Woodlawn Mine Site Environmental Monitoring Plan...2019/01/30 · Environmental Monitoring Plan. 2...
Transcript of Woodlawn Mine Site Environmental Monitoring Plan...2019/01/30 · Environmental Monitoring Plan. 2...
Heron Resources Limited Woodlawn Zinc – Copper Project
Copyright 2018 Heron Resources Limited. All rights reserved. No part of this document may be reproduced by any means or in any form without the express permission in writing of Heron Res ources Limited.
Woodlawn Mine Site Environmental Monitoring Plan
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 2 of 29
TABLE OF CONTENT
1 PURPOSE ................................................................................................................................ 4
1.1 Management Plans associated with the EMS .............................................................................. 4
2 SCOPE ..................................................................................................................................... 5
3 APPROVALS, LICENCES, PERMITS AND LEASES ....................................................................... 5
4 AUDIT, INSPECTION, REPORT AND REVIEW SCHEDULES ........................................................ 6
5 METEORLOGICAL .................................................................................................................... 6
5.1 Weather station .......................................................................................................................... 6
5.2 Weather reporting requirements ................................................................................................ 7
6 WATER RESOURCES ................................................................................................................ 7
6.1 Ground Water ............................................................................................................................. 7
6.1.1 Groundwater monitoring sites ........................................................................................................... 7 6.1.2 Groundwater monitoring pollutants – compliance monitoring ........................................................... 8 6.1.3 Groundwater monitoring– additional monitoring sites ....................................................................... 9 6.1.4 Groundwater sample collection method ............................................................................................ 9 6.1.5 Sample bottle labelling requirement ................................................................................................ 10 6.1.6 Additional across-site groundwater collection points ....................................................................... 10 6.1.7 Data recording.and reporting .......................................................................................................... 11
6.2 Surface Water ........................................................................................................................... 11
6.2.1 Surface water parameters to be tested ............................................................................................ 12 6.2.2 Surface water sample collection method ......................................................................................... 12 6.2.3 Data recording.and reporting .......................................................................................................... 13
7 NOISE MONITORING ............................................................................................................ 13
7.1 Noise assessment Criteria ......................................................................................................... 13
7.2 Noise monitoring locations ....................................................................................................... 14
7.2.1 Data recording.and reporting .......................................................................................................... 14
8 BLASTING OVERPRESSURE/GROUND VIBRATION MONITORING ......................................... 15
8.1.1 Data recording.and reporting .......................................................................................................... 15
9 AIR QUALITY ......................................................................................................................... 15
9.1 Depositional Dust ...................................................................................................................... 16
9.2 High volume air sampler ........................................................................................................... 16
9.2.1 Data recording.and reporting .......................................................................................................... 16
10 LAND MANAGEMENT ........................................................................................................... 17
10.1 Flora management .................................................................................................................... 18
10.2 Fauna management .................................................................................................................. 18
10.3 Erosion and sediment control ................................................................................................... 19
10.4 Invasive plant species management .......................................................................................... 19
10.5 Invasive animal species management ........................................................................................ 19
11 REFERENCES ......................................................................................................................... 20
11.1 External documents or legislative .............................................................................................. 20
11.2 Related Heron Environmental Management Plans .................................................................... 21
12 READ AND UNDERSTOOD DOCUMENT REQUIREMENTS ...................................................... 22
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 3 of 29
13 APPENDICES ......................................................................................................................... 23
Appendix 1 – Definitions .................................................................................................................... 24
Appendix 2 – Roles and Responsibilities ............................................................................................. 25
Appendix 3 – Example COC ................................................................................................................ 26
Appendix 4 – Groundwater Field Data Sheet ...................................................................................... 27
Appendix 5 – Surface water field data sheet ...................................................................................... 28
Appendix 6 – Noise monitoring field data sheet ................................................................................. 29
LIST OF FIGURES
Figure 1. Sample bottles to be used for groundwater sampling ........................................................ 10
LIST OF TABLES Table 1. Environmental monitoring program ...................................................................................... 5
Table 2. List of compliance audit, inspections and reporting schedules ............................................... 6
Table 3. Meteorological station data .................................................................................................. 6
Table 4. Groundwater monitoring sites .............................................................................................. 8
Table 5. Groundwater parameters to be tested quarterly ................................................................... 8
Table 6. Groundwater parameters to be tested annually .................................................................... 8
Table 7. Additional groundwater monitoring sites .............................................................................. 9
Table 8. Parameters for additional groundwater monitoring points.................................................... 9
Table 9. Veolia compliance monitoring - groundwater sites.............................................................. 11
Table 10. Surface water collection points ......................................................................................... 12
Table 11. Surface water laboratory testing parameters .................................................................... 12
Table 12: Noise Criteria dB(A) .......................................................................................................... 13
Table 13: Applicable Meteorological Conditions ............................................................................... 13
Table 14: Noise Monitoring Locations .............................................................................................. 14
Table 15. Objectives and Key Performance Indicators for Air Quality Management .......................... 15
Table 16. Deposited dust criteria ...................................................................................................... 16
Table 17. Long term criteria for particulate matter ........................................................................... 16
Table 18. Short term criteria for particulate matter .......................................................................... 16
Table 19. Locations of LFA monitoring sites. ..................................................................................... 17
Table 20. Sediment control monitoring regime ................................................................................ 19
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 4 of 29
1 PURPOSE The Woodlawn mine site is operated by Heron Resources Limited (Heron). Project Approval 07-0143 was issued on 4 July 2013. Subsequent modifications have been received on 22 April 2016 and 6 July 2017. The Project Approval (PA) is subject to the following Conditions:
Prevent, minimize, and/or offset adverse environmental impacts;
Set standards and performance measures for acceptable environmental performance;
Require regular monitoring and reporting; and
Provide for the ongoing environmental management of the project.
Condition 1 of Schedule 6 of the Project Approval (07_0143) requires that an Environmental Management Strategy (EMS) be implemented within 12 months of the approval. In August 2018 the EMS was updated. The purpose of the EMS is to:
Provide the strategic framework for the environmental management of the project;
Identify the statutory approvals that apply to the project;
Describe the role, responsibility, authority and accountability of all key personnel involved in the environmental management of the project;
Describe the procedures that would be implemented to: o Keep the local community and relevant agencies informed about the operation and
environmental performance of the project; o Receive, handle, respond to, and record complaints; o Resolve any disputes that may arise during the course of the project; o Respond to any non-compliance; o Respond to emergencies; and Include o Copies of any strategies, plans and programs approved under the conditions of this approval;
and o A clear plan depicting all the monitoring required to be carried out under the conditions of this
approval.
The Woodlawn Mine – Environmental Management Strategy provides the strategic framework for the environmental management of the Woodlawn Mine project. This Environmental Monitoring Plan details the documented procedures for monitoring and measuring the environmental impact of the Project.
1.1 Management Plans associated with the EMS
The Woodlawn Mine operates alongside a suite of operational management plans which provide the overarching framework for the management of Woodlawn Mine.
These include:
Construction Environmental Management Plan;
Community Engagement Plan;
Pollution Incident Response Management Plan
Extraction Plan;
Noise and Blasting Management Plan;
Air Quality Management Plan;
Water Management Plan, including: Site Water Balance, Surface Water Management Plan, Groundwater Management Plan, Surface and Groundwater Response Plan;
Vegetation and Rehabilitation Management Plan (incorporating the Tailings Management Strategy, Vegetation Management Plan and Rehabilitation Management Plan);
Heritage Management Plan;
Transport Management Plan, including Road Transport Protocol;
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 5 of 29
Paste Fill Management Plan;
Waste Rock Management Plan; and
Environmental Monitoring Plan.
2 SCOPE The Woodlawn Mine - Environmental Monitoring Plan details the program of environmental monitoring to be undertaken to achieve compliance with the Project Approval Conditions and Schedules. Key elements of the Plan are summarised in Table 1. The monitoring detailed in each section meets the minimum requirements for compliance with the Project Approval and EPL Licence. Where applicable, details of additional monitoring undertaken by TOP for the management of the mine operation are also indicated in this Plan. Table 1. Environmental monitoring program
Parameter Construction Operational Post Closure Section
Meteorological ✔ ✔ 5
Water 6
Groundwater ✔ ✔ 6.1
Surface water ✔ ✔ 0
Noise ✔ ✔ 7
Vibration and overpressure
✔ 8
Air Quality ✔ ✔ ✔ 9
Land management ✔ ✔ 10
Flora ✔ ✔ 10.1
Fauna 10.2
Erosion and sediment control
✔ ✔ ✔ 10.3
Weed control ✔ ✔ Error! Reference
source not found.
Pest control ✔ ✔ Error! Reference
source not found.
Bushfire management
✔ ✔ ✔ 12.5
3 APPROVALS, LICENCES, PERMITS AND LEASES The following approvals and licences have been obtained for the operation of Woodlawn Mine:
Project Approval 07_0153 Modification 2, July 2017
Environmental Protection Licence No. 20821 version date 18 January 2019 (anniversary date 29 March)
Special (Crown and Private Lands) Lease 20 (Act 1969) – Approved 15 August 2013, Expiry 16 November 2029
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 6 of 29
4 AUDIT, INSPECTION, REPORT AND REVIEW SCHEDULES The key audit, inspection, reporting and review schedules essential for compliance criteria set in the Project Approval 07_0153 Modification 2, and Environmental Protection Licence No. 20821 are summarised in Table 2.
Table 2. List of compliance audit, inspections and reporting schedules
Audit/inspection/report Frequency Next due Responsibility
Dam Surveillance Report Every 2 ½ years Nov 2020 Qualified dams safety consultant
Dam surveillance inspections
Annually June each year
Qualified dams safety consultant
Dam monitoring Monthly/Weekly (based on trigger points
Each month Environmental Officer
EPA Annual Return Annually May each year
Environmental Officer
Annual Review –Department of Planning and Environment
Annually 1st September each year
Environmental Manager/Environmental Officer
Independent Environmental Audit
Every 3 years September 2021
Independent Auditor
Monthly environmental report posted on Heron Web Site
Monthly Each month Environmental Officer
Rehabilitation Report NSW Department of Planning and Environment, Resource Regulator
Annually Nov each year
Environmental Officer
5 METEORLOGICAL
5.1 Weather station
Access to meteorological data is provided by Veolia who operate a meteorological station on the EPL 11436 premises at location E734922 N6117469. The weather station records the parameters listed in Table 3.
Table 3. Meteorological station data
Parameter Unit of measure Averaging period Frequency
Average wind speed m/s 1 hour Continuous
Average wind direction Deg 1 hour Continuous
Temperature at 10m Kelvin and oC 1 hour Continuous
Temperature at 2 m Kelvin and oC 1 hour Continuous
Solar radiation W/m2 1 hour Continuous
Rainfall mm 24 hours Continuous
Barometric pressure Hpa 1 hour Continuous
Evapotranspiration mm 1 hour Continuous
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 7 of 29
5.2 Weather reporting requirements
Weather is reported as follows:
The Summary of Environmental Monitoring Data that is reported monthly and available on the HR website http://www.heronresources.com.au/woodlawn-environment-monitoring.php
EPL Annual Return
Annual Review prepared in accordance with Condition 4 of Schedule 6 of the Project Approval
6 WATER RESOURCES Water monitoring is undertaken to monitor potential impacts of the Project on the environment. The Project Approval requires that all ground and surface water resources be monitored periodically. Schedule 4, Condition 4 of the Project Approval requires the proponent to prepare and implement a Water Management Plan. The Woodlawn Mine - Water Management Plan (2017) and the EPA licence number 20821 contain specific details of the water monitoring requirements.
6.1 Ground Water
The Woodlawn Mine - Water Management Plan revised August 2017 details the criteria for ground water monitoring as follows:
Baseline data of all groundwater levels, yield and quality of any privately-owned groundwater bores that could be affected by the project;
Groundwater assessment criteria;
Definition of areas of existing groundwater contamination;
A program to monitor: o Existing groundwater contamination identified on the site; o Impacts on the groundwater supply of potentially affected landowners; o The volume of groundwater inflow into the underground workings; o Regional groundwater levels and quality in potentially affected aquifers; o Potential groundwater quality impacts from paste fill operations; o Potential acid rock drainage; o Potential seepage from tailings and evaporation dams; o The effectiveness of the seepage collection, treatment and storage system associated with the
tailings dams, waste rock dumps, evaporation dams and all other water storages that receive contaminated or salt-laden water; and
o Reporting procedures for the results of the monitoring program.
6.1.1 Groundwater monitoring sites
The Woodlawn mine has a network of over 50 monitoring bores and piezometers which monitor the tailings dams, evaporation dams, waste rock dump and plant / processing / administration areas. In accordance with the requirements detailed in EPL 20821 a number of groundwater monitoring sites are required to be tested for the purpose of monitoring and/or the setting of limits for discharges of pollutants to water from the point. The groundwater monitoring points are listed in Table 4.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 8 of 29
Table 4. Groundwater monitoring sites
EPA site Identification number
Location description Frequency
11 MB4 - East side of void, Near DG22 Quarterly
12 MB5 - South face of waste rock dump Quarterly
13 MB6 – Adjacent to mine entry Quarterly
14 MB8 – Adjacent to Collector Road and downstream of proposed processing plant site
Quarterly
15 MB12 – Below ED2 dam wall Quarterly
16 MB13 – Western premises boundary Quarterly
17 MB14 – Background ground water Quarterly 18 MB15 – To measure seepage from
rehabilitated waste rock dump Quarterly
21 MB11 – Below ED2 dam wall Quarterly
22 MB16 – To measure seepage from rehabilitated waste rock dump
Quarterly
23 MB17 – To measure seepage from rehabilitated waste rock dump
Quarterly
6.1.2 Groundwater monitoring pollutants – compliance monitoring
Groundwater parameters detailed in EPL 20821 to be tested each quarter using samples of groundwater are listed in Table 5.
Table 5. Groundwater parameters to be tested quarterly
Pollutant Unit of measurement Comments
Alkalinity (as CaCO3) Milligrams per litre
Total Al, As, Ba, Cd, Ca, Cl, Co, Cr, Cu, F, Pb, Mg, Mn, Hg, K, Na, S, Zn
Milligrams per litre Total metals
Nitrate, Nitrite, Nitrogen (ammonia) Milligrams per litre pH Electrical Conductivity (EC) Total dissolved solids (TDS) Total organic carbon (TOC)
pH Microsiemens per centimetre Milligrams per litre milligrams per litre
Standing water level metre In situ
Groundwater parameters detailed in EPL 20821 to be tested annually are listed in Table 6.
Table 6. Groundwater parameters to be tested annually
Pollutant Unit of measurement Comments
Chromium (hexavalent) Millligrams per litre
Benzene, Ethyl Benzene, Toluene, Xylene (BTEXN)
Milligrams per litre
Organochlorine pesticides (OCP), Organophosphate pesticides (OPP), Polycyclic aromatic hydrocarbons (PAH), Total Petroleum Hydrocarbons (TPH), Total Phenolics
Milligrams per litre
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 9 of 29
6.1.3 Groundwater monitoring– additional monitoring sites
In addition to the groundwater sample collection points detailed in EPL 20821, Heron Resources also monitors the standing water level and water quality in additional bores located across the Site as summarised in Table 7.
Table 7. Additional groundwater monitoring sites
Site identification Site description Frequency
NTP2 North Tailings Dam East wall Bi-annually
SP3C North Tailings Dam East wall Bi-annually
ETP8 North Tailings Dam East wall Bi-annually SP11B North Tailings Dam East Wall Bi-annually
E3 South Tailings Dam South Wall Bi-annually
F1 South Tailings Dam South Wall Bi-annually
F7 South Tailings Dam South Wall Bi-annually
X1 South Tailings Dam East Wall Bi-annually
X2 South Tailings Dam East Wall Bi-annually
Y1 South Tailings Dam East Wall Bi-annually
Z1 South Tailings Dam South Wall Bi-annually
MB21D East of South Tailing Dam Quarterly
MB22S East of South Tailing Dam Quarterly
MB19 West of Evaporation Dam 2 Quarterly
MB20 West of Evaporation Dam 2 Quarterly
Parameters to be tested for the additional groundwater monitoring sites (paragraph 6.1.3) are detailed in Table 8.
Table 8. Parameters for additional groundwater monitoring points
Pollutant Unit of measurement Comments
Alkalinity (as CaCO3) Milligrams per litre
Total Al, As, Ba, Cd, Ca, Cl, Co, Cr, Cu, F, Pb, Mg, Mn, Hg, K, Na, S, Zn
Milligrams per litre Total metals
Nitrate, Nitrite, Nitrogen (ammonia) Milligrams per litre
pH Electrical Conductivity (EC) Total dissolved solids (TDS) Total organic carbon (TOC)
pH Microsiemens per centimetre Milligrams per litre milligrams per litre
Standing water level metre In situ
6.1.4 Groundwater sample collection method
The method used for collecting ground water samples for the annual suite of parameters (Table 6) is as follows:
(1.) Measure height of water in stand pipe;
(2.) Measure depth to base of monitoring bore;
(3.) Calculate volume of water to purge;
(4.) Purge the bore (slow recharge bores to be purged and left to recharge over night until
sufficient volume is extracted);
(5.) Extract water sample;
(6.) Undertake field analysis for each bucket of water obtained for pH, EC, DO, ORP, Temperature.
Record for each bucket full of water obtained;
(7.) Collect samples in the ALS sample bottles as indicated in Figure 1;
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 10 of 29
Figure 1. Sample bottles to be used for groundwater sampling
(8.) Store in cooler box with ice blocks until stored in a purpose dedicated fridge; and
(9.) Prepare a COC to be transported with sample(s) to the Laboratory (example COC at Appendix
3).
6.1.5 Sample bottle labelling requirement
Sample bottles are to be labelled as follows:
Client/Reference: Heron Resources
Sampled by: Sampler (s) initials
Sample ID: HR_SML_site id_YYMMDD
Date/Time: Date and time sample is collected
Details on the sample label are to be the same as the field data sheet and COC documentation.
6.1.6 Additional across-site groundwater collection points
Veolia operate under the provisions of EPL 11436 and are required to monitor a number of groundwater monitoring points. The Veolia groundwater points providing information important to HR and commonly reported in the HR AR are detailed in Table 9. Veolia provide monitoring results as required. Frequency of sampling details are contained in EPL 11436 with some parameters monitored annually and others quarterly.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 11 of 29
Table 9. Veolia compliance monitoring - groundwater sites
Site ID Location Frequency
MB1 Near bore field water tank Annually/Quarterly
MB2 Woodlawn farm entrance Annually/Quarterly
MB3 Woodlawn farm behind yards Annually/Quarterly
MB7 Between core shed and MBTF Annually/Quarterly
MB10 ED1 below dam wall Annually/Quarterly
ED3B ED3 Annually/Quarterly
WM1 Top of void Annually/Quarterly
WM5 Above Woodlawn Dam Annually/Quarterly
WM6 Near pond 4 evaporators Annually/Quarterly
MW8S Between ED1 and ED3 Annually/Quarterly
MW8D East of ED3 Annually/Quarterly
MW9S Between ED1 and ED3 Annually/Quarterly
MW10S SE of ED1 Annually/Quarterly
6.1.7 Data recording.and reporting
For each sample, field data and observations are recorded on a field data sheet (appendix 3). The field data sheet includes:
Sample date, time;
Depth to water, bore base and calculation for volume of water to be removed from a bore;
Field measurements for pH, conductivity, DO, ORP, Temp and comments;
Field data reports are filed together with hard copies of the lab reports. Electronic copies of reports are also retained.
Groundwater results are reported as follows:
EPA Annual Return, and
Annual Review prepared in accordance with Condition 4 of Schedule 6 of the Woodlawn Project Approval.
6.2 Surface Water
The Woodlawn Mine - Water Management Plan (August 2017) details the management strategy for surface water. The surface water monitoring requirements contained in the PA for the operational phase of the projects are as follows:
Baseline data on surface water flow and quality in natural waterbodies that could be affected by the project;
a program to monitor: o the effectiveness of the water management system; o surface water flows, quality and impacts on other water users; o potential acid rock drainage from the waste rock dumps; and o potential seepage from tailings and evaporation dams.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 12 of 29
The surface water sample collection points detailed in EPL 20821 are listed in Table 10
Table 10. Surface water collection points
EPA site ID No Location description Frequency
6 Site 115 - Allianoyonyiga Ck Quarterly
7 Site 105 - Crisps Creek Quarterly
8 Site 100 – Woodlawn/Willaroo boundary South, (below waste rock dam)
Quarterly
9 Site 109 – Pylara Boundary below South Tailings Dam
Quarterly
10 Site 300 – Processing plant pollution control dam – Final dam below new processing facility
Quarterly
19 Evaporation Dam 2 (ED2) Quarterly
20 Tailings Storage Facility 4 (TSF 4) Quarterly
24 Mine water monitoring at the discharge point into the holding dam being used at the time of monitoring
Monthly
6.2.1 Surface water parameters to be tested
Parameters detailed in EPL 20821 to be analysed each quarter using grab samples of surface water listed in Table 11.
Table 11. Surface water laboratory testing parameters
Pollutant Unit of measurement
BOD Milligrams per litre
pH pH
Electrical Conductivity Microsiemens per centimeter
Dissolved Oxygen Millligrams per litre
Nitrogen (ammonia) Milligrams per litre
Potassium Milligrams per litre
Redox potential Milligrams per litre Total dissolved solids (TDS) Milligrams per litre
Total organic carbon (TOC), Milligrams per litre
6.2.2 Surface water sample collection method
Samples are obtained using a clean plastic container attached to an extension pole and collected into a clean bucket. Field analysis for pH, EC, DO, ORP, Temperature using a multi parameter meter and a visual assessment of the water quality is to be recorded on a field data sheet (Appendix 5). The water sample is to be decanted into two clearly labelled one litre plastic bottle (Figure 1). Whilst in the field, the bottles are to be kept cool in a cooler box with ice blocks. If longer term storage is necessary samples should be stored in a refrigerator. During transport to the laboratory the samples are to be carried in a cooler box with ice-blocks. A Chain of Custody (COC) document is to be raised for delivery with the samples (Appendix 3).
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 13 of 29
6.2.3 Data recording.and reporting
For each surface water sample, field data and observations are recorded on a field data sheet (appendix 5). The field data sheet includes:
Sample date, time;
Weather conditions;
Field measurements for pH, electrical conductivity, DO, ORP, Temp and comments; and
Field data reports are filed together with hard copies of the laboratory reports. Electronic copies of reports are also retained.
Groundwater results are reported as follows:
EPA Annual Return, and
Annual Review prepared in accordance with Condition 4 of Schedule 6 of the Woodlawn Project Approval.
7 NOISE MONITORING Schedule 4, Condition 7 of the PA requires that a noise and blast management plan (NBMP) be developed. The Woodlawn Mine – Noise and Blasting Management Plan was issued by Heron in August 2017.
7.1 Noise assessment Criteria
Schedule 4, Condition 5 of the PA requires the Proponent to ensure that noise generated by the Project does not exceed the criteria at any residence on privately-owned land. The criteria are reproduced in Table 12. Table 12: Noise Criteria dB(A)
Receivers Day/Evening/Night (LAeq(15-minute))
Night (LA1(max))
All residential Receivers 35 45
Note: After the first review of any EPL granted for this project under Section 78 of the POEO Act, nothing in this approval prevents the EPA from imposing stricter noise limits on the mining operations on site under the EPL.
The meteorological conditions under which the nose conditions apply are detailed in Conditions 1 and 2 of Appendix 5 of the PA. The meteorological conditions are reproduced in Table 13. Table 13: Applicable Meteorological Conditions
1. The noise criteria in Table 3 of the conditions are to apply under all meteorological conditions except the following:
(a) During periods of rain or hail; (b) Average wind speed at microphone height exceeds 5 m/s; (c) Wind speeds greater than 3 m/s measured at 10 m above ground level; or (d) Temperature inversion conditions greater than 3oC/100m.
2. Except for wind speed at microphone height, the data to be used for determining meteorological conditions shall be that recorded by the meteorological station located on the site.
Condition 3 of Appendix 5 of the Project Approval states that monthly attended monitoring is to be used to evaluate compliance with the relevant conditions of the Project Approval.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 14 of 29
Condition 4 to Appendix 5 of the Project Approval requires that monitoring be carried out in accordance with the NSW Industrial Noise Policy (as amended from time to time), in particular the requirements relating to:
(a) Monitoring locations for the collection of representative noise data;
(b) Meteorological conditions during which collection of noise data is not appropriate;
(c) Equipment used to collect noise data, and conformity with Australian Standards relevant to such
equipment; and
(d) Modifications to noise data collected, including for the exclusion of extraneous noise and/or penalties
for modifying factors apart from adjustments for duration.
Attended noise measurements are undertaken and recorded using a calibrated Type 1, Castle Group Ltd dBAir
environmental monitor. Noise monitoring is carried out using two measurement profiles:
Measurement 1 – Frequency weighting A, time weighting F
Measurement 2 – Frequency weighting C, time weighting F.
Real time meteorological conditions are obtained at each location using a BL-300 Anemo-thermometer and
hygrometer and validated using the authorised Woodlawn on-site weather station. Readings are routinely
taken at the Pylara, Woodlawn and the Cowley Hills residences. All locations represent the nearest receptors
and are owned by Veolia. The results show that the construction activities have little noise impact on any of
the receptor locations.
7.2 Noise monitoring locations
The following noise monitoring program has been developed to satisfy the Project Approval. During mining operations monthly operator-attended short-term noise monitoring will be conducted, as a minimum, at the locations listed in Table 14.
Table 14: Noise Monitoring Locations
Location Approximate distance from Project site (km)
Woodlawn Farm 1.4
Cowley Hills 0.7
Pylara 3.2
The results of the monitoring are reviewed on a quarterly basis.
7.2.1 Data recording.and reporting
For each sample, field data and observations are recorded on a field data sheet (appendix 6). The field data sheet includes:
Location
Recording date, start time and end time
Meteorological conditions (Wind speed m/s, Wind direction, Air temperature, relative humidity, barometric pressure
Sound level and cause/source of noise peaks
The noise monitor also records the noise parameters during the recording period and provides a summary of noise as LAeq.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 15 of 29
8 BLASTING OVERPRESSURE/GROUND VIBRATION MONITORING Blasting overpressure and vibration criteria is detailed in Condition 8 of Schedule 4 of the Project Approval. The maximum level of airblast overpressure allowed at any residence on privately owned land during operations is not to exceed 115 dB (Lin Peak). These criteria may be exceeded up to 5% of the total number of blasts over a 12 month period. The maximum level shall not exceed 120 dB (Lin Peak).
The maximum ground vibration level recorded at any residence on privately owned land during operations is 5 mm/s peak particle velocity. However, this level may be exceeded no more than 5% of the total number of blasts over a 12 months period. The maximum level shall not exceed 10 mm/s.
Overpressure and vibration monitoring is undertaken continuously. Monitoring is undertaken using an Instantel micromate monitor. The monitor is regularly relocated at various positions, depending on operational requirements on the site boundary or at locations within Site. It will also be located at nearby residences to monitor the effects of blasting. The monitor is set to trigger with thresholds set at 0.21 mm/s and 110 dB (Lin Peak).
8.1.1 Data recording.and reporting
Monitoring results are downloaded onto a portable data storage media and uploaded for interpretation and review using proprietary software.
Results are summarised in the monthly environmental monitoring report.
9 AIR QUALITY The Air Quality Management Plan (AQMP) has been prepared in accordance with Schedule 4, Condition 17(a) of PA 07_0143. Air quality is monitored across the site using 5 Deposited Dust Gauges and two high volume air samplers (HVAS).
The objectives and key performance outcomes for air quality are detailed in Table 15.
Table 15. Objectives and Key Performance Indicators for Air Quality Management
Objectives Key performance indicators
1. Implement the commitments made in the Environmental Assessment including specific conditions of approval and the Statement of Commitments
2. Ensure compliance with relevant environmental legislation
3. Manage air quality risks associated with the Woodlawn Project
Provide for continuous improvement in dust control performance
Provide a mechanism to identify and correct areas of non-compliance
i. Air quality management achieved within the limits detailed in the Project Approval.
ii. Maintain a network of air quality monitoring stations for continuous assessment of operational performance
iii. Monitoring is consistent with the Air Quality Management Plan and in accordance with Australian Standards
iv. Air quality results are reported in the Annual Report
v. Complaints are managed in accordance with the Community Complaints section of the AQMP
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 16 of 29
9.1 Depositional Dust
Four deposited dust gauges are shared with Veolia as listed in EPL 11436. The fifth is monitored by Heron Resources.
Deposited air quality criteria as specified in Schedule 4, Condition 15 is shown in Table 16.
Table 16. Deposited dust criteria
Pollutant Averaging period Maximum increase in deposited dust level
Maximum total deposited dust level
cDeposited dust Annual b2 g/m2/month a4 g/m2/month
Deposited dust is collected on a monthly basis. The results for deposited dust are recorded in the monthly environmental monitoring report that is publicly available on the Heron Resources Web site.
9.2 High volume air sampler
The HVAS receivers collect PM10 and Total suspended particulate (TSP) matter. Schedule 4, Condition 15 of the Project Approval set the criteria for particulate matter emissions as shown in Table 17 and Table 18.
Table 17. Long term criteria for particulate matter
Pollutant Averaging period Averaging period Maximum total deposited dust level
Total suspended particulate (TSP) matter Annual 90µg/m3
Particulate matter <10 µm (PM10) Annual 30 µg/m3
Table 18. Short term criteria for particulate matter
Pollutant Averaging period Averaging period Maximum total deposited dust level
Particulate matter <10 µm (PM10) 24 hour 50µg/m3
9.2.1 Data recording.and reporting
High volume air samples are collected every 6 days. The results for HVAS air sampling are recorded in the monthly environmental monitoring report that is publicly available on the Heron Resources Web site.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 17 of 29
10 LAND MANAGEMENT Condition 20 of Schedule 4 of the Project Approval requires that a vegetation management plan be implemented. Three documents refer:
1. Vegetation and rehabilitation management plan ,
2. Environmental management strategy
3. Mine operation plan
As detailed in the Vegetation and Rehabilitation Management Plan (VRMP), a program of verification and adaptive management for vegetation and rehabilitation management will be implemented incorporating the Landscape Function Analysis (LFA) visual assessment tool (Tongway and Hindley, 2004). LFA uses visual assessment to rapidly quantify temporal and spatial changes to soil physical, chemical and biological properties that are useful to monitor changes and/or improvements to landscape functionality following disturbance or rehabilitation. The method uses 11 soil surface assessment indicators that relate to specific soil properties and processes.
The 11 indicators are then used to derive three integrative indices as follows:
Soil stability; being the soil’s ability to resist erosion and reform after disturbance,
Infiltration; the soils capacity to retain rainfall and plant-available water,
Nutrient cycling; how efficiently organic matter is cycled back into the soil.
Permanent LFA monitoring sites incorporating transects and photographic references will be established at key rehabilitation and analogue (baseline and target reference) sites. Permanent LFA sites will be established on the Rehabilitated Waste Rock Dump, within the Vegetation Offset area and eventually on the rehabilitated tailings dams. The LFA assessment will be undertaken quarterly and assessment scores reported. LFA transects will be established on newly rehabilitated sites as necessary.
Table 19. Locations of LFA monitoring sites.
Location Analogue or rehabilitated Frequency
Waste rock dump 12 Rehabilitated locations – 6 grassy and 6 shrub
Quarterly
Vegetation offset area (78 ha) 12 Revegetated locations -6 grassy and 6 shrubs
Quarterly
Vegetation offset with mature natural regrowth
4 Analogue sites within Quarterly
Rehabilitated tailings dams TBA
Results of LFA can be used to identify sites that require rehabilitation, those where rehabilitation has been successful, and cases where rehabilitation or analogue sites need remedial action. Results from LFA are also useful to determine the impact of native fauna and drought on the vegetation across site.
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 18 of 29
10.1 Flora management
The Woodlawn mine site and the region generally has experienced extensive clearing for agriculture since European settlement. Hence there are no threatened ecological communities on site. The Woodlawn site is located within the South Eastern Highlands Bioregion. Prior to European settlement the area would have been predominantly Western Tablelands dry sclerophyll forest. Two regrowth vegetation communities are present on site:
Hickory wattle low open forest, comprising
o Acacia falciformis
o Eucalyptus mannifera
o Eucalyptus dives, and
o Sparse understory species
Black she-oak low open forest
o Allocasurina littoralis
o Eucalyptus dives
Monitoring the health of remnant flora will be incorporated into the LFA program.
10.2 Fauna management
Although Woodlawn mine site is highly disturbed, with only sparse areas of remaining natural habitat remaining, through strategic revegetation it is feasible that some threatened fauna may utilise the planted and regenerating vegetation on site. Indeed, Condition 20d of Schedule 4 of the Project Approval requires that native vegetation and fauna habitat on the revegetated area be focused on targeted establishment and maintenance of fauna habitat features for the Eastern Bent-wing bat and yellow bellied sheathtail bat.
Fauna monitoring activities include observation and reporting to the environmental team on site of encounters with wildlife. All employees are encouraged to report wildlife interactions, particularly if they are unusual sightings. All wildlife are provided a wide berth and disturbance to habitat is minimal. Any nesting sites are left alone and not disturbed.
Fauna commonly encountered on site include:
Eastern grey kangaroo (Macropus giganteus),
Common wombat (Vombatiformes),
Echidna (Tachyglossidae),
Reptiles:
including tiger snake, eastern brown snake, red belly black snake. Snakes that are encountered at operational areas on site are either given opportunity to move on undisturbed or are relocated by licenced snake handlers to alternate locations on Site,
Various lizards,
Long neck turtle,
Birds
o Wedgtail eagle,
o Black swan,
o Grey teal,
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 19 of 29
o Wood duck,
o Australasian darter.
10.3 Erosion and sediment control Erosion and sediment control structures have been installed around site. These include pollution control ponds, evaporation dams and sediment fencing. The management strategy for erosion and sediment control is detailed in the Mining Operations Plan.
Monitoring of erosion is undertaken via visual inspection, especially following rainfall. Typical indicators of erosion on site include rilling, gullying and sediment transfer.
The monitoring regime for sediment control is detailed in Table 20.
Table 20. Sediment control monitoring regime
Monitoring regime Location Frequency
Visual inspection Surface erosion, drains, ditches, road culverts Following heavy rainfall Visual inspection Gabion structures, batters and bench stability Following heavy rainfall
Visual inspection Sediment fencing Following heavy rainfall, and periodically for native animal damage
Water quality - TDS Surface monitoring points 115, 105, 100, 109 Following heavy rainfall
10.4 Invasive plant species management
Woodlawn mine site has few invasive plant species of concern. Weed management particularly for serrated tussock (Nassella Trichotoma), blackberry (Rubus fruticosus) and scotch thistle (Onopordum acanthium) is carried out annually.
Monitoring for invasive plant species is an ongoing. Monitoring for invasive flora species is ongoing. Additionally, all employees are encouraged to report sightings of the weeds of concern to the Environmental team.
10.5 Invasive animal species management
A number of invasive animal species inhabit the Woodlawn mine site including deer, rabbits, foxes, and feral cats. The populations of these invasive species is monitored by the environmental officers carrying out specific field observations and employee reports.
Management of feral animals is carried out as recommended in the South East Regional Strategic Pest Animal Plan 2018-2023 (NSW South East Local Land Services). In particular, feral animals will be controlled as follows:
Deer, will be managed by progressively excluding them from areas across the Woodlawn site using exclusion fencing;
Rabbit and fox baiting will carried out when required, and
Feral cats will be trapped and euthanised
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 20 of 29
11 REFERENCES
11.1 External documents or legislative
DOC ID TITLE
Protection of the Environment Operations Act, 1997 (POEO Act)
Australian Standard 3580.9.3 - 2003
Methods For Sampling and Analysis of Ambient Air – Determination of Suspended Particulate Matter – Total Suspended Particulate Matter (TSP) – High Volume Sampler Gravimetric Method
Australian Standard 3580.9.6 – 2003
Methods For Sampling and Analysis of Ambient Air – Determination of Suspended Particulate Matter – PM (sub) 10 High Volume Sampler With Size Selective Inlet – Gravimetric Method
Australian Standard 3580.10.1 – 2003
Methods For Sampling and Analysis of Ambient Air – Determination of Particulate Matter – Deposited Matter – Gravimetric Method
Australian Standard 5667.1 – 1998
Water quality - Sampling - Guidance on the design of sampling programs, sampling techniques and the preservation and handling of samples
Australian Standard 5667.6 – 1998
Water quality - Sampling - Guidance on sampling of rivers and streams
Australian Standard 5667.11 – 1998
Water quality - Sampling - Guidance on sampling of groundwater
Australian Standard 1269
Occupational noise management:
Part 0: Overview and general requirements Part 1: Measurement and assessment of noise emission and exposure Part 2: Noise control management Part 3: Hearing protector program
Australian Standard 4482.1-2005
Guide to the investigation and sampling of sites with potentially contaminated soil Part 1: Non-volatile and semi-volatile compounds
Australian Standard 14001:2004
Environmental management systems – Requirements with guidance for use
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 21 of 29
11.2 Related Heron Environmental Management Plans
DOC ID TITLE
TOP-SSE_MAN-0039 Environmental Management Strategy
TOP-SSE_MAN-0040 Construction Environmental Management Strategy
TOP-SSE_MAN-0041 Community Engagement Plan
TOP-SSE_MAN-0042 Pollution Incident Response Management Plan
TOP-SSE_MAN-0043 Extraction Plan
TOP-SSE_MAN-0044 Waste Rock Management Plan
TOP-SSE_MAN-0045 Paste Fill Management Plan
TOP-SSE_MAN-0046 Noise Blasting Management Plan
TOP-SSE_MAN-0047 Air Quality Management Plan
TOP-SSE_MAN-0048 Water Management Plan
TOP-SSE_MAN-0049 Vegetation and Rehabilitation Management Plan
TOP-SSE_MAN-0050 Heritage Management Plan
TOP-SSE_MAN-0051 Transport Management Plan
TOP-SSE_MAN-0052 Environmental Monitoring Plan
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 22 of 29
12 READ AND UNDERSTOOD DOCUMENT REQUIREMENTS All employees have a legal obligation to follow safe work practices and procedures when carrying out
any work task. Following the requirements of this document and other documents applicable to the
task being performed is critical in protecting the safety of all operators, co-workers and visitors to the
site.
All employees must strictly adhere to these requirements. Failure to do so could result in a serious
safety breach with consequences as part of the Code of Conduct. You are signing this
acknowledgement sheet agreeing to work to this procedure and have either read the document
personally or had the document read and explained to you and, have clearly understood the
requirements.
You also acknowledge that at any time you may not be sure of the requirements and the contents
contained within this and/or any other documents, you are to ask for a copy so that you are familiarised
again with the contents and requirements allowing you to operate this equipment and perform your
work safely.
Print Full Name: Full Signature: Date:
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 23 of 29
13 APPENDICES Appendix 1 – Definitions
Appendix 2 – Roles and Responsibilities
Appendix 3 – Example COC
Appendix 4 – Groundwater field data sheet
Appendix 5 – Surface water field data sheet
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 24 of 29
Appendix 1 – Definitions
TERM DEFINITION
Company Heron Resources Limited - Tarago Operations Pty Limited
AQMP Air Quality Management Plan
AR Annual Report
EMS Environmental Management Strategy
EPL Environment Protection Licence
LFA Landscape Function Analysis
PA Project Approval
TOP Tarago Operations
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 25 of 29
Appendix 2 – Roles and Responsibilities
The following outlines the responsibilities in relation to the compliance to this document.
Position Personnel Company Responsibility Contact Details
Managing Director Wayne Taylor Heron Overall responsibility for the construction and operation of the Woodlawn Project
02 9119 8111
Chief Operating Officer
Andrew Lawry Heron Responsible for project delivery and operations
02 4816 6341
General Manager Brian Hearne Heron Conduct of mining operations
02 4816 6344
Mine Manager Simon Fitzgerald Heron Mine Planning and Design
02 4816 6323
General Manager – Exploration and Geology
David von Perger Heron Resource evaluation
08 6500 9205
Site Services Manager
Jeffrey Lewis Heron Site Services 02 4816 6300
Environmental Officer
Dr Zoe Read
Kat McGilp
Heron
On site environmental management
02 4816 6335
Environmental Consultant
Robert Byrnes IEC Conduct of environmental management and compliance
02 4878 5502
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 26 of 29
Appendix 3 – Example COC
FO
R L
AB
US
E O
NLY
CO
OLE
R S
EA
L
No …
…
Inta
ct
…..
CO
OLE
R T
EM
P:
deg.C
MA
TR
IXD
ATE
TIM
ETY
PE
& P
RE
SE
RV
ATIV
E
CH
AIN
OF
CU
ST
OD
Y D
OC
UM
EN
TA
TIO
N
He
ron
Re
sou
rce
s li
mit
ed
LA
BO
RA
TO
RY
BA
TC
H N
O.:
SA
MP
LE
R(S
)):
(
Ple
ase c
onta
ct
sam
ple
r in
the e
vent
of
any
pro
ble
ms)
SE
ND
RE
PO
RT A
TTN
:S
EN
D IN
VO
ICE
ATTN
: P
HO
NE
:
FA
X:
EM
AIL
:
Date
:R
EP
OR
T N
EE
DE
D B
Y:
PL
EA
SE
PR
OV
IDE
RE
PO
RT
VIA
EM
AIL
(M
on
Pro
, p
df.
& E
xce
l) T
HA
NK
YO
U
PR
OJE
CT ID
: Q
UO
TE
NO
.:
AN
AL
YS
IS R
EQ
UIR
ED
P.O
. N
O.:
C
OM
ME
NTS
/SP
EC
IAL H
AN
DLIN
G/S
TO
RA
GE
OR
DIS
PO
SA
L:
SA
MP
LE
ID
# b
ott
les
Yes …
...
Bro
ken …
…
SA
MP
LE
DA
TA
* CO
NTA
INE
R D
ATA
Of:
Tim
e:
RE
LIN
QU
ISH
ED
BY
:R
EC
EIV
ED
BY
*Wate
r sam
ple
conta
iner
type a
nd P
reserv
ative
Codes:
P =
Neutr
al P
lastic;
N =
Nitric A
cid
Pre
serv
ed;
C =
Sodiu
m H
ydro
xid
e P
reserv
ed;
S =
Solv
ent
Washed A
cid
Rin
sed G
lass B
ott
le;
VC
= H
ydro
chlo
ric A
cid
Pre
serv
ed V
ial; V
S =
Sulp
huric A
cid
Pre
serv
ed V
ial; B
S =
S
ulp
huric A
cid
Pre
serv
ed
Gla
ss B
ott
le;
Z =
Zin
c A
ceta
te P
reserv
ed B
ott
le;
E =
ED
TA
Pre
serv
ed B
ott
les;
ST =
Ste
rile
Bott
le;
O =
Oth
er.
Nam
e:
Date
: N
am
e:
Date
:
Of:
Tim
e:
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 27 of 29
Appendix 4 – Groundwater Field Data Sheet
Da
te:
__
__
_ / _
__
__
/ _
__
__
Dip
To
Wa
ter
(DT
W):
_
__
__
__
Sa
mp
led
By:
__
__
__
__
__
__
__
__
__
__
__
__
__
Dip
To
Ba
se
(D
TB
): _
__
__
__
Fie
ld A
na
lys
is:
Tim
e
Vo
lum
e
Re
mo
ved
(L)
pH
EC
(uS
/cm
)
DO
(mg
/L)
OR
P
T
(de
g. C
)
Wo
od
law
n B
iore
ac
tor
La
nd
fill &
He
ron
Re
so
urc
es
Gro
un
dw
ate
r S
am
plin
g D
ata
Sh
ee
t
Bo
re V
olu
me
To
Purg
e [B
ore
Vo
lum
e *
3]: _
__
__
__
__
_
Bo
re N
o. _
__
__
__
__
__
__
__
Co
mm
en
ts
Bo
re V
olu
me
[(D
TB
- D
TW
) *
2]: _
__
__
__
__
_
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 28 of 29
Appendix 5 – Surface water field data sheet
Da
te:
_
__
__
_ / _
__
__
_ / _
__
__
_ S
am
ple
d b
y:
Fie
ld A
na
lys
is:
We
ath
er
co
nd
itio
ns
: _
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
__
_
Tim
eS
am
ple
Poin
tpH
EC
(uS
/cm
)T (
deg.
C)
DO
(m
g/L
)O
RP
Photo
(Y
/N)
Com
ments
Su
rfa
ce
Wa
ter
S
am
plin
g D
ata
Sh
ee
t: W
oo
dla
wn B
iore
acto
r , C
risp
s
Cre
ek I
nte
rmo
dal F
acili
ty, W
MB
T, H
ero
n R
eso
urc
es a
nd
SM
L
Title Plan
Document Owner: Jeffrey Lewis Authorised By: Brian Hearne
Doc. ID: TOP-SSE-MAN-0052 Rev No: 0 Date Issued: 30/01/2019 Date Printed: 31/01/2019 Page 29 of 29
Appendix 6 – Noise monitoring field data sheet
Heron Resources Noise Survey Worksheet Location__________________
Date________________ Start time__________ Finish time___________
Sound level to be stored down each column
Atmospheric conditions Air temperature (oC)
Wind speed (m/s) Relative humidity (%)
Wind direction Barametric pressure (hPa)