allan kelly Twitter: @allankellynet http://www.allankelly.net Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020

Transcript of What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric...

Page 1: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

allan kellyTwitter: @allankellynethttp://www.allankelly.net

Xanpan“Zan-pan” Team centric Agile

What do you get if you cross Kanban

with Extreme Programming?

2014-2020

Page 2: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

We don’t need another Methodology

Scrum

FDDASDPrince2

SSADM

Crystal(s)Method1 Lean

Kanban

Xanpan

Extreme

ProgrammingRUP

OUP

Pragmatic AgileScrumBan

DSDM

Page 3: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Choose your Cola

Kent BeckXP-Cola

Ken & Jeff’sScrum-Cola

David AndersonKanban-Cola

Allan KellyXanpan-Cola

Page 4: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Where did Xanpan come from?

• Experience (Lean+XP)– Blue-White-Red

• Kanban• XP• Plus – Seeing others– Reports of other cross-overs

• Making sense of what I see

XP Kanban & Lean

1First

concept

XP Kanban & Lean

Product Management

2

XP &

ScrumKan

ban

& Lean

Product

Management Other s

tuff3

Page 5: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Principles

• Iteration routine• Team Centric– Planned & Unplanned work– Team over projects

• Invest in Quality / “Quality is Free”• Dis-economies of Scale• Flow: Emphasize, Level, Span, Constrain• Goodhart’s Law• Constructivism learning• Visualise

Page 6: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Practice

1. XP Technical practices: TDD, CI, etc.2. Teams can work on more than 1 stream– Flow multiple projects/product to 1 team

3. Break Stories to Tasks– Colour code work– Estimate in Points– Small is better - Think Small!

4. Benchmark against self– Velocity

Page 7: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Practices

5. Flow– Use Product “Ownership” (Product Management

& Business Analysis) to control (restrict) flow– Apply WIP limits– Absolute Prioritization

6. Planning levels (horizons)7. Pick’n’Mix8. Action over words

Page 8: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Practices

9. Fit work to the time– Deadlines are good– Limit WIP

10.Evolutionary change– Small Bangs are OK – but Big Bangs are bad

Page 9: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Some detail….

Page 10: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Iterations & Flow

• Iterations bring structureBut• Strict iterations break flow– “Story must be finished in sprint”– “Story cannot be bigger than a sprint”– Sprint tail overwhelmed by finished stories– Testers drop standards

• Strict iteration– Difficult at first – learn to think small

Page 11: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Repeat

Thursday

Friday

Monday

Tuesday

Wednesday

Ends

Work

Release

Dem

oStart

Prio

ritiza

tion

Brea

kdow

nAg

reem

ent

Review &

Retrospective

Planning

meeting

Thursday

Friday

Monday

Tuesday

Wednesday

Iteration - 2 week routine

Page 12: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Iterations & Flow

• Stories spanning sprints levels work– Break down stories to tasks– Tasks only counted when completed– When all tasks done, Story done

• 3 Strikes and you are out!– Story span 1 Sprint, OK, good– Story spans 2 Sprints, umm… Red Flag– Story spans 3 Sprints, Out! Story too big

Page 13: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Breakdown

• In planning meeting• Part– Software Design– Requirements elicitation– Opportunity to reduce scope– Estimation exercise

Image from Paul Goyette, Creative Commons Licensehttp://commons.wikimedia.org/wiki/File:Wrecking_ball.jpg

Page 14: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Epic

StoryStoryStoryStory

Not essential, use if useful

Blues – Stories• Business facing• Have automatic business value• Deliverable in own right• Deliverable sometime soon • Typically software feature but

anything which brings value –documentation, etc.

TaskTaskTaskTask Whites – Tasks• Typically developer tasks• No business value alone

Page 15: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation: useful but building on sand

Page 16: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation

1st rule of estimation:

Estimate value before effort

2st rule of estimation:

Only effort estimate work which is expected to happen within 3 months

Page 17: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation

3srd rule of estimation:

Use historic data when making forecasts

e.g. if team averages 18 points a sprint then expect about 18 points next sprint

Page 18: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Yes, Estimation

I’ve come to like Planning

Poker but choose your own poison

• Estimate White tasks in planning meeting– Ball-park estimate Blues

• Estimates in Points– Your currency £ $ €– One currency– Forget hours

Page 19: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation worthwhile? “I can bring a project in to the day”

?

• For scheduling? Perhaps– Some teams report good results– Some teams placebo effect– Long run average accurate enough

• Provides Developers with safety valve• Useful input to design process(Forget actuals – retrospective estimates)

Page 20: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation…

• Within 3 months effort estimates:– Generally right– Useful in designing & scheduling

• Beyond 3 months:– Estimates too variable– Work changes

• Value estimate beyond 3 months essential

Page 21: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Estimation

4rd rule of estimation:

Assess deliveries for benefit realizedClose the loop on value estimates

5th rule of estimation:

Count effort points but do not change retrospectively

Page 22: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Reds

YellowsUnplanned work

GreenSpecific to you

Page 23: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Planned & Unplanned work

• Work planned in planning meeting• Unplanned work allowed at any time– Tag it, e.g. Yellow card– Retrospective estimation

• At end of the iteration count points unplanned– Graph/Track planned v. unplanned– Incorporate into planning velocity

Page 24: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Velocity: planned & unplanned work

0

2

4

6

8

10

12

14

16

18

20

1 2 3 4 5 6 7 8 9 10 11 12

Planned work done Unplanned work done Total done

Page 25: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We
Page 26: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Light Sabre

Every team must design their own board

Page 27: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Quality…

… makes all things possible

Page 28: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Quality core

Page 29: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

What qualities are important to you?

Page 30: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Goodhart’s Law

Any observed statistical regularity will tend to

collapse once pressure is placed upon it for control

purposes.

Professor Charles Goodhart, CBE, FBA

Velocity & points break down if abused … and so do other measurements

Page 31: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

Is Xanpan useful?

• Maybe – Take it– Use it

• Inspiration– Roll your own

Image from Ildar Sagdejev under Creative Commons licensehttp://commons.wikimedia.org/wiki/File:2009-02-15_Rolling_a_cigarette.jpg

Page 32: What do you get if you cross Kanban with Extreme Xanpan ... · Xanpan “Zan-pan” Team centric Agile What do you get if you cross Kanban with Extreme Programming? 2014-2020. We

33

E-book http://leanpub.com/xanpanAmazon for eBook & printed – Audio coming soon

Which brand of Cola are you drinking?