Well Intervention Vessels Used in the G.O.M. Macondo Incident Response
Mark de CastroMark de CastroHelix - Well Ops
June 2011
Helix Vessels at Macondo
Helix Q4000
Helix Express
Helix Producer I
2
Q4000 Macondo Response
Static KillDynamic Kill
With Evergreen Burners Full Stack recovery • Arrived in staging area within3 days of call‐off
• Multi functional and ease of adaptability between operating modes
• Containment
• Dynamic KillDynamic Kill
• Flaring
• Static Kill
• Recovery
• Control platform for
3
Control platform for LMRP/BOP yellow pod
Q4000 Intervention MODU
• DP3 MODU
• US Flag – ABS classed
• DP3 MODU
• US Flag – ABS classed
• 600 Te. Multi Purpose Tower (Derrick)
• 360 Te. / 160 Te. Deepwater Cranes
• 600 Te. Multi Purpose Tower (Derrick)
• 360 Te. / 160 Te. Deepwater Cranes
• 2 x 150 HP ROV’s
• 3,000 barrel fluid handling system
O d k til t
• 2 x 150 HP ROV’s
• 3,000 barrel fluid handling system
O d k til t• Open deck versatile – not your typical rig
• Large accomodations
• 11.9 x 6.4 m moonpool
• Open deck versatile – not your typical rig
• Large accomodations
• 11.9 x 6.4 m moonpoolpp
4
Intervention Semi Sub (Cat.B) vs Drill Rig (Cat.C)
Q400014 000 GRT
Development Driller
38 000 GRT38 000 GRT
5
SIMOPS subsea
6
DP 2 FPS Helix Producer 1
• Capacity:• 45,000 BOPD
• 60,000 BLPD
• 80 MMCFD (can be expanded)
• Lloyds classed and DOI and USGC approved FPU with quick disconnectable side mounted
7
turret with swivels
HP1 Macondo Deployment
Called to action on June 12, 2010. Departed Phoenix / Typhoon location in GC237 within 2 days and was operational in MC252 30 days later.
Permanent modifications to the HP1 will shorten response time from 30 to 10 days.Permanent modifications to the HP1 will shorten response time from 30 to 10 days.
Our goals• Call‐off on Day 1• Response time of 10 days from call‐off to• Response time of 10 days from call‐off to
in‐service
HP1 Modifications for Macondo• Fabrication of new buoy• Fabrication of new buoy• Fabrication of water curtain system to
cool the flare boom• Fabrication of off‐loading systems
Future Response• HP1 is GOM based and is ideally suited
for hydrocarbon containment• Key is to keep the vessel in the GOM• Key is to keep the vessel in the GOM
and make permanent modifications to meet response time goal
270 te. Buoy designed and built in two weeks..
8
MSV DP2 Express
Used to install Macondo Containment Subsea Infrastructure
• 520 foot (158m) long DP2 reel lay vessel
• 450 Te. deck crane; 250 Te., A&R cable and 150 Te. AHC deepwater crane capable of reaching 10,000 ft.
• Reels hold 3,000 tons of rigid steel pipe up to 14 inches in diameter
• Open deck allows the vessel to carry multiple reels of flexible flowlines
9
• Carries up to three WROVs
Helix Fast Response System (HFRS)Target in‐service date of 10 days from call‐outTarget in service date of 10 days from call out
10
Deepwater Containment System – Phase 2
Target in‐service date of 17 days from call‐out
11
Additional production capacity and system redundancies will become available as the system evolves.
Macondo by the Numbers
80 Barrels of kill fluid pumped every minute through four vessels daisy chained to the Q4000 during the Top Kill operation
285,000 – Man hours Helix ESG and BP staff onboard the Q4000 during the blowout responseg p
32,000 – Barrels of fluid used during the Static Killand cementing operationand cementing operation
135 – Days Q4000 worked at response siteHydrates in the containment dome
1,000,000 lbs. Deepwater Horizon’s BOP lifted from the sea-floor to the Q4000’s deck
280,000 bbls. Oil burned on Q4000 over 33 days operation
12
Discussion points
• Ideal response resources are locally based, flexible, self supporting and able to respond quickly in event of a subsea spillp q y p
• Industry participation is necessary to modify and prepare assets for specialized responsep p
• Containment response will expand and require industry standardization and research/developmentstandardization and research/development
• A pragmatic approach must be taken as to how much containment capacity and redundancy is actually neededcapacity and redundancy is actually needed
• The perfect solution for every conceivable scenario cannot be prepared Focus should be on flexible systems with quick ability toprepared. Focus should be on flexible systems with quick ability to adapt and respond.
13
Current Readiness (GOM)
• Capping Wells at Water Depths up to 5,600 fsw and
10,000 psi
• Capture and flow back operations to Q4000 Up to
12,000 bbl/D & 65 MMSCFD
• Estimated Deployment Time Based On Macondo is 9
days
14
Expected Readiness (GOM) – Q3 2011
• Capping Wells at Water Depths up to 8,000 fsw and 10,000 psi, p
• Capture and flow back operations to Q4000 and HP1 UpCapture and flow back operations to Q4000 and HP1 Up to 55,000 bbl/D & 95 MMSCFD
• Estimated Deployment Time Based On Macondo is 10 days