Welcome to the Online Consultation

54
Preliminary Construction Planning Welcome to the Online Consultation Preliminary Construction & Traffic Planning Intro to Shop Local/Shop Eglinton Initiative Please review the presentation and complete the survey by July 11, 2012.

Transcript of Welcome to the Online Consultation

Page 1: Welcome to the Online Consultation

Preliminary Construction Planning1

Welcome to the Online ConsultationPreliminary Construction & Traffic PlanningIntro to Shop Local/Shop Eglinton Initiative Please review the presentation and complete the survey by July 11, 2012.

Page 2: Welcome to the Online Consultation

Preliminary Construction Planning2

Update• The first Tunnel Contract (Keele St to Yonge St) will be awarded

this summer

• Detailed traffic plans will be developed after the contract is awarded

• Additional public meetings in Fall 2012 to discuss detailed construction plans for the first tunnelling contract

• The earliest utility work could begin on Eglinton in the vicinity of Allen Road is late 2012 (west side of Allen southbound)

Page 3: Welcome to the Online Consultation

Preliminary Construction Planning3

Tunnel Construction Principles • Package contracts to coordinate all work under same umbrella

(utilities, city, transit)

• Maintain a minimum of one lane eastbound and westbound on Eglinton in construction zones

• Access to buildings from Eglinton remains open

• Only propose road closures if required for safety reasons or to provide exceptional time savings and reduction to long term disruption

Page 4: Welcome to the Online Consultation

Preliminary Construction Planning4

The Crosstown – 2012 *Final number and location of stations subject to Provincial review

• 60% faster than current bus routes

• 15 minutes from Keele to Yonge

Page 5: Welcome to the Online Consultation

Preliminary Construction Planning5

Eglinton Bus Ridership • Eglinton 32 & 34 buses carry 68,500 riders every weekday

• Transfers required at Eglinton West and Eglinton Stations (Allen & Yonge)

• Eglinton has amongst the highest ridership of all bus routes

Page 6: Welcome to the Online Consultation

Preliminary Construction Planning6

Eglinton at Bathurst (looking west)

Page 7: Welcome to the Online Consultation

Preliminary Construction Planning7

Eglinton West Station

Page 8: Welcome to the Online Consultation

Preliminary Construction Planning8

Looking east from OakwoodLooking east from Oakwood

Page 9: Welcome to the Online Consultation

Preliminary Construction Planning9

Crosstown Construction Update

• Tunnel preparation work at Black Creek and Eglinton in Keelesdale Park

• Piling rigs are building concrete support walls for the future west tunnel launch shaft

• The west launch shaft will enable tunnelling works in late 2012 towards Allen Road

Page 10: Welcome to the Online Consultation

Preliminary Construction Planning10

West Launch ShaftKeelesdale Park near Black Creek Drive

Launch Shaft• 60m Long• 20m wide• 16m deep

Eglinton Ave

Page 11: Welcome to the Online Consultation

Preliminary Construction Planning11

Tunnel Construction Overview• Relocate utilities at major intersections to maintain services (gas, water,

cable)

• Construct “headwalls” (support walls formed by a series of concrete columns) at east and west ends of each future station location

– 4 - 5 months per station location

– Process called “Jet Grouting” when soil conditions allow - 3 - 4 months

• Concurrently, construct Tunnel launch and extraction shafts. These are large pits where tunnelling machines are first lowered for assembly and then extracted from the ground.

• The tunnel machines are launched from Keelesdale Park (just west of Keele Street) and tunnel eastward through the station “headwalls”

Page 12: Welcome to the Online Consultation

Preliminary Construction Planning12

Tunnel Construction OverviewContinued

• To ensure subway service is maintained throughout construction, tunnelling machines are removed from a pit at the west side of Allen Road on Eglinton and re-launched from a new pit on the east side of Allen Road on Eglinton

• Tunnelling proceeds to Yonge Street, and a second extraction pit is built to remove and re-furbish the machines before they reach Eglinton Station

• Following this tunnelling work, the Crosstown Stations between Keele and Yonge will be constructed. Stations will each take approximately 4 years to construct

Page 13: Welcome to the Online Consultation

Preliminary Construction Planning13

Utilities - Bathurst Intersection

STACKED SANITARY

SEWERS

600mm WATERMAIN

EXISTING STORM SEWEREXISTING SANITARY SEWER

EXISTING COMBINED SEWEREXISTING GASMAINEXISTING BELL/ROGER CONDUITEXISTING TELUS/GT CONDUITEXISTING T.H.E.S./COGECO DUCT BANK

STACKED SANITARY

SEWERS 1125mm STORM

SEWER

BELL/ROGERSCONDUITS (20)

EGLINTON AVENUE WEST

BATH

URST

STR

EET

150mm GASMAIN (ABANDONED)

T.H.E.S. DUCT BANK (12)

TELUS/GT DUCT BANK (18)

300mm COMBINED

SEWER

BELL/ROGERSCONDUITS (2)

300mm GASMAIN (TO BE

ABANDONED)

PEVE

RIL

HIL

L N

OR

TH

EXISTING WATERMAIN

225mm SANITARYSEWER

Page 14: Welcome to the Online Consultation

Preliminary Construction Planning14

Challenge of Underground Utilities

Page 15: Welcome to the Online Consultation

Preliminary Construction Planning15

Tunnel Drive SequenceLaunch Shaft

Extraction Shaft

Leading Tunnel

Mine-Through Headwalls

Excavate Station and Remove Tunnel Liners

Trailing Tunnel

21 3

StationHeadwalls

54 6

Page 16: Welcome to the Online Consultation

Preliminary Construction Planning16

Extraction Shaft Example Spadina Subway Extension - Keele and Finch

KEELE STREET

Page 17: Welcome to the Online Consultation

Preliminary Construction Planning17

Extraction Shaft Example Spadina Subway Extension - Keele and Finch

KEELE STREET

FINCH AVE

Page 18: Welcome to the Online Consultation

Preliminary Construction Planning18

Extraction Shaft Example Spadina Subway Extension - Keele south of Finch

KEELE STREET

Page 19: Welcome to the Online Consultation

Preliminary Construction Planning19

Eglinton and Allen - Existing

Page 20: Welcome to the Online Consultation

Preliminary Construction Planning20

Utility Relocation WorkExact Lane Setup TBD

Page 21: Welcome to the Online Consultation

Preliminary Construction Planning21

Utility Relocation WorkExact Lane Setup TBD

Page 22: Welcome to the Online Consultation

Preliminary Construction Planning22

Utility Relocation WorkExact Lane Setup TBD

Page 23: Welcome to the Online Consultation

Preliminary Construction Planning23

Extract TBM & Re-Launch

Page 24: Welcome to the Online Consultation

Preliminary Construction Planning24

Soil removal for Tunnelling• 1 165 000 cubic metres

of soil to be removed during tunnelling

• Enough to fill the ACC rink higher than the CN Tower

Page 25: Welcome to the Online Consultation

Preliminary Construction Planning25

West Tunnelling – Keele Street to Yonge Street Traffic Management Overview

Page 26: Welcome to the Online Consultation

Preliminary Construction Planning26

Existing Conditions on Eglinton • Rush Hours : 7am to 9am & 4pm to 6pm

• Most sections of Eglinton between Keele and Allen have one lane in each direction for general traffic in rush hours

• Between Allen and Yonge, most sections have two lanes in each direction available for general traffic in rush hours

• In most sections during rush hours, the curb lane is for buses only

• Outside of rush hours, the curb lanes are used for on-street parking, generally leaving one lane per direction for moving traffic

Page 27: Welcome to the Online Consultation

Preliminary Construction Planning27

Existing Conditions Eglinton Avenue Dufferin to Chaplin

• External traffic represents 45% of the auto trips (AM peak)

• 45% of traffic has an origin and destination outside the area & use Eglinton as a traffic corridor

• PM peak period is similar, 42% external, 58% local

Page 28: Welcome to the Online Consultation

Preliminary Construction Planning28

During Tunnel Construction• One lane of traffic available on Eglinton both EB and WB all-day

in active construction zones. Buses and general traffic will share this lane.

• Advance warning signs will be placed in the vicinity of the corridor. Changeable Message Signs and Static Signs.

Page 29: Welcome to the Online Consultation

Preliminary Construction Planning29

Transit Services during Tunnel Construction• Pedestrian and bus access to Eglinton West and Eglinton

Stations will remain open

• No major change to existing bus routes

• Local bus route detours may be required for key construction activities for tunneling

• TTC buses along Eglinton will be monitored and additional vehicles added as needed to respond to changes in traffic conditions

Page 30: Welcome to the Online Consultation

Preliminary Construction Planning30

Parking• Currently, 3 hour paid parking is available on Eglinton Avenue

West outside of weekday rush hours.

• In order to provide space for construction work, some of these spaces will be unavailable

• One-hour parking on some local roads will be extended to 3 hours, only while construction is impacting parking availability on Eglinton Avenue

• Parking on local roads will be enforced to discourage long-term parking and will be closely monitored by Toronto Police Services Parking Enforcement

Page 31: Welcome to the Online Consultation

Preliminary Construction Planning31

Pedestrians/Cyclists• Front door access to Eglinton Avenue buildings maintained

• Minimum 1.5 metre sidewalk widths

• Some temporary closures of sections of sidewalk required. Where necessary, crossings will be available at traffic signals. One side open at all times.

• Bike lanes not currently provided on Eglinton

• During construction, cyclists will continue to share general traffic lanes

• Where space is available, wider lanes provided to accommodate all users

Page 32: Welcome to the Online Consultation

Preliminary Construction Planning33

Jet Grouting

Typical Rig

2–3m Diameter Jet Grout Formed Soilcrete Columns Jet Grouting Process

Page 33: Welcome to the Online Consultation

Preliminary Construction Planning34

Allen Road Area• Tunnelling under Eglinton West Station carries risk to subway

operations

• Detailed Traffic management plans to be developed upon award of tunnel contract and presented at Fall 2012 follow-up meeting

• 2013 – Potential for occasional, off peak (overnight) Southbound Right Turn prohibitions from Allen to Eglinton for utility relocations at Extraction Shaft

• Potential short duration Eastbound to Northbound left turn prohibitions from Eglinton onto Allen Road for decking installation at ramp

Page 34: Welcome to the Online Consultation

Preliminary Construction Planning35

Allen RoadProposed One Year Closure in 2014 to Northbound Access at Eglinton

• Potential closure of northbound access to Allen Road at Eglinton to expedite tunnelling

• Closure projected to reduce construction by approximately one year• Northbound Allen would remain open north of Eglinton • Closure would give contractor enough space for construction staging and

movement of 150 trucks per day directly onto Allen Road - All prohibitions at Allen Road require City Council approval - Anticipated report timing is FALL 2012 Public Works Committee/City

Council

Page 35: Welcome to the Online Consultation

Preliminary Construction Planning36

Tunnel Launch Shaft – Sheppard Subway

Page 36: Welcome to the Online Consultation

Preliminary Construction Planning37

13 Division – Working with Police Temporary Property Requirements

• 5 metre area between sidewalk and 13 Division building

• Utility construction area

• Temporary sidewalk

• Tree removals are unavoidable

• Sign removal/ relocation

• Tiebacks

Page 37: Welcome to the Online Consultation

Preliminary Construction Planning38

Cross Passages – 2014 • Cross passages are used for emergency evacuation of the

tunnels and for access between the tunnels for maintenance

• Constructed by hand mining between the two tunnels

• Area needed on road for pumping equipment to dewater the area where the mining is conducted

• Impact = 2 - 3 months per location

• 1 lane per direction

Page 38: Welcome to the Online Consultation

Preliminary Construction Planning39

Temporary Local Road Closures at Eglinton Avenue Temporary closures at Eglinton intersections with some local streets will

unfortunately be required during different phases of tunnel construction to safely complete work (access always maintained from one direction)

• Yarrow Road (2012-2013 - 7 weeks) • Kane Avenue (2013 - 5 weeks) • Little Boulevard (2013 – 4 days) • Strathearn Road (2013 - 11 Weeks) • Flanders Road (2013 - 11 Weeks) • Peveril Hill North Road (2013 - 9 Weeks) • Chaplin Crescent Southbound Thru & Left (2013 - 9 Weeks) • Latimer Avenue (2013 - 9 Weeks) • Highbourne Road (2014 - 9 Weeks) • Maxwell Avenue (2015 - 17 Weeks)

Page 39: Welcome to the Online Consultation

Preliminary Construction Planning40

Ministry of Transportation (MTO)Highway 401/Allen Road Ramp Improvements

• MTO is rehabilitating 8 structures in the Highway 401 and Allen Road Interchange

• Bridge improvements have been broken into 2 contracts • Contract 1 (Bridges 4 and 24) Contract 2 (Bridges 5, 6, 12, 16 19 22) • Construction for Contract 1 commenced in Spring 2012• Completion for Contract 1: late Fall 2012• Construction schedule for Contract 2 TBD

Page 40: Welcome to the Online Consultation

Preliminary Construction Planning41

Ministry of Transportation (MTO)Highway 401/Allen Road Ramp Improvements

Page 41: Welcome to the Online Consultation

Preliminary Construction Planning42

• Lane reductions on the 401 to Allen Road ramps and bridges

• Periodic overnight ramp/bridge closures

• Advance traffic warning signs will be posted in the area to advise the public of traffic restriction and lane closures

• Construction is planned to take place during daytime hours from Monday to Friday

• Extended working hours (periodic night time work) & weekend work required to complete construction on schedule.

Project information: Mr. Sam Molai, P.Eng., Senior Structural Engineer Ministry of Transportation, Central Region tel: 416-235-5506 e-mail: [email protected]

MTO – Highway 401 /Allen Road Ramp Construction Details

Mr. Larry NG, Project Manager, Design SNC Lavalin tel: 416-252-5315 Ext 2711

Page 42: Welcome to the Online Consultation

Preliminary Construction Planning43

City of Toronto – Long Term PlanningConstruction Details

• The City of Toronto is studying ways to improve Allen Road

• The study will follow a provincially mandated Environmental Assessment process.

• Study investigating current challenges and opportunities in the Allen Road corridor from Eglinton to just south of Transit Road

• Currently, a Terms of Reference (Study Framework/Work Plan) is being developed to guide future work

Page 43: Welcome to the Online Consultation

Preliminary Construction Planning44

Allen Road Environmental Assessment For more information, please contact:

Jason Diceman Tel: 416-392-3787 E-mail: [email protected] Web Site: www.toronto.ca/involved/projects/allenrdstudy

Page 44: Welcome to the Online Consultation

Preliminary Construction Planning45

Station Construction Overview Projected Start – 2015

• After tunneling is completed, station construction begins

Page 45: Welcome to the Online Consultation

Preliminary Construction Planning46

Eglinton Pre-Construction -Existing Right of Way Use

Watermain

Page 46: Welcome to the Online Consultation

Preliminary Construction Planning47

Station Construction Stage 1A Piling - Divert Traffic & Construct Support of Excavation

(Exact Construction Set-Up TBD by Location for all stages)

Watermain

Page 47: Welcome to the Online Consultation

Preliminary Construction Planning48

Station Construction Stage 1B – Construct Centre Piles

Watermain

Page 48: Welcome to the Online Consultation

Preliminary Construction Planning49

Station Construction Stage 2A – Construct Roadway Decking on one Side

Watermain

Page 49: Welcome to the Online Consultation

Preliminary Construction Planning50

Station Construction Stage 2B – Construct opposite side Decking & Support of Excavation

Watermain

Page 50: Welcome to the Online Consultation

Preliminary Construction Planning51

Station ConstructionStage 3 – Construct Station Box under the Roadway Decking

Watermain

Page 51: Welcome to the Online Consultation

Preliminary Construction Planning52

Station ConstructionStation Complete – Restore Roadway, Utilities & Traffic

Watermain

Page 52: Welcome to the Online Consultation

Preliminary Construction Planning53

Next Stepsa) Meetings in advance of construction

(Review and input on traffic and construction staging plans)

b) Construction Liaison Groups Smaller groups (10 local representatives per station with local councillor) give input, questions & concerns directly to construction team

c) Contact Community Liaisons with specific local issues & recommendations for investigation

Page 53: Welcome to the Online Consultation

Preliminary Construction Planning54

The Crosstown Team Please get in touch with usDevin Horne, Franca Di Giovanni, Denise Jayawardene E-mail: [email protected] Online: www.thecrosstown.caTel: 416-338-6310Fax: 416-397-8193TTY: 416-481-2523Visit our West Community Office at 1848 Eglinton Avenue West (at Dufferin)

Community Office Hours — 2012Monday, Wednesday, Friday: 9:00 a.m. – 5:00 p.m. Tuesday & Thursday: by appointment

Page 54: Welcome to the Online Consultation

Preliminary Construction Planning55

Thank You!