Wind Report 2 Mike
-
Upload
scottyheist1990 -
Category
Documents
-
view
218 -
download
0
Transcript of Wind Report 2 Mike
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 1/27
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 2/27
Outline
ATA wind project origin and objectives
Resource assessment sites
Measurement equipmentWhat is a wind resource assessment and why is it
undertaken?
Key measurement results
A simple model for direct turbine energy yield
Turbulence findings
Key findings of this project
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 3/27
Project origins
ATA 2007 desktop study The Viability of Domestic Wind Turbines for Urban Melbourne
Micro Wind Turbine (MWT) technology focused.The main findings of this report included:
Recommendations to gather representative wind data fromurban locations as a prelude to any MWT installation.
The requirement for verification of turbine power curves withfield testing.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 4/27
Urban Wind Resource
Assessment Objectives Produce a portrait of wind characteristics at a variety of
urban sites around Melbourne’s CBD based on at least 3
months of wind speed and direction data from each site.• Coastal areas
• Typical built-up urban areas
• Hilly areas
Investigate differences in wind behavior at likely MWT
mounting locations:
• Pitched and flat roofs (building mounted turbines)
• Open yard areas (pole mounted turbines)
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 5/27
Urban Wind Resource
Assessment Objectives The essential role of a wind resource assessment is to
allow for quantification of available wind energy
Measure levels of wind turbulence at these sites.
Correlate ATA data from sites with BOM station data.
All wind resource assessments are wholly specific to thesite where measurements are gathered
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 6/27
Measurement Sites Ten Measurement sites in total:
• Five sites with a roof mounted anemometer and a 10m pole
mounted anemometer in an open yard area.
• Three pitched roofed dwellings.• Two flat roofed dwellings.
• Four of the remaining sites hosted a single anemometer.
• Two flat roofed dwellings.
• One open coastal area.
• One open suburban yard area.
• The single remaining site was a prominent high rise CBD building
that hosted a single ultrasonic anemometer at a height of approx10m above the roof surface.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 7/27
Measurement Sites
http://maps.google.com.au/)
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 8/27
Edithvale
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 9/27
Anemometers and Masts
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 10/27
ATA Anemometer at
Manningham
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 11/27
Measurement equipment and
duration Min 3 months of 2-D anemometer data from all sites
except the CBD site, consisting of 10 minuteaverages of wind direction and horizontal wind
speed.
An additional minimum of 2 weeks of high speed
(10hz) averaged ultrasonic anemometer data from
most sites. High speed data is necessary for examining rapid changes in wind flow character
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 12/27
Anemometers
APRS World Cup Anemometer
& data logger Gill Windmaster Ultrasonic
Anemometer
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 13/27
Why should we gather
this data? We want to model energy availability.
Pwind =½.ρ.A.v
3
[Pwind]= W=Js-1
• ρ = Air density(kgm-3) (also a function of
temperature, relative humidity and pressure)
• A = Area perpendicular to flow (m2)• v = Flow velocity (ms-1)
We are interested in power density [ Wm-2] available
for turbines to harness. Velocity is the mostimportant variable in determining available wind
power.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 14/27
Theoretical Wind Power Density
•How do we get to energy estimates from power?
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 15/27
Power, energy and probability
Power has units of energy per second.
Integrate power with respect to time gives us an estimate of
available energy. If we observe wind conditions for long enough we can build a
model of the likelihood of different wind speeds.
If we understand how velocity changes with time at a site, we
can understand how energy availability changes with time at
the site.
How do we model wind probability?
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 16/27
The Weibull Distribution
• We can fit a statistical distribution to our observations.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 17/27
What makes a suitable
MWT site? Energy production.
Low turbulence levels.
Sites suited for grid connected MWT installation aregenerally considered in the wind industry to require an
average horizontal wind speed of 5 ms-1.
Apart from deriving estimates of wind speed probability
at all sites, what did ATA’s Study reveal?
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 18/27
Summary of Results
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 19/27
Confused?
All this probability and statistics can be hard to grasp.
How about combining the Weibull curves with turbine
power curves (which relate available power to wind
speed) and estimating energy yield? Then we can just
compare single numbers from site to site….
For some context we can compare this to how a
common 1kW rooftop PV system would perform.
This is not intended as a model of actual end user energy yield.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 20/27
A simple model for direct
turbine energy yield
PV Array modelled using ANU PV performance simulator:
http://solar.anu.edu.au/EduResources/applets/PVPanel/_PVpanel.php
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 21/27
Conclusions so far
• Only the Williamstown and CBD site can be considered
as potential MWT sites if turbines were to be installed at
the measurement heights.
• The remaining sites are likely to operate at low capacity
factors and suffer extended or indefinite financial and
energy payback periods.
• Most typical urban sites around Melbourne are likely to
fall into this category- there simply is not sufficient
available energy density for MWT installation to beattractive. They are highly unlikely to be able to compete
with PV arrays as an embedded generation technology.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 22/27
Turbulence
Wind turbulence can be described as chaotic, highly
variable and unpredictable air movement.
It is typically characterised by Turbulence Intensity, adimensionless quantity which expresses the relative
change in wind conditions in a time interval.
High levels of turbulence reduce the ability of a turbine to
harness energy from a wind flow, reduce infrastructure
life spans and increase maintenance requirements.
High levels of Turbulence Intensity are undesirable for
turbine installation sites especially when they occur at
high wind speeds.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 23/27
Turbulence Intensity vs. Wind Speed
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 24/27
Turbulence and Turbine
Performance
There are no established standards for the formulation of
MWT power curves to incorporate TI.
We know that turbulence reduces effectiveness of turbines, but without standardisation we cannot say by
how much.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 25/27
Comment on Project Objectives Only open areas situated on the coast and high rise
buildings appear promising for MWT installation.
Most sites in built up urban areas appear to be situated
within the turbulent urban boundary layer of wind flow,significantly reducing the quality of the wind resource.
No clear differences in wind energy abundance were
observed at pitched and flat roofs and open areas inyards.
Vertical velocity components were not found to be
significant at all sites. BOM data suggests study covers a windy period.
These findings match those of similar studies performed
elsewhere.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 26/27
Conclusions
Successfully deploying turbines at sites like the CBD
site, with high levels of turbulence and only modest
available wind energy represent the true challenge of urban wind technology.
The Williamstown site lies on the boundary of the urban
realm and represents wind conditions more akin to those
found at commercial-scale wind farms rather than other
built up domestic sites.
A wind resource assessment is a vital prelude to
installation of a MWT in an urban area.
The wind resource is and will always be site specific.
There is no substitute for gathering real data from a site
of interest.
8/8/2019 Wind Report 2 Mike
http://slidepdf.com/reader/full/wind-report-2-mike 27/27
Most gracious thanks to all site owners,ATA members and ATA employees
who helped out with this project.