WORKING WITH AGILE IN A WATERFALL ENVIRONMENT A case study in the Challenges of a High Risk Project

description

 

Transcript of Working with agile in a waterfall environment wwp

Page 1: Working with agile in a waterfall environment wwp

WORKING WITH AGILE IN A

WATERFALL ENVIRONMENT

A case study in the Challenges of a High Risk Project

Page 2: Working with agile in a waterfall environment wwp

DEVELOPMENT ENVIRONMENT Largest Health Insurance provider in

the Pacific Northwest  ~6000 of employees

Typical Projects Claims Processing (CP-SS) Compliance Web, “eBusiness”

 90/10 : Waterfall /Agile

Page 3: Working with agile in a waterfall environment wwp

TRANSPARENCY: HEALTH COST ESTIMATOR 100 members

5 Scrum teams

3 year $8.5 Million

Corporate Key Initiative

Page 4: Working with agile in a waterfall environment wwp

High Company Risk

High Importance to the CEO

Complex Data Analysis

Complex Org. Silos

No external project drivers = no drivers

CHALLENGES: HEALTH COST ESTIMATOR

Page 5: Working with agile in a waterfall environment wwp

WHY AGILE? Waterfall failed

Early risk visibility

Adapt and make changes early

It was a web project…

Page 6: Working with agile in a waterfall environment wwp

RESULTS Risks explored in

increments Most important

features delivered first 4 major releases 1 ½ year product

roadmap

Project

A year later Received “Best of Blues” Award

Page 7: Working with agile in a waterfall environment wwp

This case study in ENTERPRISE Agile

ENTERPRISE AGILE IS LIKE…

Waterfall

Enterprise

Agile

Page 8: Working with agile in a waterfall environment wwp

HOW TO REACH: JOSEPH FLAHIFF Joseph Flahiff, PMP, CSP www.WhitewaterProjects.com [email protected]

m Twitter.com/joseph_flahiff Enterprise Agile Podcast 206.276.1386

SMART WAY Lead

PROJECTS

THE

TOYOUR