Welcome

Transcript of Welcome [] ·  · 2017-12-01Welcome . Introduction to the project Sharon Bleese, ... Do nothing...

Welcome

Introduction to the project

Sharon Bleese, Project Manager

December 2013 tidal surge impacts

• Largest in Lowestoft since 1953

• Over 160 properties affected

• Businesses brought to standstill

• Highlighted the inadequacy of Lowestoft’s defences and the impact on existing and potential growth

5

Economic study headlines (1)

Total jobs: 10,900 Total GVA (million) £499

Proportion of current economic footprint at risk of flooding under two scenarios Without climate change With climate change

Scenarios

Jobs GVA Jobs GVA

1. Do minimum 22% 23% 63% 71%

1. Preferred tidal gate and wall scheme 2% 2% 2% 2%

6

Economic study headlines (2)

Total jobs: 14,400 Total GVA (million) £694

Future economic footprint (assuming AAP delivered)

Scenarios

Jobs GVA Jobs GVA

1. Do minimum 28% 27% 70% 77%

1. Preferred tidal gate and wall scheme 2% 2% 3% 3%

Proportion of future economic footprint at risk of flooding under two scenarios Without climate change With climate change

Tidal Flood Risk Management Ben Purkiss, CH2M

9

Lowestoft FRMP – Tidal scheme

Options considered

1. Do nothing – walkaway

2. Do minimum – maintain status quo

3. Improve: Walls only

4. Improve: Outer harbour barriers & walls

5. Improve: Bascule bridge barrier & walls

6. Improve: Barriers at Third Crossing & walls

7. Temporary flood defences

8. Property level resilience

(Shortlisted options in bold)

11

Key shortlisted options 3. Improve –

flood walls only

Discounted, due to:

Tidal inundation into Lake Lothing.

Increased flood risk - 5 times longer sea frontage.

Walls built on existing quay wall, interact with major services, businesses,

road/ rail network.

Raising of bascule bridge or road closure for temporary demountable at

Waveney road beyond year 50

5. Improve –

Bascule Bridge

barrier & walls

Recommended as the preferred option, due to:

Shorter length of floodwalls.

Single barrier in narrow river channel.

6. Improve –

Barriers at Third

Crossing & walls

Discounted, due to:

3 barriers, longer length of walls, interaction with quay walls, major

services

Disruption to quayside businesses during construction.

Raising of Bascule Bridge/road closure for temporary demountable

Waveney Road beyond year 50.

New control building required.

23

Now

Completion

Further activities and programme

Outline designs, May-Oct`17 OBC, Oct 17– April 18

Planning application for walls, Nov 17 –Jul 18 Legal & funding Agreements, Nov 17- Jul 18

TWAO, Marine license Sep 17- Jul 19

Flood Walls D&B, Nov17- Mar 19

Barrier D&B, Nov18- Dec 20

FBC, Aug 18- Nov18

SOC and consultation 2016/17

Summary and next steps

Sharon Bleese, Project Manager