Wet x dry completion with risk
-
Upload
glaucio-bastos -
Category
Business
-
view
275 -
download
7
Transcript of Wet x dry completion with risk
2
WET AND DRY COMPLETION PROJECTS COMPARISON THROUGH RISK CASH FLOW ANALYSIS
Authors: BASTOS, Gláucio A.; JACINTO, Carlos Magno C.; TORRES S.Jr, Flodoaldo
ABSTRACT
After globalization, businesses do not have more borders. The decision maker
strategic positioning demands information. Ideal decisions, if existent, are
intimate closer on (almost) perfect information attainment, analysis and
interpretation. To hold reliable information in correct time became the great
differential for companies.
Exploration and production projects are complex and there is a lot of
variables that need to be considered in decision process.
Those projects can be analyzed through discounted cash flow, but would not be
real if risks on different variables are not considered. Therefore, statistical
models are fundamental on viability analysis.
3
September, 2008.
SUMMARY
1-INTRODUCTION 03
2-METHODOLOGY 03
3-APPLICATION 04
3.1-Basis Development 04
3.2-Deterministic Analysis 06
3.3–Sensitivity Analysis 08
3.4–Probabilistic Analysis 08
4-ANALYSIS OF OUTCOMES 11
4.1-Measures for outcome evaluation considering Risk 11
5-CONCLUSIONS 19
6-BIBLIOGRAPHY 19
4
1-INTRODUCTION
The current scenario of oil & gas fields development in Brazil is a
consequence of high efforts and investments made in last decades in search of self-
sufficiency in providing care to internal demand for oil derivatives, activity that
today boasts a RESERVE / PRODUCTION RELATION of 19 years that is high compared with
10 years world average, indicating the need for new projects deployment aiming
available reserves disposal. This urgency guides the project management activity
seeking outcome maximization in the possible shortest time. To do this effective
techniques application is indispensable for treating RISK in projects.
By the way, oil fields development projects demand high investments in the long
term, reflecting in project RISK, which can be quantified in terms of technology,
policy and marketing and depends on technology choice and assessment of its impact
on business.
In the calculation model being presented in this paper, the following
considerations were adopted as a strategy for its implementation:
• in two completion alternatives comparison, deployment costs are considered to be
inherent to reliability (availability, failure rate, etc.);
• monetary outcomes determination considers the "costs at risk"; and
• political risks on production flow, market uncertainties and so on are not covered
because their impact on the two technologies are similar.
The alternatives included for comparison include technical and financial
models of the following three technological scenarios:
a – Wet Completion: with Wet Christmas Trees and Standing Production Unit (SPU) of
FPSO type;
b – Dry Completion with all wells interconnected to Mini-TLP (Scenario "A"): with
Dry Christmas Trees installed in a SPU of Tension Leg Platform (TLP) type
interconnected to wells through rigid risers, where wells / SPU distance restraint
can be offset using one or more TLPs, preferably of Mini-TLPs (TLWP) type - a
smaller one in size and capacity but that otherwise provides benefits such as CAPEX
reduction, less SPU construction time and consequently early wells production start,
anticipating the revenue flow as compared with conventional TLP installation and
thus reducing the main disadvantage of TLP as compared with FPSO operation;
c – Dry Completion with production wells interconnected with the Mini-TLP and
injection wells linked to FPSO (Scenario "B"): here Mini-TLP size and capacity are
reduced as compared with previous alternative situation, besides directional
drilling becomes less complex as long as injection wells are not connected by rigid
riser to Mini-TLP, although underwater lines are kept for this arrangement.
2-METHODOLOGY
The data source was accessed from the Brazilian Agency for Oil and Natural Gas
(ANP) internet site - www.anp.gov.br treated with industry average costs and then
assembled in a spreadsheet showing revenue and development costs information to a
technical and financial cash flow model considering alternative projects according
to their different strategic scenarios.
5
The mathematical model was constructed as described and solved using @RISK - a
software for business and technical analysis under "risk" exposure which is a MS-
EXCEL applicative that incorporates decision analysis techniques. The combination of
these two products allows cash flow modeling with "risk" considerations and improves
key variables understanding on decision impact.
In this study analyses were conducted using @RISK generated responses with the
purpose of oil and gas production projects comparison, in search of financial
resource allocation to maximize the return on investment, regarding business risks.
@RISK provides two simulation techniques as user options, based on different
data sampling, which are Monte Carlo and Latin Hypercube (LH). The LH technique was
chosen considering the following advantages as compared with conventional Monte
Carlo technique:
• LH attaches equal weights to all chance tracks during iterative process
avoiding trends; and
• LH reduces the total number of iterations on about 30%.
The number of iterations adopted in each simulation was 10,000 since was
experimentally determined that for a larger number, differences among each
simulation outcomes were negligible.
3-APPLICATION
This study deals with exploration and development of SAGATIBA prospectus,
block BMS-69, considering 869 MMSTB of annual oil production through pre-salt layer
and the following additional data common to all three scenarios:
Production time (years) 24
Location to shore distance (km) 215 Wells number 22
production 15
injection 7 Exploratory expenditure (US$ 10
3) 132,535
seismic 3,000
exploration and appraisal 121,470
others 8,065 Wells development (US$ 10
3/well) 59,631
drilling 39,754
completion 19,877
Table 1
3.1–Basis Development
The specific data to each scenario may thus be compared:
6
WET COMPLETION
Subsea equipment (US$ 103/well) 16,000
Development – CAPEX (US$ 103) 2,994,111
directional drilling 1,111,523
FPSO 800,000
subsea 304,000
pipes 150,500
onshore plant 50,000
others 578,088 Development – OPEX (US$ 10
3) 2,478,668
Table 2
DRY COMPLETION – Scenario “A”
Development – CAPEX (US$ 103) 3,534,720
directional drilling 1,556,132
TLWP 400,000
FPSO 800,000
pipes 150,500
onshore plant 50,000
others 578,088 Development – OPEX (US$ 10
3) 2,268,524
Table 3
DRY COMPLETION – Scenario “B”
Subsea equipment (US$ 103/well) 16,000
Development – CAPEX (US$ 103) 3,374,278
directional drilling 1,394,890
TLWP 300,000
FPSO 800,000
subsea 100,800
pipes 150,500
onshore plant 50,000
others 578,088 Development – OPEX (US$ 10
3) 2,404,270
Table 4
Conclusions after tables 2, 3 and 4 follows:
• Wet Completion: presents the lowest CAPEX and highest OPEX;
• Dry Completion Scenario "A": presents the lowest OPEX, as long as all X-Trees are
dry, positioned on TLWP at the surface thus making workovers more cheaper besides
there is no subsea lines because wells are connected to Dry X-Trees through rigid
risers which otherwise makes directional drilling more expensive;
• Dry Completion Scenario "B": presents the lowest CAPEX among Dry Completion
scenarios as long as injection wells are linked to FPSO through subsea lines and the
TLWP that links production wells is lower and therefore cheaper than that scenario
“A” one, besides OPEX is lower than that of Wet Completion because workovers are
7
more efficient and therefore cheaper as long as production wells Dry X-Trees are
positioned on TLWP.
3.2-Deterministic Analysis
Specific data for this phase follows:
WET DRY – Scen.”A”
DRY – Scen.”B”
Estimated production (M Boe) 948 1,080 1,080 Oil price - no taxes (US$/b) 35 35 35 Income revenue tax (%) 30 30 30 Capital cost (%) 15 15 15 Depreciation (years) 24 24 24
Table 5
Dry Completion has the highest production thanks to ease and efficiency of
operations through Dry X-Trees which increase the wells recovery factor.
Below, production curves for both completion types are shown:
Graph 1
Graph 2
Production FPSO Wet Completion
0
10
20
30
40
50
60
70
80
90
2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034
Year
M
Bo
e
Production FPSO + TLWP
0
10
20
30
40
50
60
70
80
90
2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034
Year
M
Bo
e
8
The three project scenarios are mutually exclusive, since the deployment of
one of them requires the removal of other alternatives. In this case, according to
Samanez (2005, p260) a comparison of their cash flows of Internal Rate of Return –
IRR method, as long as the first one assumes that cash flows will yield the
opportunity cost when reinvesting the generated cash flows. Hence, in this situation
project selection using IRR yields inconsistencies and contradictions with NPV
method and therefore the NPV was adopted in this study as an indicator of
mathematical calculation model outcomes.
The outcome ranking after cash flow modeling and solving follows:
COMPLETION RANK NPV (US$ 10
3)
DRY – Scen.”B” 1 2,049,420 DRY – Scen.”A” 2 1,993,648 WET 3 1,867,134
Table 6
The Accumulated Present Value curves for each scenario are as follows:
Graph 3
Graph 4
FPSO Wet Completion : PV
-1.500.000
-1.000.000
-500.000
0
500.000
1.000.000
1.500.000
2.000.000
2.500.000
2004 2007 2010 2013 2016 2019 2022 2025 2028 2031 2034
Year
US
$ 1
03
FPSO + TLWP Scenario"A" : PV
-2.000.000
-1.500.000
-1.000.000
-500.000
0
500.000
1.000.000
1.500.000
2.000.000
2.500.000
2004 2007 2010 2013 2016 2019 2022 2025 2028 2031 2034
Year
US
$ 1
03
9
Graph 5
Note that the Discounted Payback is 11 years for all alternatives.
3.3–Sensitivity Analysis
Sensitivity Analysis applied to the deterministic model indicated the relevant
variables ranked as shown below including each respective outcome impact:
RELEVANT VARIABLE UNIT RANK OUTCOME IMPACT
Capital cost – MRI % 1 -
Oil price US$/b 2 +
Annual estimated production M boe 3 +
Tax % 4 -
Annual production flow % 5 +
Total investment in wells development US$10
3/well 6 -
Table 7
Note: positive impact indicates that variable increasing leads to outcome increasing
and variable decline to outcome decreasing while negative impact, on the contrary,
indicates that increasing or decreasing in variable leads to an opposite direction
outcome.
Conclusions of Sensitivity Analysis for the three scenarios can be presented
in graphic form, through either “tornado” or “spider” graphs, as for indicating the
influence percentage on outcome variables.
3.4-Probabilistic Analysis
After definition of variables that significantly impact the model, their
PROBABILITY DISTRIBUTION FUNCTIONS are established according to the bibliography
FPSO + TLWP Scenario"B" : PV
-2.000.000
-1.500.000
-1.000.000
-500.000
0
500.000
1.000.000
1.500.000
2.000.000
2.500.000
2004 2007 2010 2013 2016 2019 2022 2025 2028 2031 2034
Year
US
$ 1
03
10
presented at the end of this study according to experiments that were carried out to
determine each distribution theoretical type that best fits to historical data as
analyzed by the Chi-Square Test which indicates the best probabilities theoretical
distribution through the lower Chi-Square Index boasted.
According to Costa (2003, p211), Mian (2002, p318) and Steagall (2001, p24),
except for TAX, all other relevant variables show Probability Distribution Frequency
Curves or PDFs (which are frequency distributions for each observed value of
variable) compatible with the TRIANGULAR DISTRIBUTION which is a CONTINUING one and
whose PARAMETERS are: the lowest possible value, the more likely value and the
highest possible value. For each relevant variable, the following Triangular
Distribution parameters were used, where the most likely value – MLV is that one
considered in deterministic analysis:
a) Capital cost - MRI, according to Costa (2003, p102)
• lowest value: - 15% of MLV;
• highest value: + 15% of MLV;
b) Oil price, according to Costa (2003, p102)
• lowest value: - 30% of MLV;
• highest value: + 30% of MLV;
c) Annual estimated production, according to Steagall (2001, p61)
• lowest value: - 20.0% of MLV;
• highest value: + 12.5% of MLV;
d) Annual production flow, according to Steagall (2001, p74)
• Year 1
lowest value: - 4.0% of MLV;
highest value: + 1.6% of MLV;
• Year 2
lowest value: - 7.5% of MLV;
highest value: + 3.4% of MLV;
• Year 3
lowest value: - 15.0% of MLV;
highest value: + 8.1% of MLV;
• Year 4
lowest value: - 9.0% of MLV;
highest value: + 14.5% of MLV;
e) Total investment in wells development, according to Costa (2003, p102)
• lowest value: - 20% of MLV;
• highest value: + 20% of MLV.
For TAX, according to Costa (2003, p115) and Dallolio (2006, p72), as long as
it is considered a DISCRET variable, two separate simulations were launched, each
one for a different scenario, as follows:
• 30% tax rate in case of Income Tax imposed just on revenue;
• 60% tax rate in case of total tax applied on the venture, that also includes
Governmental Participations fraction incident on the project under a more
conservative viewpoint which makes the model more robust.
The model takes into account the probabilistic dependence possibility among
your variables. According to Mian (2002, p335), there are basically four types of
probabilistic dependence patterns among variables that are defined by Scattering
Diagrams whose vertical and horizontal lines represent respectively dependent and
independent variable, which are presented as follows:
11
Graph 6
We can describe each Scattering Diagram type as follows:
• Total Linear Positive Dependency (graph 6.a) - in this case, independent
variable increase or decrease causes the same effect on dependent variable;
• Total No Linear Negative Dependency (graph 6.b) - independent variable
increase or decrease causes the opposite effect on dependent variable;
• Diffuse Positive Dependency (graph 6.c) – this one can be positive or negative
and indicates that the variables are correlated but in a not so perfect way as
occurs in previous types;
• Without Dependency (graph 6.d) - in this case, there is no correlation between
variables which therefore are each other independent.
Among model relevant variables studied in this work was found a positive
correlation of Total Linear Positive Dependency type (as in Fig. IV.1.15.a) between
independent variable - OIL PRICE and dependent variable - TOTAL INVESTMENT IN WELLS
DEVELOPMENT presenting a Correlation Coefficient of 0.92102 – which as being
positive and around 1.0 indicates that correlation is strong and positive. This
analysis was made after the following historical data, extracted from RigLogix
(12/15/2007), which include oil price influence on certain types of offshore
development investments:
Graph 7
12
Graph 8
For such correlation the following Scattering Diagrams were established:
Graph 9
4-ANALYSIS OF OUTCOMES
NPV PDFs calculated for each scenario and tax level, according to Chi-square
Test and consistently with Mian (2002, p318), keep pace with NORMAL DISTRIBUTION,
which is a CONTINUING type distribution and whose PARAMETERS are the mean and the
NPV standard deviation. Also of relevance for the Analysis of Outcomes are
Cumulative Distribution Frequency Curves or CDFs which are frequency distributions
of values that a variable can show less or equal to each observed variable value.
About Sensitivity Analysis made after probabilistic model solution, the
relevant input variables can be ranked as follows for each tax level, in descending
order of influence on the outcome:
1st. Oil price;
2nd. Capital cost - MRI;
3rd. Annual estimated production;
4th. Total investment in wells development;
5th. Annual production flow.
4.1-Measures for outcome evaluation considering Risk
The Performance Index - PI incorporates NPV and Risk to the extent of
feasibility of an investment under restrictions either on Risk or on the investor's
decision to choose the investment that maximizes economic outcomes and is calculated
as follows:
Correlation between OIL PRICE x TOTAL INVESTMENT IN
WELLS DEVELOPMENT
0 20 40 60 80
100 120 140 160 180
0 20 40 60 80 100
Oil Price (US$/b)
TO
TA
L IN
VE
ST
ME
NT
IN
W
EL
LS
D
EV
. (
10
3 U
S$/W
EL
L)
13
In decision making the investor sets a minimum value for PI according to his
attitude to Risk. Projects with PI higher than this minimum desired amount are
selected as economically viable.
The PI is a measure of the type "mean-standard deviation" where alternatives
of higher mean (maximization of the outcome) and / or lower standard deviation
(minimization of risk) - and therefore of higher PI - dominate others.
NPV outcomes calculated for each scenario and tax level considering Risk have the
following parameters:
Table 8
After investor options of minimum PIs (e.g. PI values of 3200 and 1700
respectively to tax levels of 30% and 60%) were drawn, curves that represent
efficiency borders for three points of standard deviation are recorded in the three
scenarios for each tax rate. The three points of "NPV mean-standard deviation" from
the three scenarios simulation for each tax rate are located below the line,
indicating that they are within the efficiency border as long as for each NPV mean,
the standard deviation found was lower than expected at the limit and should
therefore be considered as valid option for the analysis of outcomes next step, as
shown below:
Graph 10
COMPLETION TAX Average NPV (US$ 103) Standard Deviation (US$ 10
3) PI
Wet
30% 1,784,145 500,714 3,563
Dry – Scenario “A” 1,902,577 572,622 3,323
Dry – Scenario “B” 1,912,366 572,079 3,343
Wet
60% 606,119 287,752 2,106
Dry – Scenario “A” 564,927 324,501 1,741
Dry – Scenario “B” 577,040 324,264 1,780
Performance Index = mean
standard deviation
Selection by mean-deviation
Tax = 30%
500000
510000
520000
530000
540000
550000
560000
570000
580000
1600000 1700000 1800000 1900000 2000000
Average PV (US$ 103)
Sta
nd
ard
devia
tio
n (
US
$ 1
03)
14
Graph 11
With NPV outcomes approved for all the scenarios under the Analysis of Mean-
Standard Deviation through PI, the analysis of outcomes next step is to check the
Stochastic Dominance comparing directly distributions through their PDFs and CDFs
for each scenario, as long as distributions mean and standard deviation of each
alternative, by themselves, do not completely describe them.
The three possible dominance rules that compare PDFs and CDFs for each
alternative, according to Mian (2002, p176), are presented below:
Graph 12
The Stochastic Dominance rules can be described in this way:
• Deterministic Dominance (graph 12.a) - in this case, the corresponding PDFs
and CDFs of the two competitive scenarios do not intersect each other and one
of the alternatives has higher mean than the other and therefore its PDFs and
CDFs are far right. Therefore this is the dominant alternative. Under this
type alternatives are ranked according to their maximum NPV, regardless of
decision maker attitude to Risk;
• First-Degree Stochastic Dominance (graph 12.b) - here, the PDFs of the two
alternatives intercept each other but the corresponding CDFs do not. In this
case, the chosen alternative is the one whose dominant CDF is far right and
therefore boasts higher economics and lower risk;
Selection by mean-deviation Tax = 60%
280.000 290.000 300.000 310.000 320.000 330.000 340.000 350.000 360.000
480.00
0
500.00
0
520.00
0
540.00
0
560.00
0
580.00
0
600.00
0
620.00
0
Average PV (US$ 103)
Sta
nd
ard
de
via
tio
n (
US
$ 1
03)
15
• No Explicit Dominance (graph 12.c) - occurs when both PDFs and corresponding
CDFs of the two alternatives intercept each other. In this case, you must
determine the areas between CDFs before and after the intersection points. The
dominant alternative is the one with the largest area where its CDF is far
right and is therefore the least Risky one.
Afterwards, the scenarios are compared in pairs under each tax level for
dominant alternative determination for each one of the two tax rates:
• Income Tax = 30%
a) Wet Completion X Dry Completion Scenario "A":
Graph 13
Graph 14
Observations for this case are taken from the two curves above:
• PDFs crossed up but CDFs did not => FIRST DEGREE STOCHASTIC DOMINANCE case;
• Dry Completion Scenario "A" PDF presents more chances of higher NPV occurrence
than Wet Completion PDF;
• Dry Completion Scenario "A" CDF, for the same cumulative frequency percentage,
presents higher NPV than Wet Completion CDF, therefore Dry Completion Scenario "A"
is the LEAST RISKY;
• CONCLUSION => Dry Completion Scenario "A" is better.
Wet Completion X Dry Completion Scenario"A" 30% Tax
0
1
2
3
4
5
6
7
8
9
0 0,5 1 1,5 2 2,5 3 3,5
NPV (US$ 103)
Valu
es x
10
^-7
Wet Dry Scen. "A" RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only
Wet Completion X Dry Completrion Scenario"A" 30% Tax
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9
1
0 0,5 1 1,5 2 2,5 3 3,5 NPV (US$ 10
3)
cdf Wet
Dry Scen. "A" RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only
16
b) Dry Completion Scenario "A" X Dry Completion Scenario "B":
Graph 15
Graph 16
Observations for this case are taken from the two curves above:
• PDFs and also CDFs crossed up but are practically coincident => case of NO
EXPLICIT DOMINANCE;
• Dry Completion Scenario "B" presents overall and individually higher NPV and lower
standard deviation than Dry Completion Scenario "A", so it is the BEST DETERMINISTIC
and the LEAST RISKY option;
• CONCLUSION => Dry Completion Scenario "B" is the best option for 30% Income Tax.
• Total Tax = 60%
a) Wet Completion X Dry Completion Scenario "A":
Dry Complet ion Scenario"A" X Dry Completion Scenario"B"
30% Tax
0
1
2
3
4
5
6
7
8
0 0,5 1 1,5 2 2,5 3 3,5
NPV (US$ 103)
pd
f V
alu
es
x 1
0^-
7
Dry Scen."A" Dry Scen."B"
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
RISKview Trial Version For E valuation Purposes Only
Dry Complet ion Scenario"A" X Dry Completion Scenario"B"
30% Tax
0 0,1 0,2 0,3 0,4 0,5 0,6 0,7 0,8 0,9
1
0 0,5 1 1,5 2 2,5 3 3,5 NPV (US$ 10
3)
cdf Dry Scen."A"
Dry Scen."B" RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only
17
Graph 17
Graph 18
Observations for this case are taken from the two curves above:
• PDFs and CDFs crossed up => NO EXPLICIT DOMINANCE case;
• Wet Completion PDF boasts more chances of higher NPV occurrence than Dry
Completion Scenario "A" PDF;
• largest curves intersection area occurs in segment where Wet Completion CDF is far
more right than Dry Completion Scenario "A" CDF therefore Wet Completion is the
LEAST RISKY;
• CONCLUSION => Wet Completion is better.
b) Wet Completion X Dry Completion Scenario "B":
Wet Completion X Dry Completion Scenario"A" 60% Tax
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
cdf Wet
Dry Scen."A" RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only RISKview Trial Version
For Evaluation Purposes Only
Wet Completion X Dry Completion Scenario"A" 60% Tax
0
0,2
0,4
0,6
0,8
1
1,2
1,4
1,6
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
Valu
es x
10^-
6
Wet Dry Scen."A"
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
18
Graph 19
Graph 20
Observations for this case are taken from the two curves above:
• PDFs and CDFs crossed up => NO EXPLICIT DOMINANCE case;
• Wet Completion PDF boasts more chances of higher NPV occurrence than Dry
Completion Scenario "B" PDF;
• largest curves intersection area occurs in segment where Wet Completion CDF is far
more right than that Dry Completion Scenario "B" CDF therefore Wet Completion is the
LEAST RISKY;
• CONCLUSION => Wet Completion is the best option for assumption of 60% Total Tax.
c) Dry Completion Scenario "A" X Dry Completion Scenario "B":
Wet Completion X Dry Completion Scenario"B" 60% Tax
0
0,2
0,4
0,6
0,8
1
1,2
1,4
1,6
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
Valu
es x
10^-
6
Wet Dry Scen."B"
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
Wet Completion X Dry Completion Scenario"B" 60% Tax
0
0,1
0,2
0,3
0,4
0,5
0,6
0,7
0,8
0,9
1
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
cd
f Wet Dry Scen."B"
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
19
Graph 21
Graph 22
Observations for this case are taken from the two curves above:
• PDFs and also CDFs crossed up but are practically coincident => NO EXPLICIT
DOMINANCE case;
• Dry Completion Scenario "B" boasts overall and individually higher NPV and lower
standard deviation than Dry Completion Scenario "A" therefore it is the BEST
DETERMINISTIC and the LEAST RISKY option;
• CONCLUSION => Dry Completion Scenario "B" is the second best option for assumption
of 60% Total Tax.
Then the final scenarios ranking is defined as below:
Table 9
COMPLETION TAX RANK Average NPV (US$ 103) Standard Deviation (US$ 10
3) PI
Dry – Scenario “B”
30% 1 1,912,366 572,079 3,343
Dry – Scenario “A” 2 1,902,577 572,622 3,323
Wet 3 1,784,145 500,714 3,563
Wet
60% 1 606,119 287,752 2,106
Dry – Scenario “B” 2 577,040 324,264 1,780
Dry – Scenario “A” 3 564,927 324,501 1,741
Dry Completion Scenario"A" X Dry Completion Scenario"B"
60% Tax
0
0,1
0,2 0,3
0,4
0,5
0,6 0,7
0,8
0,9 1
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
cd
f Dry Scen."A" Dry Scen."B"
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
RISKview Trial Version For Evaluation Purposes Only
Dry Completion Scenario"A" X Dry Completion Scenario"B"
60% Tax
0
0,2
0,4
0,6
0,8
1
1,2
1,4
-0,4 -0,2 0 0,2 0,4 0,6 0,8 1 1,2 1,4
NPV (US$ 103)
pd
f V
alu
es x
10^
-6
Dry Scen."A"
Dry Scen."B" RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only RISKview Trial
For Evaluation Purposes Only
20
The selection between the two tax rates depends on strategic and conservative
policies applied by the company when evaluating its project portfolio which demands
specific analysis.
5-CONCLUSIONS
Considering the decision making methodology that this work proposed to
develop, we can conclude that supportive tools application in this task improves the
decision making process, particularly in oil and gas business management context.
The combination of experts knowledge and tools application provides a
considerable improvement on the understanding level of possible scenarios for the
analysis undertaken by the decision maker. Under this perspective by application of
mentioned before techniques, analysis improvement was attained.
Outcomes for 30% tax rate showed that the Dry Completion Project economic
yields are better than that of Wet Completion Project ones as long as the former
project higher production overcomes the higher CAPEX demanded by the Wet Completion
one besides its very positive outcome contribution, considering that OPEX variable
influence was found to be irrelevant for this comparison.
Otherwise, as verified in the Sensitivity Analysis under 60% tax rate the Wet
Completion Project boasts better cash flow indicators than that of Dry Completion
one because former technique outcomes are less sensitive to higher tax rates which
have a more negative impact on the lower NPV determined to Wet Completion Project
cash flow.
For any tax rate, the Dry Completion Scenario "B" Project outcomes are better
than that presented by the Dry Completion Scenario "A" one as long as the technical
configuration of injection wells connected to FPSO, which occurs in former
alternative, reduces directional drilling cost and also Mini-TLP size. Therefore,
Scenario "B" lowest CAPEX contributes more positively to a better outcome than that
one from Scenario "A".
Thus we can say after those alternative technological scenarios comparing that
introducing Risk to the model through relevant variables values mean dispersion, it
was not enough to change deterministic outcomes.
6-BIBLIOGRAPHY
COSTA, Ana Paula A. Quantificação do Impacto de Incertezas e Análise de Risco no
Desenvolvimento de Campos de Petróleo. 2003. D.Sc. thesis. Faculdade de Engenharia
Mecânica. Universidade Estadual de Campinas.
DALLOLIO, Valério Machado. Análise de Viabilidade Econômica de Projetos. 2006.
Paperback of MBA in Oil and Gas Management course. Capital Humano – Fundação Getúlio
Vargas. Niterói.
HOBOKEN, New Jersey/2001. Ed. John & Sons Inc.
JACINTO, Carlos Magno Couto. Workshop on Reliability and Risk Analysis in Well
Technology Enginering. PETROBRAS / CENPES / PDP / TEP. Rio de Janeiro.
21
MIAN, M.A. Project Economics and Decision Analysis – Volume II: Probabilistic
Models. Tulsa, Oklahoma: PennWell, 2002.
MOCH, Stephen J.; KUNEUTHER, Howard C. Wharton on Making Decisions: Stephen J. Moch,
Howard C. Kunreuther. The Wharton School with Robert E. Hunther.
PALISADE® Corporation. Guide to using @RISK. Risk Analysis and Simulation Add-In for
Microsoft® Excel. Version 4.5. 2002. Newfield, New York.
RIGLOGIX. Weekly Offshore Rig Review: Day Rate Driver. Houston, Texas. 15/11/2007.
Disponível em www.rigzone.com.
SAMANEZ, Carlos Patrício. Matemática Financeira. 3ª ed., São Paulo: Pearson-Prentice
Hall, 2005.
SENE, Eustáquio de; MOREIRA, João Carlos. Espaço Geográfico e Globalização. Ed.
Scipione, 1997.
STEAGALL, Daniel Escobar. Análise de Risco nas Previsões de Produção com Simulação
Numérica de Fluxo – Exemplo de um Campo na Fase de Delimitação. 2001. M.Sc. thesis.
Faculdade de Engenharia Mecânica. Universidade Estadual de Campinas.
ABOUT THE AUTHORS:
Bastos, Gláucio A. has MBA title from Rio de Janeiro Fundação Getúlio Vargas (FGV)
where has just finished an Oil and Gas Management Course, and a Chemical Engineering
degree from Rio de Janeiro Federal University (UFRJ) and a post-graduate diploma
from UFRJ’s Coordination of Engineering Post-Graduation Programs (COPPE/UFRJ). He is
a former PETROBRAS’ trader.
Jacinto, Carlos Magno C. is an Electrotechnical from CEFET - Campos, Graduate in
Economics from Universidade Federal Fluminense, Master in Production Engineering in
the area of Quantitative Methods, Fluminense Federal University and PhD in Civil
Engineering, in the area of Computer Systems for the Coordination of Postgraduate
Programs Engineering ( COPPE ), Federal University of Rio de Janeiro. Member of the
SRA - Society of Risk Analysis and Society of Petroleum Engineers SPE. He is
currently Professor of Petrobras University School of Science and Technology
Exploration and production coordinator of the research group in Reliability
Engineering and Risk Analysis in Engineering from Wells CENPES - Centre for Research
and Development of Petrobras. Acts as a collaborator / researcher of the research
group CEERMA - Centre for Studies and Essays in Risk and Environmental Modeling UFPe
and research group ARCADE - Risk Analysis , Reliability and Decision Support UFF.
Has experience in Modeling, Simulation and Optimization Systems, working mainly in
Risk Analysis and Reliability Engineering in the Area of Oil and Gas.
Torres S.Jr., Flodoaldo has MBA title from Rio de Janeiro Fundação Getúlio Vargas
(FGV) where has just finished an Oil and Gas Management Course.