Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

15
Windfarms Implementing SPP6 Nick Evans 6 th December 2007

Transcript of Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Page 1: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

WindfarmsImplementing SPP6

Nick Evans 6th December 2007

Page 2: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

WindfarmsImplementing SPP6

• Appointing an expert consultant

• Advice on preparing supplementary planning guidance (SPG)

Page 3: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

SPP6 - Overall Aims “…to enable Scotland to realise its considerable

renewable energy potential”

“Support renewable energy…and.. protect and enhance Scotland’s natural and historic environment”

“Wind farms should be accommodated where the technology can operate efficiently and the environmental and cumulative impacts can be addressed satisfactorily.”

Page 4: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

SPP6 published in March 2007

Spatial frameworks for wind farms

Jim Mackinnon’s letter to Heads of Planning

Prepare SPG

Guidance plus support by a consultant

Background

Page 5: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Appointing an expert consultant

Why appoint a consultant?

Criteria for the appointment

Expectations

Timing

Page 6: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Advice on preparing SPG analysis of existing DPs and SPG

Strengths Commitment to rewewables International and national designations Local environmental issues/biodiversity Small scale/community schemes Stakeholder and public involvement

Page 7: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Advice on preparing SPG analysis of existing DPs and SPG

Issues for advice Broad areas of search Green belts Different designations different policies Grid capacity Noise

Page 8: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Windfarms over 20 MW

Windfarms below 20 MW

Annex A still relevant, but Consider scale of project with scale and

character of landscape More flexible approach to designated areas Particularly for community schemes

Scope of the SPG

Page 9: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Aims of the SPG

1 - Broad areas of search

2 - Areas of significant protection

3 - Criteria to be followed elsewhere

Page 10: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

The SPG process

1 - Areas of significant protection

2 - Criteria to be followed elsewhere

3 – Outwith the above Broad areas of search

Page 11: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Natural heritage designations International designations National designations

Green belts

Areas where the limit of cumulative impacts have been reached

Areas of significant protection

Page 12: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Historic environment Regional and local natural heritage areas Tourism and recreational interests Communities Aviation and defence interests Broadcasting installations

Criteria for Elsewhere

Page 13: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Areas with no significant constraints Locally sensitive areas Project viability Grid capacity

Broad areas of search

Outwith protected and potentially constrained areas

Page 14: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

Planning challenge Widespread experience of DPs/SPG SPP6 means a review of DPs/SPG Appointing an expert consultant Advice on preparing supplementary planning guidance

(SPG)

Conclusions

Page 15: Windfarms Implementing SPP6 Nick Evans 6 th December 2007.

WindfarmsImplementing SPP6

Nick Evans 6th December 2007