Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka...

14
Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen

Transcript of Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka...

Page 1: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Wireless Sea Measurement Unit

Intermediate ReportA Plan for Aarne Halme Project

Juha VanhalakkaErkka Mutanen

Page 2: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

ContentsO Project Schedule

RepriseO CodeO HardwareO Components

PurchasedO Building Board i-ivO Ready ChipO CasingO MechanicsO After Installation

Page 3: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Project Schedule Reprise

O Project Plan 25.09.O Progress Report 30.10.

+ electronics ready, code runningO Demo A 20.11.

+ casing ready, code readyO Demo B 27.11.

+ mounting prototype doneO Documentation done 10.12.

Page 4: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

CodeO Xbee communication is workingO Measurement data logging incompleteO No tests done on the XBee chip O UI Code is lateO Challenges: learn PHP from the start,

learn JavaScript from the startO Also, possible changes in UI makes the

programming take more time and more difficult

Page 5: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

HardwareO Hardware is on timeO We have a lab worker making us a

seabed mount steel tubeO Todo : power electronics

dimensioning, (battery capacity against solar panel power)

O Budget ?

Page 6: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Components PurchasedO We have ordered all parts from

Farnell and DigikeyO We have a WIKA hydrostatic

pressure sensorO We have a PT100 temperature

sensorO We have an industrial grade casing

from EnstoO List of components in Excel sheet

Page 7: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Building Board I

Page 8: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Building Board II

Page 9: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Building Board III

Page 10: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Building Board IV

Page 11: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Ready ChipO 10 x 12 cmO Build start Oct 13th

O Finished Oct 22nd

O Includes recharging circuit and Xbeeradio I/O connectivity

O Juha drew the boardO Built 2 identical ones

for parallel testing

O Here it is:

Page 12: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Casing

Page 13: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

Mechanics

Page 14: Wireless Sea Measurement Unit Intermediate Report A Plan for Aarne Halme Project Juha Vanhalakka Erkka Mutanen.

After Installation: