Westward Ounalashka Final Report R1

10
Westward Seafood’s/Ounalashka Corporation Wind Data Assessment Report Final Report August 1, 2009-Unalaska, Alaska Tower 1 SW Ridge Site-erected September 13, 2006 (data base changed September 16 and September 21, 2006)*. Tower 1 was lowered and rewired in July 2008. Site Description South West Corner –Pyramid Valley Ridge Latitude/Longitude 53 50.0 North 166 31.0 West Site Elevation 250 Feet Load Logger and Tower Second Wind Load logger- 100 Foot NRG Tower

Transcript of Westward Ounalashka Final Report R1

Page 1: Westward Ounalashka Final Report R1

Westward Seafood’s/Ounalashka Corporation Wind Data Assessment Report

Final Report

August 1, 2009-Unalaska, Alaska

Tower 1 SW Ridge Site-erected September 13, 2006 (data base changed September 16 and September 21, 2006)*. Tower 1 was lowered and rewired in July 2008.

Site Description South West Corner –Pyramid Valley RidgeLatitude/Longitude 53 50.0 North 166 31.0 WestSite Elevation 250 FeetLoad Logger and Tower Second Wind Load logger- 100 Foot NRG

Tower

Page 2: Westward Ounalashka Final Report R1

DATA SYN0PIS

There are two NRG 30 meter metrological towers installed. One tower is on Westward property (T1) and one on the adjoining property of the Ounalashka Corporation (T2). At each site there is installed a 100’ (30 meters) guyed tower with three wind anemometers, wind vane and temperature devices collecting data 24 hours. The wind speed anemometer at 100’ C1 has backup recording equipment at 100’ C2 and there is a third anemometer installed at 66’ (20 meters) to evaluate wind speed and potential wind shear. The wind vane is installed at the elevation of 80’. The data is being collected into a data base logger providedby Second Wind Software. The data is being collected on an average interval of ten minutes. The temperature gauge on Tower 1 was destroyed in a wind storm last winter (February 2008) and not replaced. The daily temperature data is available on Tower 2.

Each site has solar panel charger connected to a 12 volt battery and a backup 9.3 volt alkaline battery. The wind information is recorded every 10 minutes and stored into flash memory on site and is being down loaded weekly to a laptop computer. The flash memory has data capacity of three plus years.

The Second Wind Software provides wind speed and direction for any period or time. The time being used is Greenwich Mean Time GMT (-9 hrs) or Alaska Standard Time. The data isbeing collected and reported in increments of 10 minute average time. For the purpose of this report data will be collected and reported on a monthly basis and added monthly to the year-to-date data base. The contract provides for a data collection period of 36 months for Tower 1---Tower 2 was relocated to the ridge South-East of Tower 1. Tower 2 will have two different data bases from the different locations.

The Second Wind Software also provides general information on power production capability at each site, average speed, daily hourly wind availability (Diurnal Information) and wind direction, temperature, daily, weekly and YTD energy information on a sample generator or on specific generating equipment. Please note any wind turbine manufactures power curve information can be added to the software for any generator type or size. The present energy report is utilizing the TMA 250 generator (250 Kw) power curve information provided by the manufacturer and a comparative 250 Kw propeller type (NED) generator. This generator comparison utilizes only data from Tower 1 located on Westward property erected in September 2006. Wind availability is also being collected and analyzed from Tower 2 and compared to wind availability from Tower 1 reinstalled in July 2008.

The 30 meter met towers and data loggers have been furnished by the Alaska Energy Authority under their wind energy assessment program. Information from the assessment report is public information and can be obtained from the consultant or the Alaska Energy Authority.

Page 3: Westward Ounalashka Final Report R1

Ounalashka Corporation Tower 2 Site

Tower 2 Pyramid Lake Site-Erected July 2008

Site Description Old military lake reservoir Pyramid ValleyLatitude/Longitude 53 59’9 North 166 33’44 WestSite Elevation 350 FeetLoad Logger and Tower Second Wind Load logger- 100 Foot NRG

Tower

A partnership between Ounalashka Corporation and Westward Seafood’s was developed to share wind information on adjoining land. The current location of Tower 2 is near the old military lake reservoir on the ridge above OSI and Westward. The site has ready access from an old military road to the lake and is located on land owned by the Ounalashka Corporation.

Wind Classes

Please note the following definition of wind classes attached to this report by the American Wind Association. The article by the American Wind Association on the “Basic Principles of

Wind” outlines the different classes of wind for power production.

Basic Principles of Wind Resource Evaluation

Page 4: Westward Ounalashka Final Report R1

Wind resource evaluation is a critical element in projecting turbine performance at a given site. The energy available in a wind stream is proportional to the cube of its speed, which means that

doubling the wind speed increases the available energy by a factor of eight. Furthermore, the wind resource itself is seldom a steady, consistent flow. It varies with the time of day, season,

height above ground, and type of terrain. Proper siting in windy locations, away from large obstructions, enhances a wind turbine's performance.

In general, annual average wind speeds of 5 meters per second (11 miles per hour) are required for grid-connected applications. Annual average wind speeds of 3 to 4 m/s (7-9 mph) may be adequate for non-connected electrical and mechanical applications such as battery charging and

water pumping. Wind resources exceeding this speed are available in many parts of the world.Wind Power Density is a useful way to evaluate the wind resource available at a potential site. The wind power density, measured in watts per square meter, indicates how much energy is

available at the site for conversion by a wind turbine. Classes of wind power density for two standard wind measurement heights are listed in the table below. Wind speed generally increases

with height above ground.Classes of Wind Power Density at 10 m and 50 m(a)

.

10 m (33 ft)

50 m (164 ft)

Wind

Power

Class

Wind

Power

Density

(W/m2 )

Speed (b)

m/s (mph)

Wind

Power

Density

(W/m2 )

Speed (b)

m/s (mph)

1

<100

<4.4 (9.8)

<200

<5.6 (12.5)

2

100 - 150

4.4 (9.8)/5.1 (11.5)

200 - 300

5.6 (12.5)/6.4 (14.3)

3

Page 5: Westward Ounalashka Final Report R1

150 - 200

5.1 (11.5)/5.6 (12.5)

300 - 400

6.4 (14.3)/7.0 (15.7)

4

200 - 250

5.6 (12.5)/6.0 (13.4)

400 - 500

7.0 (15.7)/7.5 (16.8)

5

250 - 300

6.0 (13.4)/6.4 (14.3)

500 - 600

7.5 (16.8)/8.0 (17.9)

6

300 - 400

6.4 (14.3)/7.0 (15.7)

600 - 800

8.0 (17.9)/8.8 (19.7)

7

>400

>7.0 (15.7)

>800

>8.8 (19.7)

(a) Vertical extrapolation of wind speed based on the 1/7 power law

(b) Mean wind speed is based on the Rayleigh speed distribution of equivalent wind power density. Wind speed is for standard sea-level conditions. To maintain the same power density, speed increases 3%/1000 m (5%/5000 ft) of elevation.

(from the Battelle Wind Energy Resource Atlas)

In general, sites with a Wind Power Class rating of 4 or higher are now preferred for large scale wind plants. Research conducted by industry and the U.S. government

is expanding the applications of grid- connected wind technology to areas with more moderate wind speeds.

Page 6: Westward Ounalashka Final Report R1

Wind data for the NRG Towers is being collected at 20 meters (66’) and 30 meters (100’).

© 1998 by the American Wind Energy Association.

May be freely distributed provided this notice is included.

All other rights reserved.

June 2009 Assessment Report

In July 2008 Tower 1 was lowered and the wind anemometers and weather vane were rewired. The data logger was not operating and was returned to Second

Wind for evaluation. It was determined that the wet cell battery had failed. The data logger was reinstalled at the end of July with a new battery . In September

the data logger on T1 encountered additional voltage issues and the battery was exchanged with the T2 battery. The issue seems to be resolved but will require

constant monitoring. On June 24, 2009 the T1 system shut down with a continuing voltage issue. No attempt is being made to repair the system with the

termination of the study by Westward Seafood on May 31, 2009.

The June, July and August 2007 monthly wind was at the lowest velocity when compared to the previous months of the study. Given the historical wind data,

June and July are the normal months with the lowest wind velocity and average wind strength. Information from Tower 2 in July 2008 and from Tower 1 and

Tower 2 in August supports the lower summer wind velocities. It is interesting to note on the August 2008 “Diurnal Graphs” that during the peak evening hours

of 6:00PM to 9:00PM there still was economic wind speeds (12 MPH) for energy production.

In September 2008 the lower wind velocities continued when compared to the prior years. The wind capacity factor was 16% for September 2008 and 30% for

September 2007. In mid-October the data logger failed on Tower 2 and was returned to Second Wind for repairs. The data logger for Tower 2 was reinstalled at

the end of November 2008.

Vertical Axis Generation comparison to Horizontal Axis Generation

Westward Seafood’s has elected to consider a vertical axis generator developed by TMA in Wyoming as an option. The consultant received the power curve

information from TMA on their 250Kw vertical axis generator during the month of July 2007. The consultant has incorporated the TMA power curve information i

nto each of the monthly study periods. The consultant has selected a NED 250 Kw propeller (horizontal axis) type generator for comparative analysis . The

NED wind turbine power curve was included with the Second Wind Software. Any manufactures wind turbine power curve data can be added to the software for

calculating the energy production from the respective generating unit.

In an e-mail received from TMA the following comments have been received.

The following information is from Scott Taylor of TMA, Inc on July 27, 2007 : 

“My thoughts regarding the differences in the capacity factors of the TMA turbine and a similarly rated prop turbine are as follows: 

The referenced prop turbine has a rotor swept area = 710 m2 , while the referenced TMA turbine has a rotor swept area = 285 m2 .  The prop has a 2.5X larger rotor swept area, therefore having

the ability to capture more energy from the wind.  Above 20 mph, the TMA wind turbine is more efficient and is converting more kW per unit of rotor swept area, but has trouble overcoming the

large difference in rotor swept area.  The formula for energy conversion of a turbine is:

Power = ½ x air density x rotor swept area x wind speed3 x turbine efficiency

The rotor swept area has a linear affect on the power conversion.  Based on the cube effect of the wind speed, the TMA turbine can make up production in the higher wind speeds where the prop

efficiency drops and shuts down.

The referenced prop power curve shows a cut-out wind speed of 55 mph.  In my experience, I haven’t seen a prop turbine in the 250 kW rated size, or larger for that matter, operate above 45

mph in the type of terrain that we are evaluating.

Although wind speed data is a good indicator of the power production available at a site, there are other factors that really should be considered in the evaluation.

Turbulence Intensity (TI):  In general, it is a quantity that characterizes the intensity of gusts in the airflow.  The CPP engineers have indicated that most prop manufacturers won’t even consider

placing their turbines in locations with turbulence intensities greater than 15%.  Higher TI’s adversely affect the performance of the turbine and can cause excessive loads on the blades which

require shutting down the turbine at wind speeds below the cut-out speed to prevent damage.  This should not be a problem for the TMA design.

Wind Shear :  The local variation of the wind vector in a given direction, i.e. change in wind speed with change in height.  Excessive wind shear can also cause highly fluctuating blade load

conditions on props that may cause them to be shut down prematurely to prevent damage.  It may also affect the aerodynamic performance of the rotor.  This should not be a problem for the

TMA design.

Turbine Availability:  Dick’s numbers are based wind availability and on the turbines being available to operate 100% of the time that the wind is sufficient for production.  I would argue that the

Page 7: Westward Ounalashka Final Report R1

TMA turbine would have a higher turbine availability than a prop based on the robust design of the TMA turbine.  The TMA turbine would require less downtime for maintenance and would

continue to operate in conditions that would require a prop to be shut down to prevent possible damage. 

With the generator technology that we may incorporate into the turbine, the TMA power curve may not have to be “flattened out” above rated wind speeds and may continue up the available

curve until the cut-out wind speed is reached.  This ability will greatly increase the amount of kWh produced by the TMA turbine”. 

The following comparison is the (Tower 1) monthly and Period to Date wind capacity information for power production from both types of generating

units:

NED 250Kw Wind Turbine (Propeller)

Month Capacity* Capacity* Capacity*

1st Year (2006) 2nd Year (2007) 3rd Year (2008)

October 43% 29% 28%

November 49% 39% 33%

December 40% 30% 36%

January 40% 39% 25%

February 34% 30% 41%

March 40% 33% 45%

April 27% N/A 36%

May 27% N/A 14%

June 23% N/A 18%

July 6% N/A -

August 17% 9% -

September 44% 16% -

Period-To-Date

Kwh

31%

667,354

28%

399,588

31%

422,110

TMA 250Kw Vertical Axis Turbine

Month Capacity* Capacity* Capacity*

1st Year (2006) 2nd Year (2007) 3rd Year (2008)

October 27% 9% 16%

November 29% 22% 21%

December 15% 17% 21%

January 25% 21% 13%

February 19% 16% 25%

March 21% 20% 25%

April 13% N/A 20%

May 12% N/A 6%

June 10% N/A 7%

July 3% N/A -

August 8% 4% -

September 26% 7% -

Period-To-Date

Page 8: Westward Ounalashka Final Report R1

Kwh 17%

362,743

15%

215,918

17%

222,418

Wind Capacity*

*The wind capacity information is calculated based on the amount of actual Kwh produced for the period noted (based on the manufactures power curves ) and

compared to the maximum Kwh that could be produced for each period. The wind capacity formula is hours of the period times the generator’s output capacity (

8,760 hrs X 250 Kw) equals (2,190,000 Kwh) maximum YTD energy. The amount of Kwh actually produced (based on the manufactures power curves) during

the YTD period is then divided by the maximum Kwh that could be generated to determine wind capacity. I; E, 667,354 /2,190,000Kwh =s 31% wind capacity f

or the first 12 months of the study period. These Kilowatt-hours produced are based on the wind capacity during the initial twelve month study period. The

above Tower 1 data covers 32 months of the study period.

Average monthly wind capacity for the NED generator at the T1 location is 31% (winds above 7 MPH and below 55 MPH) during th e initial 12 months study

period (Oct 2006-Sept 2007). During the 2008-09 study period wind capacity has averaged 27% for the Ned Generator. This average wind capacity information

is based on the NED 250Kw turbine power curves as utilized by the Second Wind Software.

Average monthly wind capacity for the TMA generator at the T1 location is 17 % (winds above 10 MPH and below 60 MPH) during the first 12 months study perio

d (Oct 2006-Sept 2007) and 15% for the TMA unit during the second year of the study period. This wind capacity information is based on the TMA 250Kw

generator power curve as added to the Second Wind Software. The second year of the study period utilized only eight months of actual data. In the present stud

y period (July 2008-June 2009) wind capacity is averaging 17% for the TMA 250Kw VAT.

I would note there is some wind shear recorded at Tower 1 for the past monitoring periods. Wind shear or wind differential is noted between C1 at 30 meters

and wind velocities at 15 meters for C3. It is interesting to note that Tower 1 and Tower 2 have experienced class 5 to 7 winds during the study period.

Also attached is the period-to-date summary of wind direction for the Tower 2 site since July 2008. During the first 12 month study period (Oct 2006-Sept 2007) T

ower 1 wind was from the North in general 48% of the time. The most prevalent wind direction was from the due North at 23% of the period hours. During the

current 12 month study the wind was predominately from the South, with South West wind was the most prevalent at 16% of the hours.

One report that is not printed is the hourly wind speed graph that is available in a scroll format for each month or the entire study period. The average speed

data is recorded at 10 minute average increments 24/7.

Available Wind Capacity Comparison between Towers (based on a NED 250 Kw wind Turbine) propeller type

Month Tower 1 Capacity* Energy Tower 2 Capacity* Energy

July 2008 (17%) (29,202 Kwh) 17% 29,202 Kwh

August 9% 15,008 Kwh 9% 15,008 Kwh

September 16% 28,074 Kwh 16% 28,942 Kwh

October 28% 49,749 Kwh (28%) (49,749 Kwh)

November 33% 57,980 Kwh (33%) (57,980 Kwh)

December 36% 63,539 Kwh (36)% (63,539 Kwh)

January 25% 45,505 Kwh 26% 47,455 Kwh

February 41% 68,672 Kwh 40% 67,534 Kwh

March

Page 9: Westward Ounalashka Final Report R1

45% 84,440 Kwh 45% 83,692 Kwh

April 36% 64,047 Kwh 38% 68,549 Kwh

May 14% 24,432 Kwh 12% 22,049 Kwh

June (18%) 32,478 Kwh 18% 32,478 Kwh

Average Wind Capacity for

study period

27% 27%

Average Energy

For study period

563,126 Kwh 566,177 Kwh

*Percentage of the monthly hours that wind is available for power production. July data from Tower 2 was incorporated into the Tower 1 data set and utilized for

report ing purposes (Tower 1 data is mirroring Tower 2). In October, November and December data from Tower 1 is inserted into Tower 2 data set for reporting

purposes. There is very little difference in the actual wind velocity data between towers. Note the actual data from January, February, March, April, May and

June 2009.

Attached are the copies of the June 2009 graphs from Tower 2 and wind direction summaries for the study period. The study to date has indicated economic

wind values from September 2006 through June 2009 in excess of 12 MPH (Class 4) from Tower 1. The new Tower 2 location is mostly a mirror image of data

being collected from Tower 1. Please note the data from Tower 1 and Tower 2 in the above graph

The consultant would like to note the two 30 Meter towers and all equipment for the wind assessment study has been supplied by the Alaska Energy Authority

under their wind program. The consultant is very appreciative of the support and recommendations of the AEA staff during the wind assessment study period.

Data can be exported in a raw format in an “Excel” spreadsheet from the data base collected over the study periods.

The consultant Richard G. Peck can be reached by e-mail: [email protected] or phone at 907.395.0333 or cell phone 907.741.2131 . The information from

the study can be obtained from the consultant or the Alaska Energy Authority.

Final Wind Assessment Report

Westward Seafood’s—Ounalashka Corporation

August 1, 2009

The (Westward Seafood’s-Ounalashka Corporation) wind assessment study for Pyramid Valley was concluded on June 30, 2009 . The joint (Westward-OC) wind assessment w

as for a period of one year and consisted of two NRG 30 meter metrological towers erected on their adjoining Pyramid Valley lands.

The study area in Pyramid Valley had

excellent access on a ridge that ran in a North-Northwest to an East-Southeast direction. Tower 1 was located at an elevation of 250’ at the Latitude 53 50.0 North and L

ongitu

de 166 3.0 West. Tower 2 was re-located at elevation of 350’ at the Latitude 53 59’9 North and L ongitude 66 33’44 West on “OC” land.

The towers and the associated

equipment were provided by the Alaska Energy Authority under their wind tower loan program. The data loggers were manufactured by Second Wind, Inc.

The data was

collated and analyzed utilizing Second Winds’ “Nomad Software”. The thirty-three month data from Tower 1 and twelve month data from Tower 2

has been also collected in its

raw format and is available in “Excel” spreadsheets.

The initial Westward wind assessment study started on October 2006. Tower 2 was initially installed at a lower elevation on Westward land and then relocated to Ounalashka

Corporation land in July 2008. Tower 2 at its initial location had winds approximate 30% less capacity when compared to Tower 1 during the first two years of the study. The

To

wer 2 wind speed at lower Westward elevation location ha s limited economic value.

The three year long Westward wind assessment study indicates that the monthly wind capacity has varied form a high of 49% in the winter and a low of 9% during the

summer months. The average yearly wind capacity during the study period was 30% at the Westward Tower 1 site. The average 30% wind capacity data

at the Tower 1

location is based on wind speeds that are above 7 MPH and below 55 MPH.

Tower 1 and Tower 2 wind speeds and direction are a virtual mirror imagine of each other during

the past year’s joint study.

The wind power class has averaged about Class 4 (5.6 to 6.0 M/S) or 12 MPH for the entire thirty-three month study period according to the “American Wind Energy

Page 10: Westward Ounalashka Final Report R1

Association” classification system. June, July and August are the months with the lowest average wind capacity of about 18% during the 33 month study period .

The nine

months of October through May often experience Class 5-7 winds, wind speeds that average in excess of 14 mph or 6.2 M/S. Note Chart

1-average wind speed for the

past thirty –three months for Westwards Tower 1 location.

Winds in Pyramid Valley have been strongly directional from the North-23% in Year one, 15% in Year two and 14% in the third year. The Pyramid Valley wind flow was not alw

ays laminar and wind shear was experienced

on several occasions. In depth wind shear information can be obtained by analyzing wind data form the C1-C2 anemometer (30

meters) and comparing it to the wind speeds recorded from the C-3 anemometer located at (15 meters). There were minimal

icing conditions experienced during the study

periods due to the low elevations of the Towers at an approximate height of about 300’ MSL. Note Chart 2-wind rose major wind directions for the Tower 1-Averaged

Nort

h 16.5% of the time for the thirty-three month study period.

The maximum wind gust speed recorded during the study period was 98 MPH. In contacting the local weather bureau at the Dutch Harbor Airport (PADU) their records indicate

a maximum recorded wind gust of 98 Knots or 126 MPH recorded in 1995.