Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office (RMO) Shared Service Stephen Flynn C. Eng Senior Engineer

Transcript of Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag...

Page 1: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Working together effectivelyAg obair go héifeachtach le chéile

The Road Management Office (RMO)

Shared Service

Stephen Flynn C. EngSenior Engineer

Page 2: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Page 3: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

What are we at?

• Road Licensing• Software development• Pavement Management

• Pavement Management Working Group• Mechanical Survey• Collation of Data• What to do with it

Page 4: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group

Page 5: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group:• Carlow (chair), Cork City, Dún Laoghaire –Rathdown,

Galway, DTTAS, Limerick City and County, Wexford, LGMA, RMO

• Current Work:• Works App• Footways• Drainage• Pavement Management Strategy / Management Pavement Plans

• Process: – scope – specify – pilot – review – implement

Page 6: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group

Footways

Page 7: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group - Footways (scoping)

Principals! Don’t develop something

which doesn’t give value Don’t develop something

which won’t be used With all the data available,

develop tools to interpret and assist with decision-making

Don’t make work for engineer/technician

• WHY ?

Page 8: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

• Hierarchy of footways

References IPB Managing Roads and Footpath Risks , Sections 4 & 5.2 IPAG

• Condition

• Risk

• Frequency

Pavement Management Working Group - Footways (scoping)

Page 9: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

• Survey methodology• Full vs. Hazard• Video vs. Photos vs.

Descriptive• Technical supports

Pavement Management Working Group - Footways (scoping)

Page 10: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group

Works App

Page 11: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group – Works AppCurrent Functionality:•Down load planned works to tablet.•Update start and end and mark as complete•Creation of new works (inc. extents)•Rate road at planned works site•Upload new works to MapRoad

Page 12: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Management Working Group – Works AppDevelopment Options:

• Traffic Management?

• Site Specific Heath and Safety Plan?

• Quality Assurance Records

Element: Planning Criterion: Hazard Identification, Risk Assessment and Determining Controls

Risk Assessment Summary Sheet

Risk Assessment Summary Sheet

Activity/Workplace

Generic Risk Assessment Risk Assessment after application of Control Measures

Hazard Risk Risk Group Li

kelih

ood

Sev

erity

Risk Rating before controls CONTROL MEASURES

Responsible Person Li

kelih

ood

Sev

erity

Risk Rating after controls

Sample risk rating matrix

Numeric Rating Likelihood Severity

1 Very Unlikely Very minor injuries

2 Unlikely First aid minor injury/illness

3 Likely “3 Day” injury/illness

4 Very Likely Major injury/illness

5 Almost Certain Permanently disabling injury /illness or fatality

5 5 10 15 20 25

4 4 8 12 16 20

3 3 6 9 12 15

2 2 4 6 8 10

1 1 2 3 4 5

1 2 3 4 5

S e v e r i t y

Principals!Don’t develop something which doesn’t give valueDon’t develop something which won’t be usedWith all the data available, develop tools to

interpret and assist with decision-makingDon’t make work for engineer/technician

-Users views are essential

Page 13: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Surveys and Data Collation

Page 14: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

• RW 21 Nov 2014

• Visual – PSCI

• Mechanical – IRI, rut depth, texture, cracking, scrim

Surveys:• PSCI Network survey

2015• Regional – 100%• Local Primary -100%

• PSCI Work Survey• Before and after 100%

of each project

• Mechanical• Network 2015 - 10% min sample of Local Primary network only• Works 10% of Local Primary, 10% of Local secondary and 5% of

Local Tertiary jobs completed.• Some LA have proceeded • Available through LA Quotes• Specification and tender documents to be issued to each LA

once framework is in place• Each LA can tender for survey works using RFT via LA Quotes at

any stage during the next 3 years.• Ability to contract out PSCI survey to service provider.• RMO to procure national regional road survey next year.

Page 15: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Data Collation

Page 16: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

“If you do not ask the right question, you discover nothing”

W. Edwards Deming

“Without data you are just a another person with an opinion”

W. Edwards Deming

“If we have data, let’s look at data. If all we have are opinions, let’s go with mine.”

– Jim Barksdale

Some Quotations

Page 17: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Data on system:

• PSCI data 2015 and previous years.

• Data uploads from 2014

• Roadworks Programme 2015

• €180M of planned works loaded across 3600 projects and 3600km.

• Work ongoing to programme these.

• 17 Local Authorities with DTTAS submissions made

Page 18: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Learning:

• Additional guidance on PSCI vs categories of intervention.

• Clarifications on stages of process: Planned- Approved – Complete.

• What data is recorded and use

Page 19: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

“Data by its self is useless. Data is only useful if you apply it”

Todd Park

Page 20: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Surface Condition IndexRelatable to treatments

Page 21: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Work to date: (surveying)RW 21 2014

Over 56000km surveyed over 60% of network:

• R 47%, • LP 73%, • LS 63%, • LT 50%

Page 22: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Page 23: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Selected Regional Roads

Page 24: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Selected Local Primary Roads

Page 25: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Selected Local Secondary Roads

Page 26: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Back of the envelope calculations

Intervention Est. CostRegional €/m2

Est. CostLocal Primary €/m2

Road Reconstruction (1, 2) 35 25

Structural Overlay (3, 4) 20 15

Surface Restoration (5, 6) 10 6.5

Resealing and Restoration of Skid Resistance (7, 8) 5.5 4.5

Routine Maintenance (9, 10) 0 0

Page 27: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Back of the envelope calculations

X 8

Women of Algiers - Picasso Intervention Budget Cost €Regional

Budget Cost €Local Primary

Road Reconstruction (1, 2) € 9,656,677.70 € 15,380,652.68

Structural Overlay (3, 4) € 110,545,967.52 € 176,967,980.19

Surface Restoration (5, 6) € 167,014,539.94 € 215,787,541.22

Resealing and Restoration of Skid Resistance (7, 8) € 253,014,152.44 € 258,069,257.00

Total € 540,231,337.60 € 666,205,431.08

Page 28: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

IPAG: Pavement Management Guidelines

• Asset Register (Roadways, Footways, Structures, Traffic Management, Markings etc)

• Network Referencing• Inventory and Data Management• Routine Maintenance ( categories of

intervention)• Condition Surveying and Rating• Pavement Asset Management Strategies• Reinstatements• New Roads and Taking in Charge

Options?

Page 29: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Asset Management Strategies:•Prioritisation

• Condition ( PSCI, Mech Survey)• Strategic Importance• Defects• Collision history• Repairs• Claims• Traffic (volume, hg, agricultural,

forestry)• Statutory undertakers works

•Cost by category of road or location•Role of Members

Page 30: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Asset Management Strategies:

•Are we all starting from the same place?

•Categories of road – standardisation?•Cost of maintenance for different locations•Efficiency

Page 31: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Asset Management Strategies:

•Performance Measures - KPIs?

•Roads Requiring Maintenance?•Roads surfaced?•Backlog (headline vs. maintenance)•When to intervene?•Consistency between MD’s?

Page 32: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Pavement Asset Management Strategies:

• Strategy at a National Level

• Plan at a local level

• Pilot sites in 2015/2016

• Increased flexibility

• Increased accountability

Page 33: Working together effectively Ag obair go héifeachtach le chéile Working together effectively Ag obair go héifeachtach le chéile The Road Management Office.

Working together effectively

Ag obair go héifeachtach le chéile

Thank you – come to our stand!