What does BIM mean to the Project? - BIMMEPAUS · ― 202 Revit to SQL DB tables ― Project Co FFE...
Transcript of What does BIM mean to the Project? - BIMMEPAUS · ― 202 Revit to SQL DB tables ― Project Co FFE...
Chris Penn - BIM Manager new Royal Adelaide Hospital
What does BIM mean to the Project?
― Introduction(s)
― Why we implemented BIM
― What BIM means to the project
― Lessons Learnt
― Aims & Objectives
― Summary
Agenda
― Building Services Engineer
― 34 Years in Industry
― Implementation of RUCAPS 1985
― Development of SONATA/Reflex/ProReflex
― UK Chapter IAI (buildingSMART) Founding Board Member 1995
― Own Business – Major UK Projects
― Group IPD/BIM Director Scott Wilson
― buildingSMART Australasia
― AIA Consult Australia
Personal Introduction
nRAH Introduction
― Project Value $1.8BN
― Hospital Facility, 175,000m2
― Car Park 76,000m2
― 800 Single inpatient Units
― 40 Technical Suites, some with MRI facilities
― Technology Features including patient weighing beds, wireless, intelligent systems
― Gardens and Green Courtyards
― Advanced IT, clinical & patient information
― AGV system
― Commercial Precinct, crèche, mini-mart, restaurant, cafes, gymnasium
― Emergency Dept 25% extra cap
nRAH Project Design Team
nRAH Key Contractors
7
The Technical Challenges
― 1,800 operatives on site at peak
― HYLC 160 Staff
― Over 450 user group meetings
― Closed out in 14 months
― 20 Construction Contractors
― 14 Services/ICT Contractors
― Over 2,000 piles
― 25,000 tonnes of reinforcing
― 2,500 tonnes of steel
― 4,880m3 Concrete poured in June
― 12,000 Facade Panels
― 9,500 Associated Facade Items
― 7,500 Sanitaryware Fixtures
The Challenging Facts
― 40KM of Partitioning
― 8,000 Doors
― 240 Discrete Packages to State, issued 114 (48%)
― 220 Revit base models to date
― 14,518 Drawings issued to date
― 102 Shop drawings issued to date
― 1,201 3D Models issued to date
― 4,831 State comments rec’d to date
― 202 Revit to SQL DB tables
― Project Co FFE items 172,017
― Objects in Partition models 390,414
Why we implemented BIM – Process?
9
Ideal
situation
Current
practice
Time
Valu
e
Concept Detail Design Construction Operation &
Maintenance
The building process – paper based
10
Main Contractor
Designer
Sub contractor
Facility Manager
11
The building process – co-ordination
We will sort it out on site!
12
The building process – skills gap
The building process - challenges
― Waste/duplication
― Paper based
― Collaboration
― Communication
― Co-ordination
― Lack of Planning
― Lack of skills
― Lean Construction
― Management of risk
― Outdated Contracts
― Change Management
― Right first time
― Technology
― People
14
What BIM means to the project
“Building Information Modelling (BIM) is the process of generating and
managing digital information during an Assets life cycle”
BIM Execution Plan (BEP)
16
Discipline for the collaborative production of architectural, engineering and construction information.
WIP
Architect Share
Publish Archive
M&E
Struct
R1
R2
etc
P1
P2
etc
WIP
WIP
Collaboration – Standards, Standards
Building Prototype Technology
Object Based Structured Data
Library Content (Lego Bricks)
Supply Chain Involvement
Virtual Design Management
Spatial Co-ordination
Build it twice, once in the computer once on site.
Co-ordination Management
Fire Strategy Co-ordination
4D Construction Sequencing
Business Development
BOQ/Labour
Earned Value Reporting
Link to Cost Data
5D Estimating/BOQ
Offsite Manufacture
“Design for Manufacture”
Engineering Services Integration
Engineering Services Integration
Engineering Services Integration
Field BIM – Construction Technology
SPOTNIC – Managing Completion Data
Generate Custom Reports/Extract Data
Single Point of Truth – newRAH Information Centre
Completion Data
SPOTNIC – Data Analysis
― Department areas by colour
― Area Comparison
― FFE Management
― Bi-Weekly Bid Comparison
33
The Facade, Structural and Fit-out discipline will have a set of levels to submit and access information
SPOTNIC – WBS
34
Sector / Level model opens containing all Fit-out disciplines
SPOTNIC – Fit-Out
35
All disciplines are able to be viewed for the selected Sector / Level
SPOTNIC – Engineering Services
36
All disciplines are able to be viewed for the selected Sector / Level
SPOTNIC – Architectural
37
All disciplines are able to be viewed for the selected Sector / Level
SPOTNIC – FFE
38
A barcode attached to each Facade panel will create a direct link into the SPOTNIC
system.
Scanned barcodes will automatically link completion data into the 3D Hub.
SPOTNIC – Barcode Wayfinding
SPOTNIC - Field BIM
― Consistent BIM Documents
― Standards, Methods & Procedures
― Collaboration
― Structures Set Out
― Transparency, Discipline
― Data Management
― Co-ordination QA
― Identify Champions
― Involve everybody
― Supply Chain Partnering
― Education
― Promote a ‘We’ Approach
40
Lessons Learnt
How do ‘we’ get there……….
41
BY INVOLVING EVERYBODY & REMINDING THEM ITS THE ‘WE’ APPROACH
42
Business Benefits: Data Capture
new Royal Adelaide Hospital Loyalty Card
Our Aims & Objectives
43
― Reduction of Waste
― Reworking Potential Savings 12%
― Improved Co-ordination
― Better design fit for purpose
― More data management focused
― Integration of supply chain
― Better management of risk
― Program efficiencies
― Greater cost certainty
― Everybody benefits
― Driving Change in the SA Industry
44
‘Shared Ambitions delivers great Results’
Summary