Welcome to the Distributed Generation Forum Cardiff 17th October 2013 Fora/2015... · Welcome to...
Transcript of Welcome to the Distributed Generation Forum Cardiff 17th October 2013 Fora/2015... · Welcome to...
Welcome to the Distributed Generation ForumCardiff – 23 September 2015
The Voice of the Networks
Welcome and Introductions
Prof. Graham AultDevelopment DirectorSmarter Grid Solutions
DG Forum Cardiff 2015
The Voice of the Networks
Agenda - AM
DG Forum Cardiff 2015
The Voice of the Networks
10.00 Welcome and IntroductionProf. Graham Ault – Development Director, Smarter Grid Solutions LtdDistribution Network Operators (DNO): Overview Brian Hoy – Head of Market Regulation, Electricity North WestDECC PerspectiveRobert Kinnaird - Future Electricity Networks, DECCOfgem PerspectiveJames Veaney – Head of Distribution Policy, Ofgem
11.00 Coffee Break11.20 DNO Progress Update
Charl Oosthuizen – Finance Director, Western Power DistributionStephen Stewart – Director, SP ManwebDG Customer PerspectivesDr Graham Pannell – Energy Networks, Renewable Energy SystemsNicola Waters - Chief Operations Officer, Primrose SolarPanel Discussion and Audience Q & A
13.00 Lunch and Networking
Agenda - PM
DG Forum Cardiff 2015
The Voice of the Networks
14.00 Statement of Works ProcessRoom – David Morgan RoomFlexible Connection Offers Room – Preseli Room Competition in ConnectionsRoom – Sony RoomDNO Roundtable Room – Japan Room
14.45 Repeat of breakout sessions15.30 Round up16.00 Close
EnergyNetworksAssociationOverview of progress
Name Brian HoyPosition Chair DG-DNO Steering GroupDate 23 September 2015
The Voice of the Networks
6 The Voice of the Networks
What can you expect from today?
Improving service for customers
Explanations of what DNOs
have done
Opportunities to give us feedback
Opportunities for discussion
What best practice looks like
7 The Voice of the Networks
How the approach has developed
DG Fora
Refinement of the
approach
Building on progress and
learning
First ENA led ForaDNOs
reported back on progress
First series of Fora held
by Ofgem
2011
2014
2013
2012
2015
8 The Voice of the Networks
DG-DNO Steering Group
Membership
6 DNOs 9 TAs2 CinC
Best Practice
Compare approaches
Identification of issues
“To discuss and address distributed generation connection issues, share best practice, develop agreed solutions, and communicate progress to all
stakeholders, notably at the annual DG Forum”
9 The Voice of the Networks
Customers
Blueprint for ‘ICE’
Incentive on Connections Engagement
Builds on DG approach
Trial – 2014Incentive - 2015
‘Looking Forward’ ReportEngagement, work plan & key performance
outputs for the forthcoming year
‘Looking Back’ ReportPerformance against ‘Looking Forward’ plan
that the DNO set itself
10 The Voice of the Networks
Areas of focus over the last year
C
Saturated Networks & ‘flexible’ connection offersTransmission interfaces and dependencies
Emergingissues
Contracted Capacity Registers
Slow moving projects
Competition in Connections
Incentive on Connections EngagementDG Fora planning
11 The Voice of the Networks
Despite all those challenges....
Increasing amounts of DG Connected
50% increase last year
Significant increase in EHV connections
Increasing solar installed
0
1,000
2,000
3,000
4,000
2011 2012 2013 2014 2015
MW Connected
TOTAL LV TOTAL HV TOTAL EHV TOTAL 132
12 The Voice of the Networks
Final thoughts
Use the opportunity to engage
&AnswersQuestions
Share learning, challenges and outcomes
Give us feedback to make next year even better
Robert KinnairdFuture Electricity Networks, DECC
DG Forum
Wednesday 23rd September 2015
Responding to the growth of DGThe network challenge
James VeaneyHead of Distribution Policy
23/09/2015
15
Introduction
• We’re seeing a transformation in how energy is generated and used
• This has profound implications for the distribution and transmission networks and how the overall system operates
• Exciting time – new entrants emerging on the energy market can deliver great benefits to consumers
• Uncertainty is fact of life but DNOs have to be active in addressing these issues
16
• 5 years ago, generators had a lengthy list of complaints
• Application process was long winded
• Little information available up front to inform connection choice
• Customer service was patchy
• Hard to know what you were paying for
• Different arrangements in different DNO regions
• No innovation or desire to find ways around a problem
• At times, far too expensive
• At times, far too long to connect
• DG Forum and new Incentive on Connections Engagement introduced to focus DNOs on customer needs – or face penalties
• General sense that progress has been made - DNOs are now more customer focused
Service quality has improved
17
Innovation has enabled smarter approaches
• We’ve invested over £71.3m of customer money funding innovative projects to release capacity/improve connections for DG
Flexible Plug and Play (UKPN)
Low carbon hub (WPD)
Active Network Management (SSE)
Real time thermal ratings (NPG)
Kent Area System Management (UKPN)
Accelerating Renewable Connections (ARC) (SP)
FlexDGrid (WPD)
Capacity to Customers (ENWL)
Low Voltage Network Templates (WPD)
Network Equilibrium (WPD)
• These need to be business as usual. Customers should have a choice between firm and a viable non-firm offer – or an explanation why not.
18
ICE Plans published on our website describing how service will improve
NPG: Assess alternative connection options to reduce connection costs and timescales.Develop and implement a design tool that runs connections network assessments.
ENWL: HV & LV schemes have a detailed study on acceptance rather than quotation stage ‘Connect and manage’ policy on bulk PV schemes
SSE: Active Network Management as Business as Usual Connection surgeries
WPD: Rolling out flexible connection offers across the network
SP: Development of Power Networks Demonstration Collation and Centre - trialling new technologies Development of Flexible Networks Project to provide 20% increase in network capacity ARC Project to trial a new connections process in East Lothian and the Borders of Scotland
UKPN: Review design toolsMaximise Flexible Plug and Play opportunities
Up to you to tell the DNO and us what you think
Improvement must be ongoing
19
The growth of DG
0
500
1000
1500
2000
2500
3000
3500
4000
4500
2010/11 2011/12 2012/13 2013/14 2014/15
Other generation CHPPhotovoltaic Waste incineration (not CHP)Landfill gas, sewage gas, biogas (not CHP) Biomass & energy crops (not CHP)Offshore wind Onshore wind
• 11.5 GW connected since 2010
• 45 MW of PV connected in 2010. By 2015 over 5 GW had connected
20
Dis
trib
ute
d G
ener
atio
n c
apac
ity
(MW
)
Increasing irradiance
Mix of technologies varies by region
21
UK installed the most solar capacity in Europe in 2014. Total installed solar capacity of 5.71 GW at the end of March 2015 - 41% increase
687,000 solar installations in the UK compared to just over 7,000 five years ago
Forecasting is challenging
22
With growth comes issues
• Fundamental changes to the flows of energy across the system – regions built to handle demand now net export
• Headroom for growth being exhausted - Grid constraints are becoming more severe
Connections to Distribution network in SW
Total MW -
connected,
accepted and
offered
Biomass and energy crops (not CHP) 111,050
CHP 68,648
Offshore wind 181,351
Onshore wind 202,433
Photovoltaic 2,593,920
Waste incineration 115,765
Other generation 649,522
Total 3,922,689
Winter Maximum Demand 2,530,000
Summer Minimum Demand 980,000
23
• NGET use DNO forecasts of DG and for individual larger schemes the Statement of Works (SoW) process to identify impact DG may have on the network
• Rapid (unforecasted) growth in DG in some regions and its ability to deploy in 3 to 6 months is creating significant challenges.
• Cumulative impact of lots of ‘small’ generation (not covered by SoW) and intermittent nature of when DG exports compounds the challenge
• Embedded generation can reduce demand on the network (ie.excess generation at times of low demand - sunny day at 5AM). Challenging for NGET to keep voltages within limits - may result in restrictions on transmission-connected generation and/or what the DNO can connect
Impacts on the wider system
24
Being done• Sharing of all FiTS data – so everyone knows how much is connected
• DNO/Transmission workshop to consider whole-system impacts and solutions
• Review of Engineering Recommendations that may allow DNOs more flexibility in planning connection requirements
Further work required• Needs to be more consistency in approach to queue management – some may lose out
but overall there must be benefits from a more efficient approach
• Want customers to know what smart/alternative connection solutions are available
• Want transparency on flexible terms offered by DNOs
So what’s being done/ needs to be done
25
• Price signals are important - most of the connections in last 5 years didn’t require reinforcement. This is a real success story.
• But not sustainable indefinitely. DNOs have a duty to connect customers. Only offering prohibitively expensive connections across a region is not acceptable.
• Either new capacity is required or smarter solutions have to be deployed (or both)
• Uncertainty is fact of life. So DNOs have to review and update plans on ongoing basis and consider how to enable growth and minimise risk
- Scenarios for growth- Phased expenditure- User commitment- Smart solutions
• Quicker, More Efficient Connections consultation to explore alternative approaches to investment, including alternate commercial arrangements (consortium)
Strategically - DNOs can’t constrain growth
26
• These are our expectations – we believe DNOs should manage and develop their networks to accommodate growth and customers should be presented with choice on the type of connection they are offered
• ICE should drive this behaviour – you need to use this ensure DNOs are responding to your needs
• Alongside DNO-led engagement we plan to issue our own consultation in October to hear directly from you how well DNOs are rising to these expectations.
Is this happening?
DISTRIBUTED GENERATION FORUMCharl Oosthuizen – WPD Finance Director
Wednesday 23rd September 2015
Cardiff
Agenda
29
• Fulfilling our commitments from last year
• The challenge we face: Network constraints
- Statement of works- Queue management
• What we are doing to address these challenges
• How are we doing – WPD’s DG survey
• Top 3 priorities for 2016
Fulfilling our commitments from last year’s forum
We have:
• Engaged with over 2,400 connections stakeholders in the last 12 months – Including for example, a large scale solar event (300 stakeholders) and 4 further Community
Energy scheme workshops (120 stakeholders)
• Amended our annual DG survey – segmenting by LV, HV and EHV
• Introduced alternative connection offers as appropriate
• Met with our Connections Customer Steering Group (CCSG) 3 times per year and developed 66 improvement actions in our ICE workplan. With key focus on:
- Availability of network information including available capacity- Consistency of process and communication across WPD- Improving the post acceptance process
30
Network Constraints - background
Demand for DG connections has increased ten-fold over the last four years despite:
– DECC intervention on subsidy rates– Available capacity being utilised
(where little or no reinforcement required)
Take up in the South West– Network designed for MD of 2.6 GW– 1.3 GW renewable connections
already made– Quotes accepted on a further 1.8
GW of renewables– 23% of all energy from renewables
31
The driver of DG volumes is an economic one i.e. the level of subsidy
Network constraints across WPD
32
• There are now many constraints across WPD – maps published on our website
Network constraints South West – customer impact
• A delay of 3-6 years will apply to all generator connections in the South West requiring works at HV (i.e. 6.6kV or 11kV) or above
• In addition, there are likely to be other reinforcement works included in the connection offers (for more localised issues), plus a requirement to obtain a Statement of Works from National Grid transmission
• We are currently exempting restrictions from:- Individual SSEGs - DG where only LV works are involved- Generation on predominantly demand connections as long as the load offsets the generation
requirements at all times
• These restrictions are subject to constant review
33
DG forecast using 2011/12 data
DG Connected and Accepted (MW) – South West cumulative 2009-2012
NGT 400kv line - planned
completion
DG forecast using 2012/2013 data
DG Connected and Accepted (MW) – South West cumulative 2009-2013
NGT 400kv line - planned
completion
WPD’s response – facing up to the issues
• Rather than avoid these difficult issues, we have taken a number of steps to engage with stakeholders, communicate the challenges and review our plans to address them. E.g:
36
- Ofgem and DECC briefed in March
- Briefing note advising DG community published on WPD website in March
- Cornwall Energy Island event 20th March (100 attendees - Councils, developers, community energy)
- WPD Exeter DG event 14th April (60 DG developers)
- Regen SW annual conference 21st April (400 attendees – DG, Councils, community energy)
- Additional DG developer meetings as requested
“It is very welcome that WPD are not afraid to put their heads above the parapet to talk about these difficult issues” – DG developer
What are we doing to address the issue?
• What more can we get out of F route? – LiDAR
• WPD promoting ‘alternative’ connection schemes - Active monitoring of constraint limits and curtailment as necessary (active, timed, intertrip). Since 1st April 2015 we have:- 127 schemes already accepted (a further 112 offered)- 342MW of additional connections facilitated
• Rolling out zones that are fully automated (‘Active Network Management’ zones)
• Demand Side Response - discussions with major utilities and other large I&C customers “Project Sync”
• Export Capping schemes - DG developers required to keep export levels to zero where capping scheme employed
• Innovative “sunshine tariff” trial with Tempus energy
37
Effective utilisation of existing capacity
WPD’s response - forecasting
• Consider various strategic options and costs of facilitating higher levels of DG in the South West
• Hosted a stakeholder event (15th Sept) to review our approach
• We will:- Assess the potential growth in DG by type, location and year, against potential demand changes- Identify thermal, voltage and fault level constraints that result- Assess options for reinforcement
• This will enable us to:- Provide recommendations for ‘low regret’ investment- Develop background energy scenarios and resulting generation and demand scenarios- Identify future network solutions (including required NGET upgrades)- Estimate capacity provided by these solutions and costs/timescales- Reveal the potential for demand response or generation constraint take up vs network solutions
38
Scoping out a more detailed study and scenarios
WPD’s response - mitigation
• LiDAR
• Trialling reduction of the 132kV network voltage to reduce transmission system impact
• Assessing the potential for reactive compensation through transformer tap operation or the installation of further reactive compensation equipment
• Examining options for switching our capacitor banks based on network conditions
• Working with NGET to look at options for our Active Network Management schemes responding to NG boundary flows
39
WPD’s response - Statement of Works
• To date WPD has been encouraged by NGET to make ‘bulk applications’ i.e. a number of applications have been grouped together as part of a SoW application
• Any conditions from NGET are then applied to connectees in the bulk application
• Problems nationally have led to a national working party to review the process
• We have set up a new team to make individual SoW applications above 1MW, but NGET may require higher or lower limits at some GSPs
40
Move to individual SoW process
WPD’s response - queue management
For example:• DG Developers are required to demonstrate that their scheme is progressing by meeting
milestones
• When a DG developer does not install their full offered capacity, the unutilised capacity will be recovered unless they can demonstrate the capacity will be utilised within 18 months
• Relinquished capacity will be made available to other applicants in strict order
41
Several changes following consultation (April 2014) and workshop (Aug 2015)
• WPD have conducted a bespoke DG survey for the 4th consecutive year• We have seen a decline in most areas, but overall satisfaction remains above 8.5/10:
• We have improved the consistency of the process – 88% customers with previous service experience said the most recent was the same or better
How are we doing?
42
• Following feedback we have disaggregated the surveys by voltage:
• Despite the challenges faced, satisfaction remains high in some areas:
• But we are getting a clear message for improvement in other areas
How are we doing?
43
NOTE: Sample size too small on EHV completed connections (5 customers) to be statistically robust
Ease of initial contact (to get a quotation) 8.92
Understanding the customer’s requirements (during quotation process) 9.06
Clarity of explanation of the connections process 8.74
Clarity of explanation of the likely charge 8.98
2014: 2015:
Time taken to provide a quotation 8.53 7.88
Amount of communication throughout the process 9.03 8.57
Promptness of contact to agree dates for work 9.08 8.00
Arrangements made before work started 9.30 8.46
Priorities for 2016
44
1. Scope out a more detailed study and scenarios for DG volumes and potential network investment- Using our experience & learning over the last 2yrs to improve our techniques and forecasting to
facilitate more DG
2. Move to an individual Statement of Works process- Provide quicker response to DG customers and increased certainty on their project risks
3. Implement the ICE plan and publishing associated KPIs- Actions identified by stakeholders will drive improvements, measured by clear KPIs
2015 DG Forum
Millennium Centre, Cardiff
23rd September 2015
Agenda
• Who are SP EnergyNetworks?
• Our contribution to the Renewables sector
• The highlights from the past year
• Our focus over the next year
• Summary
SP EnergyNetworks
We deliver electricity to;
• 2m customers in Scotland
• 1.5m customers in England and North Wales
Our network serves;
• 14% of UK demand customers
• 29% of all connected DG
Our network contains;
• 30,000 substations
• 40,000km of OHL
• 65,000km of cable
We employ;
• 2,600 internal staff
• Supported by 2,500 contractors
SP Distribution
SP Manweb
We cover;
• 3 different countries and Governments
• Multi-lingual
An aerial view of QASP. - Photo courtesy Quaid-e-Azam Solar Power (Pvt) Ltd
Pilot phase of World’s largest solar park:
Pilot
100MW
400,000 PV cells
Proposed
1000MW
5.2 million PV cells
Scale is relative…
Contracted 1.3GW
Connected 0.91GW
0
200
400
600
800
1,000
1,200
1,400
1,600
1,800
2010/11 2011/12 2012/13 2013/14 2014/15
SP Manweb
Solar is the main driver of DG Growth in SP Manweb
Offers Issued
SP Manweb could be a net exporter of power…
Mainly PV generation, spread across the whole SP Manweb area except for Snowdonia National Park and Areas of Outstanding Natural Beauty
Constraints are not just a South West Issue…
First to provide heat maps….
• Geographical picture of the capacity availability of our network for generation
• Can be used for initial viability of a project
First to provide ‘Quote +’…. Most DNOs now
provide a variant thereof
Preferred option for Formal Connection Offer
Option 3
Option 2
Option 1
FeasibilityAssessment
Initial enquiry date secures queue position
Highlights from the past year…
5 Districts
We listened and implemented a new geographical model
You told us you wanted to …
• Be able to contact staff with local knowledge
• Build relationships with local staff
• Get decisions made quickly
We will provide…
• Greater autonomy and responsibility for our local operations
• Greater emphasis on stakeholders and communities
We are already seeing the improvement in Customer Service
Stakeholder Geographic Model
Industry Portal
Project Details
ICPsIDNOs
We are launching a working group to include representation from ICPs, IDNOs, Utility Consultants and Customers to establish:
Feasibility
Scope
Demand
Using “Best Practice” from outside the industry – we want to develop a “Portal” for customers to advertise for alternative connection providers to
undertake the contestable works on their projects
Encouraging Competition
Existing Demand and Generation profile
70 MVA Demand
170MW Connected & Contracted generation
160MW tidal generation
100MW other generation in the pipeline
Innovation Solution
Insertion of a flexible DC link between Anglesey and the mainland
Conversion of an existing AC circuit to DC operation
Control of power flows – solution can be used in other locations across UK
20% to 25% increase on capacity
The Anglesey Energy Challenge
Innovation – Angle DC Project
SPEN are at the forefront of plans to replace ‘Statement of Works’ process
Connection application
Connection Offer
Acceptance & payment of SoW fee
SoWRequest
SoW Issue
SoWNotification
Mod App Request and
paymentMod App Request
Mod Offer Issue
Variation Issue
Decision
Customer NGETDNO
Connection application
Connection Offer
Decision
GSP Headroom DefinedT Works Identified
BCA Schedules Agreed
Customer NGETDNO
Up
to
12
mo
nth
s A WIN - WIN for all!
• Increased certainty and control• Reduced timescales and costs • Removal of invoicing issues• Increased visibility to NGET
• SPD will trial pre-CUSC change
Current ProposedM
in. 6
mo
nth
s
Revised Statement of Works Process…
Summary
We’ve connected 4GW of Renewables & 3.3GW contracted in SPD & SPM
We have managed constraints for a number of years, they are not new
We listened and implemented a Geographical District Model
We will continue to innovate and respond to your needs
Dr Graham PannellRenewable Energy Systems
Vice-ChairENA DG-DNO Steering Group
Develop
Design
EngineerConstruct
Operate
Agenda
1 Context
2 Last Year we asked for action on… what has happened?
• Workplans
• Flex Conn & Reinforcement Signal, A&D Fees, Capacity Hoarding, Transmission
2 DNO Experience
3 Key Asks 2015/16
• Queue and Capacity Management – Do it.
• Transmission interaction – better info, better process.
• Reinforcement and optimal charging – Quicker and More Efficient, please
Context
• respect contracts
(subject to Q mgmt)
• some will make it work
(fair grace periods needed)
interim!
uncertainty
RES operates across 6 continents
5 GWOFFSHORE
DEVELOPMENTEXPERTISE
1300 MWSOLAR
inDEVELOPMENT
DEVELOP,CONSTRUCT &
OPERATE one of the LARGEST
WIND FARMSin
EUROPE
>5000 TURBINES
COMMISSIONED
>10 GWPROJECT
PORTFOLIO
>1000 kmTRANSMISSION
POWERLINES BUILT
75 MWENERGY
STORAGE
• more renewables facilitated
RES’ low carbon UK headquarters
Beaufort Court
Last Year Asks
ICE Workplans – Service improvements in train
Last Year Asks
Flex Conn = patchy (good WG progress)
Reinforcement Signal = NoneQMEDCSGF
A&D Fees = Nothing
Capacity Hoard = Q Mgmt = difficult
Transmission info =
Last Year Asks
WPD:
Mostly positive.
Connections made. Escalation path clear
SoW – history catching up still
Some contract difficulties. T&Cs out-dated.
Plan - good choices, good ambition, poor KPIs.SPEN:
Hands on proj mgmt.
- programming tough.
Contract management sound (not quick).
££££ especially Transmission.
flexibility .
quote+ & heat maps .
Plan promising. “You said we did”.
Customer Experience & Workplans
both DNOs: capacity reg
Priorities for 2015/16
Queue and Capacity Management – Do it.
Transmission interaction – better info, better process.
Reinforcement and optimal charging – Quicker and More Efficient, please
Priorities for 2015/2016
Priorities for 2015/16
Queue & Capacity Managementoperational capacity & old contracts
trip/export management costs must be reasonable
no trading
Transmission System Interactionbetter, earlier info
Interim Restrictions options without BEGA
replace Statm’t of Works; D-Offer to include Transmission detail!
Reinforcement and Charging“Quicker and More Efficient Distribution Connections”
Least regrets grid capacity investment built on needs case, as per NG
…with signal from flex connections.
NOW, not 2017+.
charges post connection, rationalise £200/kW cap.
Priorities for 2015/2016
Dr Graham PannellRenewable Energy Systems
Workplans – DG: give feedback
Queue and Capacity Management – DNOs: Do it.
Transmission interaction – DNOs & TSO: better info, better process, quickly.
Reinf’ts & optimal charging – Ofgem & DNOs: Quicker and More Efficient, now.
DG Customer Perspective
Nicola WatersSeptember 2015
Overview
• Introduction to Primrose Solar
• DG industry
• Progress last year
• Ongoing challenges
Primrose Solar as a customer
• Buy, build, own/operate, and sell projects
• Active industry participants
• 183MW built, up to 100MW planned for before April ‘16
DG industry
• Changes to the subsidies mean that the way DG is developed and connected will significantly alter from 2016 onwards. Likely to include:
• Bigger connections
• More challenging locations
• Company consolidation- more sophisticated industry
• Less foreign investment
• Different project motives
• The outlook for community schemes are uncertain
• Storage is on its way
Progress last year
• More connections than ever before
• Mostly positive improvements
• Working relationships with DNOs
• Increased visibility across the board
• Queue management
• Transmission implications
• Curtailment explanations
Ongoing challenges
• Grace period management
• Subsidy free projects
• Queue and capacity management
• More transparency
• Transmission info
• Curtailment is more complex, DG need support
• Making flexible connections work