Work Shop - Construction Materials Quality Control

download Work Shop - Construction Materials Quality Control

of 34

Transcript of Work Shop - Construction Materials Quality Control

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    1/34

    www.unops.org

    Construction Materials

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    2/34

    1. Fulfillment of Requirements

    Material Requirements

    Process Requirements Equipment Requirements

    End Product Requirements

    2. Fitness for Purpose

    Riding comfort at design speed Ability to serve till the end of design life at design level of

    serviceability

    What is Quality in Construction?

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    3/34

    Quality is generally to mean compliance withspecified requirements

    Quality control is a means to control quality i.e.to verify compliance of materials, equipment,process and final product to predetermined

    requirements.

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    4/34

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    5/34

    Fine Aggregates (Sand)No. Inspection and TestingDescription

    Testing

    method

    Acceptance criteria Frequency of Test

    1

    Grading

    AASHTO T-27 Sieve(mm) % pass

    10 100

    4.76 95-100

    2.38 68-861.19 47-65

    0.59 27-42

    0.3 9-20

    0.15 0-7

    0.075 0-2.5

    One sample per 1500 m3

    2 Soluble chlorides BS 812

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    6/34

    Rapid field Technique to Estimate silt content

    River or pit sand shouldbe sharp, angular, hard,clean uncoated particles

    free from clay andorganic impurities.

    Well graded sand must beused for all cement work.

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    7/34

    Coarse Aggregate (Gravel)No. Inspection and Testing

    Description

    Testing method Acceptance criteria Frequency of Test

    1Grading

    AASHTO T-27 Different for different

    nominal sizes

    One sample per 1500 m3

    2 LAA AASHTO T-96

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    8/34

    WaterNo. Inspection and Testing

    Description

    Testing method Acceptance criteria Frequency

    of Test

    1 Chloride content ASTM D 512

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    9/34

    Cement

    No. Inspection and

    Testing Description

    Testing

    method

    Acceptance criteria Frequency

    of Test

    1cement

    AASHTO T-

    131

    AASHTO M-85 Every lot

    1.1 Consistency test AASHTO M-85 Every lot

    1.2 Initial setting time AASHTO M-85 Every lot

    1.3 Final setting time AASHTO M-85 Every lot

    The cement to be used in the work should be ordinary Portlandcement complying with ASTM C-150 or BS-12.

    Both Roads and Building specifications of UNOPS specify OPC,not PPC

    Hardened cement will not be permitted in the works and is tobe removed from site at the contractors expense.

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    10/34

    Brick

    Brick must have correct size, shape and sharp edges.

    Bricks shall not break when dropped from 1m height, shall give ringingsound when struck with each other and leaves no impression withfinger nail

    1. Mortar joint thickness shall not exceed 10mm in the class bricksand 12mm in second class bricks

    2. Crushing strength (shall not be less than 35kg/sqcm for ordinarybricks) and water absorption (shall be less that 20%) waterabsorption dry the bricks and weigh (w1), immerse in water for24 hours and weigh again (W2). Then WA=(w2-w1)/W1*100 orA Brick shall not absorb more than 1/6th of its weight ofwater after being soaked for one hour

    3. Bricks shall be soaked at least for 1 hour before use

    4. Bricks work should be raised uniformly and height of work in a dayshall be less than 1.5m. Difference in height between two different

    portions shall be less than 1m

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    11/34

    Shall be regular and uniform in size and shape with sharp square edges andparallel faces.

    They shall be free from flaws, cracks and chips.

    should have the following dimensions: 400mm x 200mm x 200mm.

    There should be a longitudinal groove with 10mm depth and 20mm width oneach block in order to provide place forhorizontal steel reinforcement for themasonry work.

    Sample shall be collected randomly and tested every 10m3 of blocks produced.Three samples (blocks) shall be selected at random from every batch.

    The crushing strength of blocks shall be tested in a laboratory and the averagecrushing strength of blocks shall not be less than 15MPa (10 MPa) ??? (N/m2)and the water absorption of the blocks shall be not more than 240kg/m3 ofconcrete.

    Blocks

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    12/34

    Timber shall be free from twists, knots, splits and other visual or physicaldefects

    TIMBER

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    13/34

    Examples of Poor Materials

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    14/34

    Process Control

    The assistant engineers shall always be at site to inspect and control thecontractors work processes.

    Contractors always give priority for profit than for quality. Therefore, willgo for cheaper materials .

    When you do process control, strictly ad

    here to t

    he Specifications

    A number of factors should be controlled during construction as a vital partof process Control:

    Material - is the contractor using approved material?

    Mixing is the contractor using proper mix ratios? Proper mixingtechniques?

    Moisture content is the contractor applying proper water content?Thickness / Lift what is the maximum thickness or lift specified forearth work, brick work, concreting etc?

    Compaction what equipments are used during compaction?Whatare the number of passes?What is the sequence/direction passingduring compaction? etc

    General finish what is the quality of the final product?

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    15/34

    Examples of Poor Process Control

    Top soil and Overburden were notremoved properly due to weakness inprocess Control

    Removal of overburden of the sameborrow pit after PM and ME instruction

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    16/34

    Poor Process Control Excessive material spreading with outclearing the road bed

    The maximumallowed thicknesswas 200m

    The road bedshould have beencleared properlybefore dumping

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    17/34

    Poor workmanship, Substandard work, and poor Masonrystones due to Poor Process Control during Culvert apron

    construction

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    18/34

    Excessive Back Fill and Dry Compaction byContractor Lack of Process Control

    Maximum allowed thickness of compaction at a time was 150mm butcontractor is filling 1000mm at a time

    Contractor is supposed to apply optimum moisture to the back fill, but

    prefer to compact it dry

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    19/34

    Improper Soaking of CBR test specimens Poor

    Process Control

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    20/34

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    21/34

    End Product Specification

    e.g. RoadIs the surface free from compaction planes, ridges, cracks, loose material andmovement under construction equipment?

    Has the loose, segregate and otherwise defection areas made good to full depth?

    Is the thickness of the layer in limits?The size of the coarse material does not exceed 2/3 of layer thickness?

    Does the rolling pattern confirm to specification?

    Does survey results conform confirm to requirements grade, cross fall, side ,surface levels, slopes etc

    Moisture content prior to compaction ok?

    Is Degree of Compaction acceptable?

    Is the thickness as per the design?

    Then Approve the layer!

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    22/34

    How can we control Quality of ConstructionMaterials in Particular and constructionactivities in General?

    1. By Inspection and Process Observation

    2. By Random sampling

    3. By Testing

    4. By Measuring

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    23/34

    InspectionInspection of Storage of Construction MaterialsSI. No Material/pr

    oduct

    Storage Precaution(Do`s and

    Donts)`Location Method

    1 Rebar open Store on timber

    Runners or concretebeam

    1. Dont mix different

    dais.2. Cover with

    polythene sheet in

    rainy season

    3. Dont block access

    to vehicle

    2 Cement Bag Shelteredstore Placed on pallets lifted300mm above ground. 1. Dont allow contact withmoisture or side walls

    2. Dont exceed 12 bags

    stacking

    3 Concrete

    pipes

    Curing tank

    for 7 days

    Open Stack yard Proper ramp is made for

    loading & unloading

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    24/34

    Testing/Inspection Item Yes No

    Has the pipe culvert location been excavated as per the drawings

    Have the bed levels of the excavation been checked as per the

    drawings

    Has the type of bedding specified in the drawing or ordered by the

    engineer constructed

    Is the manufactured or imported pipe culvert is as per the Technical

    Specification

    Are the installed pipe culverts are free of defects like crack

    Have the jointing of the pipes done properly and collars satisfactorilygrouted

    Has the pipe culvert invert elevation checked as per the drawings

    Does the pipe culvert bed slope conform to the drawings

    Have the pipes culvert been backfilled according to the Technical

    Specification

    Have th

    eh

    eadwalls constructed as per th

    e drawings and inconformance to the Technical Specification

    Inspection for Different types of Construction

    Pipe Culvert Installation

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    25/34

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    26/34

    Testing/Inspection Item Yes No

    Has the foundation location been excavated as per the drawings

    Have the bed levels of the foundation excavation been checked as per

    the drawings

    Have the form works and reinforcements of the Footing, Abutment,

    Piers, Girders and slab being properly spaced as per the drawings.

    Has the proportion of the concrete mix been as per the mix design

    proportion

    Have cube and/or cylinder samples taken for concrete compressive

    strength

    Has slump test taken frequently

    Has the minimum compressive strength obtained

    Has the slump test satisfactory

    Has backfilling at the abutment, piers and footings done properly

    Has the bearings, and filter media placed properly

    Have the pre cast Concrete beam placed properly on the abutments

    and piers

    Is the Expansion joint as per the drawings

    Inspection for Bridges

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    27/34

    Testing/Inspection Item Yes No

    Working drawing checked and approved

    Latest revision being used

    Bar schedules approved

    Reinforcing steel material approved

    Bar bending and cutting satisfactory

    Corrosion treatment of bars, if required,

    satisfactory applied

    Bar size and spacing correct

    Bar lap length and location correct

    Bar tied as specified Bar assembly rigid and adequately supported

    Cover to bottom bars correct

    Cover to side bars correct

    Cover to top bars correct

    Cover blocks approved including fixing

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    28/34

    Description Yes No Not available

    Method statement approved

    Batching plant mixers in working order(separate dispenser for admixture, if required,

    available)

    Stand by batchers in working order

    Water , sand, coarse aggregate, cement, admixture approved

    Water, sand, coarse aggregate, cement, cement stock sufficient.

    Concrete conveying arrangement (including transit mixers) available in working condition

    and of sufficient capacity

    Formwork approved

    Reinforcement approved

    Pre stressing sheathing approved

    Concreting equipment in working order

    Stand by crane, vibrators present

    Tremie in working order (for under water work)

    Concrete ganging present, including carpenter, steel fixer, mechanics and electrician

    Access provided

    Safety arrangements adequate

    Lighting provided

    Communication between various points provided

    arrangements for arranging suspension/stoppage of concrete provided

    curing arrangements made

    laboratory notified

    Inspection for Concrete works

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    29/34

    Description Yes No

    Are the site, orientation and plan of the buildings approved?

    Is the site layout as per the drawings?

    Is the foundation material of the buildings acceptable for the superstructure load or need

    improvement?

    Is the foundation material compactedsatisfactorily?

    Are the materials for masonry work like stone, sand and water approved?

    Is the stone for masonry work shaped and dressed satisfactorily?

    Is the mortar mix proportion as per the standard requirements of UNOPS?

    Is the hardcore and masonry works constructed as per the drawings and site condition?

    Is the backfill in foundation construction made with approved material?

    Is the back fill material compacted to satisfactory level?

    Is the reinforcement arrangement of the grade beam, beams and columns (if any) as per the

    drawings?

    Is the proportion of cement, sand and coarse aggregates for grade beam and column as per the

    UNOPS standards?

    Is the walls constructed with fiber cement or other approved material?

    Are the walls double and filled with insulating materials?

    Is the fittings of the buildings are provided as per the drawings, and UNOPS spec?

    Is the floor of the buildings as per the requirements of UNOPS spec?

    Is the building painted with approved paint?

    Is the paint work maintained regularly?

    Inspection for Building

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    30/34

    Procedures

    Quantity

    Location

    Time

    Representative sampling?

    Sampling

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    31/34

    Testing

    Standards Common standards are ASTM, BS,AASHTO

    Laboratory management Joint Laboratory,Separate Laboratory, External Laboratory

    Contractors will manipulate results to their

    interest if there is no proper control duringtesting

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    32/34

    The quantity of the sources

    Visual uniformity/variability of the sources

    Intended use (more critical materials require exhaustivetesting)

    Quality of the sources (more tests will be made on marginalsources)

    Type of tests (more number of tests will be made for moreimportant requirements)

    The minimum number of tests, however, will not be generallybelow three.

    Procedures forM

    aterials Source Approval

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    33/34

    Problem soils in Construction

  • 8/3/2019 Work Shop - Construction Materials Quality Control

    34/34

    When we build Let us think that we buildforever, Let it not be for the present

    delight!!!

    Thank You!