WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project...
Transcript of WORKFACE PLANNING CONFERENCE‐WIDE SESSIONgroupasi.net/conferencelibrary/2010/WFPC 2010...Project...
WORKFACE PLANNINGCONFERENCE‐WIDE SESSIONFROM CONCEPT TO COMMISSIONING
INTRODUCTION
• From Concept to Commissioning: what does it mean?
• Who is on the panel?
Ron Embury | Engineering Team Leader, NOVA Chemicals (Owner)
Ken Kohlruss | Vice President Operations, Commonwealth Construction [CH2M Hill] (CMT)
Jose Herrero | Vice President, Fluor (Engineering Contractor)
Tannis Liviniuk | Lead Construction Analyst, Cenovus Energy (Construction Contractor)
Lloyd Rankin | Researcher, COAA (Facilitator)
INTRODUCTION
Defines the basic design parameters for the intended project. Generation, review, and approval of the DBM is a prerequisite for the development of the Engineering Design Specification (EDS).
DESIGN BASIS MEMORANDUM (DBM)
DESIGN BASIS MEMORANDUM (DBM)
DBM: OWNER
DBM: OWNER
At the DBM phase, we have three documents that set the stage for WorkFace Planning:
• Project Execution Plan
• Construction Execution Plan
• Constructability Implementation Plan
DBM: OWNER
Project Execution Plan (PEP):
• Overall Project Milestone Schedule
• Project Strategy:
o The project will be Construction‐driven
o Engineering and Procurement will sequence their work to meet Construction needs.
o There will be extensive constructability input into the design and Engineering Work Package (EWP)
o WorkFace Planning will be part of the Construction Execution Plan
o No work packages (FIWPs) will start without all engineering, materials, tools, equipment and labour present on site.
o Owner‘s commissioning sequence will be by operating systems and will be introduced in the engineering and construction schedules.
Construction Execution Plan (CEP):
• With respect to WorkFace Planning, the construction execution plan will:
o Set out the Construction Management Organization.
o Describe the Contracting Strategy
o Contain the WorkFace Planning Execution Plan
Workface Planning Approach
Workface Planning Overview
Workface Planning Implementation
Workface Planning Training
Workface Audit Process
o Progress Reporting
DBM: OWNER
DBM: OWNER
Constructability Implementation Plan (CIP)
• CIP is developed and started in the DBM phase. CIP is used to support WFP concepts.
o Led by Construction
o Sponsor(s) identified, Policy Statements described and Constructability Manager is appointed.
o Sets out focus groups between engineering disciplines, Procurement, Owner, etc.
o High‐level construction sequence is developed.
o Details of schedule integration is developed between parties.
i.e., Engineering drawing sequence developed to support FIWP Schedule
i.e., Procurement deliverables developed to support FIWP Schedule.
o Various other activities are completed to promote ease of construction (design, layout, modular design, pre‐fabrication, construction methods, weather, etc.)
DBM: OWNER
Contract types:• C• CM• EP• EPC• EPCM
DBM: CONSTRUCTIONMANAGEMENT TEAM
1.0 Definition2.0 Purpose3.0 Scope4.0 Strategies5.0 Participants6.0 Roles and Responsibilities7.0 Method8.0 Systems9.0 FIWP’S Release Process10. Auditing
WorkFace Planning Execution Plan
DBM: CONSTRUCTION MANAGEMENT TEAM
High‐level project review which leads to Path of Construction
DBM: CONSTRUCTION MANAGEMENT TEAM
MAINTENANCE AISLEWAY
MAINTENANCE AISLEWAY
ROW M
ROW D
ROW C
ROW B
ROW D
ROW C
ROW B
MAIN PIPERACK
ROW A
ROW A
RO
W W
RO
W E
NORTH
SOUTH
2
3
1
Path of Construction
DBM: CONSTRUCTION MANAGEMENT TEAM
DBM: CONSTRUCTION MANAGEMENT TEAM
ConstructSim
V8i
DBM: CONSTRUCTION MANAGEMENT TEAM
DBM: CONSTRUCTIONMANAGEMENT TEAM
• Experienced trainers, educators and assessors (auditors)
• Assessment services
• Self‐assessment tools
DBM: ENGINEERING
DBM: ENGINEERING
999D 999E
999G
800C
999H
999B 999C
Sample plot plan (partial)
DBM: ENGINEERING
Click to see process
Click to see table of contents
DBM: ENGINEERING
PEOPLE TOOLS
PROCESSES
DBM: CONSTRUCTIONCONTRACTOR
• Demonstrate high‐level capacity to support WorkFace Planning
• WorkFace Planning Awareness for Trades People scheduled for delivery February 2011.
• Pre‐beta sample available at this conference
DBM: CONSTRUCTIONCONTRACTOR
WorkFace Planning Awareness for Trades People:
DBM: CONSTRUCTIONCONTRACTOR
WorkFace Planning Course Development Roadmap
DBM: CONSTRUCTIONCONTRACTOR
EDS defines all elements of project scope and is the control document for commencement of detailed engineering and procurement activities on the project. It is also used in scoping the development of the Authorization for Expenditure (AFE).
ENGINEERING DESIGNSPECIFICATION: DEFINITION
ENGINEERING DESIGNSPECIFICATION (EDS)
EDS: ENGINEERING
EDS: ENGINEERING
Level 2 Schedule
EDS: ENGINEERING
EWP Release Plan
WBI/EWP Structure • Activity code breaks down discipline code into different activities
Discipline Code
Model Type
0 Civil Works1 Concrete2 Structural Steel3 Buildings4 Equipment5 Piping6 Electrical7 Control Systems
U Underground
N New construction, stick built above ground
P Paving and Road.
L Miscellaneous steel
T Electrical Heat Tracing
F Equipment Fireproofing
DBM: ENGINEERING
EDS: ENGINEERING
Level 3 Schedule
EDS: CONSTRUCTION MANAGEMENT TEAM
Proactively resolve conflicts
EDS: CONSTRUCTION MANAGEMENT TEAM
Review and integrate WFP processes and support functions
EDS: CONSTRUCTIONMANAGEMENT TEAM
Ensure all databases are up to date
EDS: CONSTRUCTIONMANAGEMENT TEAM
EDS: CONSTRUCTION
Define and Issue CWP release plan
• Identify the size and description of all CWPs
• Determine when those CWPs will be developed and released
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
• The EWP schedule will be driven by the CWP schedule
EDS: CONSTRUCTION
Appoint lead planner and commence WFP process
EDS: CONSTRUCTION
Define and Issue FIWP release plan
• Identify the size and description of all FIWPs
• Determine when those FIWPs will be developed and released
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
• FIWP development is driven by the CWPs
EDS: CONSTRUCTION
DETAILED ENGINEERING
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
Construction develops and delivers CWPs
Detailed Level 4 Schedule
• This is a schedule of the release of the Field Installation Work Packages (FIWPs)
• These can be reported in Excel spreadsheets, Primavera schedules, and other documents
DETAILED ENGINEERING: CONSTRUCTION CONTRACTORS
Break CWPs into FIWPs
DETAILED ENGINEERING: CONSTRUCTION
CWP
FIWP
FIWP
FIWP
DETAILED ENGINEERING: CONSTRUCTION
DETAILED ENGINEERING: CONSTRUCTION
DETAILED ENGINEERING: ENGINEERING
DETAILED ENGINEERING: ENGINEERING
CONSTRUCTION PHASE
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
Implement and Release FIWP
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
Execute FIWP
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
One of our silver‐level sponsors ‐ Phoenix Industrial ‐ has incorporated their maintenance experience into the Phoenix WorkFace Planning approach.
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
Progress project
What if execution doesn’t go according to plan?
CONSTRUCTION PHASE: CONSTRUCTION CONTRACTOR
BACKLOG‘PLAN B’RISK
EVENTS
CONSTRUCTION PHASE: OWNER
WorkFace Planning Lessons Learned:
• Conduct Lessons Learned at the end of each phase of the project
• Do ‘temperature checks’ during each phase
• At the end of the project, conduct a final Lessons Learned.
CONSTRUCTION PHASE: OWNER
Two of our sponsors have been recognized by COAA, winning awards for their excellence and
leadership in WorkFace Planning.
WORKFACE PLANNINGEXCELLENCE
AUDIENCE FEEDBACK
NOTE: The information collected is anonymous and may be used for research purposes. By participating, you are giving your consent for the use of this data.