What is Design Build?
Design-Build is a method of project delivery in which one entity (the design-builder) forges a single contract with the project owner to provide both architectural, engineering design services and construction services.Source: Design-Build Institute of America
WELCOME TO
DESIGN BUILD
MIRACLE NIGHTMARE?
Design Build Panel
Wayne Larsen – Parsons Brinkerhoff
Tom Loo – Alberta Transportation
Karen Stein – Utah Department of Trans.
ROUND TABLE DISCUSSION
U.S. R/W Perspective
Ms. Karen Stein, SR/WA, R/W-RAC
Deputy Director for the Utah Department of Transportation
Traditional Design Bid Build
Plan
UDOT Staff or Consultant
Clear ROW
UDOT Staff or Consultant
Design
UDOT Staff or Consultant
Build
UDOT Staff or Consultant
Design Build
Plan + 30% Design
UDOT Staff or Consultant Design
Design BuildConsultant Team
Clear ROWDesign BuildConsultant Team
BuildDesign BuildConsultant Team
When is Design Build a good idea?
Projects where in-house resources are not sufficient
Projects that can benefit from fast-tracking Projects with a high need for innovation Projects on an Interstate Risks known and transferable
With Design Bid Build(the traditional model)
In DBB projects there is a balance between Scope Schedule Budget
With Design Build
It is all about the Schedule!
Design Build from the U.S. Agency’s perspective
Benefits
Identify and manage risk Reduce acquisition time line Encourage negotiated settlements Encourage design to mitigate “damages” Encourages use of effective scheduling methods and software Expands DOT resources for Acquisition/Relocation Process DB incentives help promote implementation of an effective Public
involvement plan
Design Build from the ROW perspective
Risks
Increased overhead and direct acquisition and relocation costs Potential for coercive acquisition methods Increased number of condemnation cases & admin settlements Potential for precedent setting practices which are out of compliance
with URA and or UDOT ROW Policies and Procedures. Increased time for each ROW task due to increased hand offs between
DB and Central DOT ROW Delay Claims if DOT fails to meet schedule requirements
Issues for ROW with Design Build
The Selection Process Right of Way section of RFP must be
sufficiently and accurately detailed Selection Team must include a ROW Staff
person ROW component of the DB Proposals may
not be sufficient to affect the overall selection of the DB team.
Design Build from the Engineering point of view
Benefits Early known cost Reduce delivery time Reduce design errors Improve Constructability Identify and manage risk Encourage innovation Less detail required in
design Expands UDOT resources
Risks• Proposal costs
• Innovation limited to contractor experience
• Third Party Delay
Canadian Perspective
Mr. Tom Loo, P. E.
Executive Director of Major Capital Projects for Alberta Transportation
Ring Roads
The Premier and the Government of Alberta have made a commitment to complete the ring roads in a free flow condition around the cities of Edmonton and Calgary
The majority of the land required for these major freeways were purchased by the province in the 1970’s
Current Status of Ring Roads
Segments of Anthony Henday Drive in Edmonton and Stoney Trail in Calgary are currently open to traffic
Planning, design, and construction is continuing on all remaining segments of the ring roads
Edmonton Ring Road
Calgary Ring Road
Project Delivery Mechanisms
Traditional Design-Bid-Build Projects up to approximately $100 million Majority of projects delivered using this method
Design/Build Projects approximately $100 to $300 million One project being delivered using this method
Public Private Partnerships (P3) under a Design/Build/Finance/Operate (DBFO) agreement
Projects approximately over $300 million Two projects designed, constructed and currently in operations Two other projects being delivered using this method
Anthony Henday Drive – Stony Plain Road Interchange
Being delivered through Alberta Transportation’s first design/build contract
Includes 50 lane km of new and rehabilitated roadway and seven bridge structures which will provide for a free flow systems interchange
Anthony Henday Drive – Stony Plain Road Interchange
Anthony Henday Drive – Stony Plain Road Interchange
Design/Build Procurement commenced in summer 2008 Issued RFQ in August 2008 Short-listed to three proponents Issued RFP September 2008 Executed agreement with preferred proponent February 2009
Contract price of $168.6 million
Construction commenced April 2009
Traffic availability scheduled for October 15, 2011
Design/Build Advantages
Cost certainty Schedule certainty Compressed schedule (fast-track design and
construction) Clearly defined project scope Risk transfer Opportunity for innovation
Design/Build Disadvantages
Clearly defined project scope Design must be further advanced for accurate pricing Unknowns removed (geotechnical, etc.) Regulatory issues resolved in advance (risk not
transferred) Less “control” by owner during
design and construction
Design/Build Disadvantages
Clearly defined project scope Design must be further advanced for accurate pricing Unknowns removed (geotechnical, etc.) Regulatory issues resolved in advance (risk not
transferred) Less “control” by owner during design
and construction
Design/Build Disadvantages
Potential for quality issues Costly procurement process Not ideal for projects with:
Geotechnical unknowns Environmental issues Utility issues Any 3rd party which may add risk to contractor
Design/Build Procurement Process
Detailed Technical Requirements Pass/Fail criteria for technical submissions by proponents Allow multiple runs at the gate to achieve pass within a set
time period Must be compliant technical proposal (pass) to proceed to
price submission Lowest price wins
Quality Management
Quality is very important to the owner Quality Manager required and evaluated as part of
RFQ Quality Management System must be ISO compliant Contractor responsible for overall Quality Control
and Quality Assurance Owner has maintained rigorous quality management
oversight
Elements of Design/Build
Utility cost sharing threshold Progress payments during construction 10% holdback Late completion penalty of $10,000 per day 2-year warranty
Land Acquisition
Owner best party to manage the risk of property acquisition
In general, risks not properly allocated or mitigated will ultimately be transferred back to the owner through the bid price
Ideally, all required land should be acquired prior to the start of the procurement process
Majority of required land purchased by the provincein the 1970’s
Land Acquisition
Some slivers or small parcels required for design and construction
Private contractors do not have the ability to expropriate property if required
Property acquisition can be a lengthy process and negate the advanced schedule benefits of Design/Build
Land Acquisition
Where the required sliver or parcel of land was not obtained prior to procurement, Design/Build agreement specifies when the required land will be available
Provincial staff continued to work during procurement period and early construction period to secure required land
Contractor required to mitigate impacts of not having required land at start of construction
Process has worked reasonably well
Current Status of Design/Build Project
Ahead of schedule
On budget
Good quality
Good working relationship with contractor
DB Consultant Perspective
C. Wayne Larsen, SR/WA, R/W-AC
FORBES RatesBest & Worst Cities for Commuters
Forbes ranked Salt Lake City the best city in the country for commuters (FEB 16, 2010)
"One of the reasons we are ranked so high by Forbes is because we have such a comprehensive transportation system."
"One of the biggest, most aggressive, and most successful rail expansion program in the country right now,"
UTA – FRONTLINES 2015 PROGRAM
FRONTRUNNER CRS
MID-JORDAN LRT
DRAPER LRT
WEST VALLEY LRT
AIRPORT LRT
UTA – FRONTLINES 2015 PROGRAM
70 Miles in 7 Years (2015) Using a Design Build team approach 70 Miles in 5 Years (2013)
The Most Important Lessons Learned by UDOT ROW
The RFP is your controlling document Write and re-write the RFP to make sure all expectations are
clearly written A commitment to oversight is required by the DOT
Don’t underestimate the amount of time and number of resources this will require
Hold the DB accountable, be assured that the DB will hold the DOT accountable
Manage Risk wisely and make the DB retain the responsibility of clearing ROW after the NTP date as stipulated in the RFP
Additional Lessons Learned
Monitor the QC/QA process to make sure it is adequate and effective
Have a strong Public Information component of the DB team
Make sure the DB carefully plans and conducts effective Community and Neighborhood focus meetings
Identify and work with 3rd party stakeholders early in the process
Include utility, outdoor advertizing signs, rail roads, local agency and or 3rd party agreements in the environmental document if possible.
If, not in the environmental agreement, develop utility, local agency and or 3rd party agreements as early as possible
DESIGN BUILD
ROUND TABLE DISCUSSION
Thank you
[email protected] (801) 965-4057
[email protected] (780) 913-0330
[email protected] (801) 550-9259
History of DB with ROW in Utah
I-15 (prior to 2002 Olympics) Reconstruction UDOT cleared ROW for Residential
properties, DB team cleared ROW for Non-Residential properties
Under traditional DBB- 8 years estimated time to complete the construction
Actual under DB – completed in 4 years
Current DB ROW Projects
Pioneer Crossing * (I-15 Interchange) (Region 3) I-15 Core * (Region 3) SR-68; Bangerter to Saratoga Springs (Region 3) 114th South (I-15 Interchange) (Region 2) Fort Lane Interchange (I-15 in Region 1) 6200 South CFI (SR-68) (Region 2)
See UDOT’s website for interactive video of these highly innovative projects: www.udot.utah.gov (Under public/innovations)
Projects with specific innovative components
Pioneer Crossing -- Diverging Diamond Interchange (DDI) and Accelerated Bridge Construction (ABC)
S.R. 92 -- Commuter Lanes Express Lanes--I-15 Core Continuous Flow Interchange (CFI) SR-68
Details about each project can be found on the Udot website under public info/innovations and or under Projects.
Home page is www.udot.utah.govVideo overview of UDOT’s program with emphasis on innovations is available on
this website:
RFP must describe the specific Scope of Work
1. Prepare list of parcels with high priority 2. Determine clear scope of work for the ROW Design3. Prioritize 3rd party entities and all utilities4. Provide the DB with a list of properties already acquired or which
will be acquired by the DOT 5. Determine whether the DB will be responsible for the Closings and
if so, will they provide Title Insurance 6. Detail who will have signature authority for every step of the
process Just Compensation Pre-Approval of Admin. Settlement amounts Contracts and or Settlement Authority for Mediations, Arbitrations and
Condemnations. Relocation Claims
7. Develop a negotiated Flow Chart with the DB 8. Meet and discuss status on a weekly basis9. Track all hand offs to and from the agency (using a shared system if
available) IE using our in house EPM system, or the DB’s tracking system. Agree on the method to be used to track the process, status and deliverable
Best Practice RE: Scope of Work
Based on UDOT DB Projects
DOT should begin early acquisition process (total acquisitions & complex acquisitions or 3rd party involvement)) as soon as possible once the project has Environmental Clearance
Purchase based on 30% design for the widest estimated footprint to include all potential easements
Transfer the responsibility of clearing ROW and the Risk as of the Notice to Proceed (NTP) Date.
Appraisal/Valuation Issues
Consistency in methodology and use of comparable sales data
Out of state appraisers and review appraisers are not recommended, out of necessity out of state reviewer may be ok but not ideal.
Single review appraiser or at least one reviewer per identified segment of the project for consistency purposes
Acquisition Issues
Monitor to ensure that policies and RFP are followed Require good faith negotiations Do not allow DB to use Right of Entry (ROE) unless other means to acquire
have been exhausted Use Right of Occupancy Agreement (ROO) responsibly and only if owner is
willing to negotiate and or mediate differences of value If ROO is obtained DB must follow up to acquire or condemn based on
negotiated time line (negotiated with property owner) with authorization of the DOT
Condemnation Resolutions prepared timely Condemnations may only be withdrawn by the Director of ROW
Relocation Issues
Ensure that proper notices are prepared and issued Ensure that advisory assistance is appropriate and timely given Make sure that DOT pre-authorizes studies and notices of eligibility before DB
issues them DB to keep log current and available to the DOT after each contact with
property owner or displaced person Sky is not the limit for relocations! Rush to clear should not result in super adequate and or inappropriate relocation
benefits offered DB must insure that agents employed on the DB project meet or exceed
minimum qualifications as if they were working directly for the DOT Agents employed by the DB must be familiar with the subject area to ensure that
what is thought to be comparable for replacement property is in fact comparable Agents employed by the DB must remember that they are the face of the DOT
and must conduct themselves accordingly
Property Management Issues
Salvage rights Lease agreements Terms of assumed leases Walk through and release of security or key
deposits Security issues Demolitions Surplus Property Staging Areas
12300 South
360 ownerships (over 1000 parcels) DB project completed in 3 years vs. 9 years
projected under DBB. Higher administrative settlement frequency due to
aggressive schedule & cost pass through
114th South
Special complexities New Bridge over Jordan River Relocation of a power substation New I-15 Interchange 270 ownerships plus Utility easements Current status: Construction is 61% complete Acquisitions and Relocations in progress
approximately 67% of needed ROW is cleared
Access Utah Projects and I-15 Core (Innovation)
Pioneer Crossing, a new, five-lane urban arterial from Redwood Road in Saratoga Springs to 300 East in Lehi.
Innovative Components A new diverging diamond interchange (DDI) at I-15 and American Fork Main Street, which
will replace the existing diamond interchange. Includes an Express Lane in each direction through the interchange (to tie in to the upcoming I-15
widening project). ABC Bridge Construction (American Fork Bridge)
Estimated completion in 2 years Construction is Currently 62% Complete Managed as part of the “Access Utah”: group of 5 separate projects. Central ROW provides oversight and helps to direct, train and oversee the ROW firms
hired to clear the right of way.