Western Underground - Hv and Ehv Cables-cme
-
Upload
hisham-ali -
Category
Documents
-
view
227 -
download
1
Transcript of Western Underground - Hv and Ehv Cables-cme
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
1/38
Type Testing and Pre-Qualification Testing
of a 230 kV EHV Cable System
WesternUnderground
September27,
2012
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
2/38
TAT and PQT of 230 kV System(Re: IEC, AEIC and ICEA)
Company Introduction and CapabilitiesPlans for 230 kV System
Certification and Reports
Range of Approval
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
3/38
Introduction to XIGNUX
LOW,MEDIUM&HIGH
VOLTAGECABLES
LOW,MEDIUM&HIGH
VOLTAGECABLES
CMEWIRE&CABLE
CMSA
MAGNEKON
ELETEC
MULTIPAK
CDN
SAOMARCO
TRANFORMERSTRANFORMERS
PROLECGE
INDOTECH
GEPROLEC
PROCESSING
INDUSTRIES
PROCESSING
INDUSTRIES
CARNESFRIAS
BOTANAS
DESIGN
CONSTRUCTION
DESIGN
CONSTRUCTION
Infrastructures
VOLTRAK
PROSEL
SCHRADER
IOESA
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
4/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
5/38
HV & EHV Technological Advances inViakables History
1976. The first 69 kV high voltage cable with EPR insulation in Latin-American.
1986. 115 kV XLPE HV cable.
1998. 138 kV XLPE HV cable.
2005. 138 kV XLPE HV cable IEC 60840 Qualification (CTL Lab).
2011. 230 kV XLPE EHV system IEC 62067 (NEETRAC).
2011-2012. 138 kV XLPE HV Smooth Aluminum Sheath Cable and Copper Wires
Shield and Aluminum Foil Laminated Cable, IEC 60840, AEIC CS9 & ICEA S-108-
720 Qualification (CTL Lab).
2011-2012. 230 kV XLPE EHV system AEIC/ICEA (NEETRAC).
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
6/38
HV Cables Experience
MV Extruded (XLPE / EPR) and PILC cable
manufacturer for more than 45 years.
HV XLPE Extruded 69 kV manufacturer for
over 30 years.
HV XLPE Extruded115 /138 kV
manufacturer for over 25 years.
More than 1.1 million meters for HV & EHV
Products.
Largest order: 190 km Cu 800 mm2 115 kV.
Average order: 10 km.
69 -138 kV history highlights in recent years:
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
7/38
HV & EHV Technical Capabilities
Dry Cured Extrusion.
True Triple Extrusion
(Vertical state of the art process).
For HV & EHV:
69 kV 138 kV
250 2000 mm2
230 kV
380 2000 mm2
Eccentricity lower than 5%.
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
8/38
Introduction to CME
CABLESCABLES
DISTRIBUTIONBUILDINGWIRE
ENERGYPOWER&CONTROL
CABLESCABLES
DistributionDivision
Constructionwire
Residential
Commercial
Industrial
Energy
DivisionUtilityT&D
Substations,PowerGeneration
Industrial
OEM&Specialty
CABLESCABLES
MAGNEKONMAGNETWIRE
MagnetWire
MotorRepair
TransformerWinding
OEM
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
9/38
Introduction to CME
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
10/38
Plans for 230 kV System
Critical Elements
MarketStudy Tounderstand demandforcablesystems&
decideonconstruction.
Accessories Inhouseorworkwith amanufactureof
accessories.Identifyaccessoriesfortesting.
Testing Understandrequirementsforsystem testing
ExternalLaborInhouse?
SelectWitnessingEngineer/sExecution Preparation,Testing,Reporting,etc.
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
11/38
230 kV Cable Construction
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
12/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
13/38
ABB Kabeldon SF6 Cable Termination and Joints
APEGA245kVGasInsulatedSwitchgear(GIS)Terminations
PremoldedEPDMStressConeforgeometricstresscontrol
Weight:270Kg Length:1680mm,Diameter:450mm
Maximumstressintheaccessory:3.7kV/mm
ABBKabeldon
245kVJXM and JSM
PremoldedOnePieceEPDMJoints
Crossbondedandstraight
Length:2690mm,Diameter:330mm
Maximumstressintheaccessory:5kV/mm
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
14/38
Testing Requirements for HV & EHV Power Cable
Systems 46< kV 345 (Ref: AEIC CS9)
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
15/38
Testing Requirements for HV & EHV Power Cable
Systems 150< kV 500 (Ref: IEC 62067)
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
16/38
Testing Requirements for HV & EHV Power Cables
46< kV 345 (Ref: ICEA S-108-720)
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
17/38
Protocols for 230 kV System
IEC 62067 (System)
ICEA S-108-720 (Cable)
Combined (IEC and ICEA) Test Program (Ref: NEETRAC)
Sequential IEC, ICEA Test Program to Satisfy both IEC and
AEIC Requirements
Compliance with AEIC CS9 through Compliance with:
IEC 62067 (System)+ICEA S-108-720 (System, not cable only)+
IEC 62067 Annex D (Test for outer protection of buried joint)
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
18/38
Testing Capabilities (EHV)
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
19/38
Witnessing EngineersCFEComisin FederaldeElectrcidad
LaboratoryEquipmentandMaterialsTesting(LAPEM)isanorganizationoftheFederalElectricityCommissionwhichaimstomeettheneedsofnationalandinternationalpowersector,providingspecializedengineeringstudies,laboratoryandfieldequipmentandmaterials,andasqualitymanagementandsupplysystems
inareliable,timelyandeffective,basedonahighdegreeofspecializationofitsstaff,withaserviceorientedattitude.
NEETRACisaselfsupporting,membershipbasedcenterwithintheSchoolofElectricalandComputerEngineeringat
Georgia
Tech.
Our
goal
is
to
helptheelectricutilityindustrysolvetheeverydayproblemsassociatedwiththecomplextaskoftransmitting
anddistributingelectricenergyreliabilityandefficiently.
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
20/38
IEC 62067 Type Test set up for 230 kVSET
UP
LOOP
IEC
62067
20
DAYS
@
254
kV
20HEATINGCYCLES@95C
IMPULSETEST
10
@
1050
kV
ANNEXD
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
21/38
IEC 62067 Type Test Results
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
22/38
AEIC CS9 & ICEA S-180-720 Type Test set up for 230 kV
SETUP
LOOP
20
DAYS
@
266
kV
20HEATING
CYCLES
@
105C
IMPULSETEST
10
@
1050
kV
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
23/38
AEIC CS9 & ICEA S-108-720 Type Test Results
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
24/38
IEC 62067 Pre-Qualification set up
JOINT:STRAIGHT
TERMINATION:Right Porcelain,Left
Composite.Middle
termination
is
thevoltagefeed(siphon)fromthe
laboratory
SF6TERMINATIONS
JOINT:
CROSS
BONDED
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
25/38
IEC 62067 Pre-Qualification set up
OUTDOORTERMINATIONS 180HEATINGCYCLES@95C&365DAYS@216kV
SF6TERMINATIONS IMPULSE
TEST
10
@
1050
kV
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
26/38
IEC 62067 Pre-Qualification Results
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
27/38
AEIC CS9 Pre-Qualification for 230 kV
Additional 90HEATINGCYCLESafterIECPQT@
105Cand226kV
IMPULSETEST
10
@
1050
kV
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
28/38
AEIC CS9 Pre-Qualification Results
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
29/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
30/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
31/38
Sequence of Load Cycles Applied to the 230kV XLPE Pre Qualification Cable System
It is particularly noteworthy that the compliance with AEIC CS9-06 was achieved
on a cable that had previously completed the requirements of IEC 62067 2006
Section 13 cable system test (reported separately). Thus it had completed a
sequence of load cycles as shown in Table 1. Furthermore the 230 kV XLPE Pre
Qualification Cable System has completed two sequences of impulse tests atelevated temperatures (10 positive / 10 negative).
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
32/38
Test of Outer Protection for Buried Joint IEC 62067 ANNEX D
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
33/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
34/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
35/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
36/38
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
37/38
1. Cable system voltages 230 kV
2. Conductor sizes 2000 mm2
3. Cable systems with emergency operating temperatures 105 C.
4. Cable systems with the same or similar construction as that tested:
a) CablesmanufacturedatConductoresMonterrey Plant,usingaVerticalContinuousVulcanization(VCV)lineandinsulatingandsemiconductingmaterialsDowHFDA0801BK/DowHFDB4201SC/DowHFDK0587BKS
b) TerminationsprovidedbyABBKabeldonofSweden(APECB245kVOutdoorTerminations(Composite&Porcelain))
c) TerminationsprovidedbyABBKabeldonofSweden(APEGA245kVOutdoorTerminations(GIS))
d) 245kVJSAMPremoldedOnePieceEPDMSlipOnStraightJoint type14,providedbyABBKabeldonofSweden
e) 245kVJXBMPremoldedOnePieceEPDMSlipOnCrossBondedJoint type14,providedbyABBKabeldonof
Sweden
5. Cable systems with the same or lower electrical stresses as that tested:
a) Cableswithvoltagestressesonthecableattheconductorscreen 7.58kV/mmandattheinsulationscreen 4.37
kV/mm.
b) Terminationswithcompositeandporcelainbodiesforvoltages 230kVandmaximumelectricalstresseswithinthe
insulation 3.7kV/mm(detaileddocumentationonfilewithConductoresMonterrey).
c) GISTerminationsforvoltages 230kVandmaximumelectricalstresseswithintheinsulation 3.7kV/mm(detailed
documentationonfilewithConductoresMonterrey).
d) PremoldedOnePieceEPDMSlipOnStraightJointforvoltages 230kVandmaximumelectricalstresseswithinthe
jointinsulation 5kV/mm(detaileddocumentationonfilewithConductoresMonterrey).
e) PremoldedOnePieceEPDMSlipOnCrossBondedJointforvoltages 230kVandmaximumelectricalstresses
withinthejointinsulation 5kV/mm(detaileddocumentationonfilewithConductoresMonterrey).
Range of Approval for 230 kV System
AEIC CS9 06
-
8/13/2019 Western Underground - Hv and Ehv Cables-cme
38/38
Thank You!