Work Study – Method Study and Work Measurement

download Work Study – Method Study and Work Measurement

of 23

Transcript of Work Study – Method Study and Work Measurement

  • 8/14/2019 Work Study Method Study and Work Measurement

    1/23

    Work Study Method Study and Work Measurement

    Work Study

    Body of Knowledge [BoK] to improve the productivity of jobs:

    -by better ways of doing jobs : analysis of work methods & equipment

    used / design of optimum method / standardisation of proposed

    method

    -by better Control over the output of jobs

    -by better standards with respect to time

    -by obtaining cooperation between management and workers for

    maximum mutual prosperity

    Method Study Work Measurement-Systematic Recording of existing method

    -Critical examination of existing method

    -Developing improved / easier / cheaper /

    more effective method

    -Application of techniques designed

    to establish the time for a qualified

    worker to carry out a specified job at

    a defined level of performance

  • 8/14/2019 Work Study Method Study and Work Measurement

    2/23

    Work Study

    Qualified Worker [ILO]:

    -Necessary Physical Attributes

    -Required intelligence

    -Required Education

    -Acquired necessary skill and knowledge

    -Capable of carrying out the job with satisfactory level of safety standards,

    quantity and quality

    Foundation of work study:

    Scientific ManagementFW Taylor, Frank Gilbreth & Lillian Gilbreth

    Taylorism.The greatest production results when each worker is given a definite task to be

    performed in a definite time in a definite manner.

    What can be measured is controllable.

  • 8/14/2019 Work Study Method Study and Work Measurement

    3/23

    Work Study

    Objectives of Work Study

    To analyse the present method of doing a job to better the method

    -To measure the work content of a job by measuring the time required to do the jobby a qualified worker to establish a standard time

    -To devise the most suitable method of doing the job by ensuring the best possible

    use of human, machine and material resources to produce quality product at

    optimum cost

    -To improve operational efficiency

    Benefits of Work Study

    -Increased Productivity -Better Operational efficiency

    -Reduced manufacturing cost -Better employee morale

    -Better plant layout / working conditions -Better Job satisfaction

    -Better planning -Better incentive schemes

    -Improved work flow -Better labour efficiency standards

  • 8/14/2019 Work Study Method Study and Work Measurement

    4/23

    Work Study

    Method Study Work Measurement

    Operation Process Chart

    Flow Process Chart

    Man-Machine Chart

    Motion Study [Gilbreths]

    Memomotion Study [Mundel]

    Direct Time Study [Taylor]

    Synthesis Method

    Analytical Estimatimg

    Pre-determined Motion

    Time System [PMTS]

    Work Sampling / Activity

    Sampling / Ratio-Delay Analysis

    Components and Methods / Techniques

  • 8/14/2019 Work Study Method Study and Work Measurement

    5/23

    Work Design

    Method Study /

    Operations Analysis

    Work

    Measurement

    Motion

    Study

    Time

    StudyUsed to find

    the fastest

    motion

    sequences

    Used to

    evaluate

    alternatedesign /

    methods

    Developed by Gilbreths Developed by Taylor

    Objective:Improve

    Operations

    Objective:Improve

    Planning & Control

    Relationship of Motion and Time Study to Work design

    Work Study

  • 8/14/2019 Work Study Method Study and Work Measurement

    6/23

  • 8/14/2019 Work Study Method Study and Work Measurement

    7/23

    Work Study Procedure

    -Selectthe job / process / operation

    *High Operating Cost *Frequently repeated job *Very bad product quality

    *Bottleneck to other jobs *Labour intensive *Safety hazard *Bad working conditions*Excessive material movements *High Return on Investment etc.

    -Observe andRecord sequence / interrelationship / movement of activities

    *Operation process chart *Flow process chart *Motion chart *SIMO *Man-Machine

    Charts etc.

    -Examinethe current method. Look for ways in which tasks can be eliminated, combined,rearranged, and simplified. 5W2H

    -Developthe most practical, economic, and effective method. Obtain approval for the new

    method

    -Measurethe work content and establish the standard time

    *Time study *Synthesis method *Analytical estimating method *PMTS *Worksampling

    -Define the new / improved method. Tools / materials / operator skill / working conditions

    -Install / implement the new method as standard practice

    -Maintain the new / improved method by periodically checking it in use

    Work Study

  • 8/14/2019 Work Study Method Study and Work Measurement

    8/23

    Work Study

    5W2H Typical Questions for Processes Improvement Questions

    Who?

    Who does this?

    Who should be involved but is not?

    Who is involved but shouldnt be?

    Who has to approve?

    Should someone else do it?

    Could fewer people do it/

    Could approvals be eliminated?

    What?What is done?

    What is essential?

    Does every step have to be done?

    Are steps omitted?

    When?

    When is this activity started?

    When does it end?

    When is it repeated?

    Can it be done at a different time?

    Can cycle time be shortened?

    Can it be done less frequently?

    Where? Where is this activity done? Can it be done elsewhere?

    Why?Why do we do this? Can it be eliminated?

    Can another group do it?

    Can it be outsourced?

    How/ How is this done? Is there a better way?

    How

    much/many?

    How much does it cost? How much less could it cost?

    5W2H Questions

  • 8/14/2019 Work Study Method Study and Work Measurement

    9/23

    Work Study

    Objectives of Method Study

    -To study the existing / proposed method of doing any job

    -To develop an improved method to improve productivity

    -To reduce excessive material handling

    -To improve utilisation of resources

    -To eliminate wasteful and inefficient motions

    -To standardise work methods or processes

    Advantages of Method Study

    *Work simplification * Improved method

    *Better product quality * Better layout

    * Improved work flow * Better material handling

    * Shorter production cycle time * Higher job satisfaction

    *Improved productivity

  • 8/14/2019 Work Study Method Study and Work Measurement

    10/23

    Operation Process Chart

  • 8/14/2019 Work Study Method Study and Work Measurement

    11/23

    Work Study

    Recording Techniques in Method Study

    Cast

    Waits until

    inspection

    Inspect casting

    To buffing section

    Buffing / Polishing

    Inspect

    Store

    Flow Process Chart

    Left Hand Right Hand Machine

    Pick-up

    plate

    0.05

    Dip plate

    0.03

    Place

    plate

    0.03

    Idle

    Unload

    machine

    0.04

    Idle

    Pushbutton

    0.01

    Idle

    Being

    Unloaded

    0.04

    Idle

    Punch

    0.02

    Return

    0.02

    Man-Machine Chart

  • 8/14/2019 Work Study Method Study and Work Measurement

    12/23

    Work Study

    Motion Study

    It is the science of eliminating unwanted and or unnecessary motions in carrying

    out any jobs. The objective of motion study is to identify and implement the scheme

    of the least waste methods of labour. Micro Motion Study provides a valuabletechnique for making accurate analysis of operations.

    Purpose of Motion Study:

    -To study interrelationship among team members

    -To study interrelationship between operator and machine

    -To obtain the time of an operation

    -To establish a permanent record of the method of doing a job

    Micro Motion Study of operations is done by filming the operations and then

    analysing the film to make SIMO charts. Very small time values (1/2000 minute)are used [micro-chronometer]. A job is divided into micro motions which are known

    as Therbl igs.

  • 8/14/2019 Work Study Method Study and Work Measurement

    13/23

  • 8/14/2019 Work Study Method Study and Work Measurement

    14/23

  • 8/14/2019 Work Study Method Study and Work Measurement

    15/23

    Work Study

    Work Measurement

    Objectives:

    -Improved planning and control of jobs -Efficient manning of the plant-Reliable ideas for labour performance -Reliable basis for labour cost control

    -Basis for sound incentive scheme

    Benefits:

    -Basis for comparing alternate methods -To prepare work accurate schedules

    -To set labour performance standards -To compare actual& standardtimes

    -To make labour cost estimation -To estimate tenders / price / delivery

    Techniques:

    -Direct e Study -Synthesis method

    -Analytical Estimating -Pre-determined Motion Time Systems

    -Work Sampling or Activity Sampling or Ratio Delay Method

  • 8/14/2019 Work Study Method Study and Work Measurement

    16/23

    Work Study

    Time Study

    Time Study is concerned with the determination of the amount of time required to perform a

    unit of work.

    ILO defines it as: Time Study is a work measurement technique for recording the times andrates of working for the elements of a specified job carried out under specified conditions and

    for analysing the data so as to obtain the time necessary for carrying out the job at a defined

    level of performance.

    Objectives:

    -To determine the quantum work

    -To establish the Standard time

    -To furnish basis for comparison

    -To set labour standard

    -To determine standard costs

    -To balance the work in assembly line

    -To set piece rate incentives

    -To set completion schedule

    -To determine cycle time of job

    Criteria for selection:

    -New job for production

    -Change in manufacturing method

    -Design change

    -Employee complaint about Standard

    time

    -Bottleneck operation-Highly labour intensive

    -Job to be included in incentive

    scheme -For new tooling and

    fixtures

  • 8/14/2019 Work Study Method Study and Work Measurement

    17/23

    Work Study

    Work Sampling

    It is a statistical sampling method to estimate the proportion of time devoted to a given type of

    activity over a certain period of time by means of a large number of random spot

    observations. Particularly useful to estimate the delays [ratio-delay analysis] such as:

    Supply failures

    Supply delays

    Machine breakdowns

    Manpower idling etc.

    The larger the number of observations, the better the estimate (Accurate).

    Uses of Work Sampling:

    * To estimate time used by Operators and Machines

    * To determine allowances to include in Standard times* To indicate the distribution of work among group members

    * To provide basis for indirect labour time standards

    * To determine productive and non-productive utilization of manpower

    * To determine the standard time for repetitive operations as an alternative to time study

  • 8/14/2019 Work Study Method Study and Work Measurement

    18/23

    Work Study

    OT

    PRF

    PA

    RA

    CA

    SA

    PoA

    NT / BT

    ST

    AT

    Legend

    OT -> Observed Time.

    PRF -> Performance Rating Factor

    NT / BT -> Natural / Basic Time

    PA -> Process Allowance

    RA -> Relaxation Allowance

    CA -> Contingency Allowance

    SA -> Special Allowance

    *Interference Allowance

    *Periodic Activity

    Allowance

    ST -> Standard TimePoA -> Policy Allowance

    AT -> Allowed Time

    Computation of Standard Time and Allowed Time

  • 8/14/2019 Work Study Method Study and Work Measurement

    19/23

    Work Study

    Exercise -01

    Calculate the standard time per article produced from the following data

    obtained by a work sampling study.

    Total no of observations : 3000.

    Working observations : 2500.

    No of units produced during 100 hrs duration = 6000.

    Proportion of manual labour = 75%. Proportion of machine time = 25%.

    Observed rating factor for manual labour = 120%.

    Total allowances = 15% of normal time.

  • 8/14/2019 Work Study Method Study and Work Measurement

    20/23

    Work Study

    Exercise - 02

    Given below is the data regarding production of units:

    Direct material price = Rs. 2.

    Wage rate Rs 2000 per month consisting of 25 working days and 8 hours perday.

    Overheads expressed as percentage of direct labour = 200%.

    Time taken to manufacture 4 units each consisting of 4 elements a, b, c, d

    during 4 cycles given below:

    Element Cycle Cycle 2 Cycle 3 Cycle 4 ElementperformanceRatingabcd

    1.20.71.40.5

    1.30.61.30.5

    1.30.651.30.6

    1.40.751.20.4

    851209070

    Calculate standard time, labour cost, overhead cost, total production cost

    per piece, given the personal, fatigue and delay allowances as 25%.

  • 8/14/2019 Work Study Method Study and Work Measurement

    21/23

    Work Study

    Exercise - 03

    A 8 hours work measurement study in a plant reveals the following:

    Units produced = 320 nos. Idle time 15%. Performance rating = 120%.Allowances = 12% of normal time. Determine the standard time per unit

    produced.

  • 8/14/2019 Work Study Method Study and Work Measurement

    22/23

    Work Study

    Exercise - 04

    The following data refers to the study conducted for an operation. Table shows

    actual time for elements in minutes:

    Cycle Elements 1 2 3 4 5

    1 2.5 2.1 2.2 5.4 2.5

    2 6.2 6.0 6.1 5.9 5.9

    3 2.3 2.0 2.1 2.1 2.2

    4 2.4 2.1 2.8 3.0 2.3

    1) Element 2 is a machine element

    2) Consider the observations as abnormal and delete the same if they are

    more than 2% of the average time of that element.

    3) Take performance rating as 120.

    4) Allowances are

    Personal30 minutes in a shift of 8 hours

    Fatigue15%

    Contingency2%

    Estimate the standard time of operation and production per 8 hour shift.

  • 8/14/2019 Work Study Method Study and Work Measurement

    23/23

    Work Study

    Exercise - 05

    A job has been divided into five elements 1,2,3,4&5. The element times for the

    first 5 cycles along with performance rating are given in the following tables:

    ElementCycle time in minutes Performanc

    e(%)

    Cycle-1 Cycle-2 Cycle-3 Cycle-4 Cycle-5

    1 1.84 1.77 1.78 2.02 1.79 95

    2 1.11 1.42 1.16 1.29 1.25 110

    3 2.46 2.39 2.34 2.36 2.30 90

    4 1.48 1.55 1.72 1.63 1.51 100

    5 1.72 1.81 1.65 1.76 1.79 115

    Determine the estimated normal time for the job.

    Calculate the standard time if the permissible total allowance is 25% of

    normal time.