Woodberry Down Hybrid Planning Application · A hybrid planning application allows fewer details...
Transcript of Woodberry Down Hybrid Planning Application · A hybrid planning application allows fewer details...
Environmental Statement Non-Technical Summary September 2013
Woodberry Down Hybrid Planning Application
Woodberry Down – ES Non-Technical Summary
1
Contents
Introduction 2
The EIA Process and ES 2
Form of the Application and Basis of Assessment 5
Project Team 6
EIA Scoping and Consultation 7
The Site Context and Planning History 7
Alternatives Analysis and Design Evolution 9
The Proposed Development 10
Demolition and Construction 12
Socio-Economics 13
Traffic and Transportation 15
Air Quality 16
Noise and Vibration 17
Ecology 17
Water Resources, Drainage and Flood Risk 18
Ground Conditions and Contamination 19
Archaeology (Buried Heritage Assets) 20
Wind Microclimate 21
Daylight, Sunlight and Overshadowing 21
Townscape, Heritage and Visual Impacts 23
Effect Interaction and Cumulative Effects Assessment 23
Residual Effects and Conclusions 26
Contacts and Availability of the ES 27
References 28
Woodberry Down – ES Non-Technical Summary
2
Introduction
1.1 An Environmental Statement (ES) has been prepared in
support of the part outline, part detailed (full) planning
application (forming a ‘hybrid planning application’) for
the redevelopment of areas of the Woodberry Down
Estate, situated in the northernmost part of the London
Borough of Hackney (LBH).
1.2 Outline planning permission is being sought for the
demolition of existing buildings and structures at the
Woodberry Down Estate, to provide residential
floorspace; non-residential floorspace; new open space
and public realm. Along with associated car parking and
highway improvements.
1.3 Detailed planning permission is being sought for the
redevelopment of land bounded by Towncourt Path,
Green Lanes, West Reservoir / Spring Park Gardens and
Woodberry Down, for the erection of four buildings to
provide new homes; non-residential floorspace; new
open space and public realm with associated car parking.
1.4 The above works, for which the hybrid planning
application is being submitted, are hereafter referred to
as the ‘Proposed Development’.
1.5 This document provides a Non-Technical Summary
(NTS) of the ES and provides an overview of the findings
of the Environmental Impact Assessment (EIA).
1.6 The Proposed Development site (hereafter referred to as
the “Site”) falls within the administrative boundary of the
LBH and has an approximate area of 52 hectares (ha).
The land to be developed within this boundary covers an
approximate area of 22.7ha. The Site is bound by Green
Lanes and Finsbury Park (a large Grade II listed park) to
the west, and adjoins the London Borough of Haringey to
the north. The East and West Reservoirs are situated
within the Site and form the boundary to the south. The
New River loops around the Site, forming boundary to the
north and east, and bisects the Woodberry Down Estate
north of the reservoirs.
1.7 The Site location and context is shown in Figure 1. Figure
2 illustrates the planning application boundary, with the
area highlighted for which hybrid planning permission is
sought. Further details on the Site’s context can be found
in ‘The Proposed Development’ section of this NTS.
1.8 An original masterplan for the redevelopment of the entire
Woodberry Down Estate was granted outline planning
permission in 2009 (hereafter referred to as the ‘2009
masterplan’). However, the economic and political
context in which the 2009 masterplan is being delivered
is now different to that in which it was conceived. As
such, the scheme has since evolved and a new proposal
has been developed to reflect the elements of the
masterplan that remain to be delivered.
1.9 Since granting of the original outline planning permission,
detailed planning permissions have been granted to
areas of the 2009 masterplan through subsequent
detailed planning applications and approval of Reserved
Matters applications. Permissions are for five “Kick-Start”
Sites (KSSs) (together comprising Phase 1 of the 2009
masterplan), and for Phase 2. Further details are
provided within Chapter 1: Introduction of ES Volume I
and within the ‘Site Context and Planning History’ section
of this NTS.
The EIA Process and ES
1.10 Given the scale of the Proposed Development and
potential for effects on the environment, URS
Infrastructure & Environment UK Limited (URS) has been
commissioned by Berkeley Homes (Capital) Plc (the
‘Applicant’) to undertake an EIA of the Proposed
Development in line with the Town and Country
(Environmental Impact Assessment) (England)
Regulations 2011 (Ref. 1) (hereafter referred to as the
‘EIA Regulations’) and prepare an ES, which is submitted
in support of the hybrid planning application.
1.11 The potential environmental effects of the Proposed
Development have been systematically assessed through
the EIA process, the results of which are presented in full
within the ES. The ES is designed to inform readers of
the nature of the Proposed Development, the likely
environmental effects and the measures proposed to
eliminate, reduce or mitigate any significant adverse
effects on the environment. The ES describes the
environmental effects of the Proposed Development
during the demolition and construction phase, and on
completion and occupation of the Proposed
Development.
1.12 The significance of effects has been evaluated with
reference to specific standards, accepted criteria and
legislation where available. Where it has not been
possible or appropriate to quantify effects, qualitative
assessments have been carried out, based on
professional experience and judgement. Effects have
been classified as being (and further defined within
Volumes I and II of this ES):
• Adverse - Detrimental or negative effects to an
environmental / socio-economic resource or receptor
(a component of the natural created or built
environment such as human being, water, air, a
building, or a plant that is affected by an impact);
• Negligible - Imperceptible effects to an
environmental / socio-economic resource or receptor;
• Beneficial - Advantageous or positive effect to an
environmental / socio-economic resource or receptor.
Woodberry Down – ES Non-Technical Summary
3
Figure 1: Site Location and Context
Woodberry Down – ES Non-Technical Summary
4
Figure 2: Planning Application Boundary
Woodberry Down – ES Non-Technical Summary
5
1.13 Where adverse or beneficial effects have been identified,
these have been assessed against the following scale
(and further defined within Volumes I and II of this ES):
• Minor - Slight, very short or highly localised effect of
no significant consequence;
• Moderate - Limited effect (by extent, duration or
magnitude), which may be considered significant; or
• Major - Considerable effect (by extent, duration or
magnitude) of more than local significance or in
breach of recognised acceptability, legislation, policy
or standards.
1.14 Effects are also generally assigned a geographic extent
(local, regional or national) and duration (temporary
(short, medium or long-term) or permanent). In addition,
the ES identifies the potential for effect interactions and
cumulative effects.
1.15 Where there are adverse effects, mitigation measures
have been identified to eliminate, mitigate or reduce
those effects. Where mitigation measures have been
identified, these measures have been incorporated into
either the design of the Proposed Development;
translated into demolition and construction commitments;
or operational or managerial standards / procedures. The
ES highlights the ‘residual’ effects, which remain
following the implementation of suitable mitigation
measures, and classifies these in accordance with the
effect significance criteria terminology given above.
1.16 In order to assess the potential effects of the Proposed
Development, the existing conditions of and around the
Site (known as ‘baseline conditions’) have been
determined and considered. For the purposes of the EIA,
the baseline conditions have been taken as the
environmental and socio-economic conditions that
currently exist on the Site and of the surrounding area, in
the absence of any future redevelopment. Throughout the
ES, where the baseline deviates from the current
conditions, this has been explained and justified within
the technical chapters of the ES.
1.17 The ES consists of:
• Volume I: Main Assessment Text and Figures – this
document forms the main body of the ES, detailing
the results of environmental investigations, effects
arising and proposed mitigation measures. The ES
also includes details of the Proposed Development
and of the demolition and construction activities;
• Volume II: Townscape, Heritage and Visual Impact
Assessment – this document reports the findings of
the assessment of the effects on key and strategic
views to and from the Site. Volume II also reports the
findings of the assessment of effects to above ground
built heritage;
• Volume III: Technical Appendices – Comprises
survey data, technical reports and background
information supporting the assessments and
conclusions given within the main ES; and
• Non-Technical Summary (this document) –
summarises the key findings of the ES in non-
technical language.
Form of the Application and Basis of Assessment
Detailed and Outline Elements of the Hybrid Application
1.18 The Applicant is seeking to obtain a ‘hybrid’ planning
permission for the Proposed Development. A hybrid
planning application allows fewer details about certain
aspects of the Proposed Development to be submitted to
the local planning authority, whilst other aspects are
submitted in more detail.
1.19 As set out within the planning application Development
Specification, the Proposed Development will comprise
the following:
‘‘Outline planning permission (all matters reserved) for
demolition of existing buildings and structures at
Woodberry Down Estate to provide up to 275,604sqm
floorspace GEA [Gross External Area] (excluding car
parking); comprising up to 3,242 residential units and a
maximum of 10,921sqm non-residential floorspace within
Classes A1-A4, Class B1, Class D1 and D2 use and
Energy Centres; along with provision of new open space
and public realm and associated car parking and highway
improvement works to Seven Sisters Road including a
narrowing from six carriageways to four carriageways.
Full details submitted for the redevelopment of the land
bounded by Towncourt Path, Kayani Avenue, Green
Lanes, West Reservoir/Springpark Drive and Woodberry
Down (Phase 2) for the erection of four buildings between
3 and 20 storeys to provide 670 new homes, 550sqm of
non residential floorspace GEA within Classes A1-A4,
Class B1, Class D1 and D2 use and new open space and
public realm with associated car parking at ground and
basement level.”
1.20 All of the application will be submitted in outline, with the
exception of the previously permitted Phase 2 Blocks B,
D and F, which will be submitted in detail. The remaining
development sites identified within the consented 2009
masterplan will be submitted in outline only and form the
later phases of development (Phases 3-8).
1.21 This component of the planning application seeks outline
approval, at this stage, in relation to the following:
• Use – the use or uses proposed for the Proposed
Development and distinct building plots;
• Amount of development – the maximum amount of
proposed for each use;
• Indicative layout – an indicative layout showing
separate building plots proposed within the site
boundary;
Woodberry Down – ES Non-Technical Summary
6
• Scale parameters – an indication of the upper and
lower limits for height, width and length of each
building within the site boundary; and
• Means of Access – the principal access point / points
to the Woodberry Down Regeneration Area.
1.22 This component of the planning application ‘reserves the
detail of’ the following (known as ‘reserved matters’) for
future determination:
• Layout – the way in which buildings, routes and open
spaces are provided within the Proposed
Development, and their relationship to buildings and
spaces outside the development;
• Scale – the eight, width and length of each building
proposed, in relation to its surroundings;
• Appearance – the aspects of a building or place which
determine the visual impression it makes, excluding
the external built form of the Proposed Development;
• Access –accessibility to and within the site for
vehicles, cycles and pedestrians in terms of the
positioning and treatment of access and circulation
routes and how theses fit into the surrounding access
network; and
• Landscaping – the treatment of private and public
space to enhance or protect the site’s amenity though
hard and soft measures (e.g. through tree or hedge
planting, or screening by fences or walls).
1.23 The extent of the Proposed Development which is to be
fixed as part of the outline submission is defined within
the Development Specification, Parameter Plans and
Design Principles document, which are all submitted with
the planning application.
1.24 Full details have been provided for Phase 2 of the
Proposed Development and thus approval for Phase 2 is
sought for access, layout, scale, appearance and
landscaping. As such, outline planning permission is
sought for the Proposed Development, with the exception
of Phase 2, where the Applicant has provided more
details. In terms of Phase 2, where the Applicant has
provided more detail, the LBH has been asked to
approve the detail now, meaning that details of those
matters will not need to be subject to later agreement.
1.25 The detailed and outline components of the Proposed
Development are further detailed and summarised within
Chapter 4: The Proposed Development of ES Volume
I, and in the corresponding section of this NTS.
Assessment Scenarios
1.26 Owing to the long demolition and construction period
(approximately 25 years) and the various phases of
demolition and construction on the Site, four sequences
and ‘timeslices’ across the programme of works have
been defined to inform the EIA. Each timeslice represents
points in time when multiple works (and in the majority of
cases, occupation) are likely to occur across the Site.
The ES, where relevant to the assessment of demolition
and construction related effects, has assessed the
potential effects occurring at each of the four
representative timeslices. This is further explained in ES
Chapter 5: Demolition and Construction and the
corresponding ‘Demolition and Construction’ section of
this NTS.
1.27 For each technical topic of the ES, two Proposed
Development scenarios have been considered to allow
for the currently consented, but not yet constructed, Kick
Start Sites (KSSs) to be included within the EIA.
1.28 Proposed Development Scenario 1 assesses the existing
Site and surrounding area (baseline) and the hybrid
planning application, whilst Proposed Development
Scenario 2 assesses the baseline and hybrid planning
application, but also considers the surrounding consented
KSSs which are treated as being fully built out and
occupied.
1.29 For the purposes of the cumulative effects assessment,
Proposed Development Scenario 2 and other relevant
cumulative schemes (including non-Woodberry Down
schemes and proposed Woodberry Down amendment
applications for the KSSs) are assessed. These
cumulative schemes are detailed in Chapter 2: EIA
Methodology of ES Volume I and are summarised in
‘Effect Interaction and Cumulative Effects Assessment’ of
this NTS.
Project Team
1.30 This ES NTS has been compiled by URS and presents
the results of the EIA carried out by URS and a number
of technical specialists, consultants and designers
appointed by the Applicant. This team is presented in
Table 1, along with their respective disciplines and
contribution to the EIA.
Table 1: Design and Consultant Team
Organisation Expertise/EIA Input
Berkeley Homes (Capital) plc
The Applicant
URS
EIA Project Managers, in addition to authoring the following chapters and reports: Introduction; EIA Methodology; Demolition and Construction; Air Quality; Noise and Vibration; Ecology; Water Resources and Flood Risk; Ground Conditions; Effect Interactions and Cumulative Effects Assessment; Residual Effects Assessment and Conclusions; production of the Non-Technical Summary; Waste Strategy, Flood Risk Assessment; and Preliminary Surface Water Drainage Strategy
Woodberry Down – ES Non-Technical Summary
7
Fletcher Priest Architects
Architects for Phase 2 Block F and outline element of the application, in addition to authoring the following chapters: Alternatives and Design Evolution and the Proposed Development
Rolfe Judd Architects
Architects for Phase 2 Blocks B and D
Rolfe Judd Planning
Planning Consultant
WSP Traffic and Transportation
MOLA Archaeology (Buried Heritage Assets)
Quod Socio-Economics
RWDI Anemos Wind Microclimate
Antsey Horne Daylight, Sunlight and Overshadowing
Peter Stewart Consultancy and Cityscape
Townscape, Heritage and Visual Impact Assessment Report
CBRE Retail Impact Assessment
Richard Hodkinson Consultancy
Sustainability Statement and Energy Strategy, BREEAM and Code for Sustainable Homes
Townshend Landscape Strategy
George Cochrane
Statement of Community Involvement
EIA Scoping and Consultation
1.31 Consultation is critical to the development of a balanced
ES. Views of statutory and non-statutory consultees
serve to focus the studies and identify those issues which
require further investigation. In addition, consultation
enables mitigation measures to be incorporated into the
project design; consequently limiting adverse effects and
enhancing benefits.
1.32 An EIA Scoping meeting was held with the LBH as part of
the pre-application consultation process, prior to the
submissions of the EIA Scoping Report, to determine the
proposed scope of the EIA. In addition, over the course of
the design and EIA process, a number of consultees
have been consulted including, but not limited to, the
following:
• LBH;
• Greater London Authority (GLA);
• AMEC;
• Natural England;
• Environment Agency (EA);
• Transport for London (TfL); and
• London Fire and Emergency Planning Authority.
1.33 As part of the EIA process, an EIA Scoping Report was
submitted to the LBH on 11th March 2013. EIA Scoping
forms one of the first stages of the EIA process and it is
through EIA Scoping that the LBI and other consultees
are consulted on the scope and methodology of the EIA.
AMEC Environment & Infrastructure UK Ltd (hereafter
referred to as ‘Amec’) was appointed on behalf of LBH in
April 2013 to undertake an independent review of the
Scoping Report. Amec considered the consultees
responses and produced a Scoping Review. The LBH
issued their formal EIA Scoping Opinion (including the
Amex Scoping Review) on 26th June 2013. This EIA
Scoping Opinion and associated responses of other
consultees have been taken into account throughout the
EIA process and during the preparation of the ES.
Planning Policy Context
1.34 The EIA has been undertaken and the ES prepared with
regards to relevant national, regional and local planning
policy. At the national level, the key planning policy
document is the National Planning Policy Framework
(2012) (Ref. 2) which broadly sets out the Government’s
vision of sustainable development, which is to be
interpreted and applied locally to meet local development
aspirations.
1.35 At the regional level, the planning strategy for London is
set out within the London Plan: Spatial Development
Strategy for Greater London (2011) (the ‘London Plan’)
(Ref. 3). A number of London Plan policies are relevant to
the location, context and nature of the Proposed
Development. In addition to the London Plan, a number
of other regional planning documents have been
consulted including, but not limited to, the London View
Management Framework (2012) (Ref. 4) and the Mayor’s
supplementary guidance on Sustainable Design and
Construction (2006) (Ref. 5).
1.36 At the local level, consideration has been given to the
LBH Core Strategy (2010) (Ref. 6), which is the principal
document of the Local Development Framework, and
saved policies of the LBH Unitary Development Plan
(1995) (Ref. 7). Other local planning policy documents of
relevance include the LBH Development Management
Local Plan (Draft 2012) (Ref. 8), Woodberry Down Area
Action Plan Supplementary Planning Guidance (SPG)
(2004) (Ref. 9), and the Manor House Area Action Plan
SPG (2013) (Ref. 10).
The Site Context and Planning History
1.37 The Site (as shown in Figures 1 and 2) is approximately
52 ha in size (the land to be developed within this
boundary covers an approximate area of 22.7ha) and is
located in the north of the LBH, bound by Green Lanes
and Finsbury Park to the west. The Site adjoins the
London Borough of Haringey to the north with the London
Woodberry Down – ES Non-Technical Summary
8
Borough of Islington one kilometre (km) away to the
southwest. The East and West Reservoirs are situated
within the Site and form the boundary to the south. The
New River loops around the Site, forming the boundary to
the north and east and bisects the Woodberry Down
estate north of the reservoirs.
1.38 Seven Sisters Road (A503), a major highway, runs
directly through the northern section of the Site in a north-
easterly direction. Green Lanes (the A105) runs north-
south to the far west of Woodberry Down, with Manor
House Underground Station located at the junction of
Green Lanes and Seven Sisters Road.
1.39 The Site is situated on the ridge of a hill, running in
approximately the position of Seven Sisters Road. The
land falls from it to the north, allowing clear views of north
London, including Alexandra Palace. To the south, the
land also falls away, allowing views of the reservoirs and
City beyond.
1.40 The Site is currently occupied by the existing Woodberry
Down Estate which was constructed in stages from the
1940s through to the 1970s. The earliest residential
blocks on the estate (Nicholl, Needwood, Ashdale and
Burtonwood Houses) were constructed as eight storey
buildings with experimental lifts and reinforced concrete
construction. Later blocks followed the predominantly
five-storey balcony access model. A number of existing
blocks have been demolished as part of the regeneration
process and a number of sites have been constructed or
are under construction within Woodberry Down as part of
the 2009 masterplan, previous consented planning
application for the Site (see the ‘Previous Planning
Application’ section below).
1.41 The Estate includes a some shops on the western side of
Woodberry Grove, three schools (Woodberry Down
Primary School, Beis Chinuch Lebanos School and
Skinners’ Academy), St. Olave’s Church and Church Hall
and the John Scott Health Centre.
1.42 To the immediate north of the Site is an area of
employment land in the form of an industrial estate and a
retail complex adjacent to Haringey Green Lanes. The
East and West Reservoirs are located to the immediate
south of the estate, with Clissold Park and Stoke
Newington beyond that. The wider area is comprised
primarily of Victorian suburban housing, with limited 20th
century infill estates, incorporating some interwar and
post-war housing. To the west of Manor House lies
Finsbury Park an important green space within London.
1.43 The wider area is comprised primarily of Victorian
suburban housing, with limited 20th century infill estates,
incorporating some interwar and post-war housing. The
residential Portlands Estate is located to the south of
Finsbury Park along the south-western edge of the Site.
The area to the east, and beyond the reservoirs to the
south of the Site, is primarily residential. Land to the north
of the Site (within the boundary of the London Borough of
Haringey) includes residential development, the Arena
Shopping Park (including a Sainsbury’s supermarket) and
the Crusader Industrial site. Clissold Park, and Abney
Park Cemetery are all located within 2km of the Site and
Warwick Reservoirs and Leyton Marsh are approximately
1.8km away from the eastern boundary of the Site.
Previous Planning Application – the 2009 Masterplan
1.44 In 2009 Hackney Homes produced the 2009 masterplan
for the redevelopment of the entire Woodberry Down
Estate which set out a 20 year demolition and rebuild
programme. The 2009 masterplan was granted outline
planning permission on the 24th July 2009 for the
following:
‘To demolish all existing buildings on the Woodberry Down
Estate, with the exception of St.Olaves Church, the Beis
Chinuch Lebonos Girls School, Reservoir Centre, Primary
school and Health Centre. Redevelop the site with 4,684
homes (including 41% affordable), comprising 1-bed, 2-
bed, 3-bed, 4-bed flats, and 5-bed flats, 5-bed and 6-bed
houses with associated car parking at an overall site
provision rate of 50%; approximately 38,500 sqm of non-
residential buildings and associated car parking, including
5194 sqm of retail buildings within classes A1-A5, 3144
sqm of class B1 Business use, 30,000 sqm of class C1, D1
and D2 use including education, health centre, children’s
centre, community centres, youth centre; provision of new
civic space, public parks, open space, landscaping of the
edges of the New River and the East and West Reservoirs,
construction of bridges across the New River; reduce width
of Seven Sisters Road from 6 to 4 lanes and related
improvements to the public realm; formation of new access
points to the new Woodberry Down Neighbourhood, the
creation of new and improvement of existing cycle and
pedestrian routes to and within the estate (Outline
Application matters for determination siting, design and
means of access).’
1.45 Since then, detailed planning permissions have been
granted to areas of the 2009 masterplan through
subsequent detailed planning applications and approval
of Reserved Matters applications. Permissions are for
five “Kick-Start” Sites (KSSs) (together comprising Phase
1 of the 2009 masterplan), and for Phase 2, as shown on
Figure 3. Please refer to Chapter 1: Introduction of ES
Volume I for further details.
1.46 A number of the sites have been constructed or are
under construction within Woodberry Down as part of the
2009 masterplan. In addition there are a number of sites
for which planning permission has been granted which
have not been implemented (KSS4 and KSS5 Block 1).
Woodberry Down – ES Non-Technical Summary
9
1.47 The economic and political context in which the 2009
masterplan is being delivered is however now different to
that in which it was conceived. As such, the scheme has
since evolved and a new proposal has been developed to
reflect the elements of the masterplan that remain to be
delivered. The new proposal (in the form of the hybrid
planning application) is sufficiently flexible to enable the
scheme to adapt to changing circumstances including
shifts in the housing market.
Alternatives Analysis and Design Evolution
1.48 Under the EIA Regulations, an ES is required to provide
“an outline of the main alternatives studied by the
applicant or appellant and an indication of the main
reasons for the choice made, taking into account the
environmental effects”. Alternatives analysis is a key part
of the EIA process and serves to ensure that
environmental considerations are built into the project
design at the earliest possible stage. The ES considers
the ‘no development option’; ‘alternative sites’; and
‘alternative designs and design evolution.’
1.49 The ‘no development’ option refers to the option of
leaving the Site in its current state. This option is
undesirable for a number of reasons:
• Under-utilisation of the current Site by the existing
partly vacant buildings; and
• The fact that some of the buildings have been left
vacated and as such would degrade. The possible
use of the existing buildings is dependent upon the
property market and the current designated use.
1.50 As a result of the above, the ‘no development option’ was
ruled out by the Applicant.
1.51 No other development sites have been considered by the
Applicant. The development opportunity development
opportunity for the Site arose with the development
agreement between the Applicant and the Landowner.
The development agreement was formed on the basis of
the 2009 masterplan extant permission to develop the
land.
1.52 Alternative sites have not been considered by the
Applicant also because there are very few sites suitable
for a development in the area with all of the following
requirements:
• A site suitable for a development which can
incorporate space suitable for occupation by up to
3,912 residential dwellings (depending on precise mix
of units) or 333,408 sqm (Use Class C3);
• Up to 11,451 sqm non-residential floorspace (plus
energy centres) with potential for retail shops,
financial or professional services, or food and drink
(Use Classes A1-A4), business (Use Class B1), non-
residential institutional use e.g. as a clinic/health
centre, public hall or museum (Use Class D1) and/or
amenity and leisure (Class D2) use; and
• A site subject to excellent transport links for ease of
access.
1.53 The proposals have been created as an output of a
masterplan review process, undertaken over more than a
year from early 2012 onwards to review the consented
2009 masterplan. This process arose from a concern
from the Applicant and other stakeholders that the 2009
masterplan was not fully maximising the opportunities of
the Site and in various aspects was not able to respond
to changing circumstances since the original proposals
for the Site were first created.
1.54 Analysis of the 2009 masterplan found that it:
• Is relatively neutral in its character;
• Does not fully exploit the most significant asset of the
Site, namely the reservoirs and New River, limiting
the benefit of these to blocks adjacent to the water;
• Creates landscaped open spaces that are neutral in
character and could form a stronger overall network of
public realm that could unite the Site;
• Physical linkages to Finsbury Park could be
strengthened as well as exploiting views towards the
major open space;
• Places significant amounts of development adjacent
to Seven Sisters Road, potentially without visual or
other amenity to compensate for this location;
• Creates a large number of short streets and creates
public routes dominated by cars and on-street
parking;
• Restricts the scale and diversity of house types that
can be provided due to its block sizes and orientation.
In doing so, it limits the opportunities for usable
amenity in open spaces within blocks; and
• Is restrictive in its parameters, limiting the scope for
future proposals to adapt to changing demands and
circumstances.
1.55 The 2009 masterplan created a point of reference for many
aspects of the project, including the fundamental regeneration
of the estate, the key principles for that regeneration and the
physical form of the first phase buildings that have been
delivered as a consequence of that consent.
1.56 The key considerations throughout the evolution of the
Proposed Development have been:
• The desire to respond strongly to the opportunities
established by the landscape context of the Site;
• The need to weave in and around fixes set by existing
highways and built/consented buildings;
• The reconfiguration of streets and open spaces to
create a landscape structure that strongly connects
north-south from the reservoirs to the New River,
Woodberry Down – ES Non-Technical Summary
10
treating this as a primary organising device for all
aspects of the masterplan;
• The desire to increase the quality and scale of public
open spaces across the masterplan;
• The desire to locate taller buildings in locations that
can respond well to views and minimise their impacts
on immediate neighbours; and
• The desire to create improved housing.
1.57 A comprehensive review of the alternatives considered and
the design evolution of the Proposed Development since the
concept scheme in 2011 can be found within Chapter 3:
Alternatives and Design Evolution of the ES (Volume I).
The Proposed Development
1.58 The planning application description of the Proposed
Development is set out in the ‘Form of the Application and
Basis of Assessment’ section earlier in this NTS. It will
comprise outline planning permission for the demolition of
existing buildings on Site and the provision of up to
275,604sqm of residential and non-residential floorspace
(retail, business, community and culture and assembly and
leisure); along with the provision of new open space and
public realm and associated car parking and highway
improvement works to Seven Sisters Road (including a
narrowing from six carriageways to four carriageways). It also
comprises full (detailed) planning permission for the
redevelopment of the land bounded by Towncourt Path,
Green Lanes, West Reservoir/Spring Park Gardens and
Woodberry Down for the erection of four buildings between 3
and 20 storeys to provide 670 new homes, 550 sqm of non-
residential floorspace GEA (retail, business, community and
culture and assembly and leisure) and new open space and
public realm with associated car parking.
1.59 Figure 3 presents the Proposed Development Site Plan. The
Proposed Development is subdivided into development
phases; Phases 3-8 will be delivered within the outline
application while Phase 2 is made up of the detailed
components of the Proposed Development and includes
three blocks (B, D and F) and a new public open space
known as Spring Park (see Figure 4). Figure 3 also shows the
location of the five consented KSSs which together comprise
Phase 1 of the 2009 masterplan.
1.60 In terms of the scale of the Proposed Development, buildings
heights vary between 3 and 20 storeys (plus basement and
ground levels) across the Phase 2 component. The tallest
element of the Phase 2 scheme at 20 storeys (including
ground floor) is one of the towers proposed within Block F.
The heights in the outline component of the Proposed
Development range from minimum 44.6m AOD to maximum
92.8m AOD in northwest portion of the Site adjacent to Green
Lanes.
1.61 The detailed component of the Proposed Development
provides 670 residential units and up to 3,242 residential
units within the outline component and will include a mix of
town houses and apartments and affordable housing. It is
estimated that there will be approximately 1,030 new
residents within the detailed component and between 5,720
and 5,740 residents (gross) living on-site in the outline
component, depending on the final housing mix. Of these, the
net additional population living in the private and intermediate
units within the outline component of the Proposed
Development is estimated to be between 3,920 and 4,100
based on the indicative minimum and maximum housing
mixes respectively. The new community will contribute to the
creation of a new sense of identity for the Site and a vibrant
environment.
1.62 Table 4 presents the maximum floorspace allocations of the
Proposed Development.
Table 4 Maximum Floorspace of the Proposed
Development (Both Outline and Detailed Phase 2
Components)
Proposed Use
Gross External
Area (GEA)
(m2)
Residential (Use Class C3) 333,408
Retail (Use Class A1/A2/A3/A4) 3,281
Business (offices and flexible workspace) (Use Class B1)
2,500
Community and culture (Use Class D1)
2,000
Assembly and leisure (Use Class) D2
2,000
Energy Centres 1,670
Total 340,979
.
1.63 The Proposed Development will provide a maximum of
3,281sqm (GEA) of retail use (A1/A2/A3/A4). The proposed
retail floorspace use has the potential to be distributed across
a number of development phases but is expected to be
focused around the central square and along Seven Sisters
Road.
1.64 A maximum of 2,500 sqm (GEA) of floorspace has been
provided for business use (B1) and is expected to provide
flexible office and workspace at ground and first floor level.
1.65 A maximum of 2,000sqm (GEA) of floorspace has been
provided for assembly and leisure use (D2) and could be
used to provide a variety of facilities such as sports or multi-
use halls, gymnasiums, health clubs and cinema. A maximum
of 2,000sqm (GEA) of floorspace has also been provided for
community and culture use (D1).
Woodberry Down – ES Non-Technical Summary
11
Figure 4: Phase 2 Block Layout
Figure 3: Proposed Development Site Plan showing Indicative Phases of the Proposed Development and Consented KSSs
Block F
Block D
Block B
Spring Park
Block E
Woodberry Down – ES Non-Technical Summary
12
1.66 The Proposed Development will include areas of open space
comprising Principal Open Spaces (Spring Park, Rowley
Gardens); Secondary Public Open Spaces (major public
routes); the New Central Square and Strategic Public Open
spaces. These landscaped spaces and routes will form ‘green
fingers’ throughout the Site. Spring Park will become a
significant part of the public realm, providing a wide range of
community activities and uses. A network of space will be
created by a series of landforms, planting and edges; each of
these spaces will offer a different character and use, creating
a journey through the public realm.
1.67 The Proposed Development will include a range of formal and
informal areas of play including Doorstep Playable Space
(DPS) for under 5’s. These will be located within 100m
walking distance from homes and will include lawns for
external play, small scale fixed equipment for spinning or
running and play features built into the topography. Further
information on Play provision is set out within the Landscape
Strategy which supports this hybrid planning application.
1.68 Access around the Site will be created by legible, safe and
attractive connections that provide increased access from the
New River to the reservoirs as well as from east to west.
Measures will be incorporated to facilitate access such as
ensuring all facilities are in accessible locations, recognising
the need for level access to buildings, providing a choice of
routes where required and providing safe pedestrian routes
and road crossings.
1.69 A maximum of 1,262 car parking spaces will be provided
across the Proposed Development. This will include on street
parking, podium/undercroft parking, basement parking and
service zone parking. One cycle parking space will also be
provided for every residential unit. A quantum of car parking
spaces equivalent to 10% of the residential units will be
designed to disabled standards.
1.70 For residential parking, a minimum of 20% of the overall
number of parking spaces will be equipped with electric
vehicle charging facilities with a further 20% with passive
provision. For retail parking, 10% of all spaces will have
electric car charging points with an additional 10% passive
provision for electric vehicles in the future.
1.71 An appropriate level of car club spaces is to be provided
within the Proposed Development. The provision will be
reviewed as the development evolves through the site-wide
Travel Plan.
1.72 The key sustainability credentials for the scheme are as
follows:
• Code for Sustainable Homes rating of Level 4 to be
achieved by all residential dwellings;
• BREEAM ‘very good’ to be achieved by all non-
residential units;
• CO2 emissions to be reduced with the use of
combined heat and power (CHP);
• All dwellings designed to principles of Lifetime
Homes;
• Water use for all dwellings limited to no more than
105 litres/person/day;
• Green and/or brown roofs to be incorporated where
feasible, maximising ecological value and helping to
reduce urban heat island effect;
• Cycle parking to be provided throughout;
• Provisions for Home Offices to reduce need to travel;
• Site Waste Management Plan to reduce construction
waste going to landfill;
• Construction of all blocks to be registered with
Considerate Constructor’s Scheme; and
• Ecological value to be maximised where possible
throughout.
1.73 A full description of the Proposed Development is provided
within Chapter 4: The Proposed Development of the ES
(Volume I).
Demolition and Construction
1.74 Demolition and construction works are anticipated to
commence in winter 2013. Given the scale of the
Proposed Development, the current expectation is that
these works would take approximately 25 years with an
end date of approximately winter 2037.
1.75 It is anticipated that the demolition and construction
works will take place in seven phases (Phase 2 – 8).
Phase 1 refers to the Kick Start Sites (KSSs) which
obtained consent under the 2009 masterplan and
subsequent Reserved Matters and detailed planning
applications.
1.76 The demolition and construction phases will comprise the
following key stages:
• Demolition;
• Arrangement prior to commencement of works;
• Enabling works;
• Piled foundations;
• Construction of the basement and floor frames;
• Construction of the cladding and roof finishes;
• Internal fit out; and
• External works.
1.77 Owing to the long construction period and the various
phases of demolition and construction on the Site, four
sequences and ‘timeslices’ across the programme of
works have been defined to inform the EIA. Each
timeslice represents points in time when multiple works
(and in the majority of cases, occupation) are likely to
occur across the Site. The ES, where relevant to the
assessment of demolition and construction related
Woodberry Down – ES Non-Technical Summary
13
effects, has assessed the potential effects occurring at
each of the four representative timeslices as follows:
• Sequence 1: start 2013 to the end of 2019 (7 years),
with representative ‘timeslice’ assessment year as 3rd
quarter of 2016;
• Sequence 2: start 2020 to the end of 2025 (6 years),
with representative ‘timeslice’ assessment year as 4th
quarter of 2021;
• Sequence 3: start 2026 to the end of 2032 (7 years),
with representative ‘timeslice’ assessment year as 4th
quarter of 2028; and
• Sequence 4: start 2033 to the end of 2037 (5 years),
with representative ‘timeslice’ assessment year as 4th
quarter of 2034.
1.78 It is anticipated that the core working hours for both the
demolition and construction phases would be as follows:
• 08:00 – 18:00 hours weekdays;
• 08:00 – 13:00 hours Saturday; and
• No working normally undertaken on Sundays or Bank
Holidays.
1.79 It is recognised that approval from the LBH is required for
any works that need to be undertaken outside these
permitted hours.
1.80 Access routes to and from the Site to be used by heavy
goods vehicles (HGVs), for deliveries of material to the
Site and for the removal of wastes, will be agreed with
the LBH prior to initiation of demolition and construction
works.
1.81 Demolition and construction vehicles are expected to
access Phase 2 block F via Woodberry Down to the north
of the Site via a dedicated site entrance. For Phase 2
blocks B and D, all vehicles will enter and exit the site via
Green Lanes and a dedicated site entrance to the west of
the site.
1.82 The Site will be registered with the ‘Considerate
Constructors Scheme’. This is a national initiative
through which construction sites and companies
registered with the Scheme are monitored against a
Code of Considerate Practice, designed to encourage
best practice beyond statutory requirements.
1.83 The commitments made within the ES would be
incorporated into a Construction Environmental
Management Plan (CEMP), which would include roles
and responsibilities, detail on control measures and
activities to be undertaken to minimise environmental
impact, and monitoring and record-keeping requirements.
A commitment would be made to periodically review the
CEMP and undertake regular environmental audits of its
implementation during the construction phase of the
Proposed Development.
1.84 A Waste Strategy has been produced for the Site and
accompanies the planning application (please refer to ES
Volume III Technical Appendix J). This outlines that
waste arising from the demolition and construction
phases of the Proposed Development would be
separated into key waste groups, with the contractor
providing a suitable area(s) within the Site for the
separation of materials for recycling (e.g. timber, metals,
packaging, hardcore etc.), or if necessary (due to space
constrictions) arranging for this segregation to instead be
undertaken off-Site by a suitable waste contractor.
1.85 All relevant contractors would be required to investigate
opportunities to minimise and reduce the use of energy
and water, such as:
• Use of alternatives to diesel/petrol powered
equipment where possible;
• Selection and specification of energy efficient plant
and equipment wherever viable;
• Implementation of staff based initiatives such as
turning off taps, plant and equipment when not in use
both on-Site and within Site offices; encouraging a
paper-reduced office and encouraging double sided
printing and photocopying when these activities are
necessary;
• Use of recycling water systems such as wheel
washes;
• Use of a rainwater harvesting system for use in
equipment and vehicle washing will also be
investigated; and
• Above ground oil storage tanks to mitigate
watercourse contamination.
Socio-Economics
1.86 Chapter 6: Socio-economics considers the potential
socio-economic effects arising as a result of the
Proposed Development. The assessment considers the
following effects:
• Demolition and construction employment;
• Housing provision;
• Population;
• Healthcare;
• Employment;
• Additional household spending;
• Open space; and
• Crime and safety.
1.87 The Proposed Development forms part of the wider
Woodberry Down Masterplan. As an estate renewal
project, a large proportion of the existing residents on-site
are expected to be rehoused on-site in the new housing.
Therefore all of the residents of the new housing will not
all be net additional to the Site. The decanting of the
existing housing is on-going and therefore, it is not
possible to determine the exact number of residents
which will be rehoused. This assessment, therefore
Woodberry Down – ES Non-Technical Summary
14
assumes that all of the social housing proposed will
accommodate existing residents. The population
expected to live in these units are not considered to be
net additional.
Demolition and Construction
1.88 The demolition and construction phases of the detailed
part of the Proposed Development will generate 180
permanent (“Full Time Equivalent”) construction jobs. At
the regional level, the likely direct effect of the
construction employment is considered to be of a
negligible significance in comparison to the scale of the
broader regional construction force.
1.89 The demolition and construction phases of the outline
part of the Proposed Development will generate 520
permanent (“Full Time Equivalent”) construction jobs.
Similarly, the likely direct effect of the construction
employment is considered to be of a negligible
significance at the regional level.
Complete and Occupied Proposed Development
1.90 The detailed part of the Proposed Development includes
the delivery of 670 new homes which could
accommodate up to 1,030 residents. The effect of the
detailed part of the Proposed Development on housing
delivery will be of moderate, beneficial, permanent
significance at the local and district level. The detailed
part of the Proposed Development includes private and
intermediate housing, therefore all of the residents
expected for this part of the development are considered
to be net additional.
1.91 The outline part of the Proposed Development could
deliver between 3,007 and 3,242 homes. For the
purposes of this assessment an indicative minimum and
maximum housing mix has been assessed, as the
detailed design of the housing within the outline part of
the Proposed Development has not yet been fixed. It is
estimated that this could accommodate between 5,720
and 5,740 residents, which would equate to a net
additional population estimated to be between 3,920 and
4,100 residents. The effect of the outline part of the
Proposed Development on housing deliver will be of
major, beneficial, permanent experience at the local
and district level.
1.92 These new residents will increase the demand for social
infrastructure, particularly healthcare, education and open
space.
1.93 The detailed part of the Proposed Development will
create demand for the services of less than one
additional General Practitioner (GP). It has been
assessed that this additional demand could be met
through existing provision available locally. The outline
part of the Proposed Development will create demand for
the services of over two additional GPs. Mitigation may
be required to increase the level of healthcare provision
in the local area to meet this future demand. The residual
effect of both the detailed and outline part of the
Proposed Development on healthcare will be of
negligible significance.
1.94 The detailed part of the Proposed Development is
estimated to result in an additional 24 primary school
places and 6 secondary school places. This additional
demand could be met by existing provision locally. The
effect of the detailed part of the Proposed Development
on education will be of negligible significance.
1.95 The outline component of the Proposed Development is
estimated to result in the demand for between 102 and
133 net additional primary school places and between 28
and 38 secondary school places. This additional demand
would be mitigated through financial contributions to be
agreed as part of any future planning consent. The effect
of the outline component of the Proposed Development
on education will be of negligible significance.
1.96 The Proposed Development includes the provision of
open space provided throughout the Site in a range of
spaces which can be categorised into the following types
of spaces: Principal Public Open Spaces; Secondary
Public Open Spaces; a new Central Square; Strategic
Public Open Spaces; and Private Open Space.
Playspace provision will be met within these spaces in
line with the policy guidance on playspace provision.
Playspace will be provided within a hierarchy of types
according to the age profiles catered for. Doorstep
Playable Space will provide for children under 5 years,
Local Playable space will provide for children under 11
years, Neighbourhood and Youth Space will provide for
older children over 12 years. The effect of both the
detailed and outline component of the Proposed
Development on open space and play provision will be of
moderate, beneficial, permanent significance at the
local level.
1.97 Non-residential floorspace proposed in both the detailed
and outline parts of the Proposed Development would
generate employment. In total there could be up to 9,781
sqm GEA of non-residential floorspace, although the
amount and exact use of the non-residential floorspace
has not been fixed. Therefore a potential range of
employment types has been assessed to estimate the
number of jobs which could be generated on-site. It is
estimated that the detailed part of the Proposed
Development could accommodate up to 30 jobs, and the
outline part of the Proposed Development could
accommodate up to 305 jobs. The effects of the detailed
and outline components of the Proposed Development on
employment would be of minor to moderate, beneficial,
permanent significance at the local level.
Woodberry Down – ES Non-Technical Summary
15
1.98 In addition to the delivery of new housing, open space
and employment, the Proposed Development would
increase the level of household spending which could be
captured in the local area. It is estimated that the detailed
part of the Proposed Development could generate up to
£8.4 million per year in additional household spending,
and the outline part of the Proposed Development could
generate between £30.2 and £33.2 million per year net
additional household spending. This represents effects
on additional spending of minor to major, beneficial,
permanent significance.
1.99 As part of the estate renewal, the Proposed Development
will increase the mix of tenures on-site, which will help to
create a balanced and mixed community. The increase in
housing and population will have a positive impact on
crime and safety. Higher levels of activity across the site
will increase the level of natural surveillance which helps
to improve people’s sense of security. The design of the
buildings and public realm will be carried out in line with
Secure by Design principals to ensure opportunities for
crime are minimised and security is maximised. The
effect of both the detailed and outline parts of the
Proposed Development on crime and safety will be of
moderate, beneficial, permanent significance.
1.100 Overall any potential increase in the demand for social
infrastructure would be mitigated through on-site
provision within the non-residential floorspace proposed,
or through financial contributions provided when planning
consent is given. The Proposed Development would have
a positive effect by providing new housing, improved
open space and public realm and the creation of
employment through the construction and operational
phase.
Traffic and Transportion
1.101 Chapter 7: Traffic and Transportation of the ES
(Volume I) considers the potential impacts and likely
effects of the Proposed Development Scenarios on public
transport, the highway network, pedestrian movement, as
well as a summary of the findings of the Transport
Assessment (TA). The assessment follows the relevant
methodologies set in the current policy guidance or
otherwise relies on the application of professional
judgement.
1.102 This assessment has been undertaken in a number of
stages. The first stage involved analysing the baseline
conditions of the existing Site, the second stage
calculated the likely trips generated by the Proposed
Development, and the third stage undertook an
assessment of these trips in relation to the baseline
conditions, taking into consideration mitigation measures
integral to the development proposals.
Demolition and Construction
1.103 Demolition and construction workers would access the
Site by public transport; however the effect of these trips
is judged not to be significant. Following mitigation
measures such as scheduling and consolidating
deliveries and loading / unloading of materials and
equipment to occur within the individual Phase Site
boundary wherever possible, minimising the likelihood of
congestion on highways surrounding the Site, the likely
increase in additional vehicle trips and Heavy Goods
Vehicle (HGV) trips on the local road network during the
demolition and construction works will result in a
negligible effect.
1.104 The number of construction vehicles that will access and
leave the Site will be very low (maximum of 19 per hour
two way trips during peak times) and the frequency of
occurrences when pedestrians encounter an operational
vehicle would therefore be very low. On this basis, there
would be a negligible effect on pedestrians using the
footways immediately surrounding the Site. A Demolition
Method Statement (DMS), Construction Method
Statement (CMS), Construction Environmental
Management Plan (CEMP) and Construction Logistics
Plan (CLP) will be prepared to manage traffic, including
the use of banksmen (to monitor and direct vehicle
movement on or around the Site).
Complete and Occupied Proposed Development
1.105 The Proposed Development is predicted to mainly
generate trips taken on public transport, albeit there will
also be some associated car driver trips. These trips
would be expected to be comparatively low, due to low
level of car parking provision.
1.106 The main pedestrian desired routes are anticipated to be
along Seven Sisters Road. The existing good pedestrian
facilities would be enhanced by the narrowing of this
road, but the delivery of the Proposed Development is not
dependant on the road narrowing being implemented.
The pedestrian environment within the Site would be of
high quality with the provision of permeable and attractive
open spaces focused around a new public park. The
permanent residual effects would be:
• Minor Beneficial on pedestrian severance (perceived
divisions that can occur within a community when it
becomes separated by a traffic route), given that the
Proposed Development would facilitate improved
access through the Site, improved pedestrian
footways and crossing facilities;
• Minor Beneficial on pedestrian delay, due to
increased permeability across the Site;
• Negligible on pedestrian fear and intimidation, due to
lighting of walkways and improved natural
surveillance; and
Woodberry Down – ES Non-Technical Summary
16
• Minor Beneficial on pedestrian amenity, due to
proposed improvements and additions to pedestrian
facilities.
1.107 The effect on the bus network equates to up to an
additional 6 passengers per bus service for the entire
Woodberry Down Masterplan Development. There would
be an increase in demand for London Underground trips
among Woodberry Down residents of up to 7% and the
number of rail trips is calculated be negligible due to the
wide range of National Rail stations accessible from the
Site. Therefore the effect of the Proposed Development
on the bus, underground and rail networks is considered
to be negligible.
1.108 The number of additional vehicular trips associated with
the Proposed Development is reviewed in context of the
Baseline conditions experienced on the road network.
Along local roads the Proposed Development would
increase in traffic flows; however this results in no road
capacity issues. For the strategic roads the Proposed
Development trips would have a negligible effect.
1.109 A draft Travel Plan and Servicing Management Plan have
been produced aiming to reduce car driver trips and
hence the effect on the road network. These documents
will be agreed and finalised in conjunction with LBH.
Air Quality
1.110 Chapter 8: Air Quality of the ES provides an
assessment of the potential effects on local air quality
from the on-site construction plant and associated dust
generation; road traffic during both the demolition and
construction phase, and the operational phases of the
Proposed Development; and the emissions associated
with the heating and power plant attributed to the
Proposed Development once operational.
1.111 The dispersion models have been used to quantify the
change in pollutant concentrations at representative
existing air quality sensitive receptors in the vicinity of the
Proposed Development Site. This has been based on
predicted emissions data from the change in traffic flow
as a result of the Proposed Development, and the
operation of energy plant. The predictions of annual
mean nitrogen dioxide, particulate matter and fine
particulate matter concentrations have been made for
baseline, construction and operational scenarios.
1.112 Baseline (existing) air quality has been predicted to be in
exceedance of or at risk of exceeding the national air
quality objective for nitrogen dioxide at existing,
committed and proposed sensitive receptor locations in
the 2011 and 2016 air quality scenarios considered. By
2021, concentrations have fallen to levels that are not at
risk of exceeding the national air quality objective for that
pollutant. Baseline concentrations of all other pollutants
considered in this assessment are well below their
respective national air quality objectives in all of the
scenarios considered.
Demolition and Construction
1.113 In general, construction activities have the potential to
generate fugitive dust emissions as a result of demolition,
construction, earth works or trackout of material. For the
Proposed Development, the concentrations of any
airborne particulate matter generated by these activities
would be controlled using on site management practices
to the extent that the Proposed Development should give
rise to effects of negligible significance on dust
deposition rates at the nearest sensitive receptors. The
impact of fugitive emissions of particulate matter at these
receptors, with proposed mitigation applied would be
negligible. Overall the effect of fugitive emissions of dust
and particulate matter from the proposed works will be
managed during the demolition and construction process
and is considered to be not significant with respect to
potential effects on health and amenity.
1.114 During the construction of both detailed (Phase 2) and
outline components of the Proposed Development,
construction emissions associated with construction
phase vehicle movements would lead to an imperceptible
to small increase in annual mean concentrations of
nitrogen dioxide. Such an effect on local air quality is not
considered to be significant.
Complete and Occupied Proposed Development
1.115 With the Proposed Development in operation, there is in
an imperceptible to small change in nitrogen dioxide
concentrations across the study area. A small change in
annual mean concentrations of nitrogen dioxide, in an
area where baseline levels are below the air quality
objective, would result in a negligible effect on local air
quality.
1.116 By 2021 the majority of the areas within the air quality
study area will be below the national air quality objective
for the pollutants considered. By 2034 and 2037, when
the Proposed Development is complete, all areas of the
study area where there is relevant exposure will be below
the national air quality objectives considered. As such, it
is considered that the Proposed Development is suitable
for residential use.
1.117 Overall, the detailed (Phase 2) and outline components of
the Proposed Development would not have a significant
effect on local air quality. Whilst the Phase 2 would
introduce receptors into an area where the quality of air
exceeds the national air quality objective nitrogen
dioxide, concentrations are expected to fall below the
objective within a few years of its operation.
Woodberry Down – ES Non-Technical Summary
17
Noise and Vibration
1.118 Chapter 9: Noise and Vibration of the ES (Volume I)
presents an assessment of the likely significant effects of
the Proposed Development with respect to noise and
vibration in terms of:
• Predicted noise and vibration levels from the
demolition and construction works;
• Noise from building services plant associated with the
Proposed Development during operation; and
• Any increases to road traffic attributed to the
Proposed Development.
1.119 A baseline noise survey was undertaken to establish
noise levels at selected locations around the Site. It was
noted during the baseline survey that the noise
environment is dominated by road traffic on the
surrounding road network;
Demolition and Construction
1.120 The assessment indicates that demolition and
construction activities may result in negligible to
temporary moderate adverse noise effects at nearby
properties. It should be noted that construction noise
predictions are based on a worst case scenario where,
over the course of a working day, all plant are operational
at all areas of all worksites. In reality, it is likely that the
worst case noise levels predicted will only occur for
limited periods of time.
1.121 Temporary piling activities are likely to occur close
enough to the John Scott Health Centre/Nursery that
vibration may be noticeable, but will not be strong enough
to result in cosmetic building damage.
1.122 Demolition and construction noise and vibration
mitigation measures include, but are not limited to, the
following:
• Use of only modern, quiet and well maintained
equipment;
• Use of low impact techniques;
• Use of modern piling rigs;
• Use of electrically powered equipment run from the
mains supply;
• Careful planning of the sequence of work in order to
minimise the transfer of noise or vibration to
neighbours; and
• Erection of acoustic screens where necessary.
1.123 The highest increase in road traffic due to construction
vehicles on the surrounding roads is a 2% increase on
Woodberry Down and Springpark Drive. This increase in
road traffic would not result in a noticeable increase in
noise level and is expected to be of negligible
significance.
1.124 Although no mitigation is required, in order to reduce the
perception of impacts of demolition and construction
traffic noise, a number of mitigation measures will be
implemented. For example, all traffic entering and leaving
the worksite will be closely controlled and all vehicles will
travel via designed traffic routes which will be previously
agreed with the LBH and Transport for London. As such,
as stated above, the residual demolition and construction
traffic noise impact will be of negligible significance.
Complete and Occupied Proposed Development
1.125 Changes in road traffic flows due to the Proposed
Development have been calculated as increasing noise
levels by an imperceptible level. Therefore, changes in
road traffic flows are considered to be acceptable in
terms of noise and of negligible significance.
1.126 Fixed plant associated with proposed buildings has been
set noise limits based on background noise levels
measured in quiet areas around the Proposed
Development site. Fixed plant should be designed to
produce noise levels at existing properties that do not
exceed these noise limits and is of negligible
significance.
Ecology
1.127 Chapter 10: Ecology of the ES (Volume I) assesses the
likely potential effects on ecology and conservation,
arising from the demolition, construction and operation of
the Proposed Development.
1.128 The Site is dominated by buildings and hardstanding. The
remainder of the Site is comprised of scattered trees,
introduced ornamental shrubs and a small area of
amenity grassland. The Site contains a range of habitats
suitable for breeding and overwintering birds; most
notably the East and West Reservoirs and mature trees,
some of which are located within private gardens. In
addition, a number of statutory and non-statutory sites
designated for their nature conservation value have been
identified within 2km of the Site.
Demolition and Construction
1.129 Due to the temporary and transient nature of demolition
and construction works, any effects to local habitats
(including Lee Valley Special Protection Area, New River
and Stoke Newington Reservoirs) either directly (for
example through compaction and disturbance by
machinery) or indirectly (through for example emission of
pollutants), will be of low impact and of negligible
significance.
1.130 A survey for all nesting birds will be undertaken by a
suitably qualified ecologist prior to undertaking the works
during the bird breeding season, to check for the
presence/absence of any bird’s nests. If any active nests
are found, the work will cease, the area with the nests will
be left in situ and an appropriate buffer zone will be
established. This area will be left intact until it has been
Woodberry Down – ES Non-Technical Summary
18
confirmed by the ecologist that the young have fledged
and the nest is no longer in use.
1.131 Works will not be undertaken at night, avoiding impacts
relating to increased light and noise disturbance at night,
which may affect foraging and commuting bats and other
nocturnal mammals.
1.132 A CEMP will be developed to provide a framework for the
management of environmental impacts throughout the
demolition and construction phase. The CEMP will
outline the measures that are to be adopted for the
protection of: habitats and trees, birds, bats, wild
mammals and amphibians, in addition to general pollution
control measures. All personnel involved in the
demolition and construction works will be briefed on
relevant wildlife legislation and the ecological
management measures detailed within the CEMP.
Complete and Occupied Proposed Development
1.133 A minor beneficial residual effect will become apparent
once the Proposed Development is operational, due to an
increase in available bird nesting habitat. The landscape
strategy will comprise new landscaped areas comprising
lawns and shrub and flower planting, green and brown
roofs, a water feature, hedgerows and trees. This will
provide both a greater area and greater variety of habitat
types to those currently present within the Site,
enhancing the ecological value of the Site following
completion of the Proposed Development. The provision
of brown and green roofs, trees, soft landscaped area,
water features, as well as the provision of bat roost boxes
in the outline component of the Proposed Development,
would benefit both foraging and roosting bats. The effect
of these enhancements is a moderate beneficial effect.
Water Resources, Drainage and Flood Risk
1.134 Chapter 11: Water Resources, Drainage and Flood
Risk of the ES (Volume I) presents an assessment of the
impact of the Proposed Development on water resources,
drainage and surface water run-off associated with the
demolition and construction and operation of the
Proposed Development. The chapter also examines the
potential for flood risk associated with the Proposed
Development. A separate Flood Risk Assessment has
been prepared (which supports this hybrid planning
application) and details the full assessment of flood risk
and the proposed mitigation for these risks.
1.135 There are two surface water features within 1km of the
Site that could potentially be affected by the Proposed
Development; the New River and the East and West
Reservoirs. All of which fall within the hybrid planning
application boundary.
1.136 The New River flows, from north to south and forms the
northern, eastern and southern boundary of the Site. The
East and West Reservoirs are located to the south of the
Site. The New River and the East Reservoir are used for
public water supply and are owned and maintained by
Thames Water. The LBH own and operate the West
reservoir.
1.137 The Site falls entirely within Flood Zone 1. This is
defined as an area that is classified as of being at low risk
of flooding.
1.138 The New River and East Reservoir are classified as
being of good ecological potential by the Environment
Agency under the Water Framework Directive.
1.139 The Environment Agency has classified that there is
London Clay underlying the Site, under which lies Upper
Chalk (a ‘Principal Aquifer’). Given the overlying
thickness of London Clay, the Principal Chalk aquifer is
considered to be of low sensitivity from activities at the
Site. There may be zones of perched water beneath the
Site associated with areas of anticipated Made Ground,
but they would not be extensive or have a high resource
potential.
1.140 The Site is also located within groundwater protection
zone (Inner (Zone 1) Source Protection Zone (SPZ)), due
to the presence of groundwater abstraction in close
proximity of the Site.
Demolition and Construction
1.141 Pollution sources arising from demolition and
construction works that could impact water resource
receptors comprise the following:
• Leaks and spillages from oils/hydrocarbons;
• Suspended sediments; and,
• Disturbance of contaminated land.
1.142 Spillages and leaks associated with plant and machinery
and from fuel storage pose a moderate adverse impact
(pre-mitigation) to the New River and the East and West
Reservoirs, as there would be locally measurable
changes to the water quality and the change could affect
abstractions for public water supply. However, with the
implementation of mitigation measures, such as oil
interceptors, impermeable bunds and drip trays, the
residual effect is considered negligible.
1.143 Potential sources of suspended sediments occurring as a
result of land clearance, excavations, exposed ground
and stockpiles, plant and wheel washing and dust and
sediment generated pose a moderate adverse risk (pre-
mitigation). Adoption of mitigation measures such as cut-
off ditches, limited earth movement and settling tanks
reduce minimise the magnitude and likelihood of
uncontrolled release of sediment, resulting in negligible
effects.
Woodberry Down – ES Non-Technical Summary
19
1.144 Previous ground investigations have found some
contamination. Disturbance of potentially contaminated
soils during the demolition and construction works could
adversely affect the groundwater and the New River and
the East and West Reservoirs. In the event that any
contaminated land is disturbed, work will stop
immediately and measures will be taken to prevent
disturbance and mobilisation of contaminants, until the
contamination has been treated in-situ or removed for off-
site disposal. With the appropriate mitigation measures
in place, the resulting effect is considered negligible.
1.145 Water supply for demolition and construction processes
may represent a short term increase in supply volumes to
the Site. However water saving measures will be adopted
where possible, thereby reducing the impact on the water
supply network.
Completed and Occupied Development
1.146 Pollution sources arising from the operational use of the
Proposed Development, which could affect surface and
groundwater comprise the following and are discussed in
more detail below:
• Leaks and spillages from oils/hydrocarbons,
application of fertilisers and pesticides within
landscaped areas;
• Leaks /Breakage in drainage system; and,
• Flood risk.
1.147 The use of oil interceptors in the design of the drainage
network will reduce the risk of contaminants entering the
drainage network. The design of the roads and the
proposed riparian landscaping act as a buffer to the local
waterbodies. It is considered that implementation of these
mitigation measures will reduce the impact on the New
River and the East and West Reservoirs so that residual
effects will be negligible.
1.148 The presence of over 40m of London Clay directly below
the Site, also negates the potential for contaminants to
migrate vertically, and cause contamination of the Upper
Chalk (Principal Aquifer). Therefore it is considered that
there would be a negligible impact on groundwater.
1.149 The implementation of Sustainable Urban Drainage
Systems (SuDS), by using void systems provided below
green roofs on the podium deck, porous paving within car
parking spaces and cellular storage tanks to contain
runoff from extreme event, reduce the runoff and volume
of surface water from the Site. These measures will
provide a permanent, direct major beneficial effect.
1.150 The Proposed Development incorporate water efficient
sanitary fittings, water meters and Sanitary Supply Shut-
Offs within commercial buildings. These water savings
will be beneficial in terms of reducing the overall water
‘footprint’. These measures will provide a minor
beneficial effect.
Ground Conditions and Contamination
1.151 Chapter 12: Ground Conditions of the ES addresses
the effects of the Proposed Development on ground
conditions including geology, hydrogeology and ground
contamination of the Site and surrounding area. The
assessment considers the effects during the demolition,
construction and operational or occupational phases of
the proposed development. The need for mitigation
measures and any monitoring that may be required
during the demolition and construction phase is also
considered and, where appropriate, any residual effects
from both the construction and operational phases of the
Proposed Development are indicated.
1.152 Review of published geological maps indicates that the
geology beneath the Site is London Clay, with Thanet
Sands and Upper Chalk below. Made Ground is
anticipated to be present beneath the footprint of the
current on-site buildings.
1.153 The London Clay is classified as Unproductive Strata
(none water bearing) by the Environment Agency and the
underlying Thanet Sands and Upper Chalk as a Principal
Aquifer (water bearing). The overlying thickness of
London Clay is likely to minimise potential risk to the
Principal Aquifer from on-site activities.
1.154 The Site lies in an Inner Zone source protection zone,
thought to relate to the groundwater abstractions used for
potable water supply within the vicinity of the Site. These
abstractions are likely to be sourced from the Principal
Aquifer and are not considered a viable receptor with
respect to the Site.
1.155 The nearest surface water features are the New River
which flows along the northern site boundary before
meandering across the centre of the Site. The West and
East Stoke Newington Reservoirs are located in the
south of the Site and form the southern site boundary.
Both the river and the reservoirs are man-made features,
likely to have been constructed with impermeable liners.
It is considered unlikely that these receptors are at
significant risk of effect from on-site activities.
1.156 The Site lies in an area which was bombed during the
Second World War. There may be risk of discovering
unexploded ordnance during any ground works.
Demolition and Construction
1.157 During demolition and construction, precautions will be
taken to minimise exposure of workers and the general
public to potentially harmful substances. Potential effects
to on-site workers are considered negligible if
appropriate site safety procedures are implemented and
followed, and if necessary, appropriate personal
protective equipment (PPE) is used.
1.158 Should asbestos containing materials be found in soils
during any intrusive investigation or in the building fabrics
Woodberry Down – ES Non-Technical Summary
20
during demolition, they will be removed in-line with
current environmental legislation. This will mitigate any
effect to on-site workers to negligible.
1.159 Previous intrusive investigations at the Site have
identified elevated concentrations of contaminants in the
soils and shallow groundwater beneath the Site. This
could pose a negligible effect to the identified receptors
should mitigation measures implemented. Potential
effects to on-site workers will be managed with the use of
appropriate PPE. The effect to the New River, the West
and East Reservoirs and the below ground aquifer is
considered negligible given that it is unlikely that these
are viable receptors with respect to the Site. Vapour
inhalation emanating from soils or groundwaters beneath
the Site may require remediation on a building by building
basis to mitigate the potential effect to human health
receptors.
1.160 The installation of gas protection measures within site
buildings and the use of ventilation during any excavation
works will reduce the potential effect from ground gas to
negligible.
Complete and Occupied Proposed Development
1.161 The completion of the Proposed Development is likely to
have a minor to major, long-term, beneficial effect by
treating or removing (as necessary) any soil or
groundwater contamination in-line with current
environmental legislation.
1.162 The effect to water resources within the region is also
likely to be positive, given that the new buildings will be
built with water saving technologies (such as low-flow
toilets, dishwashers) and that green or brown roofs will be
implemented which will reduce surface runoff.
Archaeology (Buried Heritage Assets)
1.163 Chapter 13: Archaeology (Buried Heritage Assets) of
the ES assesses the effects of the Proposed
Development on known or likely buried heritage assets
(archaeological remains) which may be present within the
Site. The potential effects of the Proposed Development
on built heritage assets (including Listed Buildings and
Conservation Areas and their setting) has been dealt with
separately in the Townscape, Heritage and Visual Impact
Assessment (ES Volume II, but also summarised within
this NTS).
1.164 The Proposed Development entails the demolition of
most of the existing mid-20th-century housing estate
buildings within the Site and the construction of new
residential led mixed-use blocks. The archaeological
(buried heritage) assessment provides a baseline
heritage assessment of the whole estate, but discusses
the Proposed Development of one area (Phase 2) in
detail and several other plots in outline form.
1.165 Buried heritage assets (archaeological remains) that may
be affected by the proposals comprise:
• Features relating to the construction and water
management of the 17th century New River and the
19th century East and West Reservoirs. Remains
could include consolidation material, former walls,
gates and other features preserved behind the
modern river and reservoir walls, of low to medium
heritage significance. The New River itself is
considered to be a heritage asset of medium or high
significance;
• Truncated footings of 19th-century houses and
associated features such as wells and cess pits, of
low significance;
• Possible post-medieval clay pits, of low significance;
and
• Possible later medieval road surfaces, road ditches
and agricultural features, of low significance.
1.166 The Site lies at some distance from known centres of
historic settlement. The heavy London Clay on which the
Site is located was less favourable for settlement and
cultivation than the extensive gravel terraces of the River
Thames to the south, and in all likelihood much of the
area was in woodland or pasture until the latter half of the
post-medieval period. An archaeological evaluation in the
central part of the Site on a Kick Start Site in 2009
revealed the footings of 19th century walls but otherwise
archaeological understanding of the majority of the Site,
in particular for the prehistoric and Roman periods, is
limited. Nevertheless the potential for survival of
significant archaeological remains is in general
considered low.
1.167 The survival potential for buried archaeological remains
will have been severely compromised by the construction
of the mid-20th century London County Council housing
estate, which will have removed or severely truncated
archaeological remains within the footprint of all the
buildings, and potentially across most of the Site
depending on the level of landscaping and other ground
works that took place in advance of, and during
construction.
Demolition and Construction
1.168 The Proposed Development would remove
archaeological remains (if any do survive) immediately
below or adjacent to the footings of the existing buildings
during demolition. Any remains within the footprint of the
new buildings would be removed during the construction
of their foundations and basements (if applicable). Across
the Site shallow deposits would be removed during site
preparation and landscaping. The removal of
archaeological remains within the Site would be a minor
Woodberry Down – ES Non-Technical Summary
21
to moderate adverse effect prior to mitigation (depending
on the significance of the remains removed).
1.169 An initial targeted archaeological evaluation carried out
as part of a standard planning condition prior to the
commencement of construction works is likely to be
required to establish the degree of survival in areas of
higher potential survival (i.e. outside the footprint of the
current buildings, and close to the New River and
Reservoirs). The results of these investigations would
inform a mitigation strategy, if required, involving targeted
archaeological excavation and/or a watching brief for
remains of lesser significance. It is possible that no
further work would be necessary. Any archaeological
work would need to be carried out in accordance with an
approved Written Scheme of Investigation (WSI) and
could be undertaken under the terms of a standard
archaeological planning condition.
1.170 Appropriate mitigation would mean residual effects would
be negligible.
Complete and Occupied Proposed Development
1.171 No effects upon buried heritage assets are anticipated
once the Proposed Development is completed and
occupied as no further below ground disturbance is
anticipated.
Wind Microclimate
1.172 Chapter 14: Wind Microclimate of the ES (Volume I)
presents an assessment of wind microclimate around the
existing Site and Proposed Development.
1.173 The wind microclimate assessment for the Proposed
Development was based upon the results of a series of
wind tunnel tests. The objective of the assessment was to
determine the potential wind microclimates for the
existing and Proposed Development scenarios. The
results for the assessment are benchmarked against the
‘Lawson Comfort Criteria’.
1.174 The prevailing winds for London approach from the
southwest throughout the year. There are secondary
prevailing winds from the northeast during the spring.
1.175 The wind microclimate around the baseline, existing Site,
is suitable for leisure walking, standing or sitting during
the windiest season.
Demolition and Construction
1.176 The likely effects during demolition and construction have
been determined by professional judgement. During
demolition, once the Site is cleared, it is likely that wind
will blow across the open Site. However, this would be a
temporary effect, mitigated to some degree by the
temporary construction buildings and hoarding. Therefore
conditions during the demolition phase are expected to
be similar to those for the existing Site, at worst
negligible.
Complete and Occupied Proposed Development
1.177 The wind microclimate for the Proposed Development
scenario was suitable for car park / roadway, business
walking, leisure walking, standing or sitting during the
windiest season. As several locations to the northwest of
the Site along Green Lanes were windier than desired (in
the outline component), mitigation measures are advised
at the Reserved Matters stage in the form of tree planting
and soft landscaping or screening. The residual effect
significance of the complete and occupied Proposed
Development ranges from a negligible to moderate
beneficial effect.
1.178 Due to this being a hybrid application, entrance locations
had not yet been determined for the outline component of
the Proposed Development. Therefore it is advised that
entrances be located within zones suitable for entrance
use, or have mitigation measures incorporated into their
design when situated in areas where standing/entrance
conditions are exceeded. For Phase 2 all entrances were
suitable for the intended pedestrian use, therefore no
mitigation measures were required.
1.179 During the summer season the majority of amenity
spaces were suitable for the desired sitting conditions,
however some amenity spaces were suitable for
standing. In order to achieve the targeted sitting
conditions mitigation measures would be required in the
form of soft landscaping, screening and/or tree planting
throughout these areas.
Daylight, Sunlight and Overshadowing
1.180 Chapter 15: Daylight, Sunlight and Overshadowing
provides an assessment of the potential effects on the
daylight, sunlight and overshadowing on the existing
surrounding properties during both the demolition and
construction phase, and the operational phases of the
Proposed Development once completed and occupied.
1.181 Due to the nature of the Hybrid Planning Application,
daylight, sunlight and overshadowing effects have been
considered in relation to both the detailed component of
the Proposed Development (Phase 2), as well as the
outline component of the Proposed Development, with
additional consideration to the light conditions within the
Proposed Development.
1.182 The daylight, sunlight and overshadowing assessments
have been undertaken in accordance with the
methodologies and numerical guidelines recommended
by the Building Research Establishment (BRE).
1.183 The assessments have been undertaken taking into
consideration the Proposed Development Scenarios
summarised earlier in this ES NTS.
Woodberry Down – ES Non-Technical Summary
22
Demolition and Construction
1.184 During demolition, there are likely to be increasing short-
term (temporary) minor beneficial daylight and sunlight
effects to the identified surrounding sensitive receptors as
a result of the progressively reducing bulk and massing
on the Site, thereby reducing the current obstructions
which influence the amount of daylight and sunlight
reaching the sensitive receptors.
1.185 These beneficial effects would cease upon completion of
demolition, and the availability of daylight and sunlight
would gradually change once more during the
construction period until the massing of the Proposed
Development reaches its maximum extents. The extent of
the changes to daylight, sunlight and overshadowing
during demolition are considered to be short-term
(temporary) minor beneficial.
1.186 The phased construction programme will mean that some
blocks may be completed and occupied within the
Proposed Development whilst other blocks are still
undergoing construction. Therefore, there will be differing
effects on the daylight, sunlight and overshadowing
experienced by both the surrounding existing and
proposed receptors within the Proposed Development, up
until the development is completed. The use of
scaffolding, hoardings and, to a lesser extent, cranes, will
temporarily increase the obstruction to daylight and
sunlight very slightly beyond that caused by the buildings
themselves. On the other hand, as the existing buildings
are demolished and until the new buildings are erected,
the surrounding receptors will temporarily enjoy
increased daylight and sunlight levels. Overall the effects
of the detailed component of the Proposed Development
(Phase 2) during demolition and construction will be
negligible.
Completed and Occupied Proposed Development
1.187 In Proposed Development Scenario 1, the residual effect
significance of the completed and occupied detailed
component of the Proposed Development (Phase 2) on
the daylight, sunlight and overshadowing to the existing
surrounding properties and public open spaces will be
negligible to minor adverse. The residual effect
significance of the completed and occupied outline
component of the Proposed Development on the daylight,
sunlight and overshadowing to the vast majority of
existing surrounding properties and public open spaces
will range from negligible to moderate adverse. There will
be some isolated major adverse impacts to the daylight
for four properties, sunlight to two properties and to the
overshadowing to fifteen of the private gardens.
1.188 In Proposed Development Scenario 2, the residual effect
significance of the completed and occupied outline
component of the Proposed Development on the daylight,
sunlight and overshadowing to the existing surrounding
properties and public open spaces will be negligible to
minor adverse. There are no properties in the vicinity of
the detailed component of the Proposed Development
(Phase 2) that will be affected by Scenario 2.
1.189 Should there be the retention of the properties in third
party ownership on the south side of the Woodberry
Grove, the residual effect significance of the completed
and occupied outline component of the Proposed
Development on the daylight, sunlight and
overshadowing to the vast majority of existing
surrounding properties and public open spaces will range
from negligible to moderate adverse. There will be
some isolated major adverse impacts to the daylight for
three properties and to the overshadowing to eight of the
private gardens.
1.190 In terms of the light conditions within the detailed
component of the Proposed Development (Phase 2), the
vast majority of habitable rooms tested across proposed
Phase 2 Blocks B, D and F will achieve the
recommended Average Daylight Factor targets, with
good levels of sunlight to around half of the south facing
windows for an urban regeneration site, where the
provision of private amenity areas such as balconies, and
close proximity to public open spaces, transport links and
local amenities will often rank more highly among future
occupants.
1.191 With regards to the potential light conditions within the
outline component of the Proposed Development, in
overall terms around half of the test points on the facades
will meet the BRE daylight (vertical sky component) and
sunlight criteria. Given that the outline parameter
massing presents a worst case scenario, it is considered
that the potential for daylight and sunlight levels within
future detailed schemes within the outline component of
the Proposed Development will be maximised during the
detailed design development stage (future reserved
matters).
1.192 Overall, the detailed component of the Proposed
Development (Phase 2) would not have a significant
effect on daylight, sunlight and overshadowing to the
existing surrounding properties and public open
spaces/private gardens with good levels of daylight and
sunlight maintained for an urban regeneration scheme.
Whilst the outline component of the Proposed
Development will have a significant effect to a number of
existing surrounding properties and public open
spaces/private gardens, there will also be a number of
insignificant effects, and it should be remembered that
the impact of the maximum parameter massing for the
outline component of the Proposed Development
presents very much a worst case scenario. It is expected
that the significant effects around the Site will be
Woodberry Down – ES Non-Technical Summary
23
designed out through iterative detailed design
development of any future detailed application schemes
(reserved matters applications) within the outline
component of the Proposed Development, taking into
particular consideration the Applicant’s Design Principles
Document and BRE Report 209.
Townscape, Visual and Heritage Impacts
1.193 ES Volume II: Townscape, Visual and Heritage Impact
Assessment presents the townscape, visual and built
heritage effects of the Proposed Development on the
townscape and heritage assets in the vicinity, and its
visual impact.
1.194 Consultation has occurred with the LBH, the GLA and a
Commission for Architecture and the Built Environment
(CABE) design review during the design development
and in its final form.
1.195 Overall the assessment concludes that the Proposed
Development would have a beneficial effect on the
townscape character area within which it is located, and a
beneficial or neutral effect on other townscape
character areas and in relation to heritage assets.
1.196 Heritage assets including Conservation Areas and Listed
Buildings were plotted, analysed and assessed for their
sensitivity to the Proposed Development. It is considered
that the townscape setting within the Stoke Newington
Reservoirs, Filter Beds and New River Conservation Area
will be enhanced through the presence of buildings within
the Proposed Development which have a carefully
considered form and scale, and would be of a high
architectural quality. Blocks B, D and F within Phase 2
would provide strong definition of surrounding streets,
including Green Lanes and Woodberry Down. New
routes into the Site, leading to Spring Park, the New
River and the West Reservoir, would improve
permeability in the wider area. The towers within Block B
and Block F would mark entrances into Spring Park,
enhancing legibility.
1.197 The assessment also concludes that the Proposed
Development would be a high quality design that would
enhance a range of local, medium and long range views.
In local to medium range views, the Proposed
Development would contribute to the strong definition of
streets and spaces, and enhanced legibility through a
common approach of locating tall elements near points of
townscape significance.
Effect Interaction and Cumulative Effects Assessment
1.198 Typically, cumulative effects are those that result from
incremental changes caused by other past, present or
reasonably foreseeable actions together with the
development. It is recognised that cumulative effects
occur as either interactions between effects associated
with just one project or between the effects of a number
of projects in an area. As a result, two types of
cumulative effects have been considered within the
cumulative effects assessment in Chapter 16: Effect
Interaction and Cumulative Effects Assessment of the
ES, as follows:
• Type 1: The combined effect of individual effects
arising as a result of the Proposed Development, for
example effects in relation to noise, airborne dust or
traffic impacting on a single receptor; and
• Type 2: The combined effects of several development
schemes (see Figure 5 for the location of the
cumulative schemes considered) which may, on an
individual basis be insignificant but, together (i.e.
cumulatively), have a significant effect.
Combined Effect of Individual Effects
1.199 The identified residual effects (as set out within the
individual technical chapters of ES Volume I) have been
reviewed against the receptors they affect. Where there
is more than one effect on a particular receptor, the
potential for effect interactions has been determined. If
there is the potential for effect interactions, consideration
is then given as to whether there is the potential for any
resultant combined cumulative effect.
Demolition and Construction
1.200 The EIA has addressed the potential combined effects of
individual effects associated with the Proposed
Development upon sensitive receptors. The prospect for
this type of cumulative effect to occur during the
demolition and construction phase includes effects to:
• Neighbouring Commercial/Residential Property
(during the demolition and construction phase) who
will experience a combined temporary adverse effect
due emissions from traffic, dust, noise and vibration
from the demolition and construction works;
• Adjacent Residential Properties (during the demolition
and construction phase) who will experience a
combined temporary adverse effect due emissions
from traffic, dust, noise and vibration from the
demolition and construction works, but are likely to
receive temporary negligible to beneficial effects with
regards to increased daylight and sunlight;
• Future on-site Users (in particular, future residents of
the Proposed Development who occupy completed
phases of the development whilst remaining phases
of the Proposed Development are completed) (during
the demolition and construction phase) who will
experience a combined temporary adverse effect due
emissions from traffic, dust, noise and vibration from
the demolition and construction works but are likely to
receive temporary negligible to beneficial effects with
regards to increased daylight and sunlight;
Woodberry Down – ES Non-Technical Summary
24
• Social Infrastructure and Community Facilities (during
the demolition and construction phase) who will
experience a combined temporary adverse effect due
emissions from traffic, dust, noise and vibration from
the demolition and construction works; and
• Ecology and Nature Conservation (during the
demolition and construction phase), who will
experience a combined adverse effect due to loss of
scattered trees, effect of loss of foraging habitat for
bats, effects of loss of nests, disturbance of any
roosts and foraging habitat on breeding birds, effect of
disturbance on wintering birds, and effect of killing
and injury of common reptiles.
1.201 As works progress across the Site, the combined effects
to the above receptors will vary. The different stages of
the demolition and construction works will generate
different magnitudes. For example, dust effects are
potentially more significant during demolition and
excavation activities than during construction activities.
As such, whilst there is the potential for combined
nuisance effects throughout the demolition and
construction stages of the project, the magnitude of the
effects will vary depending on the stage and location of
works. These effects are therefore temporary and
transient in nature.
1.202 Compliance with the mitigation measures discussed
throughout this NTS and detailed within ES Volume I,
such as the commitment to produce a site specific
CEMP; the use of site hoardings; maintenance of plant;
the setting of target noise levels and noise and vibration
monitoring which will be carried out at sensitive
receptors; wheel washing to help dust suppression; and
traffic management plans, will reduce, as far as possible,
the effects of these effect interactions.
Completed and Operational Development
1.203 There is also the potential for combined effects of
individual effects once the Proposed Development is built
and operational to:
• Neighbouring Commercial/Residential Properties
which will experience a combined beneficial effect
due to effects on pedestrian and cyclist amenity,
severance and amenity and accommodation and
facility provision along with the creation of jobs,
housing, public realm improvements and additional
spend associated with the Proposed Development but
are likely to receive lower levels of daylight and
sunlight;
• Adjacent Residential Properties which will experience
a combined beneficial effect due to effects on
pedestrian and cyclist amenity, severance and
amenity and accommodation and facility provision
along with the creation of jobs, housing, public realm
improvements and additional spend associated with
the Proposed Development but are likely to receive
lower levels of daylight and sunlight;
• Future on-site Users which will experience a
combined beneficial effect due to effects on
pedestrian and cyclist amenity, severance and
amenity, wind microclimate conditions at entrances
and thoroughfares during the windiest season and
accommodation and facility provision along with the
creation of jobs, housing, public realm improvements
and additional spend associated with the Proposed
Development;
• Social Infrastructure and Community Facilities which
will experience a combined beneficial effect due to
effects on pedestrian and cyclist amenity, severance
and amenity, the creation of jobs, public realm
improvements, open space provision and additional
spend associated with the Proposed Development;
• Local Highway Network which will experience a
combined beneficial effect due to effects on
pedestrian and cyclist amenity, severance and
amenity associated with the Proposed Development;
• Public Transport Network which will experience a
combined beneficial effect due to effects on
pedestrian and cyclist amenity, severance and
amenity associated with the Proposed Development;
• Pedestrian and Cycle Network, Safety and Amenity
which will experience a combined beneficial effect
due to effects on pedestrian and cyclist amenity,
severance and amenity associated with the Proposed
Development; and
• Ecology and Nature Conservation which will
experience combined adverse and beneficial effects
due to potential for disturbance and pollution on the
Stoke Newington Reservoirs and New River on birds,
in addition to habitat creation (birds and bats) and
reduced disturbance for bats.
Combined Effects of Several Development Schemes
1.204 The EIA considers the potential cumulative effects of the
Proposed Development in relation to other developments
within close proximity (approximately 1km) of the Site that
may have an additive effect on the surrounding area.
1.205 The location of the schemes considered within the
assessment of cumulative effects is shown in Figure 5.
1.206 An assessment of the combined effects of the Proposed
Development with the above cumulative development
schemes has been undertaken and can be found in
Chapter 16: Effect Interactions and Cumulative
Effects Assessment.
1.207 The majority of technical subjects covered within ES
Volume I are not expected to result in significantly
Woodberry Down – ES Non-Technical Summary
25
adverse cumulative demolition and construction effects,
as long as standard mitigation measures, including those
detailed within ES Volume I (such as appropriate traffic
management measures and construction routing; and the
introduction of site hoardings and compliance with the
mitigation measures detailed within the CEMP) are
adhered to. It is expected that the other cumulative
schemes’ demolition and construction works would also
adhere to such best practice measures. There is,
however, the potential for adverse cumulative moderate
adverse effect relating to demolition and construction
noise and a minor to moderate adverse visual effect.
1.208 However there are also permanent beneficial effects on:
biodiversity and improvements to public realm;
townscape, heritage and visual effects; ground
contamination; flood risk; as well as socio-economic
benefits on housing provision, employment, spending in
the local area.
Figure 5: Location of the Schemes
Considered in the Assessment of
Cumulative Effects
Woodberry Down – ES Non-Technical Summary
26
Residual Effects and Conclusions
1.209 Chapter 17: Residual Effects and Conclusions
presents the residual effects and conclusions of the ES.
Residual effects are defined as those effects that remain
following the implementation of mitigation measures.
Mitigation measures relate to any of the three key phases
of the proposed development (i.e. design; demolition and
construction; and operation).
1.210 The ES has concluded that the majority of environmental
effects during the demolition and construction phases of
the Proposed Development will be of minor adverse or
negligible significance taking into account the application
of appropriate mitigation measures.
1.211 The number of potential adverse effects are limited to:
• Air quality, specifically the effect of construction dust
and short-term concentrations of PM10 (temporary,
local, minor adverse);
• Noise and vibration, specifically the effect of
demolition and construction noise and vibration on
existing and proposed receptors (temporary, local,
negligible – moderate adverse) and the effect of
construction vibration (temporary, local, minor
adverse);
• Archaeology, the effect of demolition and construction
on the Woodberry Down Estate (permanent, local,
minor adverse);
• Ecology, specifically effects of disturbance on species
and breeding species within the Stoke Newington
Reservoirs Site of Metropolitan Importance for Nature
Conservation (SMINC) (negligible to moderate
adverse), disturbance, pollution and habitat loss on
the New River SMINC (minor adverse), loss of
scattered trees (minor adverse), disturbance of bats
(negligible – minor adverse), loss of foraging habitat
for bats (minor adverse), loss of roosts for bats (minor
–moderate adverse), loss of nests on breeding birds
(minor – moderate adverse), loss of foraging habitat
on breeding birds (minor adverse), and potential
killing or injury of common reptiles (no impact – minor
adverse); and
• Townscape, heritage and visual, specifically effects of
demolition and construction on Townscape Character
Areas (local – regional, temporary, minor to moderate
adverse), effects on local views (local – regional,
temporary, minor to moderate adverse), and effects
on local Heritage Assets (local – regional, temporary,
• minor to moderate adverse).
1.212 A number of environmental management measures
would be implemented during the demolition and
construction process. These include specific mitigation
measures for the Proposed Development and Site as well
as those measures that would be implemented as a
matter of course as appropriate for urban regeneration
projects and in line with best practice guidance.
1.213 A principal contractor will be appointed by the Applicant
to develop and implement a site-specific CEMP through
which mitigation measures will be implemented. Subject
to the implementation of the CEMP, the residual effects
resulting from the demolition and construction phase of
the Proposed Development are considered to have been
reduced as far as reasonably practicable.
1.214 The demolition and construction phase also generates a
net beneficial effect due to the removal or remediation of
any contamination land on Site.
1.215 During the completed and operational phase of the
Proposed Development adverse effects are limited and
relate to the following:
• Ecology, specifically in relation to effects on habitats
with the Stoke Newington Reservoirs SMINC (no
impact to minor adverse and New River SMINC
(minor adverse), effect of pollution on the New Rivier
SMINC (minor adverse) and effect of disturbance on
Finsbury Park SBINC and wintering birds (minor
adverse);
• Daylight, sunlight and overshadowing effects to
surrounding sensitive receptors (properties) and
amenity areas from minor to major adverse.
However, with regards to the outline component of the
Proposed Development (representing the majority of
this hybrid planning application), this chapter
assesses the impact of the maximum plot envelope /
parameter massing (see ES Volume III Technical
Appendix K for the Parameter Plans) and it should be
acknowledged that this represents very much a worst
case scenario and does not reflect the reality of the
situation following the future detailed design stage for
each phase. It is to be expected that through iterative
detailed design development, taking into
consideration the guidance of the BRE guidance and
the Applicants Design Principles Document, that
daylight and sunlight impacts to the surrounding
residential properties will be considered and designed
out. This is further demonstrated by the illustrative
scheme for the outline component of the Proposed
Development, as set out in the Design and Access
Statement, which shows that consideration has
already been given to addressing building to building
relationships, and by reference to the limited daylight,
sunlight and overshadowing effects of the detailed
component of the Proposed Development (Phase 2). ,
It is also important to note that the low existing
obstructions on the Site mean that some existing
properties on the Site currently enjoy unusually high
levels of sunlight and daylight for an urban location.
Woodberry Down – ES Non-Technical Summary
27
1.216 On completion and occupation of the Proposed
Development, beneficial residual socio-economic effects
have been identified in relation to housing delivery (local -
district, permanent, moderate - major beneficial);
additional spending (local, permanent, minor – major
beneficial); generation of employment (local, permanent,
minor – moderate beneficial) open space (local,
permanent, moderate beneficial) and crime and safety
(local, permanent, moderate beneficial).
1.217 Other beneficial effects on completion and occupation of
the Proposed Development relate to the following:
• Ecology in terms of effects on habitat creation by
scattered trees (permanent, minor beneficial), effect
of habitat creation on bats using the Site (permanent,
minor – moderate beneficial), effect of disturbance on
bats (permanent, minor beneficial) and effect of
habitat creation on breeding birds (permanent, minor
beneficial);
• Traffic and Transportation, specifically in relation to
effects on pedestrian severance (permanent, local,
minor adverse), effects on pedestrian delay
(permanent, local, minor beneficial) and effects on
pedestrian and cyclist amenity (permanent, local,
minor beneficial);
• Water Resources and Flood Risk, specifically in
relation to effects on water consumption (local,
permanent, minor beneficial) and surface water runoff
(local, permanent, major beneficial);
• Ground Conditions and Contamination, specifically in
terms of effects from soil and groundwater
contamination on human health and controlled waters
(permanent, district, minor to major beneficial);
• Wind Microclimate, specifically wind effects along
pedestrian thoroughfares (during the windiest season)
(permanent, local, negligible – moderate beneficial),
and wind effect at entrances (during the windiest
season) as a result of the completion and operation of
the detailed component of the Proposed Development
only (permanent, local, negligible – moderate
beneficial); and
• Townscape, heritage and visual, specifically in
relation to effects on Townscape Character Areas
(local – regional, permanent, minor to moderate
beneficial), effects on local views (local – district,
permanent, minor – major beneficial), and effects on
local Heritage Assets (local – regional, temporary,
minor – major beneficial).The conclusions of the
townscape, conservation and visual impact
assessment demonstrate that overall the Proposed
Development has significant urban design benefits
and would reinforce the emerging townscape
character of the Site and wider Woodberry Down
Masterplan area in a coherent and positive manner. It
is also considered that the effect on views,
surrounding Townscape Character Areas and HAs
would be beneficial or neutral in all cases.
1.218 It is recognised that the Proposed Development will result
in some short term adverse effects during the demolition
and construction phase, however it is considered that
overall the Proposed Development would have a positive
effect on the regeneration of the area and contribute to
the employment and housing objectives of LBH. The
delivery of new homes, creation of new jobs and the
provision of high quality public realm and open space will
all contribute significantly to the regeneration of the area.
1.219 The Proposed Development has been designed to
achieve high sustainable standards and has committed to
achieving a BREEAM ‘very good’ building rating for all
non-residential units and Code for Sustainable Homes
Level 4 for the residential units. There will also be
significant reductions in carbon dioxide emissions as
required by LBH policy and the London Plan with the use
of combined heat and power (CHP). The Proposed
Development meets, and in some cases exceeds,
requirements as set out in the planning policy framework
to which is applicable to the development.
1.220 The design of the Proposed Development has sought to
build on a comprehensive review of the existing 2009
masterplan, learning from the detailed work that took
place in preparing the original scheme for the Site and
the lessons that can be learned from the first phases of
implementation that have been delivered. This will
support the ongoing transformation of Woodberry Down.
1.221 Overall, the Proposed Development not only accords with
relevant national, regional and local planning policy, but
represents an appropriate development that is
encouraged by policies contained within national
guidance and the LDF. It will contribute to the vitality,
viability and continued inward investment of the area and
to the aspirations of the LBH, while finding ways to
improve the quality of the Woodberry Down
redevelopment and a proposition that can respond to the
changing context within which development is taking
place.
Contacts and Availability of the ES
1.222 The ES is available for viewing by the public during
normal office hours at the Planning Department of the
LBH. Comments on the planning application should be
forwarded to the LBH at the following address:
London Borough of Hackney
Regeneration and Planning Division
2 Hillman Street
London E8 1FB
1.223 Additional copies of the NTS (this document) are
available free of charge, while copies of the full ES
(Volume I, II and III) are available for purchase from:
Woodberry Down – ES Non-Technical Summary
28
Berkeley Homes (Capital) plc
Woodberry Down Regeneration Project
Units A&B, Riverside Apartments
Goodchild Road, off Woodberry Grove
London N4 2BA
1.224 Hard copies of the ES are priced at £300 (ES Volume I),
£150 (ES Volume II) and £600 (ES Volume III). CDs of
the ES (Volumes I, II and III and the NTS are priced at
£20.
References
Ref. 1 Her Majesty’s Stationary Office, (2011); The Town and
Country Planning (Environmental Impact Assessment)
Regulations 2011.
Ref. 2 Department of Communities and Local Government,
(2012); National Planning Policy Framework.
Ref. 3 Greater London Authority, (2011); The London Plan
Spatial Development Strategy for Greater London.
Ref. 4 Greater London Authority, (2007); London View
Management Framework – Supplementary Planning
Guidance.
Ref. 5 Greater London Authority, (2006); Sustainable Design
and Construction – Supplementary Planning
Guidance.
Ref. 6 London Borough of Hackney, (2010); Core Strategy.
Ref. 7 London Borough of Hackney, (1995); Unitary
Development Plan.
Ref. 8 London Borough of Hackney (2012); Draft Local Plan.
Ref. 9 London Borough of Hackney, (2004); Woodberry
Down Area Action Plan.
Ref. 10 London Borough of Hackney, (2013); The Manor
House Area Action Plan.