Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.
-
Upload
tamsyn-pope -
Category
Documents
-
view
212 -
download
0
Transcript of Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.
![Page 1: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/1.jpg)
Why does OTEG need a charging subgroup?
OTEG Open Meeting
3 July 2006
![Page 2: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/2.jpg)
Why does OTEG need a charging subgroup?
• What are TNUoS charges?– Price controlled revenue and TNUoS charges
• How are TNUoS charges currently set?– The TNUoS charging methodology
• Why is a charging subgroup required?– Work needed to extend the current methodology into the offshore– Proposal
![Page 3: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/3.jpg)
Price controlled revenue and TNUoS charges
TransmissionLicensees
• NGET• SHETL
• SPT
Price controlledrevenue
Users of thetransmission
system
• Generation• Demand
TNUoS charges
GBSO
![Page 4: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/4.jpg)
Price controlled revenue
• An allowed revenue is set for each transmission
licensee at the price control
• Revenue set to recover the cost of installing, operating
and maintaining the transmission system
• The transmission licensees’ charges – equal to the
allowed revenue – are paid by the GBSO
• The GBSO recovers the transmission licensees’
charges from users through TNUoS charges
![Page 5: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/5.jpg)
TNUoS charges
• TNUoS charges should, as far as practicable, recover
the allowed revenue
• The GBSO charges users of the transmission system– Develop and apply a use of system charging methodology– Approved by Ofgem– To be kept under continuous review
• Charges are for generation or demand use of system
and vary by location
![Page 6: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/6.jpg)
Current TNUoS charging methodology (1)
• Separate charges for generation and demand (from
27:73 split of revenue)
• Two elements (£/kW):– Locational charge– Non-locational charge (or residual)
• Locational charge from DC loadflow investment cost
related pricing (DCLF ICRP) transport model
![Page 7: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/7.jpg)
Current TNUoS charging methodology (2)
• DCLF ICRP transport model assesses the marginal
cost of investment in the transmission system as a
result of an increase in generation or demand
• Model takes as the starting point an onshore system
comprising secure 400 kV overhead line
• Adjustments for 132/275 kV line, potential line
upgrades, cable, “non-firm” connections…
![Page 8: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/8.jpg)
TNUoS charges offshore: Why a charging subgroup is required (1)
• Indicative charges are an important element when obtaining project financing
• Current charging methodology is complex, and the model parameters are not suited to offshore systems. For example:– Assumes double-circuit connection (GB SQSS compliant)– No adjustments for AC or HVDC submarine cables– Cannot accommodate “modular” offshore infrastructure– Shorter asset life of offshore infrastructure will result in higher
annual revenue requirement
![Page 9: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/9.jpg)
TNUoS charges offshore: Why a charging subgroup is required (2)
• Changes to the charging methodology are time
consuming to develop, consult on, notify and
implement
• Will change onshore TNUoS charges (and zones?)
• Number of options – must be cost-reflective and
non-discriminatory
• Charges will be required for adopted assets
![Page 10: Why does OTEG need a charging subgroup? OTEG Open Meeting 3 July 2006.](https://reader036.fdocuments.us/reader036/viewer/2022072006/56649d085503460f949da085/html5/thumbnails/10.jpg)
Proposal
• Charging subgroup established– Possibly as subgroup of the Charging Issues Standing Group
(CISG)– CISG already considering changes to charging methodology to
accommodate “non-firm” connections, e.g. island links
• Date for publication of draft methodology and
indicative tariffs to be added to OTEG timetable