    Work Measurement

  • 8/14/2019 Work Measure

    2/35

    Work Measurement

    application of techniques designed to

    establish the time for a qualified worker tocarry out a specified job at a defined level

    of performance

  • 8/14/2019 Work Measure

    3/35

    Why use Work Measurement

    Set time standards for a job

    Schedule work and allocate capacity

    Labor content of items producedLabor content of items produced

    Staffing needsStaffing needsCost and time estimatesCost and time estimates

    Crew size and work balanceCrew size and work balance

    Expected productionExpected production

    Basis of wage incentive plansBasis of wage incentive plans

    Efficiency of employeesEfficiency of employees

  • 8/14/2019 Work Measure

    4/35

    Basic Procedure

    Select

    Record

    Examine

    Measure

    Compile Define

  • 8/14/2019 Work Measure

    5/35

    TechniquesTechniques

    DirectDirect

    Time studyTime study

    Work samplingWork sampling

    IndirectIndirect

    Predetermined motion-time data systems (PTMS)Predetermined motion-time data systems (PTMS)

    Elemental dataElemental data

  • 8/14/2019 Work Measure

    6/35

    Time Study

    work measurement technique for recording

    the times and rates of working for the

    elements of a specified job carried outunder specified conditions, and for

    analysing the data so as to obtain the time

    necessary for carrying out the job at adefined level of performance

  • 8/14/2019 Work Measure

    7/35

    Rating

    assessment of the workers rate of working

    relative to the observers concept of the rate

    corresponding to standard pace usually expressed in decimal form

    a person working 10% faster than normal

    would have a Performance Rating of 1.10 or110% of NT

    working 10% slower, 0.90 or 90% of NT

  • 8/14/2019 Work Measure

    8/35

    Time StudyTime Study

    Involves timing a sample of a workersInvolves timing a sample of a workersperformance and using it to set a standardperformance and using it to set a standard

    Requires trained and experiencedRequires trained and experiencedobserversobservers

    Cannot be set before the work isCannot be set before the work isperformedperformed

  • 8/14/2019 Work Measure

    9/35

    Time StudyTime Study

    1.1. Define the task to be studiedDefine the task to be studied

    2.2. Divide the task into precise elementsDivide the task into precise elements

    3.3. Decide how many times to measure theDecide how many times to measure thetasktask

    4.4. Time and record element times and ratingTime and record element times and ratingof performanceof performance

  • 8/14/2019 Work Measure

    10/35

    Time StudyTime Study

    5.5. Compute average observed timeCompute average observed time

    AverageAverageobservedobservedtimetime

    Sum of the times recorded toSum of the times recorded to

    perform each elementperform each elementNumber of observationsNumber of observations

    ==

    6.6. Determine performance rating andDetermine performance rating andnormal timenormal time

    Normal time =Normal time =AverageAverageobservedobserved

    timetime

    PerformancePerformancerating factorrating factor

    xx

  • 8/14/2019 Work Measure

    11/35

    7.7. Add the normal times for each element toAdd the normal times for each element todevelop the total normal time for the taskdevelop the total normal time for the task

    8.8. Compute the standard timeCompute the standard time

    Standard time =Standard time = Total normal timeTotal normal time1 - Allowance factor1 - Allowance factor

    Standard time = NT(1 + Allowance factor)Standard time = NT(1 + Allowance factor)

    Time StudyTime Study

  • 8/14/2019 Work Measure

    12/35

    Allowances

    Personal

    Needs

    Basic

    Fatigue

    FixedAllowances

    VariableAllowances

    Relaxation

    Contingency

    Policy

    Special

    Total

    Allowances

    Stress & Strain

    environmental

  • 8/14/2019 Work Measure

    13/35

    Time Study Example 1

    You want to determine the standard time forYou want to determine the standard time for

    a job. The employee selected has produceda job. The employee selected has produced

    20 units of product in an 8 hour day. You20 units of product in an 8 hour day. You

    estimate that the employee worked about 10estimate that the employee worked about 10percent faster than what is a normal pacepercent faster than what is a normal pace

    for the job. Allowances for the jobfor the job. Allowances for the job

    represent 25 percent of the normal time.represent 25 percent of the normal time. What are the normal and standard times forWhat are the normal and standard times for

    this job?this job?

  • 8/14/2019 Work Measure

    14/35

    Time Study Example 1

    Normal time = Time worked x (Perf. rating)

    Number of units produced

    = (480 minutes/20) x (1.10)

    = 26.4 minutes

    Standard time = NT (1+ Allowances)

    = (26.4) * (1+0.25)

    = 33 minutes

  • 8/14/2019 Work Measure

    15/35

    Time Study Example 2Time Study Example 2

    Average observed time = 4.0 minutesAverage observed time = 4.0 minutesWorker rating = 85%Worker rating = 85%Allowance factor = 13% of total work periodAllowance factor = 13% of total work period

    Normal time = (Average observed time) x (Rating factor)Normal time = (Average observed time) x (Rating factor)

    = (4.0)(.85)= (4.0)(.85)

    = 3.4 minutes= 3.4 minutes

    Standard time = = =Standard time = = =Normal timeNormal time

    1 - Allowance factor1 - Allowance factor

    3.43.4

    1 - .131 - .133.43.4

    .87.87

    = 3.9 minutes= 3.9 minutes

  • 8/14/2019 Work Measure

    16/35

    Time Study Example 3Time Study Example 3

    Allowance factor = 15% of total timeAllowance factor = 15% of total time

    PerformancePerformanceJob ElementJob Element 11 22 33 44 55 RatingRating

    (A)(A) Compose and type letterCompose and type letter 88 1010 99 21*21* 1111 120%120%

    (B)(B) Type envelope addressType envelope address 22 33 22 11 33 105%105%

    (C)(C) Stuff, stamp, seal, andStuff, stamp, seal, and 22 11 5*5* 22 11 110%110%sort envelopessort envelopes

    Cycle Observed (in minutes)Cycle Observed (in minutes)

    1.1. Delete unusual or nonrecurring observations (marked with *)Delete unusual or nonrecurring observations (marked with *)2.2. Compute average times for each elementCompute average times for each element

    Average time for A = (8 + 10 + 9 + 11)/4 = 9.5 minutesAverage time for A = (8 + 10 + 9 + 11)/4 = 9.5 minutes

    Average time for B = (2 + 3 + 2 + 1 + 3)/5 = 2.2 minutesAverage time for B = (2 + 3 + 2 + 1 + 3)/5 = 2.2 minutes

    Average time for C = (2 + 1 + 2 + 1)/4 = 1.5 minutesAverage time for C = (2 + 1 + 2 + 1)/4 = 1.5 minutes

  • 8/14/2019 Work Measure

    17/35

    3.3. Compute the normal time for each elementCompute the normal time for each element

    Normal time for A = (9.5)(1.2) = 11.4 minutesNormal time for A = (9.5)(1.2) = 11.4 minutesNormal time for B = (2.2)(1.05) = 2.31 minutesNormal time for B = (2.2)(1.05) = 2.31 minutes

    Normal time for C = (1.5)(1.10) = 1.65 minutesNormal time for C = (1.5)(1.10) = 1.65 minutes

    Normal time = (Average observed time) x (Rating)Normal time = (Average observed time) x (Rating)

    4.4. Add the normal times to find the total normal timeAdd the normal times to find the total normal time

    Total normal time = 11.40 + 2.31 + 1.65 = 15.36 minutesTotal normal time = 11.40 + 2.31 + 1.65 = 15.36 minutes

    Time Study Example 3Time Study Example 3

  • 8/14/2019 Work Measure

    18/35

    5.5. Compute the standard time for the jobCompute the standard time for the job

    Standard time =Standard time =Total normal timeTotal normal time

    1 - Allowance factor1 - Allowance factor

    = = 18.07 minutes= = 18.07 minutes15.3615.36

    1 - .151 - .15

    Time Study Example 3Time Study Example 3

  • 8/14/2019 Work Measure

    19/35

    Determine Sample SizeDetermine Sample Size

    How accurate we want to beHow accurate we want to be

    The desired level of confidenceThe desired level of confidence

    How much variation exists within the jobHow much variation exists within the job

    elementselements

  • 8/14/2019 Work Measure

    20/35

    Required sample size = n =Required sample size = n =

    22zszs

    hxhx

    wherewhere hh == accuracy level desired in percentaccuracy level desired in percentof the job element expressed as a decimalof the job element expressed as a decimal

    zz == number of standard deviationsnumber of standard deviationsrequired for the desired level of confidencerequired for the desired level of confidence

    ss == standard deviation of the initialstandard deviation of the initialsamplesample

    xx == mean of the initial samplemean of the initial sample

    nn == required sample sizerequired sample size

    Determine Sample SizeDetermine Sample Size

  • 8/14/2019 Work Measure

    21/35

    Required sample size = n =Required sample size = n =

    22zszs

    hxhxDesiredConfidence

    (%)

    z Value(standard deviation required for

    desired level of confidence)

    90.0 1.65

    95.0 1.96

    95.45 2.00

    99.0 2.58

    99.73 3.00

    Common z Values

    Determine Sample SizeDetermine Sample Size

  • 8/14/2019 Work Measure

    22/35

    Time Study Example 4Time Study Example 4

    Desired accuracy with 5%Desired accuracy with 5%Confidence level = 95%Confidence level = 95%Sample standard deviation = 1.0Sample standard deviation = 1.0Sample mean = 3.00Sample mean = 3.00

    n =n =

    22zszs

    hxhx

    n = = 170.74 171n = = 170.74 171

    221.96 x 1.01.96 x 1.0

    .05 x 3.05 x 3

    h = .05h = .05 x = 3.00x = 3.00 s = 1.0s = 1.0

    z = 1.96z = 1.96

  • 8/14/2019 Work Measure

    23/35

    n =n =

    22zszs

    ee

    If desired accuracy h is expressed as an absolute amount,If desired accuracy h is expressed as an absolute amount,substitute e for hx, where e is the absolute amount ofsubstitute e for hx, where e is the absolute amount of

    acceptable erroracceptable error

    VariationsVariations

    When the standard deviation s is not provided, it mustWhen the standard deviation s is not provided, it mustbe computedbe computed

    s = =s = =(x(xii - x)- x)

    22 (Each sample observation - x)(Each sample observation - x)22

    n - 1n - 1 Number in sample - 1Number in sample - 1

    Determine Sample SizeDetermine Sample Size

  • 8/14/2019 Work Measure

    24/35

    Work SamplingWork Sampling

    Estimates percent of time a worker spendsEstimates percent of time a worker spendson various taskson various tasks

    Requires random observations to recordRequires random observations to recordworker activityworker activity

    Determines how employees allocate theirDetermines how employees allocate theirtimetime

    Can be used to set staffing levels, reassignCan be used to set staffing levels, reassignduties, estimate costs, and set delayduties, estimate costs, and set delayallowancesallowances

  • 8/14/2019 Work Measure

    25/35

    Advantages of work samplingAdvantages of work sampling

    Less expensive than time studyLess expensive than time study

    Observers need little trainingObservers need little training

    Studies can be delayed or interrupted withStudies can be delayed or interrupted withlittle impact on resultslittle impact on results

    Worker has littleWorker has littlechance to affectchance to affectresultsresults

    Less intrusiveLess intrusive

    Work SamplingWork Sampling

  • 8/14/2019 Work Measure

    26/35

    Disadvantages of work samplingDisadvantages of work sampling

    Does not divide work elements as completelyDoes not divide work elements as completely

    as time studyas time studyCan yield biased results if observer does notCan yield biased results if observer does not

    follow random patternfollow random pattern

    Less accurate, especially whenLess accurate, especially whenjob element times are shortjob element times are short

    Work SamplingWork Sampling

  • 8/14/2019 Work Measure

    27/35

    1.1. Take a preliminary sample to obtainTake a preliminary sample to obtainestimates of parameter valuesestimates of parameter values

    2.2. Compute the sample size requiredCompute the sample size required3.3. Prepare a schedule for random observationsPrepare a schedule for random observations

    at appropriate timesat appropriate times

    4.4. Observe and record worker activitiesObserve and record worker activities

    5.5. Determine how workers spend their timeDetermine how workers spend their time

    Work SamplingWork Sampling

  • 8/14/2019 Work Measure

    28/35

    Determining the sample sizeDetermining the sample size

    n =n =

    zz22 p(1 - p)p(1 - p)

    hh22

    wherewhere nn == required sample sizerequired sample size

    zz == standard normal deviate forstandard normal deviate for

    desired confidence leveldesired confidence levelpp == estimated value of sampleestimated value of sampleproportionproportion

    hh == acceptable error level inacceptable error level in

    percentpercent

    Work SamplingWork Sampling

  • 8/14/2019 Work Measure

    29/35

    Work Sampling ExampleWork Sampling Example

    Wants employees idle 25% of the timeWants employees idle 25% of the time

    Sample should be accurate within 3%Sample should be accurate within 3%

    Wants to have 95.45% confidence in the resultsWants to have 95.45% confidence in the results

    n =n = zz22 p(1 - p)p(1 - p)

    hh22

    wherewhere nn == required sample sizerequired sample size

    zz == 2 for a 95.45% confidence level2 for a 95.45% confidence level

    pp == estimate of idle proportion =estimate of idle proportion =25% = .2525% = .25

    hh == acceptable error of 3% = .03acceptable error of 3% = .03

    n = = 833 observationsn = = 833 observations(2)(2)22 (.25)(.75)(.25)(.75)

    (.03)(.03)22

  • 8/14/2019 Work Measure

    30/35

    No. ofNo. ofObservationsObservations

    ActivityActivity

    485485 On the phone or meeting with a welfare clientOn the phone or meeting with a welfare client

    126126 IdleIdle

    6262 Personal timePersonal time

    2323 Discussions with supervisorDiscussions with supervisor

    137137 Filing, meeting, and computer data entryFiling, meeting, and computer data entry

    833833

    All but idle and personal time are work related.All but idle and personal time are work related.

    Percentage idle time = (126 + 62)/833 = 22.6%.Percentage idle time = (126 + 62)/833 = 22.6%.

    Since this is less than the target value of 25%, theSince this is less than the target value of 25%, theworkload needs to be adjusted.workload needs to be adjusted.

    Work Sampling ExampleWork Sampling Example

  • 8/14/2019 Work Measure

    31/35

    Work Sampling Time StudiesWork Sampling Time Studies

    SalespeopleSalespeople

    TelephoneTelephonesalessales12%12%

    TelephoneTelephonewithin firmwithin firm

    13%13%

    Lunch andLunch andpersonalpersonal

    10%10%

    MeetingsMeetingsand otherand other

    8%8%

    Paperwork17%

    Travel20%

    Sales inperson

    20%

  • 8/14/2019 Work Measure

    32/35

  • 8/14/2019 Work Measure

    33/35

    Predetermined Time StandardsPredetermined Time Standards

    Divide manual work into small basic elementsDivide manual work into small basic elementsthat have established timesthat have established times

    Can be done in a laboratory away from theCan be done in a laboratory away from theactual production operationactual production operation

    Can be set beforeCan be set beforethe work is actuallythe work is actually

    performedperformed

    No performanceNo performanceratings are necessaryratings are necessary

  • 8/14/2019 Work Measure

    34/35

    MTM ExampleMTM Example

    Weight - less than 2 poundsWeight - less than 2 pounds

    Conditions of GET - easyConditions of GET - easy

    Place accuracy - approximatePlace accuracy - approximate

    Distance range - 8 to 20 inchesDistance range - 8 to 20 inches

    Element DescriptionElement Description ElementElement TimeTime

    Get tube from rackGet tube from rack AA2AA2 3535

    Get stopper, place on counterGet stopper, place on counter AA2AA2 3535

    Get centrifuge tube, place at sample tableGet centrifuge tube, place at sample table AD2AD2 4545

    Pour (3 seconds)Pour (3 seconds) PTPT 8383Place tubes in rack (simo)Place tubes in rack (simo) PC2PC2 4040

    Total TMUTotal TMU 238238

    .0006 x 238 =.0006 x 238 = Total standard minutesTotal standard minutes = .14= .14

  • 8/14/2019 Work Measure

    35/35

    MTM TableMTM Table