Lowestoft Flood Risk Management Project reducing risk, supporting growth, creating opportunities
December 2013 tidal surge impacts
• Largest in Lowestoft since 1953
• Over 160 properties affected
• Businesses brought to standstill
• Highlighted the inadequacy of Lowestoft’s defences and the impact on existing and potential growth
5
Economic study headlines (1)
Total jobs: 10,900 Total GVA (million) £499
Proportion of current economic footprint at risk of flooding under two scenarios Without climate change With climate change
Scenarios
Jobs GVA Jobs GVA
1. Do minimum 22% 23% 63% 71%
1. Preferred tidal gate and wall scheme 2% 2% 2% 2%
6
Economic study headlines (2)
Total jobs: 14,400 Total GVA (million) £694
Future economic footprint (assuming AAP delivered)
Scenarios
Jobs GVA Jobs GVA
1. Do minimum 28% 27% 70% 77%
1. Preferred tidal gate and wall scheme 2% 2% 3% 3%
Proportion of future economic footprint at risk of flooding under two scenarios Without climate change With climate change
7
Lowestoft Flood Risk Management Project
Reducing tidal risk - temporary defences
9
Lowestoft FRMP – Tidal scheme
Options considered
1. Do nothing – walkaway
2. Do minimum – maintain status quo
3. Improve: Walls only
4. Improve: Outer harbour barriers & walls
5. Improve: Bascule bridge barrier & walls
6. Improve: Barriers at Third Crossing & walls
7. Temporary flood defences
8. Property level resilience
(Shortlisted options in bold)
10
Options considered
11
Key shortlisted options 3. Improve –
flood walls only
Discounted, due to:
Tidal inundation into Lake Lothing.
Increased flood risk - 5 times longer sea frontage.
Walls built on existing quay wall, interact with major services, businesses,
road/ rail network.
Raising of bascule bridge or road closure for temporary demountable at
Waveney road beyond year 50
5. Improve –
Bascule Bridge
barrier & walls
Recommended as the preferred option, due to:
Shorter length of floodwalls.
Single barrier in narrow river channel.
6. Improve –
Barriers at Third
Crossing & walls
Discounted, due to:
3 barriers, longer length of walls, interaction with quay walls, major
services
Disruption to quayside businesses during construction.
Raising of Bascule Bridge/road closure for temporary demountable
Waveney Road beyond year 50.
New control building required.
12
Waveney Road
13
Tidal barrier – before and after
14
Tidal Barrier
•Mitre Gates
•Barrier width- consultation with ABP
15
Station square- before and after
16
Waveney Road- before and after
17
Port Entrance- before and after
18
Hamilton Road
19
Hamilton Road – before and after
20
Yacht Club and South Pier/Beach
21
Royal Norfolk & Suffolk Yacht Club – before and after
22
South Pier- before and after
23
Now
Completion
Further activities and programme
Outline designs, May-Oct`17 OBC, Oct 17– April 18
Planning application for walls, Nov 17 –Jul 18 Legal & funding Agreements, Nov 17- Jul 18
TWAO, Marine license Sep 17- Jul 19
Flood Walls D&B, Nov17- Mar 19
Barrier D&B, Nov18- Dec 20
FBC, Aug 18- Nov18
SOC and consultation 2016/17