Work_Breakdown_Structure

6
7/30/2019 Work_Breakdown_Structure http://slidepdf.com/reader/full/workbreakdownstructure 1/6 Inter Agency Policy and Projects Unit Department of Premier and Cabinet Project Management Fact Sheet: Developing a Work Breakdown Structure Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that this material should not be relied upon by any other person. Furthermore, to the extent that ‘this material is relied upon’, the Crown in Right of the State of Tasmania gives no warranty as to the accuracy or correctness of the material or for any advice given or for omissions from the material. Users rely on the material at their own risk.

Transcript of Work_Breakdown_Structure

Page 1: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 1/6

Inter Agency Policy and Projects Unit

Department of Premier and Cabinet

Project Management

Fact Sheet:Developing a Work BreakdownStructureVersion: 1.2, November 2008

DISCLAIMER

This material has been prepared for use by Tasmanian Government agencies and Instrumentalities.It follows that this material should not be relied upon by any other person. Furthermore, to the extentthat ‘this material is relied upon’, the Crown in Right of the State of Tasmania gives no warranty as tothe accuracy or correctness of the material or for any advice given or for omissions from the material.Users rely on the material at their own risk.

Page 2: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 2/6

Page 2 Tasmanian Government Project Management FrameworkProject Management Fact Sheet: Developing a Work Breakdown Structure, Version: 1.2, November 2008

What is a Work BreakdownStructure?

The Work Breakdown Structure is ahierarchical breakdown of the work to bedone in the project. It takes each outputand shows in sequence, from general tospecific, all the activities and tasksrequired for its production. As such theWork Breakdown Structure (WBS) alsodefines the scope of work of the project – whatever is not in the WBS is outside thescope of work for the project.

Why would you develop a WorkBreakdown Structure?

 A WBS is developed to:

define what needs to be done in theproject and the order in which tasksshould be completed

determine resource allocation anddefine tasks for delegation and theskills set required

confirm a common understanding of the scope of work among ProjectSponsor, Steering Committee/senior management and Project Team

assist with the identification of milestones

assist with the preparation of a GanttChart

assist with budget estimation

assist with identification of projectrisks by showing areas of uncertainty

When would you develop a WorkBreakdown Structure?

The WBS is usually created at the start of the project, but may be created at anytime when the work to produce an outputneeds clarification.

What you need before you start 

 An agreed Project Business Plan or Project proposal or Brief , including alist of project outputs

Knowledge and understanding of the

project

Other References you may need 

Corporate/Business Plan for theDepartment/Business Unit

Tasmanian Government Project 

Management Guidelines Departmental Project ManagementGuidelines

What you will have when you are finished 

 A complete WBS that can be used to planresource allocation, determine the budget,create a Gantt chart, and determinemilestones. It may be useful to present tosenior managers to clarify planning

estimates and work required.

How do you develop a WorkBreakdown Structure?

 A WBS can be created using anytechnique of listing and grouping projectactivities and tasks. It can be a resourceintensive activity, depending on the levelof detail required. This example uses a topdown technique, starting with the project

outputs and breaking these down into theactivities that need to be completed toproduce each output. These activities arebroken down further into smaller tasks.

 Another useful approach is to use mindmapping, either by using software or stickynotes. Write down each output on aseparate note and brainstorm with theproject team to find all the tasks that wouldneed to be completed to deliver theoutput. Write these on separate notes and

place around each output. The tasks listedwill vary in size.

Try to break them into two levels: largetasks, or activities, and their associatedsmaller tasks. Move the notes around andkeep adding more until a structureemerges, see figure 1. As a guide eachoutput will have about seven activities,each activity will have about seven tasks.Tasks, activities and outputs can then beentered into the Work BreakdownStructure. 

Page 3: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 3/6

Page 3 Tasmanian Government Project Management FrameworkProject Management Fact Sheet: Developing a Work Breakdown Structure, Version: 1.2, November 2008

Figure 1: A mind map showing an output broken into seven activities and each activity broken intoseven tasks.

Output Activity

 Activity

 Activity

 Activity Activity

 Activity

 Activity

Tasks

Tasks

Tasks

Tasks

Tasks

Tasks

Tasks

Page 4: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 4/6

Work Breakdown Structure - <Project Title> 

Page 4 Tasmanian Government Project Management FrameworkProject Management Fact Sheet: Developing a Work Breakdown Structure, Version: 1.2, November 2008

Project Name

1. <Output name> 2. New software tool  3. <Output name> 4. <Output name> 5. <Output name> 6. <Output name> 7. <Output name>

<1.1 Activity>

< 1.1.1 Task >< 1.1.2 Task >

< 1.1.3 Task >

2.1 Plan the Purchase 

2.1.1 Conduct Market Research 

2.1.2 Design the specification.

2.1.3 Determine the purchasing method.

2.1.4 Develop an evaluation plan.

2.1.5 Develop a risk management plan.

2.1.6 Develop a contract management plan.

<1.2 Activity>

< 1.2.1 Task >

< 1.2.2 Task >Etc.

2.2 Prepare the Documentation 

2.2.1 Determine the conditions.

2.2.2 Finalise the specification.

2.2.3 Determine the contract conditions.

2.2.4 Develop a Tender Form.

2.3 Invite Tenders etc 

Page 5: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 5/6

 

Page 5 Tasmanian Government Project Management FrameworkProject Management Fact Sheet: Developing a Work Breakdown Structure, Version: 1.2, November 2008

How to use this table

The Table shows outputs, activities andtasks. Generally the project will need morethan one page! The second column givesan example of the breakdown of one

output into activities and tasks.

1. Write each output across the first rowof the table. Use as many columns andpages as necessary. This is the outputlevel.

2. Break each output down intosequential smaller units of work, calledactivities. These are all the things thatneed to be done to produce the output,in the order they need to be started.

There are usually about sevenactivities for each output. This is theactivity level.

3. Write each activity in a separate cell inthe output column.

4. Break each activity into sequentialsmaller units of work, called tasks.Write these in the same cell as theactivity. This is the task level.

5. Review the list to check that theactivities and tasks seem appropriatelygrouped in terms of complexity. For example a task might be so complexthat it needs to be considered as anactivity, in its own right. This is simplya judgement call, there is no formulafor determining at what level a unit of work should sit.

6. Check to see that completion of eachgroup of tasks will result in thecompletion of activity above it. Checkthat the completion of each group of 

activities will result in the completion of the output above it. For examplefinishing all the activities that belong tothe output will mean that the outputitself will be completed. Move theactivities and tasks around asnecessary.

7. Finally, give each item on the list aunique identifier to use as a reference.

Note: Activities and tasks are written in thepresent tense using action verbs, for example ‘assemble team’, ‘develop model’and ‘sign lease’. 

 A number of different text styles have been

used within the Table, as follows:

Text in italics is intended to provide aguide as to the kind of information thatcan be included in a section and towhat types of projects it might beapplicable

Text enclosed in <angle brackets> isintended to be replaced by whatever itis describing

Using the Work Breakdown

Structure

Resource allocation 

The WBS can be used to determineresource allocation, such as budget, in aprocess known as bottom-up estimation.This involves determining resources,including budget requirements, for eachtask on the WBS. The ‘above the line’ or project management activities will alsoneed to be considered when using this

approach. As a guide ‘above the line’activities will take about 15% of the time of the project team. It is also advisable toinclude an allowance for contingencies; aguide level is 10%. (Refer to the Project Management Fact Sheet: Project Estimation) 

Developing a Gantt Chart 

 A Gantt Chart is a horizontal bar chart. Itshows all the project activities and tasksfrom the WSB in sequential order with the

bars representing the time estimated tocomplete them. The chart graphicallydepicts the time relationship of activities,tasks, and resources in a project. It canalso show milestones (see below).

It is a flexible document and is regularlyupdated through the life of the project.(Refer to the Project Management Fact Sheet: Developing a Gantt Chart)

Page 6: Work_Breakdown_Structure

7/30/2019 Work_Breakdown_Structure

http://slidepdf.com/reader/full/workbreakdownstructure 6/6

 

Page 6 Tasmanian Government Project Management FrameworkProject Management Fact Sheet: Developing a Work Breakdown Structure, Version: 1.2, November 2008

Identifying project milestones 

Milestones are significant events that actas progress markers for a project and their achievement is monitored and reported.The hierarchical structure of the WBS can

assist in identifying project milestones asthey are usually linked to the delivery of outputs or the completion of key projectactivities. The Gantt Chart can be used toidentify milestone dates. (Refer to theProject Management Fact Sheet:  Developing a Gantt Chart) 

Other things to consider:

Interdependencies 

Where there are programs of projects, or 

large and/or complex projects, possiblydivided into sub-projects, it is important todefine the interdependency managementprocesses to be applied. In other words,how will critically related activities bemonitored and managed.

For further exploration of this issue, seethe Tasmanian Government Project Management Guidelines: Section 9.0 Project/Program Integration. 

Critical Path 

In estimating timeframes the Critical PathMethod (CPM) is often used. The CriticalPath is the chain of activities that links thestart to the finish of the project, and for 

which any delay will cause the project to bedelayed by the same amount of time. Project Managers, who need to shorten theduration of their project, work on the criticalpath tasks and add resources and changepredecessor relationships to shorten their critical path tasks.

(Refer to the Project Management Fact Sheets: Project Estimation Developing a Milestone History Monitor )

Where to get additional help

Refer to the Tasmanian Government Project Management Guidelines. 

The Inter Agency Policy and ProjectsUnit offers further advice andassistance, including a formal Advisoryand Review Service.

Contact Project Services [email protected] 

Further information and resources areavailable fromwww.egovernment.tas.gov.au 

Acknowledgements

This Fact Sheet contains elements of the Tasmanian Government Project Management Guidelines prepared by the Department of Premier and Cabinet.