Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete...

20
Welcome Tehri Hydro Development Corpn.Ltd. (A joint venture of Govt.of India & Govt.of U.P.) Rishikesh 1

Transcript of Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete...

Page 1: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

WelcomeTehri Hydro Development Corpn.Ltd.

(A joint venture of Govt.of India & Govt.of U.P.)

Rishikesh

1

Page 2: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

Suggestionson

CERC’s draft Regulationson

Terms & Conditions of Tariff for

tariff period 2009-14.2

Page 3: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

3

In case of reduced generation due to the reasons beyond the control of generating company, resulting in spillage of water, the energy charges on account of such spillage should be payable to the generating company. Energy charges on the above account shall not be admissible if the energy generated during the year is equal to or more than the Design Energy.

This is required to take care of situations where the transmission line is not available and reservoir is full. In such a scenario, water shall be spilled for no fault of the generator.

Page 4: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

4

In case of reservoir type generating station, if the generation is possible to be started from the first unit only after the construction of the complete dam, spillways and other civil structures and also after the complete installation of several common hydro mechanical and electromechanical systems & equipment, then the cost of all such facilities and assets should be capitalized alongwith the first unit.

Page 5: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

Additional Capitalisation:As per draft Regulations : The capital expenditure of the following nature actually incurred after the cut-off date may, in its discretion, be admitted by the Commission, subject to prudence check:

(i) Liabilities to meet award of arbitration or for compliance of the order or decree of a court;

(ii) On account of change in law; and

(iii) Deferred works relating to ash pond or ash handling system in the original scope of work.

As Proposed : The relevant provision in the prevailing Regulations 2004-2009 , as under,should be retained:

The capital expenditure of the following natureactually incurred after the cut-off date may beadmitted by the Commission, subject to prudence check:

(i) Liabilities to meet award of arbitration or forcompliance of the order or decree of a court;

(ii) On account of change in law; and

(iii) Deferred liabilities relating to works/services within the original scope of work.

(iv) Any additional works/ service which has become necessary for efficient and successful operation of plant but not includedin the original capital cost.

5

Page 6: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

Debt-Equity Ratio :As per draft Regulations:

Debt-Equity Ratio (1) : For a project, if the equity

actually deployed is more than 30% of the capital cost, equity inexcess of 30% shall be treated

as normative loan:

Provided that where Equity actually deployed is less than 30% of the capital cost, the actual equity shall be consideredfor determination of tariff.

As Proposed :The para, as mentioned below, as existing in theprevailing Regulations 2004-09, should be incorporated after second para of the relevant draft Regulations:

“Provided that the Commission may in appropriatecases consider equity higher than 30% for the purpose of determination of tariff, where the generating company is able to establish to thesatisfaction of the Commission that deployment of equity more than 30% was in the interest of general public.”

The following is proposed to be incorporated :

“Provided further that the projects which weresanctioned by the competent Government prior to the issuance of Govt. of India’s Tariff Policy dtd.6th January 2006, the debt- equity ratio, as sanctioned by the Government in the investment approval, shall be applicable.”

6

Page 7: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

7

Page 8: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

8

Page 9: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

9

Page 10: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

10

Page 11: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

11

Page 12: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

12

Page 13: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

13

Page 14: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

14

Page 15: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

15

Page 16: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

16

Page 17: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

17

Page 18: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

18

Page 19: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

19

Page 20: Welcome [cercind.gov.in]cercind.gov.in/November08/PPT-MEETING3.11.2008/THDC/THDC.pdf · complete dam, spillways and other civil structures and also after the complete installation

20