Date: from 09/01/16 to 14/01/16 Senior Site Engineer: Houssam Slika (ID: 1953)
Zone Area: D (Z3B, Z4B) Site Engineer: Md. Shah Faisal (ID: 2747)
Site Supervisor: Talaat Elsherbini (ID: 2607)
Area boundary as highlighted between axes (G-W, 1B-9)
![Page 2: Weekly Report-8new](https://reader035.fdocuments.us/reader035/viewer/2022081604/58e7556e1a28ab55108b4ccd/html5/thumbnails/2.jpg)
COMPLETED WORKS:
A- Fire Alarm System 1. Work done and inspected for FAS point on slab of Z4B, B1 , AREA-5 between
axes(K, L)- (3, 4). Refer: (IR-PDM-B1-T00025-FAS)
2. Work done and inspected for extension PVC conduit for FAS points on Z3B, B2, Area-9 between axes (S-U), (3-5). Refer: ( IR-PDM-B2-T00042-FAS )
![Page 3: Weekly Report-8new](https://reader035.fdocuments.us/reader035/viewer/2022081604/58e7556e1a28ab55108b4ccd/html5/thumbnails/3.jpg)
3. Cleaning and preparation slab coupling foam for FAS work at stair core case in Z3B, B2, Area-9 between axis(S-U),(3-5)
4. Cleaning and preparation slab coupling foam for FAS work at Ramp core case in Z4B, B2, part-5 between axes (1A-4), (N-P).
![Page 4: Weekly Report-8new](https://reader035.fdocuments.us/reader035/viewer/2022081604/58e7556e1a28ab55108b4ccd/html5/thumbnails/4.jpg)
B- Data Network System
1. Work done and inspected for DNS points on slab ofZ4B, B1, AREA-5 between axes (K, L)-(3, 4). Refer: ( IR-PDM-B1-T00026-DNS )
2. Work done and inspected for extension PVC conduit for DNS points on Z3B, B2, Area-9 between axes (S-U), (3-5). Refer: ( IR-PDM-B2-T00043-DNS )
![Page 5: Weekly Report-8new](https://reader035.fdocuments.us/reader035/viewer/2022081604/58e7556e1a28ab55108b4ccd/html5/thumbnails/5.jpg)
Work in Progress:
1. Marking for ELV work on the ramp slab of Z4B, B2, part-5 between axes (1A-4), (N-P).
![Page 6: Weekly Report-8new](https://reader035.fdocuments.us/reader035/viewer/2022081604/58e7556e1a28ab55108b4ccd/html5/thumbnails/6.jpg)
Material installed
PVC 25mm Lm(M) PVC 32mm Lm(M)51m 0 m
Look ahead:
1. 1 FAS point on Concrete core wall in Z3B, B2, part-9 between axes (R-S), (3-4)2. 1 FAS point on Concrete column in Z4B, 01, part-5 between axes (K, 3-4).3. 1 FAS point on Concrete Column in Z4B, B1M, part-5 between axes (L-5).4. 6 FAS points and 2 DNS points on 2 concrete column in Z4B, B2, part-5 between axes
(N-Q), (7-9). 5. 1 FAS point on Concrete column in Z4B, B1, part-5 between axes (G-H), (3-5).6. ELV work on slab in Z4B, GF/UGF/MGF, part-5 between axes (G-P), (4-7).