Transcript of Windplanner’s100kW Wind Turbine Project for CHRHS
Windplanner’s100kW
Wind Turbine Project for
CHRHS
Presented by: The Windplanners
This presentation will address:•Education
•Data
•Projected Savings
•Turbine Location and Details
The first reason is education!•The turbine on campus and the data
generated and the process to date has and will continue to provide a wide variety of authentic learning opportunities.
•This will be a demonstration site for community-scale wind that is easily accessible in the midcoast.
•We want our school campus to symbolize the kind of society we want and need to become.
6 years of History•New School - Incorporated some
renewable technology (geothermal) despite this, operating costs were higher than expected. Efficiency measures taken. What else could we do? Windplanners was established.
•MET data - UMass results: wind resource is marginal but viable for this site.
•Town ordinance written
•Data challenge
•UMass third party review
Data SummaryOriginal Wind Speed (m/s)
Adjusted Wind Speed (m/s)*
Output Range (kW/yr) ***
MET Tower @ CHRHS 3.75 4.38** 88,000 -
122,000UMass Buoy 4.33 101,150
UMass Portland 4.15 75,000
UMass Augusta 5 125,000
UMass Conclusions 4.5 - 5.0 99,000 -
125,000UMass High Estimate 5.5 190,000
**The adjusted speed of 4.38 m/s was calculated by Hillary Hanson and Bill Hopwood. The original work was misfiled, so the history of this calculation is lost.
*The analysis by UMASS is viewed as the Due Diligence for this project. The Adjusted Wind Speed corrects for any inter-annual variations of wind speed and the method UMASS used is an accepted method within the industry.
***Output estimates were provided by Northern Power and UMASS.
Wind Data
February 2006 – July 2007
QuickTime™ and a decompressor
are needed to see this picture.
QuickTime™ and a decompressor
are needed to see this picture.
What does $510,000 buy?
•NPS 100 kW wind machine w/ controls: $380,000
•Transportation to site: $10,000
•Engineering and permitting: $20,000
•Electrical components: $15,000
•Site Work: $15,000
•Foundation: $25,000
•Turbine installation: $15,000
•Electrical Contractor: $25,000
•Startup and commission of machine: $5,000
Funds Raised to Date
Maine Community Foundation $7500Unity Foundation $500FMC $300Stephen and Tabitha King Foundation* $35,000Anonymous $40,000Anonymous $60,000Windplanner fundraisers* $1097Individual Contributions* $457Anonymous Matching Donor up to $200,000
*Some or all of these funds are being matched
Total to Date: $211,000
Projected Savings
Average Wind Speed
(m/s)4.2 4.5 5.0
kWh/yr(Northern Power
Estimates - lower than UMass)
77,000 99,000 125,000
20 years of energy production
(kWh)1,540,000 1,980,000 2,500,000
Current Utility rate (per kWh)
0.145Energy savings per year (at current
rate)
$11,165 $14,355 $18,125
20-year utility rate
(projected average from Northwind)
0.229
Energy savings per year
(at projected avg. rate)
$17,633 $22,671 $28,625
Energy savings over 20 yrs.
(using projected avg. rate)
$352,660 $453,420 $572,500
Operation & MaintenanceEstimate of $3500/ yr after warranty
Possible Revenue Options to cover O & M *Sell Renewable Energy Credits
(REC) - $.03/kW 105,000kW would generate $3150/yr*Fundraise to establish a reserve
*Pay from savings*Other?
Siting the Northwind 100
The Northwind 100
•Direct Magnetic Drive - quiet and cuts in at low wind speeds.
•Warranty - 2 years
•Reputation - “Best of Breed” for this size turbine. Design life (20 yrs) based on performance in the Arctic and Carribean.
•Big jump to go smaller - there are no viable turbines in the 11 - 99 kW class.
•Location - manufactured in VT, service and initial carbon impact minimized
Questions??