truck drivers and
other stakeholders operating along the Northern Corridor. Implementation of first
dimension has proceeded well, all work contractors under the project received support
from a local non-governmental organization (NGO) which is registered and recognized
by the National Aids Control Council to conduct awareness, education and information
on HIV/AIDS targeting the workers, truck drivers and local community members
including setting up of VCT centers.
C. Private Sector Participation in Road Management and Maintenance.
Provision of technical advisory services for the preparation of bid
documents for and facilitation of the concessioning of selected road
sections of the Northern Corridor; and performance-based
maintenance of approximately 300 km of selected roads by the
private sector.
Both activities under Component C were cancelled without completion. However,
positive impacts of the project on the involvement of private sectors in road management and maintenance are observed.
(a) (Completed) One segment of the Northern Corridor was offered for concession to
the private sector (target achieved), but financial closure was not concluded and as a
result, the process was terminated. There is no toll road in Kenya yet. The concept of
concession of road segments to the private sector was also new in Kenya. It was
concluded that the regulatory framework to embrace the involvement of private sector
in the management, financing, operation and maintenance of road assets would be
necessary. PPP Act was enacted in 2013 and the PPP unit was established under
section 8 of the act as the special purpose unit within the NT.
30
(b) The process was cancelled due to the receipt of nonresponsive bids. The concept of
performance-based contract was new to Kenya when the bids were invited and it was
not well understood by potential bidders. Although the process under the project was
cancelled, KeNHA worked with assistance under the project and carried out sensitization
on long-term performance based road maintenance contracting, through a workshop for
consultants and contractors. The concept has been accepted in Kenya and maintenance
of any new road constructed will be under the performance-based contract. Currently
there are 39 long-term performance based contracts awarded and under
implementation.
D. Road Safety Improvement.
Improvement of safety conditions in selected locations along the
Northern Corridor, including carrying out of a road safety and
awareness campaign, construction of approximately 5 children’s
traffic safety parks, rehabilitation of about 5 existing children’s
traffic safety parks, and improvement of safety conditions of
hazardous locations.
National Road Safety Program (NRSP) was developed and adopted by the GoK during
the first phase of project. With the establishment of the NTSA in 2012, the
implementation of the NRSP has been undertaken by the NTSA. The procurement of
information and communications technologies (ICT) equipment for institutional
capacity building has been completed. NTSA has carried out countrywide road safety
education, public awareness campaign. But the authority is facing financial and human
resource challenges to conduct road audit. The NTSA is currently collecting road
accident data for entire country from the police and reporting it on their website daily.
The NTSA also analyzes and summarizes the road safety statistics annually.
Safety Park. With the establishment of KURA, this activity was transferred to KURA.
The authority has continued to manage the parks and currently there are six (6) parks
in operation in: Nairobi, Nyeri, Embu, Kisumu, Kisii and Kakamega. The authority is
currently rehabilitating Kisii Children’s Traffic Park. An additional park is also
being established in Nairobi at the junction of Outer Ring Road/Kangundo Road
under the ongoing Outer Ring Road expansion project financed by the government and
AfDB.
The number of fatalities related to road accidents in 2015 was 3,057. The target of the
project was to reduce the total number of fatalities by10% between 2004 and 2015.
Although this target has not been achieved, fatalities per 100,000 have reduced from
8.31in 2008 to 6.4in 2015.
31
E. Institutional Strengthening in the Roads Sector and Technical Assistance.
Establishment and
strengthening of KeNHA
through provision of technical
advisory services.
Road Authorities. The Kenya Roads Act was enacted in 2007 and enabled the
creation of three road authorities: KeNHA, KURA, and KeRRA in 2008. Equipment
purchase, vehicle acquisition, and consultant service for the construction supervision,
and feasibility studies were provided. With this reform in the road sector, the ministry
can focus on policy formulation and oversight and road authorities can focus on the
implementation of programs and projects. KeNHA is currently composed of 6
departments, 10 regional offices, and 487 staff according to the annual report of
2014/15. KeNHA prepares an annual work program and submits it to the KRB, which
in turn prepares and publishes Annual Public Road Programme (APRPs) that
consolidate the annual work program of the three road agencies.
Strengthening the KRB
including reforming its
mandate through carrying out
of studies and reviews and
provision of technical
advisory services and
training.
Strengthening the capacity of the
KRB and reforming its mandate
through carrying out of studies
and reviews, and provision of
technical advisory services and
training.
KRB: All four studies have been completed. (a) Road User Charges Study, (b) Road
Inventory/Road Reclassification Study, covering 160,886 km of roads, (c) Road
Sector Investment Program (RSIP), and (d) Transport Sector Indictor Framework
Study. Road classification has been published in the national gazette in January 2016.
The RSIP is under implementation with a 5-year detailed program. Second phase of
the 5-year program (2015–19) is under preparation. In addition to RSIP, APRPs are
also disclosed on their website.
Designing Kibwezi-Kitui-
Mwingi-Maua-Isiolo road
corridor.
Conducting feasibility studies and
designing of the (a) Kibwezi-
Kitui-Mwingi- Maua-Isiolo road
corridor; (b) the alternative route
linking northern Tanzania to
Narok in the territory of the
Recipient; (c) the Sudan link road;
(d) the access road to the Moi
international airport, Mombasa;
and (e) the Mombasa By pass.
Feasibility Studies: All the feasibility and detailed engineering design studies on
selected road sections have been completed. (a) three sections along the Kenya-
South Sudan Road, which will now be reconstructed with financing under the Bank-
financed EATTEDP, (b) Kibwezi-Kitui-Mwingi-Maua-Isiolo, (c) Narok-Nothern
Lakeside Tanzania, and (d) Mombasa Southern Bypass, which is now funded by JICA
for construction.
Designing an alternative route
linking northern Tanzania to
Narok in the territory of the
Borrower, and designing the
widening of the access road to
the Moi International Airport
in Mombasa.
Carrying out of feasibility and
sector studies for the transport
sector including the Mombasa
Bypass study.
32
Preparation of a ten-year
national transportation
development plan.
Preparing a ten-year national
transportation development plan.
The development of a 50 year transport master plan including a 10 year investment plan is delayed due to poor performance by the consultant. MoTI hired a team of
experts to review the draft plan prepared by the consultant but the result was not
positive. The GoK is currently internally discussing the way forward.
Carrying out several transport
sector studies including an urban
transport study for Nairobi.
IDA funds were reallocated and the activity is financed under
NUTRIP.
Strengthening the Department
of Materials Research and
Development at MORPWH
and External Resources
Department of the Ministry of
Finance.
Strengthening and building the
capacity of the Roads Department,
Materials Research and
Development Department,
KeNHA, KeRRA, KURA, KRB,
Mechanical and Transport
Department, Kenya Institute of
Highways and Building
Technology, Engineers
Registration Board (ERB) and
associated institutions; the
External Resources Department
State Law Office, Department of
Government Investments and
Public Enterprises, and the
Institution of Engineers of Kenya
through provision of equipment,
training and technical advisory
services.
Training. Acquiring critical equipment for these departments and organizations has
been completed.
EBK: The reform of the ERB was effected through: (a) the repeal of the Engineers
Registration Act (1969) and the enactment of the Engineers Act 2011. The EBK was
created through the newly enacted act in 2011 to widen the mandate of the EBK to
oversee and regulate the standards in the engineering profession and building capacity
for individual engineers and engineering firms. Currently there are 32 accredited
programs in 6 universities in Kenya. The biggest challenge for the EBK is the
availability of funds to sustain the organization.
Capacity building for
MORPWH, NHA, the
External Resources
Department of the Ministry of
Finance and KRB in
management and financing of
roads including axle load
monitoring and control.
Monitoring, evaluation, and
impact assessment of the
Project.
Monitoring, evaluating and
conducting of impact assessment
of the Project including reviewing
of ongoing and recently completed
contracts for compliance with the
relevant contractual requirements.
The consulting division of the University of Nairobi Enterprises and Services (UNES)
was awarded the task of Monitoring and Evaluation for the project. However,
submission of reports were delayed and the final draft report initially covered the
period up to 2013 only and M&E results for 2014 and 2015 were missing. In addition,
several indicators adopted under the Results Framework of the project are not included
in the report yet. The revised final version was submitted on March 30, 2016. Although
the approach to support the enhancement of research capacity of local academia
was innovative, it was observed that there was confusion for the UNES in
33
understanding their role as a consultant as well as specific tasks assigned for this
M&E.
Establishing and building the
capacity of the National
Construction Authority (NCA).
The NCA was established in 2011 through the enactment of the NCA
Act 2011 to regulate, streamline, and build capacity in the construction
industry. The act has outlined 14 functions for the NCA and it is
already executing all the functions, focusing on contractor registration,
contractor training, and quality assurance with a total of 78 staff. The
revenue of the NCA comprises: (a) a budget from the GoK, (b)
registration fee, (c) annual renewal fee, (d) levy of civil works
contracts, and (e) training fee. For the period 2015–20, NCA’s planned
budget is KSh 27 billion and it is estimated that KSh 16–17 billion is
secured from the national budget. The NCA is currently preparing the
financial report for 2014/15 and annual report 2014/15 is expected to
be published in April 2016.
Establishing a system in KeNHA
for responding to and managing
disasters requiring emergency
road works and other related
materials.
After the discussions, the Road Disaster Management and Response
Unit has been established under MoTI (Road Department), not
KeNHA, and functions as a committee comprising representatives
from road authorities when a disaster occurs. It works with the
National Disaster Operational Center and is a member of the task
force. The unit procures materials and equipment for disaster response.
Although the unit was established, no budget has been allocated yet
and the term contract was not advertised.
F. Support to the Kenya Airports Authority.
Provision of support to KAA to improve aviation security, safety,
and operations at major airports through acquisition of equipment
and vehicles; carrying out of civil works; provision of technical
advisory service, and training, including:
Rehabilitation and
reconfiguration of old
Embakasi Airport terminal
and the main terminal at Jomo
Kenyatta International Airport
(JKIA) and construction of
the road linking the two
terminals.
Expansion of the JKIA through its
reconfiguration and construction
of a new unit.
Apron extension taxiways Unit 4 terminal building and car park of JKIA have been
completed. The EIB cancelled the finance for the design and remodeling of Terminals
1-B, C, and D because of delay of the process. There was delay in the process and also
because of the fire at the arrival hall of JKIA in 2013, the entire airport layout had to
be reviewed. The government will finance this activity and possibly with the support
from development partners.
34
Installation of fencing,
lighting, and surveillance
systems at JKIA, Moi
International Airport, Wilson
Airport, Kisumu Airport,
Malindi Airport, and Ukunda
Airport.
Installation of fencing, lighting,
and surveillance systems at JKIA,
Moi international airport, Wilson
airport, and Kisumu airport.
Significant security improvement at JKIA was achieved by completing the security
fence, enhancement of screening by use of X-ray screening machines and separation of
arriving and departing passengers. As a result, the ICAO security audit of October
2015, scored Kenya, KCAA and KAA 88 percent rate, against a cut off of 80% for
CAT1 certification.
For Kisumu and Moi Airports, the project supported the purchase of materials for
fencing.
Rehabilitation of and
reconfiguration of terminal
buildings at Kisumu and
Wilson Airports, and
rehabilitation and extension of
the runway at Kisumu
Airport.
Rehabilitation and reconfiguration
of terminal buildings at Kisumu
and Wilson airports, and
rehabilitation and extension of the
runway at Kisumu airport.
A new terminal building was constructed instead of rehabilitation of the old building.
The runway rehabilitated and extended, and an access road and parking area at Kisumu
Airport constructed. Renovation and upgrading of security at Wilson Airport:
feasibility study was completed but the KAA faced challenges as part of the airport
land was acquired for private development thereby constraining the expansion and
location of a new terminal building. In addition, due to the increased demand of
facility improvement in other national airports, priority of the KAA has changed. As
the result, the GoK requested for reallocation of IDA funds for this activity toward the
expansion of JKIA, which was done under restructuring of the project.
Enhancing aviation security
and safety, flight information
system, search and rescue
capacity, communications,
and emergency operations
centers at JKIA, Moi
International Airport, Wilson
Airport, and Kisumu Airport.
Enhancing aviation security and
safety, flight information system,
search and rescue capacity,
communications, and emergency
operations centers at JKIA, Moi
international airport, Wilson
airport, and Kisumu airport.
Transport Safety Authority of the United States cleared direct flights to/from U.S.
airports to JKIA in 2009, though an official certificate has not been issued. Delta
Airlines was supposed to have the maiden flight and the Minister of Transport of
Kenya was invited to join the first flight in 2009. However, because of the emerging
security concerns and terrorist threats in the region attributed to Somali-based Al
Shabaab direct flights were put in abeyance. The funds allocated for the following
activities were reallocated to the JKIA expansion: (a) security perimeter lighting and
detection at four airports, (b) security and communication equipment and vehicles at
four airports, and (c) support emergency operation centers.
Capacity building for staff in
airports operations security
and management.
Capacity building for staff in
airports operations, security, and
management.
A total of 171 staff attended the overseas and/or domestic training program between
2007 and 2015.
G. Support to the Kenya Civil Aviation Authority (KCAA).
Development and implementation of reforms at KCAA aimed at
enhancing aviation safety and security oversight, and safety
inspection through provision of technical advisory services and
training.
The KCAA engaged with a human resource consultant to conduct a study on the
institutional reforms to be implemented. The revenues of the KCAA have been tripled
between 2004 and 2015, which allows the KCAA to recruit more inspectors. Number
of airworthiness inspectors and flight operations inspectors increased from 3 to 18 and
1 to 16, respectively. It is expected that the KCAA can obtain the IASA CAT1 in the next audit in 2016.
35
Provision of support to
KCAA and EASA through
acquisition of training and
operations equipment
including equipment for
accident investigation
laboratory.
Provision of support to KCAA
and EASA through acquisition of
training and operations equipment.
Air traffic control training school of aviation simulator, laboratory equipment for
telecommunications engineering, test and measurement equipment, two generators, air
conditioners, search and rescue equipment, and library books were purchased. A
Trainer Plus Program was implemented. The EASA enhanced its capacity and is now
accredited by the ICAO as a regional training center of excellence. Such centers exist
only in South Africa and Kenya, in Africa, and in 14 other locations in the rest of the
world.
Implementation of GNSS-
GPS enroute and approach
procedures through provision
of technical advisory services.
Provision of technical advisory
services to use the global
navigation satellite system and
global positioning system to repair
approach navigation charts for
selected airports.
Implementation of GNSS procedures was completed for six airports (Kisumu, Malindi,
Lokichoggio, Lamu, Nanyuki, and Ol Kiombo Airports) and ICT systems were
installed and in use, improving approach and departure procedures allowing aircrafts to
fly more directly which saves fuel costs at these airports and enhances safety in the
airspace.
Carrying out of training of trainers in airworthiness inspection,
flight operations inspection, personnel licensing and security
oversight.
This was completed as follows (a) flight inspection staff were provided for 3 years to
fill the shortfall at KCAA; (b) safety regulations, technical guidance materials, on-the-
job training program and manuals for inspections and audits were developed and in
use; (c) inspector’s guidance materials were prepared and in use; (d) a database has
been established containing information on registration of aviation personnel, aircraft,
Aircraft Maintenance Organization (AMO) and air operators; (e) a strategic plan for
East Africa School of Aviation (EASA) was prepared and is under implementation; (f)
on-the-job training was conducted using the developed materials; and (g) a human
resources and financial restructuring study was carried out, which formed the basis for
the proposed restructuring of the KCAA
H. Support to the Ministry of Transport and Infrastructure (MoTI).
Capacity building for MoTC
in procurement, Project
management, financial
management; implementation
of the national transportation
policy and maritime law; and
compliance with conventions
of the International Maritime Organization; establishment
Building the capacity of MoTI in
procurement, project management,
financial management;
implementation of the national
transportation policy and maritime
law; and compliance with
conventions of the International
Maritime Organization.
The procurement of computers and other ICT equipment and installation has been
completed. This activity included the support of digitization of human resource records
in the ministry. The Traffic Act has been reviewed to ensure that it conforms to
international transport conventions including the Northern Corridor Transit
Agreement. The implementation of the National Transport Policy has enhanced road
safety, improved compliance with international road safety levels, and improved
efficiency and smooth operations in the Public Service Vehicle industry due to
behavioral change of the players. The training curriculum for driving schools has been developed and approval from the Minister of Transport and Infrastructure is awaited.
36
and strengthening of the
Maritime Authority; assisting
the GoK to comply with the
Northern Corridor Transit
Agreement; and provision of
support to Bandari College,
through provision of technical
advisory services and
training, and acquisition of
equipment.
Strengthening the capacity of the
Kenya Maritime Authority
through provision of technical
advisory services, training, and
acquisition of equipment.
The project supported the establishment of a new maritime administration, the Kenya
Maritime Authority (KMA), which was set up in June 2004 as the semi-autonomous
agency in charge of regulatory oversight of the Kenyan maritime industry.
Procurement and installation of a local area network and computers at the KMA
headquarters has been completed.
Assisting the GoK to comply with
the Northern Corridor Transit
Agreement through training and
technical advisory services.
Kenya is one of the compliant member states on the NCTTA provisions.
Provision of support to Bandari
College, through provision of
technical advisory services,
training, and acquisition of
equipment.
Procurement of navigation bridge simulator software and ICT equipment and cabling
of the training room for Bandari College has been completed. Bandari College is now
one of the four accredited institutions for maritime education and training in Kenya.
Kenya is already listed among the white list countries based on proper implementation
of the International Convention on Standards of Training, Certification, and Watch
keeping for Seafarers of 1995.
37
Annex 2b. Outputs of Project Components
Table 2.2. Achievement by outcome and intermediate indicators
PDO Outcome Indicators
Original AF/ Restructuring Original AF Restructuring Targets
Actual
Values
Percent
Achieved
1. Increase the efficiency of road transport Travel time by road from Mombasa to Malaba and
Busia reduced by 25 percent
25% 15% 61%
2. Enhance aviation safety and security to meet
international standards
(a) KCAA is cleared as category 1 safety status under
the IASA of the US FAA
(b) JKIA in Nairobi is cleared by the US TSA for direct
flights to/from United States airports
CAT 1
clearance
obtained
Direct
flight
cleared
Not obtained
but met the
requirements
Direct flight
cleared
0%25
100%
3. Promote private sector participation in the
management, financing, and maintenance of road
assets
(c) One long term performance based road management
and maintenance contract awarded to the private sector
and is effectively under implementation
(d) One road segment along the Northern Corridor
offered for concession to the private sector
100%
100%
100%+
100%
100%+
100%
4. Restore vital
infrastructure and public
assets damaged as a result
of the 2007 post-election
crisis
Vital public infrastructure and assets
destroyed or damaged during the post-
election crisis are restored and functional
again
100% 100% 100%
Intermediate Results / One per component Results indicators for each component
Original AF/ Restructuring Original AF Restructuring
Component A
Contracts awarded
and construction
Contracts awarded and
construction satisfactory
Average roughness less than International Roughness
Index (IRI) 3.0 m/km on completed sections of the
100% 100% 100%
25 Since the CAT1 clearance has not been obtained officially yet, it is considered that the project has not achieved the target. However, please note that the KCAA and KAA have met all
the requirements to obtain CAT1.
38
satisfactory on 373
km of selected
priority road
sections along the
Northern Corridor
and 8 km of the
Airport North Road
on 381 km of selected
priority road sections
along the Northern
Corridor
project roads
Damaged or destroyed
assets restored
(a) 3 bridges
repaired and
functional
(b) 3 public
buildings restored
and functional
(c) 3 term
contracts
awarded for
disaster response
readiness
(a) Not mentioned in
restructuring paper
(b) 3 public buildings
restored and
functional
(c) 3 term contracts
awarded for disaster
response readiness
3
3
4
0
100%+
0%
Component B
(a) Effective functioning of bus and truck stops at
key locations and satisfactory construction and
utilization of booths for sale of local produce and
products by roadside communities
(b) Health kiosks constructed and HIV/AIDS
awareness campaigns undertaken at key locations
along the Northern Corridor
(a) At least three roadside stations and amenities
constructed and functional as per designs and serving
road users and local communities
(b) At least 70% of road users and local persons
surveyed become aware of or make use of the
Voluntary Counseling and Testing (VCT) and other
facilities for the HIV/AIDS campaign along the
Northern Corridor
3
70%
>3
100%
100% +
100% +
Component C
Private Sector involved in road management and
maintenance
Legislation enacted for private sector participation in
roads
100% 100% 100%
Component D
Road safety improved At least 10% reduction in road related fatalities per
annum
2,700 3,057 0%
39
Component E
Management and governance improved in the
road sector
(a) KeNHA established and fully functional
(b) All feasibility and design studies carried out
satisfactorily
KeNHA
established
100%
KeNHA
established
100%
100%
100%
(c) Timely public disclosure of national
program and business opportunities in the
road sector
(d) NCA established and functioning
satisfactorily
(e) Governance and Integrity Action Plan
implemented satisfactorily*
(f) User perception and satisfaction
improved in the road sector*
Plan
disclosed
NCA
established
100%
>75%
satisfaction
Plan
disclosed
NCA
established
mostly
implemented
not assessed
100%
100%
substantial
n.a.
Component F
Security improved at major airports JKIA meets ICAO and USA TSA security
requirements.
100% 100% 100%
Capacity at JKIA expanded (a) Annual passengers handled at JKIA
increased from 4.8 million in 2007 to 6.4
million in 2012
(b) Cargo by air handled at JKIA
increased from 278,000 tons in 2007 to
383,000 tons in 2012
6.4
383,000
6.4
260,000
100%
0%
Component G
Aviation safety and air navigation standards
improved
KCAA meets ICAO and USA FAA Category 1 safety
requirements
100% 100% 100%
Component H
Compliance with IMO conventions and NCTTCA
treaty
IMO and NCTTCA certify compliance 100% 100% 100%
40
Annex 2c. Detailed Narrative Summary of Achievement of Project Development
Objectives
PDO1. Increase the Efficiency of Road Transport
Rating: Substantial
1. The project has substantially achieved first PDO by rehabilitating total 419.3 km of
the Northern Corridor satisfactorily, constructing road side amenities, reducing road related
fatalities, establishing and enhancing KeNHA, and increasing transparency and
accountability in road sub-sector.
2. The outcome indicator for the first objective, “freight and passenger travel time by
road from Mombasa to Malaba reduced by 25 percent” was 60 percent achieved by the
project closing with 15 percent lower travel time than the baseline. While a 25 percent
reduction in travel time between Mombasa and Malaba was recorded in ISR Sequence 12,
in December 2009 after the completion of Maji Ya Chumi- Miritini (40 km) and Lanet-
Njoro Turnoff (dual 16 km) road sections, 2014 and 2015 travel time data obtained from the
NCTTCA and UNES indicate the travel time decreased to 15 percent by the project closing.
The increased traffic volume along the project roads, particularly in Nairobi as shown in
table 2.3, and on-going maintenance works in other sections of the Northern Corridor are
the most likely explanation for the increase26.
Table 2.3: Traffic Survey Result in Nairobi
Survey/Year 2004 2013
Cordon line survey (total vehicles in 24 hours) 121,000 205,000
Screen line survey (total vehicles in 24 hours) 251,728 418,885 Source: Integrated Urban Development Master Plan for the City of Nairobi (final report, appendix III), December 2014, JICA
3. Seven original intermediate indicators and two revised intermediate indicators were
achieved satisfactorily. From the total length of 419.3km rehabilitated road, 389km exceeds
the target average roughness of less than IRI 3.0 as indicated in table 2.427 . The newly
established KeNHA, KURA, and KeRRA are all functional against the target of
establishment of one national highways authority. All planned feasibility and detailed
engineering design studies on selected road sections, have been completed and
implementation of Mombasa Southern Bypass is financed by JICA, and the design of
Lesseru-Nadapal/Nakodok Road has accelerated the preparation of the Eastern Africa
Regional Transport, Trade and Development Facilitation Project (P148853).
4. The newly established NCA is functional and the NCTIP meets the target of ‘timely
public disclosure of road sector program’ through the publication of the Road Sector
Investment Program (RSIP), and Annual Public Road Programs (APRP) by KRB. All road
works under the Roads Authorities are procured under open tender. The total number of
road related fatalities in Kenya has not been reduced but analysis prepared by the NTSA
shows that fatalities per 100,000 people have been reduced by 23 percent from 8.31 in 2008
26 BBC also reported heavy traffic jam stretching for 50 km (30 miles) on the highway between Mombasa and Nairobi on
November 19, 2015. 27 The road section of Nyamasaria-Kisumu Airport-Kisian (21.9 km, (8.4 km of which is dual carriageway), total 30.3km)
was handed over to the GoK in March 2016 and the IRI data for this section is not yet available.
41
to 6.4 in 2015. Two intermediate indicator related to social aspects also met the targets. In
addition, Kenya became one of the compliant Member States on Northern Corridor Transit
and Transport Agreement provisions.
Table 2.4. Average IRI score by road section
Source: PAD and maintenance data of KeNHA
5. There are other benefits of the project
which are associated with PDO1 and
worth mentioning:
6. The NCTIP rehabilitated and
improved a total of 419.3 km (including
41.4 km of dual carriage) of roads,
exceeding the revised target of 383 km
listed in the Financing Agreement by 36
km. The GoK’s contribution to the road
works was planned at US$42.63 million
at entry but it was increased to
US$126.12 million at the AF, and
US$307.94 million at closure. In
addition to the improvement of IRI
scores as stated above, the NCTTCA
also reported that the road condition
between Mombasa and Malaba is either
‘Excellent’ or ‘Good’ in 2015, which
was rated only ‘Poor’ to ‘Good’ in 2009.
The Northern Corridor runs from
Mombasa Sea Port through Kenya and
Uganda to Kigali in Rwanda,
Bujumbura in Burundi and to Kisangani
in the Democratic Republic of Congo
and about 930 km is under the Kenya’s
Section IRI
(2003) IRI (2013, 2015)
1. Maji ya Chumvi - Miritini (35 km, 5 km of
which is dual carriageway) 6.4 2.6
2. Sultan Hamud-Machakos Turnoff (55 km) 3.2-3.9 1.8
3. Machakos Turn off-JKIA (33 km, 12 km of
which is dual carriageway) 4.0-4.6 1.9
4. Lanet-Njoro Turnoff (dual carriageway 16 km) 3.2-3.3 2.0
5. Njoro Turnoff-Timboroa (84 km) 6.4-6.6 2.2
6. Mau Summit-Kericho (57 km) 4.8 2.2
7. Kericho-Nyamasaria (76 km) 4.8-5.8 2.7
8. Nyamasaria-Kisumu Airport-Kisian (21.9 km,
8.4 km of which is dual carriageway) 4.8 Not yet measured as this
section was handed over to
GoK in the end of March 2016.
Total Average n.a. 2.2
Source: Kenya Urbanization Review, 2016, the World Bank
Northern Corridor
Map 1. Concentration of Urban Population
along the Northern Corridor
42
jurisdiction. In addition, about 76 percent of urban dwellers in Kenya, which is equivalent
to 8.7 million people, are living within 15 km of the Northern Corridor. Therefore, the
positive impact of physical improvement of 419.3 km of roads on the efficiency of road
transport along the corridor is considerable.
7. Support to the KRB resulted in the completion of inventory/reclassification of
160,886 km of roads which was published in the national gazette in January 201628. This
clarifies the responsibility of each road authority, and the inventory data has been used for
the enhancement of Strategic Road Asset Management. Establishments of the NTSA, and
EBK are also the considerable achievement of NCTIP, enhancing and facilitating the
provision of safe, reliable, and efficient road transport in the country.
8. Outcome indicator of PDO1 has not been fully achieved but there should have been
more PDO indicators to assess the first PDO adequately. Attainment level of intermediate
indicators is reasonably high. In addition, considerable benefits of the project related to
PDO1 are observed and overall project contribution to the road sector is remarkable.
Therefore, achievement of PDO1 is rated Substantial.
PDO2. Enhance Aviation Safety and Security to Meet International Standards
Rating: Substantial
9. The second PDO, ‘Enhance Aviation Safety and Security to Meet International
Standards’ was substantially achieved. The CAT1 certification is expected to be obtained
later in 2016 due to the considerable improvements in aviation safety and security.
10. The highest accomplishment in the aviation subsector under the NCTIP was the
security clearance from the TSA, which allows U.S. airlines to operate direct flights from/to
JKIA, one of the PDO2 outcome indicators. Such a measure is yet to be implemented due
to security conditions in the East Africa region, not related to the airport operation itself. In
parallel, the KCAA is on track to meet the FAA CAT1 requirement, which is another
outcome indicator, through the enhancement of its oversight capacity, especially in the area
of safety, with key staff recruited with the required qualifications and in adequate numbers.
As a result, the ICAO security audit in October 2015 scored Kenya, the KCAA and KAA a
rate of 88 percent, against a cut off rate of 80 percent for CAT1 certification.
11. Achievements of the intermediate indicators for this PDO are as follows: (i) JKIA
has met ICAO and USA TSA security requirements by obtaining higher score than cut off
rate for CAT1 certification; (ii) the number of passengers handled at JKIA has met the target
of 6.4 million in 2014; and (iii) the volume of cargo handled at JKIA has not met the target
since it slightly decreased from 278,000 tons in 2007 (baseline) to 260,000 tons in 2014 due
to external factors.29
28 Kenya’s Road Network is estimated at 161,451.3km. APRP 2015/16, KRB 29 Business Daily (2013) Chemical ban hits vegetable exports to the EU market, May 2013 http://www.businessdailyafrica.com/Dimethoatel-ban-hits-vegetable-exports-to-the-EU-market--/-/539546/1694416/-
/tf5vd1z/-/index.html.
43
12. The other key outputs of aviation-related components were: (a) the construction of a
new terminal building (Terminal 1A, formerly Terminal 4); (b) the construction of a three-
story car park at the airport, increasing its capacity to a total of 1,500 cars and grade parking
for 400 cars. The ground floor of the facility is temporarily used as the arrival hall after the
fire in 2013 until the opening of a new arrival hall which has been completed; (c) the
expansion of the aircraft parking (apron) and taxiways at JKIA, which increased the apron
space by 50 percent through the creation of 13 new stands for aircrafts, a fuel hydrant system,
and two new taxiways; (d) the upgrading of Kisumu airport into an international airport,
which increased the passenger capacity to 500,000; (e) the acquisition of security and safety
related equipment (for passengers and luggage screening; an access control system; material
for perimeter fencings for major airports; and flight information display systems); (f)
enhancement of the EASA, resulting in an ICAO accredited regional training center of
excellence as one of 16 training centers in the world; and (g) various feasibility and design
studies as well as works supervision contracts.
13. The following key achievements in the aviation sector reform also contributed to the
enhancement of aviation security and safety: (a) the creation of an airport security oversight
unit which is responsible for monitoring security issues and ensuring compliance with
security regulations; (b) the financial autonomy to both the KCAA and KAA which now
retain the revenues generated from their operations, which were previously remitted to the
government’s general revenue; (c) the improved security monitoring at key airports through
transferring the responsibility for passenger, baggage and mail security screening from the
police to the KAA; (d) the adoption of harmonized aviation safety and security regulations
by each member of the East African Community; and (e) the continuation of the KCAA
restructuring through the separation of its oversight functions from service provision
activities.
14. The activities under the aviation-related components significantly contributed to
improve aviation safety and security, with achievements of one of two PDO outcome
indicators and two out of three intermediates indicators. Thus, rating for PDO2 is assessed
Substantial.
PDO3. Promote Private Sector Participation in the Management, Financing, and
Maintenance of Road Assets
Rating: High
15. The third PDO has been clearly achieved through mainstreaming OPRC, and
obtaining legal endorsement on private sector participation in management, financing, and
maintenance of road assets.
16. The first outcome indicator for the third PDO, ‘awarding of an OPRC’ is considered
achieved. The implementation of performance-based contracts is apparent in the increased
level of private sector participation in the management and maintenance of road assets over
the course of the project. Although the process of the proposed OPRC under the project was
canceled, KeNHA and KURA are managing 18 and 21 contracts, respectively30, with the
total amount of KSh 794 million (US$7.4 million) in FY15 and FY16, and this approach is
30 According to the information obtained from KRB.
44
mainstreamed in road maintenance.
17. Another outcome indicator, offering one road segment of the Northern Corridor for
concession, has also achieved the targets. With the approval of the concession contract by
the parliament in 2009, this activity was further developed into a pipeline project with a total
estimated cost of US$960 million, which was supported by several donors: IDA partial risk
guarantee (US$120 million), Multilateral Investments Guarantee Agency (US$120 million),
International Finance Corporation (US$115 million), African Development Bank (AfDB)
(US$100 million), and IDA (US$100 million). Due to the unfavorable results of due
diligence from the Bank group, however, the GoK decided to terminate the process in 2011.
18. The intermediate indicator of PDO3 met the target, too. The project supported the
enactment of the Kenya Roads Act 2007 under the institutional reform of the transport
sector, and section 53 of the act clearly stated the encouragement of private sector
participation in road construction, maintenance, and management. In 2013, the GoK
established a Public-Private Partnership (PPP) Unit under the National Treasury through the
PPP Act of 2013 and toll road projects for Nairobi Southern Bypass and the Nairobi-Nakuru
Highway were included in 71 pipeline projects.
19. Thus, the contribution of the project to PDO3 is extensive even though both
processes under the project were canceled. Since PDO indicators and results indicator
achieved the targets, rate for PDO3 is High.
PDO4. Restore Vital Infrastructure and Assets Damaged as a result of the 2007 post-
election crisis
Rating: High
20. PDO4 was to support the post-election recovery program of GoK and assessed
accomplished successfully with the achievement of a PDO4 outcome indicator and one of
two intermediate indicators: renovation and reconstruction of Oyugis office, Homa Bay
office, and Kisumu office of KeNHA have been completed and all offices are in use while
the new construction of KeNHA regional office block in Kisumu has also been completed
and is in use. In total, four public buildings became functional against the target of three
buildings.
21. Another intermediate indicator, ‘awarding of 3 term contracts for disaster response
readiness’ has not been achieved though the Road Disaster Management and Response Unit
has been established and functions as a committee composed of representatives from road
authorities when a disaster occurs. However, since PDO4 is targeting only infrastructure and
assets damaged due to the post-election crisis, the accomplishment of this intermediate
indicator is irrelevant to the overall achievement of PDO4.
45
Annex 2d. Summary of Institutional Change/Strengthening
1. The project supported the transport sector reform and made remarkable contributions to
institutional strengthening. Notable results of institutional strengthening under the
NCTIP are summarized below:
NCTIP
supported the enactment of the Kenya Roads Act 2007 and establishment of three road
authorities: KeNHA, KURA, and KeRRA in 2008. With this reform, the ministry can
focus on policy formulation and oversight, and road authorities can focus on the
implementation of programs and projects;
supported MoTI to review the Traffic Act to ensure that it conforms to international
transport conventions as well as prepare and adopt an integrated transport policy;
supported the establishment and capacity building of the KMA;
assisted the KAA to be autonomous and financially independent, which allowed the KAA
to retain the revenues generated. The responsibility of security screening was transferred
from the police to the KAA;
assisted the KCAA to be autonomous and financially independent and enhanced its
capacity to comply with international standards and practice;
enhanced the capacity of the EASA, which has been accredited by the ICAO as a regional
training center of excellence. Such centers exist in Africa only in South Africa and Kenya,
and there are only 14 in the rest of the world;
supported the establishment of the Road Disaster Management and Response Unit under
MoTI (road department), which functions as a committee composed of representatives
from road authorities when a disaster occurs;
provided assistance for the KRB in conducting the (a) Road User Charges Study, (b) Road
Inventory/Road Reclassification Study, covering 160,886 km of roads, (c) Road Sector
Investment Program (RSIP), and (d) Transport Sector Indicator Framework Study;
supported the establishment and capacity building of the NCA through the enactment of
the National Construction Authority Act 2011 to regulate, streamline, and build capacity
in the construction industry;
supported the reform of the Engineers’ Registration Board and the establishment of the
EBK through the repeal of the Engineers Registration Act (1969) and the enactment of
the Engineers Act 2011 to widen the mandate of the EBK to oversee and regulate the
standards in the engineering profession and build capacity for individual engineers and
engineering firms;
supported the preparation of a National Road Safety Program and the establishment of
the NTSA through Parliament Act Number 33 to facilitate the provision of safe, reliable,
and efficient road transport services;
provided assistance for the enhancement of maritime training capacity in Bandari College,
which became one of the four accredited institutions for maritime education and training
in Kenya; and
assisted the University of Nairobi, through the M&E assignment, to enhance research
capacity and support more than 50 post-graduate students majoring in transport and set
up a transport data bank in the university.
46
Annex 3. Economic and Financial Analysis
1. This annex summarizes the ex-post economic analysis for the following two
components under the original credit and the AF: (i) the rehabilitation and improvement of
the Northern Corridor; and (ii) the expansion of JKIA. The road works, with a total length of
419.3 km, and the civil aviation related works account for about 72 percent, and 21 percent
of the total project cost, respectively.
3.1 Rehabilitation of the Northern Corridor (Component A)
2. Ex-post economic analysis of the road rehabilitation and improvement under the
project was conducted and obtained the following results: (i) the net present value (NPV) of
the rehabilitation and improvement program is US$550 million at a 12 percent discount rate;
and (ii) the overall economic internal rate of return (EIRR) over 30 years (2004-2033) is 39.1
percent, varying from 13.3 percent to 56.4 percent, depending on road section, as presented
in table 3.1.
Table 3.1. Summary of Economic Analysis*
*Note: Results presented for each road section and for the homogeneous road subsections were analyzed
separately in the HDM4 model.
3. The ex-post economic analysis demonstrates that the Project is economically justified
despite cost overruns. The overall EIRR is higher than those estimated at the beginning of the
project and the AF economic analysis. Total NPV is also higher than at appraisal or the AF.
Significantly higher than anticipated traffic growth is one of the main contributing factors for
the positive results of analysis. Details of economic analysis are described below.
Section
Length
(KM)
NPV
(US$M)IRR %
Section
Length
(KM)
NPV
(US$M)IRR %
Section
Length
(KM)
1. Maji ya Chumvi - Miritini 35 13 37 35 49.1 44.0 35 14.1 14.1 18.7 18.7
56.1 48.2
66.3 49.9
179.5 55.5
98.3 58.0
14.6 23.2
9.8 43.7
9.3 44.1
27.1 41.7
23.3 40.8
18.5 21.0
Sub Total (original credit component) 223 372.1 34 223
6. Mau Summit-Kericho 57 14.4 17.0 57 7.9 7.9 18.0 18.0
7.2 21.9
5.9 24.8
10.7 44.4
8 Airport North Road8 7 25
9. Nyamasaria-Kisumu Airport -Kisian 24 11.6 16.0 22 1.4 1.4 13.3 13.3
Sub total (AF component) 162 65.7 19.2 155
TOTAL 367 124 27 385 437.8 N/A 378
AF Ex-Post
NPV (US$M) IRR %
Road Section
PAD
142.1 39.0 33 277.8 56.4
55 36.6 28.0 55 122.4 49.1
4. Lanet-Njoro Turnoff
99
12
335. Njoro Turnoff-Timboroa
26
33
2. Sultan Hamud-Machakos Turnoff 55 13 23
3. Machakos Turn off-JKIA 33 31 28
84 47.1 28.0 84 68.9 31.6
16 97.2 37.0 16 33.7 29.7
23.5 76 23.9 27.8
Dropped Dropped
516.9 40.3
137 22 20
7. Kericho-Nyamasaria
81 39.7
33.2 22.3
550.0 39.1
47
4. Project objectives and main benefits. The expected outcome of the proposed road
works was to increase the efficiency of road transport along the Northern Corridor. The
rehabilitated and improved road sections covered about 40 percent of the regional corridor
within Kenya and improvements contributed to improved traffic flow and road safety. As
noted in section 3.2, the road rehabilitation and improvement has reduced travel times
between Mombasa and Malaba/Busia by 15 percent in 2015 and road-related fatalities per
100,000 people in Kenya, has decreased by 23 percent from 8.31 in 2008 to 6.4 in 2015.
5. Main assumptions and methodology. Net benefits were computed using the Highway
Development and Management Model (HDM-4), which simulated lifecycle conditions and
costs and provided economic decision criteria for multiple road design and maintenance
alternatives. The evaluation followed the same methodology as the ex-ante economic analysis
assessing road users’ benefits and actual construction cost, estimated maintenance cost, and
traffic data obtained from existing studies31. The discount rate was set to 12 percent and the
evaluation period to 30 years. The data were provided by KeNHA and were adjusted to reflect
actual road works costs, incorporate a more realistic maintenance program in the base
scenario, and reflect actual traffic growth to date.
6. The main benefits are the savings made by road users on vehicle operating costs,
maintenance cost, and passenger/freight time. The evaluation calculated these benefits to road
users and costs of the investments in road works as compared to a without-project scenario,
and assessed streams of a net economic benefit to a society. Additional benefits, which have
not been quantified, include the reduction of accidents, reduction of vehicle emissions such
as GHG, and the improvement of driving and riding comfort. The costs to the road agency
are the works costs.
7. Road section. The civil works consist of rehabilitating and improving eight road
sections, totaling 377.9 km (Maji ya Chumvi - Miritini; Sultan Hamud-Machakos Turnoff;
Machakos Turn off-JKIA; Lanet-Njoro Turnoff; Njoro Turnoff-Timboroa; Mau Summit-
Kericho; Kericho-Nyamasaria; and Nyamasaria-Kisumu Airport-Kisian section), 41.4 km of
which is dual carriageways. The above eight road sections are further categorized into sixteen
homogenous road sections in terms of traffic and road condition for evaluation in HDM4.
8. Traffic volume. The traffic volumes (Average Annual Daily Traffic) and the annual
traffic growth rates are presented in table 3.2. The base year of the traffic data (2003) and the
actual traffic data in 2014 and 2015 were utilized to calculate average annual traffic growth
rates for each mode for the years 2003 to 2014/15. The annual traffic growth rates of 5 and 4
percent were applied to all modes for the periods, year 12 /13 to 19 (2015/16-2022), and year
20 to 30 (2023-2033), respectively.
31 Traffic data has been extracted from the following studies:
JICA: Goods Movement and Vehicle Traffic Survey for Master Plan on Logistics in Northern Economic Corridor in the Republic
of Kenya (2015);
PricewaterhouseCoopers(PwC) Kenya Ltd.:- Transaction Advisory Services for the Development, Operation and Maintenance
of Mombasa Nairobi (A109) Highway on PPP basis (2015/16); and,
ITEC Engineering Ltd.:- Consultancy Services for Reviewing And Updating The Economic Feasibility Study Report of Ahero
– Kisii – Isebania (A1) Road (2015).
APEC Consortium Ltd.:- Consultancy Services To Undertake Traffic Surveys On the Entire Road Network for the Kenya Roads
Board (2014).
48
Table 3.2.Traffic Volumes in 2003, and 2014/2015 and Traffic Growth Rate
9. Estimating economic benefits. The economic benefits of road rehabilitation and
upgrading works are: (i) reduction in vehicle operating costs and (ii) travel time savings. The
project contributes to increased average traffic speeds as well as improved riding comfort.
Accordingly, the economic benefits from the road works consist of the reduction of the
following transport costs: (i) vehicle operating costs, mainly, reduction in consumption of
fuels and reduction of wear due to vibration during driving, and (ii) reduction in travel time
for passengers and freight, which is converted into monetary terms and added as economic
benefits.
10. In the HDM4 model, benefits are calculated as the difference in transport costs and
benefits between a with-project scenario (alternative case) and a without-project scenario
(base case). These two scenarios include the following works:
11. With-project scenario. The following rehabilitation and maintenance activities were
assumed in the model of the with-project scenario:
a. Rehabilitation and Improvement: Actual construction period data was utilized during
the road rehabilitation and improvement period. The reduction of the International
Roughness Index (IRI) has been simulated by the model once works have been
executed, and completed.
b. Maintenance: Annual routine maintenance includes: roadside cleaning, maintenance
of road facilities, and normal road patrol. Routine maintenance costs are assumed at
the same level for all road types. Along with the maintenance, regular patching will
be carried out if the pavement surface is damaged before reaching the roughness
threshold for rehabilitation.
12. Without-project or Base scenario. The AF economic analysis base scenario assumed
annual routine maintenance and reconstruction at IRI 12.0 would be performed. Given the
significance and classification of the corridor 32 , the AF scenario assumptions likely
understated the maintenance levels that would have taken place without the project. The base
32 The Northern Corridor is classified as international trunk roads (class A)
Light Medium Heavy Light Medium Heavy Light Medium Heavy
1. Maji ya Chumvi -
Miritini 404 767 163 468 163 803 27691,269 453 280 166 696 4,362 7,226
10.0% -4.3% 4.6% -8.3% 12.8% 15.1%
492 393 80 305 566 836 2672 1,803 496 216 352 792 4,246 7,905 11.4% 2.0% 8.6% 1.2% 2.8% 14.5%
492 393 80 305 566 836 2672 1,803 496 216 352 792 4,246 7,905 11.4% 2.0% 8.6% 1.2% 2.8% 14.5%
1397 917 474 994 894 1243 5919 6,066 3,475 1,061 2,414 1,431 6,768 21,215 14.3% 12.9% 7.6% 8.4% 4.4% 16.7%
3836 2388 673 2782 1308 1715 12702 9,244 3,955 989 4,632 2,178 3,657 24,655 7.6% 4.3% 3.3% 4.3% 4.3% 6.5%
5503 2779 603 859 491 926 11162 3,973 2,303 283 2,125 711 2,591 11,986 -2.9% -1.7% -6.6% 8.6% 3.4% 9.8%
8482 5042 634 768 801 968 16697 10,030 8,034 449 2,752 1,136 2,813 25,214 1.5% 4.3% -3.1% 12.3% 3.2% 10.2%
3614 1771 551 520 551 866 7873 6,479 4,287 349 2,099 1,124 3,517 17,855 5.5% 8.4% -4.1% 13.5% 6.7% 13.6%
1802 868 287 249 210 409 3825 2,119 1,422 410 793 524 2,168 7,436 1.5% 4.6% 3.3% 11.1% 8.7% 16.4%
1036 697 470 246 186 563 3199 2,119 1,422 410 793 524 2,168 7,436 6.7% 6.7% -1.2% 11.2% 9.9% 13.0%
404 253 174 133 94 406 1464 1,347 825 98 177 478 1,734 4,659 10.6% 10.3% -4.7% 2.4% 14.5% 12.9%
6. Mau Summit-
Kericho 621 328 230 397 224 198 19971,527 957 198 228 713 734 4,357
7.8% 9.3% -1.2% -4.5% 10.1% 11.6%
703 384 230 530 391 238 2477 1,527 957 198 228 713 734 4,357 6.7% 7.9% -1.3% -6.8% 5.1% 9.8%
548 385 141 366 215 196 1850 2,141 1,528 739 828 688 1,046 6,970 12.0% 12.2% 14.8% 7.0% 10.2% 15.0%
604 588 126 365 212 145 2040 2,774 2,267 834 1,189 847 1,211 9,122 13.5% 11.9% 17.0% 10.3% 12.2% 19.4%
8. Nyamasaria-
Kisumu Airport 604 588 126 365 212 145 20403,536 1,059 322 958 474 716 7,065
17.4% 5.5% 8.9% 9.2% 7.6% 15.6%
5. Njoro Turnoff-
Timboroa
7. Kericho-
Nyamasaria
Trucks Trucks
2.Sultan Hamud-
Machakos Turnoff
3. Machakos Turn
off-JKIA
4. Lanet-Njoro
Turnoff
Trucks
Road Section Car Matatu
Large
Bus Total
2003 2014/2015 Average Growth Ratio (2003-2014/15)
Car Matatu
Large
Bus Total Car Matatu
Large
Bus
49
scenario in the ex-post analysis was therefore amended based on more realistic assumptions.
The ex-post base scenario included the same routine annual maintenance and reconstruction
at IRI 12.0 as the AF base scenario and additional maintenance work of a 50 mm overlay at
IRI 6.5 after the completion year of rehabilitation and improvement in the project scenario.
To make the base scenario and with-project scenario comparable, the additional maintenance
in the base scenario is of the same type and costs as were assumed in the with-project scenario.
13. Road works costs. Rehabilitation and improvement costs were calculated from the
final construction cost. The economic cost (excluding taxes) was estimated as 78 percent of
financial cost, similar to the proportion estimated in the economic analysis of the AF. To
make the results comparable to the results at the appraisal and the AF, the economic costs
were converted into 2008 prices using the GDP deflator published by the Bank.
14. Maintenance works. The same costs of routine maintenance works, 50mm overlay,
double surface treatments utilized in the AF economic analysis were assumed in the ex-post
analysis.
15. Table 3.3 presents the road sections lengths, road works and base investments costs
at the appraisal, the AF and ex-post evaluation:
Table 3. 3. Road Sections and Investments Costs of NCTIP
16. Vehicle Operating Cost. Vehicle fleet characteristics and economic unit costs were
defined for six vehicle classes: (i) car, (ii) matatu, (iii) large bus, (iv) light truck, (v) medium
truck, and (vi) heavy truck. The following table presents typical road user unit costs for each
type of vehicle. The parameters are based on the economic analysis at the AF, reflecting 2008
costs.
Section
Length
(km)
Road Work
description
Road
Work
cost
(US$M)
Road work
unit cost (US$
M/km)
Section
Length
(km)
Road Work
description
Road
Work cost
(US$M)
Road work
unit cost
(US$
M/km)
Section
Length
(km)
Road Work
description
Road
Work cost
(US$M)
Road work
unit cost
(US$
M/km)
1. Maji ya Chumvi - Miritini 35 Rehabilitation 13.0 0.37 35 Rehabilitation 24.55 0.7 35Rehabilitation
and Widening 48.63 1.39
2. Sultan Hamud-Machakos Turnoff 55 Rehabilitation 24.7 0.45 55 Rehabilitation 39.20 0.71 55 Rehabilitation 65.23 1.19
3. Machakos Turn off-JKIA 34 Widening 35.0 1.04 33 Widening 61.57 1.87 33 Widening 115.39 3.50
4. Lanet-Njoro Turnoff 16 Widening 39.20 2.45 16Rehabilitation
and Widening54.68 3.42
5. Njoro Turnoff-Timboroa 84 Rehabilitation 56.55 0.67 84 Rehabilitation 83.36 0.99
6. Mau Summit-Kericho Rehabilitation 55 Rehabilitation 86.44 1.57 57 Rehabilitation 72.52 1.27
7. Kericho-Nyamasaria Rehabilitation 81 Rehabilitation 101.66 1.26 76 Rehabilitation 99.16 1.30
8. Airport North Road 8 Widening 10.0 1.30
8. Nyamasaria-Kisumu Airport n/a n/a n/a n/a 24Rehabilitation
and Widening 66.88 3.04 22
Rehabilitation
and Widening 70.26 3.32
TOTAL 368 161.8 383 476.05 378 609.23
Dropped Dropped
AF Ex-post
Road Section
PAD
99
137
37.1
42.0 0.31
Widening 0.71
Rehabilitation
0.32
Rehabilitation
and Widening
50
Table 3.4. Vehicle Fleet Characteristics and Economic Unit Costs
Car Matatu Large
Bus
Light
Truck
Mediu
m
Truck
Heavy
Truck
Vehicle Characteristics
Number of axles 2 2 3 2 2 3
Number of wheels 4 4 10 4 6 10
Average Operating Weight (ton) 1.6 3.2 12.6 5 12.3 25
Service Life (years) 6 6 7 10 8 8
Km driven per year 20,000 100,000 150,000 60,000 80,000 80,000
Hours driven per year 400 1,600 3,000 1,300 2,500 2,500
Number of passengers 2 12 40 0 0 0
ESA loading factor 0.00 0.10 1.20 0.03 4.30 4.60
Economic Costs in 2008 price
New vehicle price (US$) 19,300 24,325 77,075 34,783 65,217
135,26
3
New tire price (US$) 55 58 298 397 397 435
Fuel cost (US$/Liter) 0.78 0.78 0.78 0.78 0.78 0.78
Lubricants cost (US$/Liter) 2.08 2.08 2.08 2.08 2.08 2.08
Labor cost of maintenance (US$/hour) 7.38 7.38 7.38 7.38 9.53 9.53
Crew wage (US$/hour) 0.00 1.63 1.63 1.63 3.29 3.29
Time costs for working passenger (US$/hour) 1.80 0.67 0.67 0.67 0.67 0.67
Time costs for non- working passenger
(US$/hour) 0.45 0.18 0.18 0.18 0.18 0.18
Cargo time (US$/hour) 0.00 0.00 0.00 0.02 0.04 0.13
Annual Interest Rate (%) 12 12 12 12 12 12
3.2 Civil Aviation Component
17. The aviation components (Components F and G) in the PAD amounted to US$51.65
million, or some 18.6 percent of the original project costs. The PAD notes that the proposed
interventions were required for upgrading the aviation safety and security status based on
internationally accepted standards and were not subject to economic analysis given the non-
quantifiable benefits associated with increased safety and security.
18. The project paper (PP) for the 2009 AF confirmed the change in project scope from
December 2005, when permission was sought and agreed, by exchange of letter to replace
the proposed renovation of Old Embakasi Airport (Nairobi) and increase the expansion of
JKIA, adding the development of the Unit 4 Terminal and Car park, with corresponding
reallocation of the credit proceeds, from the former to the latter. The PP also noted the
expected benefits of the JKIA expansion comprise: (i) increased revenue for the KAA; (ii)
reduced congestion at the airport; (iii) increased safety and security; (iv) increased reliability
and reduced delays in passenger and cargo handling; and (v) multiplier effects of reduction
in the cost of doing business, particularly in the horticulture and fresh flower industries.
19. The PP presented the results of a feasibility study for all the interventions at JKIA.33
Whilst an economic analysis was not undertaken to ascertain whether it represented an
appropriate use of public investment, the PP reported the results of a financial analysis, which
33 Queens Qay Architects Intl Ltd (Canada) 2005 Jomo Kenyatta International Airport Terminal Master Plan, Design and
Construction Final Report, KAA, February 2005
51
estimated project costs of US$134 million, NPV (at 10% discount rate) of US$218 million,
and an IRR of 19 percent.
20. While the financial analysis has not been redone for the ICR, this result was predicated
on demand forecasts that predicted 5.5 million passengers (domestic, international and transit)
with an annual growth rate of 4.7 percent for 2011-2016 and 353,000 tons of air-freight by
2015. Actual data from KAA reveals that total passenger numbers through JKIA reached 6.4
million in 2014, an average annual growth rate of 6.4 percent, and cargo throughput reached
260,000 tons.
21. The actual growth in passenger numbers exceeded the demand forecasts in the high
scenario, despite the impact of the global economic slowdown and the fire at JKIA. The drop
in air-freight is at least partially due to the introduction of stricter European Union import
regulations concerning pesticide levels on fresh products (Dimethoate) 34 . The European
market accounts for up to 80 percent of Kenya’s fruit and vegetable sales and 42 percent of
flower exports.
22. While actual financial costs (US$270 million) exceeded estimated costs markedly, the
growth in passenger traffic, the increase in the Airport Passenger Service Charge, a levy
charged on each passenger to pay for the improvements, from US$20 to US$40, would be
expected to more than ensure the investment was financially viable.
34 Business Daily (2013)
52
Annex 4. Bank Lending and Implementation Support/Supervision Processes
(a) Task Team members
Names Title Unit Responsibility/
Specialty
Lending
Anil Bhandari TTL AFTTR TTL
Josphat Sasia
Jean
Economist AFTTR Co TTL
Jean Francois Marteau Transport Specialist AFTTR Transport
Nina Chee Environment Specialist AFTES Environment
Amadou Konare Consultant/Environmental AFTES Environment
Moses Wasike Financial Management Specialist AFTFM Financial Management
Nyambura Githagui Sr. Social Develop. Specialist AFTES Social safeguard
Dahir E. Warsame Procurement Specialist AFTPC Procurement
Pascale Dubois Senior Counsel LEGAF Legal
Hisham A. Abdo Kahin Consultant/Counsel LEGAF Legal
Fabio Galli Sr. Financial Analyst SASEI Financial Management
Rodrigo Archondo-Callao Technical Specialist TUDTR Transport
Jaswant Channe Consultant/Highway Engineer SASEI Transport
James Karuiru Consultant/Infrastructure Eng. AFCO5 Infrastructure
Yoshi Kawasumi Consultant/Road Safety AFTTR Road Safety
Farida Khan Operations Analyst AFTTR Operations Analyst
Nina Jones Program Assistant AFTTR Program Assistant
Anne Njuguna Team Assistant AFTTR Team Assistant
Anne Odera Team Assistant AFCO5 Team Assistant
Hye Ra Kim Finance Analyst LOAG2 Finance
Hyacinth D. Brown Senior Finance Officer LOAG2 Finance
Marc Juhel Peer Reviewer TUDTR Peer Reviewer
Cesar Queiroz Peer Reviewer ECSIE Peer Reviewer
Henry Kerali Peer Reviewer ECSIE Peer Reviewer
Supervision/ICR
Josphat Sasia
Lead Transport Specialist GTIDR TTL
Fabio Galli Lead Transport Specialist GTIDR Transport
Nina Chee Lead Environmental Specialist OPSPF Environment
Anil Bhandari Consultant GGODR Team Member
Nyambura Githagui Lead Social Development Specialist GSU07 Safeguards
Dahir E. Warsame Senior Procurement Specialist AFTPC Team Member
James N. Karuiru Consultant GSU19 Team Member
Anne Khatimba Program Assistant AFCE2 Program Assistant
Jean Francois Marteau Program Leader ECCU5 Program Lead
Akiko Kishiue Urban Transport Specialist GTIDR ICR Team leader
Moses Sabuni Wasike Sr. Financial Management Specialist GGO21 Financial Management
Damon C. Luciano
Program Assistant GTIDR Team Member
Tim Ulrich Hartwig Consultant N/A Team Member
Amadou Konare Senior Environmental Specialist N/A Environment
Henry Amena Amuguni Sr. Financial Management Specialist GGO31 Financial Management
Masafumi Yabara Consultant N/A Team Member
Banu Setlur Senior Environmental Specialist GEN05 Environment
Diana M. Masone Operations Officer N/A Operation
53
Noreen Beg
Peter
Senior Environmental Specialist GEN 04 Environment
Peter Thinwa Warutere Senior Communications Officer AFRSC Communication
Shamis Salah Musingo Senior Executive Assistant AFCE2 Team Member
Armin Morz Consultant LCSTR Team Member
Silverster Kasuku Consultant N/A Social Development
Josephine Kabura Kamau Sr. Financial Management Specialist GGO31 Financial Management
Felly Akiiko Kaboyo Operations Analyst GPSOS Team Member
Josephine Kabura Ngigi Consultant GGODR Team Member
Lucy Kang’aura Program Assistant AFCE2 Team Member
Gibwa A. Kajubi Sr. Social Development Specialist GSURR Safeguards
Joel Buku Munyori Procurement Specialist GGO01 Procurement
Lucy Antango Musira Program Assistant AFCE2 Team Member
Charlene D’Aleida Consultant AFTTR Team Member
Samuel Iyasu Zerom Operations Analyst AFMRW Team Member
Solomon Muhuthu Waithaka Sr. Highway Engineer GTIDR TTL
Pascal Tegwa Procurement Specialist GGO01 Procurement
Rosemary Ngesa Otieno Program Assistant AFCE2 Team Member
Monica Gathoni Okwirry Program Assistant AFCE2 Team Member
Svetlana Khvostova
Natural Resources Mgmt. Spec GEN01 Safeguards
Tito Kodiaga Safeguard Specialist GSURR Safeguards
Justin Runji Senior Transport Specialist GTIDR Peer Reviewer
Kavita Sethi, Senior Transport Economist GTIDR Peer Reviewer
Natalya Stankevich Transport Specialist GTIDR Peer Reviewer
(b) Staff Time and Cost (from System)
Stage of Project
Cycle
Staff Time and Cost (Bank Budget Only)
No. of staff weeks US$, Thousands (including
travel and consultant costs)
Lending
FY03 15.32 87.2
FY04 50.81 262.7
Total: 66.18 349.9
Supervision/ICR
FY05 38.46 136.1
FY06 32.13 141.9
FY07 25.49 123.8
FY08 38.28 134.1
FY09 37.75 204.9
FY10 19.21 129.2
FY11 28.51 149.5
FY12 18.62 95.1
FY13 27.63 136.1
FY14 26.02 114.6
FY15 20.79 76.9
FY16 27.70 157.8
Total: 406.71 1,949.7
54
Annex 5. Beneficiary Survey Results Not applicable
55
Annex 6. Stakeholder Workshop Report and Results Not applicable
56
Annex 7. Summary of Borrower’s ICR and Comments on Draft ICR NORTHERN CORRIDOR TRANSPORT IMPROVEMENT PROJECT
(NCTIP)
Credit 3930-KE and Credit 4571-KE
Borrower's Implementation Completion and Results Report (ICR)
Date: March 31, 2016
(i) Background
Implementation period. The Financing Agreement for the Northern Corridor Transport Improvement
Project (NCTIP) became effective on September 16, 2004. The Development Credit Agreement was
amended and restated on May 8, 2009 so as to close on December 31, 2012. However, the government
requested the World Bank for an extension on September 21, 2012, which the Bank approved through
a letter dated January 3, 2013, and the implementation period was thus extended to December 31,
2015. The project NCTIP therefore became the longest running transport project under
implementation by the Ministry, with a total implementation period of eleven (11) years.
Justification for second extension of the implementation period. This extension was necessitated by
exogenous factors, which caused delays in completing the following major works contracts:
- Rehabilitation of the Northern Corridor comprising the Mau Summit-Kericho-Nyamasaria-
Kisumu-Kisian section. At the time of project preparation in 2003, the country was preparing
to go to elections and from 2003 to 2012 there was significant growth of traffic surpassing the
forecasted volumes partly due to the growth of the economy. This therefore necessitated
redesign of urban sections of the Northern Corridor to provide dual carriageways within major
towns of Mombasa, Nairobi, Nakuru, Kericho and Kisumu.
- Sub-components at Jomo Kenyatta International Airport (JKIA) mainly comprising
completion of Terminal T1A (international departures) co-financed by AFD.
Project Implementing Entities. There were four Project Implementing Entities (PIEs) namely: State
Department of Transport, Kenya National Highways Authority (KeNHA), Kenya Civil Aviation
Authority (KCAA) and Kenya Airports Authority (KAA). State Department of Infrastructure
coordinated the project.
Original Credit: US$ 207 million
Additional Credit: US$ 253million
Total Credit: US$ 460 million
Effectiveness date: September 16, 2004
Restating Development Credit Agreement: May 8, 2009
Approval of Extension of implementation period: January 3, 2013
Credit Closure date: December 31, 2015
Over the implementation period, the government put in substantial resources as counterpart funding,
running to about 35% of the total cost of the project (about US$ 250 million). This included
counterpart funding that went directly to finance the works and operational expenses by the Project
Implementing Entities (PIEs).
(ii) Project Development Objectives (PDOs) The revised PDOs were to: (i) increase the efficiency of road transport along the Northern Corridor
to facilitate trade and regional integration; (ii) enhance aviation safety and security to meet
international standards; (iii) promote private sector participation in the management, financing and
maintenance of road assets; and (iv) restore vital infrastructure and public assets damaged as a result
of the 2007 post-election crisis.
57
What is significant to note is that while the project was mainly road transport-oriented, the objectives
went beyond the traditional design as attested by indicators specifically touching on maritime,
aviation and other trade facilitative aspects of transport.
(iii) Key Design and Implementation Issues
Project complexity. This project had the longest implementation period, having started in 2004 and
closing on December 31, 2015. The project combined three sub-sectors in the transport sector namely
(i) roads, (ii) aviation and (iii) maritime. Such a design therefore needed proper planning and
commitment by the implementing entities.
Project design flexibility. Although challenging, the approach of an integrated transport project is
supported by the government and has been seen to produce positive results for Kenya.
During the currency of the project, reforms were carried out and some of the institutions established
through the project participated in implementation. This could not have been possible were it not for
project flexibility.
Following the political crisis that followed the general elections in December 2007, some critical
infrastructure and public assets, were damaged. The need to rehabilitate and replace the public assets
necessitated revision of the project development objectives (PDO) accordingly. Again, this was made
possible due to the project design flexibility.
The revision of PDOs and Additional Financing necessitated extension of the implementation period.
The 11-year duration was also partly due to other exogenous factors e.g. ongoing sector reforms as
well as the election violence of 2007/08, which temporarily slowed down progress.
(iv) Key Achievements of Project Development Objectives
The key achievements are listed below:
a) Roads sub-sector
Roads completed. A total of 419.3km of roads were rehabilitated/upgraded along the Northern
Corridor between Mombasa and Kisumu. This length was noted to be longer than what was targeted
at project design due to the inclusion of the additional lengths arising from dual carriageways.
Roads Completed
No. Road Section Rehabilitated Length (km)
1. Maji ya Chumvi – Miritini 35 + 5*
2. Lanet – Njoro Turnoff dualling 16 + 16*
3. Njoro Turnoff – Timboroa 84
4. Sultan Hamud – Machakos Turnoff 55
5. Machakos Turnoff – JKIA 33 + 12*
6. Kericho – Nyamasaria Road 76
7. Mau Summit – Kericho Road 57
8. Nyamasaria – Kisumu – Kisumu Airport 14.9 + 8.4*
9. Kisumu Airport – Kisian Road 7
Total length of roads completed 419.3
Note
5* - This is the length of road that is dual
Long term performance-based road maintenance contract. The concept of performance based
contract was new to Kenya. KeNHA sensitized consultants and contractors on long term performance
based road maintenance contract through workshops. The concept has been accepted in Kenya and
maintenance of newly constructed roads are to be under the performance based contract, e.g. Thika
Road.
58
Currently there are 12 long-term performance-based contracts awarded and under implementation.
This way, private sector participation in road construction, maintenance and management is
enhanced.
Road safety. The facilities constructed alongside the roads have greatly enhanced road safety. These
include footbridges, e.g. at Mlolongo, wide shoulders (1.5-2.0m), service lanes within build up areas
and street lighting. Other facilities were construction of proper bus and truck stops at key selected
locations.
Children’s Traffic Parks. Following the reforms under the Kenya Roads Act 2007 that saw to the
establishment of three Roads Authorities, the management of children’s traffic parks was moved to
Kenya Urban Roads Authority (KURA). Children Traffic Parks have therefore been under KURA
since 2009. Budgetary allocation for the same started in 2012 as tabulated bellow. Currently there are
six (6) in operation as follows: Nairobi, Nyeri, Embu, Kisumu, Kisii and Kakamega. The Authority
is currently rehabilitating Kisii Children’s Traffic Park, which has been in operation since the 1980s
to give it a face lift. An additional one is also being established in Nairobi at the junction of Outer
Ring Road/Kangundo Road under the ongoing Outer Ring Road expansion project financed by the
Government and African Development Bank (AfDB). KURA has used from the exchequer Kshs. 135
million from 2012 to 2015 and Kshs. 40 million budgeted in FY 2015/16, thus a total of Kshs. 175
million.
Budgetary Allocation to Children’s Traffic Parks Managed by KURA
Year Allocation Kshs. Million
2012 20.00
2013 25.00
2014 60.00
2015 30.00
2016 40.00
Total 175.00
The number of fatalities related to road accidents in 2015 was 3,057, about 3% less compared to the
2008 figures. Further, fatalities per 100,000 have been improved from 8.31 in 2008 to 6.4 in 2015.
Feasibility Studies: The design of the project was futuristic, allowing for design of roads to be
considered for implementation in the future. This was aimed at reducing lead time to project
implementation for the designed road sections.
All the feasibility and detailed engineering design studies on selected road sections were completed
as follows: (i) three sections on the Kenya-South Sudan Road from Lesseru to the Nadapal/Nakodok
border, length 601km, (ii) Kibwezi-Kitui-Mwingi-Maua-Isiolo, (iii) Narok-Northern Lakeside
Tanzania, and (iv) Mombasa Southern Bypass whose implementation is under financing by JICA.
The design of Lesseru-Nadapal/Nakodok Road under NCTIP played a significant role in facilitating
the quick preparation of the Eastern Africa Regional Transport, Trade and Development Facilitation
Project (EATTEDP). This project was prepared and approved in a very short time compared to other
projects that have been prepared within the transport sector. Before closure of NCTIP, the Financing
Agreement for EARTTDFP had already been declared effective. The lead time to closure of the road
upgrading contracts for the Bank-financed sections will also be significantly shorter than usual.
Transport Sector Reforms: The project supported reforms in the transport sector. This included the
enactment of Kenya Roads Act, 2007 which set the ground for establishing of the three roads
authorities (KeNHA, KURA, and KeRRA). Further, the reforms resulted in the enhancement of
Kenya Road Board (KRB), creation of the National Transport Safety Authority (NTSA), National
Construction Authority (NCA), and Engineers Board of Kenya (EBK). Consolidation of the transport
sector, which was previously managed by three Ministries namely, Transport, Roads, and Public
Works under the Ministry of Transport and Infrastructure in 2013, has also contributed to the
59
strengthening of the transport sector governance. These initiatives have brought efficiency in the
sector.
Roadside amenities. To facilitate socio-economic enhancement, markets were built along the
Northern Corridor at Taru and Awasi, three schools at Mlolongo, a community centre at Chepseon,
and a lorry park at Nyamasaria. Further, awareness campaigns were carried out for HIV and AIDS
Mitigation.
Emergency post-election reconstruction and recovery: Offices have been rehabilitated at Oyugis and
Hama Bay (two office blocks) and Kisumu. A new KeNHA regional office block in Kisumu has also
been completed.
Road Disaster Management and Response Unit: this unit was established under MoTI (Roads
Department) and functions as a committee composed of representatives from roads authorities when
a disaster occurs. The Disaster Management and Response Unit works with the National Disaster
Operational Centre when a disaster occurs.
b) Aviation Sub-sector
JKIA Terminal T1-A Construction. The construction of this new terminal improved capacity by 100%
to 5 million per year. The terminal was substantially completed in August 2014.
Parking facilities at JKIA. These were increased, adding a multi-storey parking facility for 1,500 cars
and at grade parking for 400 vehicles. The multi-storey parking facility was converted to a temporary
arrivals facility following the fire disaster incident at JKIA in August 2013.
Security and safety at JKIA. This was enhanced and the International Aviation Safety Assessment
(IASA) Category 1 clearance for KCAA and direct flights to/from United States of America (USA)
and United States Transportation Security Administration (TSA) security clearance is expected once
the process is completed.
Significant security improvements at JKIA were achieved by completing enhancement of passenger
screening. As a result, the ICAO security audit of October 2015 scored JKIA a high of 88%, against
a cut off of 80% for CAT1 certification.
Kisumu International Airport. The runway was extended from 2.0km to 3.3km and a new terminal
building of area 5,400 m2 was constructed. This upgrade resulted in capacity increase from about
70,000 to 300,000. The facility was opened in 2011.
Structural reform and capacity building of KCAA. Reforms at KCAA are still on-going. The revenues
of KCAA have been tripled between 2004 and 2015, which allows KCAA to recruit more inspectors.
The number of airworthiness inspectors and flight operations inspectors increased from 3 to 18 and
1 to 16, respectively. These changes will facilitate KCAA obtaining IASA Category 1 in the next
audit in 2016.
East African School of Aviation (EASA) enhanced its capacity and is now accredited by ICAO as a
regional training center of excellence. Such centers exist in Africa only in South Africa and Kenya
and 14 in the rest of the world.
c) Maritime Sub-sector
Support to Kenya Maritime Authority. The project supported the establishment of a new maritime
administration, KMA which was set up in June 2004 as the semi-autonomous agency in charge of
regulatory oversight of the Kenyan maritime industry.
Enhancement of Maritime Training Capacity (Bandari College). Procurement and installation of
navigation bridge simulator software and ICT equipment for Bandari College was completed.
Bandari College is now one of the four accredited institutions for Maritime Education and Training
in Kenya. Kenya is already listed in the white list countries based on proper implementation of ‘The
International Convention on Standards of Training, Certification and Watch-keeping for Seafarers of
60
1995’.
Kenya has been re-elected by the Assembly of the International Maritime Organization (IMO), into
its 40- Member Council under Category (C) for the 2016-2017 biennium.
Support for Implementation of Maritime Laws: Consultancy services to Draft Rules and Regulations
for seven Maritime Laws had resulted in development of regulations to improve the Maritime
Sector/Industry; enforcement of the merchant shipping Act; enhanced safety; strengthened the
capacity of the Kenya Maritime Authority; and enhanced Marine Environment Protection as well as
enhanced revenue generation for Kenya Maritime Authority.
Capacity building. Capacity building has been undertaken in all implementing entities across the
board. The two levels of capacity building are procurement and installation of IT and other equipment
as well as staff training. Training has been undertaken in various institutions on diverse topics and as
a result, achievement of project development objectives was realised. Kenya Airports Authority
trained a total of 171 staff between 2007 to 2015, Kenya Civil Aviation Authority 18 staff and the
Ministry of Transport trained 71 from 2005 to 2015. KeNHA trained 112 staff members. Under the
Engineers Board of Kenya, 8 staff members received training (4 attended engineers conference in
Singapore and Nigeria respectively and 4 went on a benchmarking trip to Tanzania), a stakeholder
conference was held at Kenya School of Government and the Strategic Plan for 2014 to 2019 was
launched in 2015.
Every year the Bank holds at least one disbursement and procurement clinic, which deal with
fiduciary issues and pointing out areas that the project implementation teams should improve on.
Further, during the annual FM supervision missions, Bank staff takes the implementing teams
through the requirements for proper financial management. Project Implementation Teams (PITs)
received training on financial and fiduciary management through disbursement and procurement
clinics that were organised at least once every calendar year by the World Bank. The following were
trained: KeNHA – 6 (4 technical, 1 finance and 1 procurement); MoTI(I) – 6 (2 technical, 3 finance
and 1 procurement); MoTI (T) – 9 (6 technical including 2 from KCAA, 3 finance including 1 from
KCAA).
M&E: The consulting division of the University of Nairobi Enterprises and Services (UNES) was
awarded the task of Monitoring and Evaluation for the project and has submitted a final draft report.
The choice of a public university to undertake monitoring and evaluation was another unique aspect
of the project design. By awarding the assignment to UNES, the then Ministry of Roads and the
World Bank intended to enhance the capacity of the University of Nairobi to undertake M&E of such
a complex project.
Overall Outcome Rating: Satisfactory. The Project Development Objectives were achieved.
(v) Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
Economic activities along the Northern Corridor increased as a result of the improved road
characteristics. This in essence worked to reduce poverty among residents. By constructing the
footbridge at Mlolongo for example, the numbers of accidents occurring at the section were reduced.
The two sides of the road were also socially integrated due to ease of movement of non-motorised
transport users.
(b) Institutional Change/Strengthening
Under the NCTIP the following institutions were established thereby strengthening the road transport
sector and construction:
1. Kenya National Highways Authority – to manage national highways;
61
2. Kenya Rural Roads Authority – to manage rural access roads;
3. Kenya Urban Roads Authority – to manage urban roads;
4. National Transport and Safety Authority – in charge of road safety;
5. National Construction Authority – regulation of construction industry;
6. Engineers Board of Kenya – to regulate the engineering profession.
The following institutions were strengthened to execute their mandate:
1. Materials and Testing Department – additional testing equipment supplied;
2. Kenya Institute of Highways and Building Technology – additional training equipment
supplied;
3. Mechanical and Transport Department – ICT equipment supplied;
4. Kenya Maritime Authority – enactment of treaties.
(c) Other Unintended Outcomes and Impacts (positive or negative)
1. The way projects are managed in the transport sector changed as a result of bringing
together various sub-sectors in the transport sector. Previously, each sub-sector planned
alone but through the NCTIP, this changed and it has now become a best practice.
2. When the project brought together aviation, maritime and road sub-sectors, another
dimension of transport planning hitherto unknown was established. The interconnectivity
of these sub-sectors has now been better understood.
(vi) Assessment of Risk to Development Outcome
Rating: Moderate. While the risk rating in the Project Appraisal Document was noted as substantial,
the Government has taken steps to ensure that sustainability of the facilities implemented under the
project is ascertained. These are: a) enhancement of the Road Maintenance Levy Fund (RMLF) by
Ksh.3.00 to Ksh.12.00, b) continuation of deepening of transport sector reforms by instituting various
measures e.g. formation of National Construction Authority to regulate the construction industry,
formation of the National Transport and Safety Authority for improved safety on the road, continued
implementation of the Integrated National Transport Policy, c) the Boards of the Roads Authorities
(KeNHA, KURA, KeRRA as well as KRB) are still in place as per the Kenya Roads Act, 2007, d)
the Constitution of Kenya, 2010 gives both levels of Government – National and County, mandates
over their respective jurisdictions to ensure that maintenance of roads is given priority.
Project sustainability - the government has instituted various measures to ensure that the project is
sustained. These include operationlisation of the Road Maintenance Levy Fund to provide funds for
maintenance of the road network. Further, stakeholders are involved during the planning process of
road works to ensure that the project components are sustained.
(vii) Assessment of Bank and Borrower Performance
Rating: Satisfactory. The implementation of the road rehabilitation projects was successfully
completed.
Bank Performance
(a) Bank Performance in Ensuring Quality at Entry (i.e. performance through lending phase)
Rating: Satisfactory. The NCTIP Credit was consistent with the Country Assistance Strategy (CAS)
and focused on economic growth and improving governance. The lending was packaged into a
Specific Investment Loan (SIL) since the borrower had well defined timetables for the
implementation of major physical investments.
62
(b) Quality of Supervision (including of fiduciary and safeguards policies)
Rating: Satisfactory. The selection of consultants and contractors was performed under Bank
regulations, which ensured quality. The Kenya National Audit Office (KENAO) audits the activities
and accounts of the projects in the Credit. Further, the Bank policies on safeguards are integrated in
the projects, which have safeguards experts to ensure compliance. The Bank reviews performance of
the executing agency twice a year in supervision support missions.
Overall Bank Performance: Satisfactory. The entire Credit has been applied to meet the Project
Development Objectives as detailed in the Project Appraisal Document.
Borrower Performance
(a) Government Performance
Rating: Satisfactory. The Government applied the Credit as documented in the Financing Agreement
with the World Bank and the Project Appraisal Document of 2004 as well as the Project Report of
2009 and completed the project components as intended. The National Treasury gave leadership in
ensuring that disbursements were well managed. Further, the Government provided the required
counterpart funding and even surpassed the ratios agreed in the Financing Agreement and thus outdid
the intended outcomes in some instances as reported in the Monitoring and Evaluation Report.
(b) Implementing Agencies Performance
Rating: Satisfactory. The Ministry of Transport and Infrastructure set up a Project Oversight
Committee (POC) to oversee the overall implementation of the project. The POC met on quarterly
basis and dealt with a cross-section of issues from various Project Implementing Entities (PIEs).
Members of the POC were the Chief Executive Officers of the PIEs, the Principal Secretaries for the
State Departments of Infrastructure and also Transport, and the Principal Secretary of the National
Treasury. The project was being coordinated by the State Department of Infrastructure, with the
Principal Secretary as chairman and the Principal Secretary (Transport) as co-chairman. The Project
Coordinator was the secretary to the POC. The Project Implementing Entities namely KeNHA, KAA,
KCAA, and MOTI (T) had set up a multi-disciplinary Project Implementation Teams (PITs) that
managed the implementation of NCTIP project components to completion.
Overall Borrower Performance: Satisfactory. The Credit has been fully utilized and the planned
physical works completed as intended. From the Monitoring and Evaluation results, the project was
noted to have performed well from the point of view of achieving the intended outcomes in the
results monitoring framework.
Overall performance of the transport sector has improved tremendously following the reforms carried
out in various sub-sectors. As an example, the Ministry of Transport and Infrastructure has been left
with the function of policy formulation and oversight while policy implementation has been taken up
by various roads authorities and other institutions under the Ministry. This has not only improved
service delivery but also governance. Over the period of the 11 years that the project was being
implemented, the sector saw increased levels of competitiveness in bidding processes. This has
resulted in significant savings in large value contracts. It is also worth noting that the perception of
Kenyans on the sector’s reputation has improved significantly.
(viii) Lessons Learned
The implementation of the NCTIP brought out some lessons that would be useful in current and future
projects:
i. Regular consultative meetings between Bank and PIEs – in the implementation of the various
projects there was need to review various project aspects such as costs and time. It was realized
that processing of such changes was better expedited by holding meetings to review the matter
at hand.
63
ii. Innovative scheduling of Credit funds – as a developing country, the Government would
occasionally experience slower than expected cash flow, which would lead to delayed
payments and subsequent claims. In this regard, the Bank agreed to reschedule the payment
to contractors such that most of the payments were brought forward. This had two major
benefits; works continued unhindered and claims were avoided and the borrower was able to
realize benefits of the rehabilitated road sections in good time.
iii. Establishment of a Project Oversight Committee (POC) – this Committee was constituted of
the Ministry of Transport and Infrastructure, the National Treasury, the CEOs and PIT leaders
of the various PIEs. It provided coordination and oversight among PIEs and provided peer
review during implementation of the project. Although the project was composed of several
sub-sectors of transport, all implementing entities agreed that project coordination was
smooth. Quarterly project meetings and the project coordinator were identified as the key
factors of smooth coordination of this complex project.
iv. Project decision making – there were some contracts that required difficult decisions like
termination, e.g. the Restoration of the Public Assets. It is a lesson learnt that such decisions
should be made in a timely manner in order to realize the project objectives.
v. Project design flexibility – although challenging, the approach of an integrated transport
project is supported by the government and has been seen to produce positive results for
Kenya. It is significant to note that during the currency of the project, reforms were carried
out and some of the institutions established through the project participated in implementation.
This could not have been possible but for project flexibility.
vi. Financial management - disbursements and counterpart funding. During project
implementation, procurement plans and disbursement projections will need to be strictly
adhered to as much as is practically possible. This will help reduce delays. Late release of the
exchequer for counterpart funding was seen to be a major drawback to implementation,
resulting in delayed payments and accrual of interest. Capacity at MOTI was an issue.
Resource Mobilization Sections were set up in the two departments of the Ministry of
Transport and Infrastructure to improve capacity and reduce delays. Good knowledge of
World Bank fiduciary and financial procedures was a prerequisite to successful
implementation.
vii. Design and implementation of large value contracts. It was noted that by addressing
institutional capacity constraints, it is possible to implement expanded project activities
effectively.
viii. Implementation duration – the NCTIP was implemented in a period, which has seen three
different governments and also with strong economic development, which generated more
transport movements than anticipated. The project teams and the World Bank were flexible
enough to respond to unexpected situations, modify the activities, and provide emergency
support.
ix. Project administration World Bank country office. The relationship of the Bank project
management team and the implementing entities was key to successful implementation.
Having the task Team Leader in the World Bank Country Office made consultation easier and
regular. Delays in issuance of the No Objections were kept at a minimum.
x. Co-financing by other development partners. The project was co-financed by the Nordic
Development Fund (NDF), European Investment Bank (EIB) and the Government. By the
World Bank taking the lead in project preparation amongst the development partners,
coordination was seamless.
xi. Project design replication. Designs of future projects can borrow from the lessons learned
from NCTIP with good results. While the NCTIP took long to implement, the impact it has
had as shown in the monitoring and evaluation final report indicates that it was highly
successful. The project was quite ambitious because it covered several subsectors of the
transport sector. Owing to the concerted efforts by the key players, the challenges arising from
its complexity were surmounted.
64
Borrower’s Comments on the Draft ICR (Letter from MoTI)
65
66
NORTHERN CORRIDOR TRANSPORT IMPROVEMENT PROJECT (NCTIP)
Cr. 4571-Ke and Cr. 3930-Ke
Borrower’s Comments on the Draft ICR35 Date: June 20, 2016
Below are the Borrower’s comments on the ICR:
(a) Intermediate outcome indicators:
Under Indicator 4: add to the list of achievement by December 2015 ‘1 footbridge at
Mlolongo’. This is reported as 100% achievement while in essence 300% was achieved
since 9 amenities were constructed.
- The Bank team will revise the achievement of indicator 4 accordingly.
Under Indicator 7: in our view, more than 10% reduction in road related fatalities was
achieved when measured from the internationally recognized rate per 100,000 population.
Noting that the traffic volume continued to grow from the base year to the end of the
project as noted in paragraph 44 therefore, it is not practical to state that the target was not
achieved while at the same time acknowledging that there was a reduction of 23% as per
100,000 population.
- Unfortunately, project indicator 4 set the target as the total number of road related
fatalities, not per 100,000 people. Therefore, the ICR needs to report as designed in the
Results Framework of the project. However, the data obtained from NTSA confirmed
the 23% reduction in fatalities per 100,000 people, the ICR included this information
in the report to support the positive result of project.
Under Indicator 10: further to achieving 100% of the target, also indicate that all road
works under the Roads Authorities are procured under open tender and thus the
opportunities are open to the public
- The Bank team will include the open tender in the comment section of Indicator 10.
(b) The Borrower notes the seriousness with which the Bank takes changes in the composition
of Project Technical Teams (PTT). Paragraph 38 of the ICR clarifies that the unilateral change in
leadership of the PTT in 2006 without consulting the Bank caused a delay in start-up activities of
road construction work. Changing the leadership without consulting the Bank was in contravention
to the legal agreement. This resulted in the signing of a Memorandum of Understanding on
transitional arrangements for the proposed change in the Ministry of Roads, Public Works and
Housing (MoRPWH) PTT. Moving forward, this is a good lesson to entities implementing
components under ongoing projects.
- The Bank team appreciates this comment.
(c) The Borrower notes the comments in paragraph 53 in regard to gaps observed in the project
M&E design and implementation. Concerns of the Bank and stakeholders on the quality and
timeliness of reporting were appreciated and this will be taken as a lesson learned for future projects.
Both the Borrower and the Bank will need to be more proactive in making critical decisions relating
to the implementation of M&E in order to improve performance monitoring.
- The Bank team appreciates this comment.
35 The responses from the Bank team are inserted (texts in italic and bold).
67
(d) Paragraph 58: The street lighting, road furniture, landscaping, foot bridges, and construction
of drains for Nyamasaria – Kismu-Kisian road section including Kisumu Bypass (14.9 km, including
8.4 km of dual carriage way) had not been completed by end of the project and is scheduled for
completion in July 2016. The lorry park at Nyamasaria and market at Awasi are expected to be
completed by September 2016. Delay in their completion was as a result of budgetary constraints.
- The Bank team will update the information in the report (please see paragraph 60 of this report).
(e) Paragraph 63: As noted in the ICR, follow up of conclusion of the development of a 50-year
transport master plan and the remodeling of terminal 1-B, C and D, and the restructuring of KCAA
are being carried out. The Consultant for the 50-year transport master plan made a presentation of
the draft final master plan and stakeholders gave comments which are expected to be incorporated
by end of June 2016 and the report resubmitted to the Ministry. In regard to remodeling of T1B, C
and D, the Government wrote to the Bank requesting for a project preparation facility to complete
the design and the same is under consideration by the Bank. With respect to restructuring of KCAA,
a study on delinking of regulatory and service provision functions of KCAA was completed and
recommendations on the way forward made. The Ministry is following up the issue to ensure that
the Authority is restructured as intended.
- The Bank team takes note of this comment.
(f) Paragraph 70: you indicate that 389km of roads were rehabilitated while elsewhere
(paragraph 73) and in the Borrower’s contribution it is different. Please harmonise the figures.
- Total length is 419.3 km. Paragraph 70 in the draft ICR was referring to the total KM of road
rehabilitated with available IRI data in order to confirm the improved road condition which was
one of the achievements of the NCTIP. Since IRI is not available for the road section of
Nyamasaria-Kisumu-Kisian (21.9km, 8.4 km of which is dual carriageway) yet, total KM for 7
road sections is 389km (419.3km - 21.9km-8.4km). Please see annex 2c paragraph 3 of this report.
(g) Paragraph 71: Refer to comment (a) above.
- The Bank Team will include this point in the final document. (Please see table 3, paragraph
112, and annex 2c paragraph 4 of this report)
(h) Paragraph 77: It is worth mentioning the achievements under the East African School of
Aviation in respect to attaining the Centre of Excellence status, one of the 16 in the world as a result
of facilities majorly installed through NCTIP. The school’s capacity to train aviation professionals
within the region and develop curriculum for specialized courses has been enhanced.
- Thank you for pointing this out. The Bank team will include EASA’s achievement in section 3.2
in addition to annex 2d in the final report.
(i) Paragraph 115: We take note of the need to have adequate counterpart funding in order to
reduce project costs. This is a lesson learned and will be take into consideration for future projects.
- The Bank team appreciates this comment.
(j) Paragraph 123: The need to staff the External Resource Sections in the Ministry has been
noted. Inadequate capacity in this regard was a source of delays in payment processing.
- The Bank team appreciates this comment.
68
Annex 8. Comments of Co-financiers and Other Partners/Stakeholders
Co-financiers
1. There was no co-financier for the NCTIP.
Parallel financiers
2. The draft report was shared with the parallel financiers, NDF and AFD for their
comments. The NDF and AFD thanked the Bank for sharing the report and informed
that they had neither specific questions nor comments on the report. The AFD also
expressed their gratitude to the Bank’s project team for the quality of collaboration in
the implementation of Component F, ‘Support to KAA’.
69
Annex 9. List of Supporting Documents
Additional Financing Project Paper for the Northern Corridor Transport Improvement
Project, Report No. 43537-KE, March 5, 2009
Aide memoires, project progress reports, and implementation status reports of NCTIP
Annual Report, Kenya National Highways Authority 2014/15
Constitution of Kenya, 2010
Country Assistance Strategy, 2004–08, Report 29038-KE, May 2004
Country Partnership Strategy, FY2010–13, Report 52521-KE, March 2010
Country Partnership Strategy, 2014–18, Report 88940, June 2014
Development Credit Agreement, Northern Corridor Transport Improvement Project,
between Republic of Kenya and IDA, June 25, 2004
Feasibility Study and Preliminary Design for Upgrading of Facilities at Kisumu and
Wilson Airport Study and Rehabilitation/Upgrading of Airport Pavements Design Study
for Jomo Kenyatta International Airport, Kenya Airports Authority, November 2006
Financing Agreement (Amending and Restating Development Credit Agreement),
NCTIP, between Republic of Kenya and IDA, May 8, 2009
Guidelines for Reviewing World Bank Implementation Completion and Results Reports,
a Manual for Evaluators, last updated Aug 1, 2014
Implementation Completion Report Guidelines, OPCS, Aug 2006, last updated July 22,
2014
Integrated National Transport Policy, Ministry of Transport, 2009
Integrated Urban Development Master Plan for the City of Nairobi in the Republic of
Kenya, December 2014, Japan International Cooperation Agency (JICA)
International Roughness Index data, Kenya National Highways Authorities
Jomo Kenyatta International Airport Terminal Master Plan, Design and Construction
Final Report, KAA, February 2005
KAA Traffic Data and Analysis
Kenya Airports Authority Statistics
Kenya Facts and Figures, Kenya National Bureau of Statistics (for 2003–15 figures)
Kenya Transport Sector Memorandum (Volume I–III) 26444-KE
70
Kenya Urbanization Review, February 2016, The World Bank.
Midterm Review, Mission Report, May 2009. Second Medium Term Plan (2013–17),
Vision 2030, The Presidency, Ministry of Devolution and Planning, 2013
NCTIP Monitoring Report, University of Nairobi Enterprises and Services Limited,
March 2016
Northern Corridor Transit and Transport Coordination Agreement, October 2007
Northern Corridor Transit and Transport Coordination Authority
(http://www.ttcanc.org/), (travel time between Mombasa to Malaba and Busia, road
condition, traffic in weigh bridge)
Project Appraisal Document for a Northern Corridor Transport Improvement Project,
April 30, 2004
Road Act of 2007, Republic of Kenya
Road Maintenance and Trend, Kenya Roads Board
Road Safety Status Report 2015, January 2016, National Transport and Safety Authority,
Road Sector Investment Programme 2010–14, Ministry of Roads, Republic of Kenya
The State of Easter African Cities, 2014, UN-Habitat 2014
Traffic Act of Kenya, Revised Edition 2014
Vision 2030, Government of Kenya, 2007
Global Health Observatory data repository, Registered Vehicles Data by country 2013,
World Health Organization (http://apps.who.int/gho/data/node.main.A995)
71
Annex 10. Road Sector Governance and Integrity Improvement Action Plan -
Implementation Status Risk Control/Action Status
1. Collusion and
bid rigging.
Client: (a) Use post-qualification, instead of
pre-qualification, to avoid advance
knowledge of the firms invited to bid.
(b) Public dissemination of the overall roads
program and business opportunities in the
road sector, reinforce government’s and
Bank’s commitment to fight corruption.
This will also include publication of the
project’s detailed and updated procurement
plan on the website.
Bank: (a) Engage an independent
procurement specialist charged with
reviewing bid specifications and bids for
Bank-funded contracts, and reporting
directly to MoF, MoR and Bank.
(b) Include the Bank’s audit rights in the
works contracts.
(c) Ensure works contracts are large enough
to attract international and large domestic
firms to bid.
(d) Ensure that contracts are not deliberately
split to circumvent the Bank’s prior review
thresholds or to limit competition.
Key monitoring indicator: Increase in the
number of qualified bids obtained [4-5]
Baseline: 2-3 bids
Client: (a) Post-qualification has
been used for all major civil
works contracts.
(b) The Client held two such
public dissemination workshops
(June 2004 and August 2005) and
participated in a third organized
by the Bank during its Public
Forum (October 2007).
Bank: (a) An independent
qualified procurement specialist,
financed by the Bank as an
adviser to the Bank’s team, has
reviewed all the bids as received:
(b) The Bank’s audit rights have
already been in Standard Bidding
Documents;(c) and (d) All major
contracts are more than US$30-
US$40 million each and are
sliced and/or packaged together to
attract international and large
domestic firms. This was adopted
for other Bank-financed projects
such as KTSSP.
Indicator: Number of bids
received increased for subsequent
similar Bank financed projects.
Under the KTSSP, average 10
bids have been obtained for six
road work tenders between 2010
and 2015. In 2016 under the
EARTTDFP, between 17 and 20
bids have been received for four
contracts.
2. Fraud and
Corruption in
the Road
Construction
Industry.
Client: (a) Establish a transparent, well
documented, and consistently implemented
system for debarment of poor performers
and contractors engaged in fraudulent and
corrupt practices through the NCA.
(b) Strengthen the Recipient’s capacity to
design and supervise the construction of
roads, with particular emphasis on quality
and contract management.
(c) Review on-going or recently completed
Client: (a) (i) This is already part
of the Function of the Public
Procurement Oversight Authority.
(ii) The NCA was established
under the project in 2011 to
regulate, streamline, and build
capacity in the construction
industry.
(b) The project had a training
component and a technical
72
contract(s) to check for fraud such as
unbalanced bid, use of substandard
materials, lower quantities used than paid
for, and other non-compliance with
specifications.
(d) Determine through an independent
survey why some bidders who buy bid
documents choose not to submit bids.
Bank: (a) A technical audit to be conducted
independently of the implementing agency
on all contracts.
(b) Strengthen the use of contractual
remedies, such as performance bonds, in
case of project delays and poor
performance.
Key monitoring indicator: Percentage of
government-funded projects completed on
time, within budget, and in compliance with
specifications (measured by periodic review
of random sample of large projects).
Baseline: Less than 40% completed on time
and within budget.
assistance component to
strengthen the capacity of
KeNHA.
(c) Reporting corruption system is
established in KeNHA’s website.
An Integrity Committee in
KeNHA undertakes training and
carries out surveys through
independent firms. Quarterly
reports are forwarded to Ethics
and Anti-Corruption Commission
(EACC).
(d) A survey has not been
undertaken.
Bank: (a) Internationally
recruited and qualified
engineering firms were selected
and performed day-to-day
independent certification of the
quality of works, payment
certificates and compliance with
contract terms.
(b) Unconditional performance
bonds were mandatory as
additional remedies should the
contractor perform poorly.
Indicator: At the stage of the
ICR, it is still a challenge for the
GoK to complete government-
funded projects on time and
within budget. Still less than 40%
were completed on time and
within budget.
3. Truck
Overloading –
lack of
enforcement and
corruption.
Client: (a) Review current efforts to address
corruption in control of axle loads,
recommend appropriate measures to
mitigate such risks, and examine the need
for additional weight control infrastructure,
preferably automated.
(b) Ensure that road designs are
commensurate with the prevailing traffic
and axle load projections.
(c) Institute a fine that is commensurate with
damages to the roads and additional
deterrent measures to ensure compliance.
(d) Establish quarterly and random
independent reviews of the weigh stations’
activities including fines imposed and
collected.
Client: (a) Management of 5
weighbridge clusters covering 9
weigh stations, with 11 fixed
weighbridges and 6 mobile
weighbridges by the private
sector through competitive
bidding. Automated systems
(weigh-in motion) have been
installed at four of the weigh
stations along the Northern
Corridor.
(b) Current road designs are
based on actual axle load surveys
and projected design life
equivalent standard axle loads,
which produce higher designs but
73
Key monitoring indicator: At least 50%
decrease in the percentage of overloaded
trucks traveling on the Northern Corridor.
Baseline: Will be established once the first
automated axle-load weighing station is
constructed and functioning - expected in
one year from credit effectiveness.
are more economic in the long
run.
(http://www.itsinternational.com/
categories/enforcement/features/k
enya-wim-system-cuts-four-days-
off-journey-times/
(c) The NCTTCA is monitoring
weighbridge compliance and
reporting at their website weekly
(http://top.ttcanc.org/)
Indicator: At four weighbridges
along the Northern Corridor,
average 95 % of compliance is
reported between October 2014
and December 2015.
4. Delays in Value
Added Tax
(VAT) refunds,
causing inflated
prices in
construction
bids.
Client: (a) Assess the amount of VAT
outstanding for reimbursement to
contractors and liaise with the MoF and the
Kenya Revenue Authority (KRA) to
establish a system to minimize delays.
(b) Provide guidance notes and instructions
to the contractors on VAT procedures and
timelines.
Key monitoring indicator: Time elapsed
between receipt of required VAT
documentation by the KRA and issue of
refund to contractors decreased by at least
50%.
Baseline: To be established by MoRPWH
after survey of local contractors (within 3–6
months of effectiveness).
(a) The project assisted in
mounting regular workshops to be
conducted by KRA for
contractors to explain procedures
and resolve any issues. The
President has directed that all the
outstanding eligible tax refunds
be made within the current fiscal
year and the KRA is
implementing the directive.
However, the NCTIP was
exempted from VAT. Hence
refunds were not applicable.
(b) A workshop was held in
November 2008 where the KRA
made a presentation to contractors
and consultants on VAT
procedures.
Indicator: Since this is beyond
the scope of the project, data has
not been collected under this ICR.
5. Weak due
diligence on
bidders. The
integrity and
past
performance of
contractors is a
key determinant
of fraud and
corruption risks.
Client: (a) The Recipient must increase its
efforts in conducting due diligence of
bidders, particularly with regard to past
performance, financial and technical
capacity, equipment holding, and
compliance with tax laws and site safety
regulations.
(b) Undertaking performance reviews to
ensure poor performers are identified.
Key monitoring indicator: Extra due
diligence in verifying qualifications and past
performance is carried out by the Recipient
(a) and (b)The project promoted
greater scrutiny, in line with the
provisions of the bidding
documents. The results have been
made public by KeNHA and the
Public Procurement Oversight
Authority.
Indicator: Extra due diligence in
verifying qualifications and past
performance has been carried out.
For example, companies under
temporary Bank suspension were
informed that they were ineligible
74
on all preferred bidders, as verified in the
bid evaluation reports.
Baseline: Insufficient due diligence on
companies bidding for roads contracts.
for Bank-financed contracts, and
none of them bid for the Mau
Summit-Kisumu contracts. This
requirement has been adopted for
subsequent Bank financed
projects: KTSSP and
EARTTDFP.
6. Absence of
robust cost
estimates.
Client: (a) Cost estimates should be
developed from first principles and adjusted
for prevailing market conditions and, if
possible, also comparable to markets in the
region (i.e. East Africa).
(b) Hire a consultant to develop new, robust
cost-estimates and regularly update the cost
methodology and estimates as necessary to
reflect prevailing market conditions.
(c) Exercise the audit rights under the
contract to review true cost structure of
recently completed projects.
Key monitoring indicators: Robust cost
estimates developed; capacity developed in
National Highways Authority to monitor
actual costs obtained in the field.
Baseline: There is no systematic monitoring
of unit costs by the MoRPWH.
(a) and (b) The Cost Estimation
Manual for road maintenance
works has been developed and
published in 2011. The KRB
prepared a concept paper for the
development of a road works
construction cost index (RCCI)
and drafted the terms of reference
(TORs) for an RCCI Committee
to develop the RCCI and advise
the road sector on the RCCI
trend. The RCCI will cover road
development and maintenance
interventions carried out by the
road agencies in every financial
year.
(c) The contract provisions
already in the Standard Bidding
Document of the Bank permit
such an audit and an independent
review will be undertaken
according to item 2(c).
Indicators: Cost estimation
manual for road maintenance
works has been published.
Concept paper for the
development of a road works
construction cost index has been
prepared. Capacity of KeNHA
has been increased.
7. Weak capacity
to detect and
deal with fraud
and corruption.
Bank (a) Facilitate training workshops
focused on identifying red flags and
establishing controls in procurement,
financial management, and human resource
management particularly in the road sector,
including prevention of fraud in works
contracts.
Key monitoring indicators: At least three
(3) key people from each of the four (4)
Project Technical Teams have participated
in the training workshops.
Indicators: 24 key staff from
each of the four PTT participated
in the training workshop: KeNHA
– 6 (4 technical, 1finance and 1
procurement); MoTI(I) – 6 (2
technical, 3 finance and 1
procurement): and MoTI (T) – 12
(6 technical including 2 from
KCAA, 3 finance including 1
from KCAA)
75
Baseline: No training has taken place.
8. Weak complaint
handling
mechanisms.
Client: (a) Strengthen systems to handle and
effectively respond to complaints in a timely
manner.
(b) Establish and implement a
communications strategy to build awareness
of fraud and corruption and provide the
means for all parties to register their
complaints.
(c) Encourage the appropriate authority to
institute strong whistleblower protection
regulations.
Key monitoring indicators: (a) Internet-
based complaint lodging system established.
(b) NCA established and functioning
satisfactorily as judged from its annual
reports.
Baselines: (a) There is no Internet-based
complaint lodging system. (b) There is no
construction authority to register and
monitor contractors.
Client ((a),(b), (c)) and
Indicator: The NCA has been established
and has set up a complaints
handling mechanism. A
complaint form can be picked up
from and submitted to complaint
desk of the NCA office or
through emails. The complaints
submitted are logged into an
official complaint register and
responded to within 7 days.
http://www.nca.go.ke/index.php/a
bout-nca/complaint-handling-
mechanisim
9. Weak road
management
capacity.
Client: (a) Strengthen planning,
programming, budgeting, execution,
monitoring, and evaluation capacity of the
road agency.
(b) Ensure the key positions for the three
roads authorities are selected through a
competitive process based on their
qualifications against the established TOR.
Key monitoring indicators: (a) Key staff in
the National Roads Authority, Rural Roads
Authority, and Urban Roads Authority are
in place, and trained in work program and
budget planning, execution, monitoring and
evaluation. (b) Annual work programs,
budgets and progress reports are prepared
and published.
Baseline: The three roads authorities are not
yet fully functional.
Client: (a) Legislation has been
enacted (Kenya Roads Act 2007)
which provided for the
establishment of the three
autonomous roads authorities—
KeNHA, KeRRA, and KURA.
(b) Key positions of KeNHA,
KURA, and KeRRA have been
filled through a competitive
process based on qualifications
against the established TOR.
Indicators: KeNHA, KURA, and
KeRRA prepare annual road
works programs and submit to the
KRB, which reviews the annual
road works programs and
consolidates them into an APRP.
The APRP is published in the
website of the KRB.
10. Overall
transparency
and social
monitoring of
the road
construction.
Client, Bank, Civil Society: (a) Take
additional practical steps to foster a culture
of transparency and probity in the road
subsector.
(b) Establish a communications strategy
through radio programs and talk shows
where the issues facing the road sector are
discussed and the general public is asked to
participate through expressing their views
and comments.
Indicators: (a) Work program,
tender notices and awards, and
vacancy announcements are
placed in the websites of KeNHA
and KRB and overall
transparency and social
monitoring of the road
construction have been promoted.
(b) Road user satisfaction survey,
which involves an NGO/civil
society organization was planned
76
Key monitoring indicator: (a)
Communication strategy in place and (b) at
least two road-user satisfaction surveys
carried out during project implementation,
by NGO/Civil Society Organization.
Baseline: No system in place for
transparency and social monitoring of road
construction outside of MoRPWH.
to be conducted with the research
funds from Governance and
Anticorruption unit. However, the
funds were not allocated and the
survey was not conducted.
77
MAP