WEEKLY REPORT #86 · 2018-01-27 · 14 Structural steel works Gulf Steel Industries...
Transcript of WEEKLY REPORT #86 · 2018-01-27 · 14 Structural steel works Gulf Steel Industries...
( 14-Oct-12 : 20-Oct-12 )
Project:Twin Towers at Doha - Qatar
Client:H.E. Sheikh Khaled Bin Hamad Al-
Thani
Project Manager: HPM
WEEKLY REPORT #86
Main Contractor:Arabtec Construction CO. W.L.L
Consultant: ACG
Table of Contents
Page #
1 Subcontractors list Page 4
2 Procurement Schedules
2.1 MEP Page 9
2.2 ID Works Page 24
2.3 Civil & Finishes Page 30
2.4 Lifts Page 42
2.5 Aluminum Works Page 47
3 Material Submittal Register (MARS) Page 50
4 Summary Progress Status
4.1 Concrete Work Page 92
4.2 Concrete, Rough Finishes & Façade Page 94
5 Progress Photographs Page 96
Page 2 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Subcontractors list
Page 3 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project: TWIN TOWER PROJECT Client: H. Sheikh Khalid Bin Hamad Al Thani Project Manager: HamiltonConsultant: Architectural Consulting Group
Main Contractor: Arabtec Construction Co.
S.I. No.
Name of work Name of subcontractor
Assigned Subcontractors Ref No.Date of
Appointment
1 MEP Efeco Arabtec/AB/03/002/10 24-Feb-10
2 Earthwork Arabtec 5-Feb-11
3 Dewatering United Equipment ATC/TT/VK/LOI-3008-001 20-Jun-10
4 ID Works+FF & E Depa Qatar ACC/TT/VK/LOI-3002-001 31-Oct-10
5 Material Testing Arab Center ACC/TT/VK/LOI/3075-001 28-Feb-11
6 Structural Design E.construct 15-Feb-11
7 Formworks Doka Qatar ACC/TT/DOKA/TM/LOI-1004-001 19-Apr-11
N.B.K Readymix ACC/TT/VK/LOI/1001-A/001 4-Sep-11
Rabban Readymix ATC/TT/VK/LOI/1001-001 19-Apr-11
9 Supply of Reinforcement Al Watania Steel ACC/TT/VK/LOI/1002-001 27-Mar-11
10 Waterproofing Tadmur Roof & Pools W.L.L. ACC/TT/VK/LOI/3012-001 13-Mar-11
11 Post Tension Slab CCL ACC/TT/VK/LOI/3052-001 20-Jun-11
12 Lifts Schindler ACC/TT/VK/LOI/3004-001 12-Nov-11
13 Alumnium & Glazing Aluminium Gulf Ray (AGR) ACC/TT/VK/LOI/3006-001 15/04/2012
14 Structural steel works Gulf Steel Industries ACC/TT/VK/LOI/3013-001 9-Oct-12
15 Non-structural metal works Qatar Indo Fabs ACC/TT/VK/LOI/3022-001 15-Sep-12
16 Garbage Chute Globtech Engineering W.L.L. ACC/TT/VK/LOI/3025-001 9-Oct-12
Subcontractor To be Assigned
1 Paints Jotun Paints/Roots Qatar Hotel, L04, Planned Start (as revised prog.): 24-Dec-12
2 Road markings Jotun Paints/Roots Qatar Bas.1, Planned Start (as revised prog.): 3-Nov-13
Sayyar Trading
Al Farman
ARTCORP Office, L04 12-Jan-13
Eurodesign
Technogard/ Dorma
Aqfal/ HOPPE
Hafele
Silver Shore
Aluone
1000 walls Interior
Ramco Carpentry
Stone Gallary
Specialized marble
Deemah Stone
Al Farman
Hotel, staircase & Services rooms, Planned Start (as revised prog.):
16-Mar-13
16-Jul-13
16-Jul-13
2-Feb-13
Office, L04, Planned Start (as revised prog.):
Office, L04, Planned Start (as revised prog.):
Office, L04, Planned Start (as revised prog.):Stone works (marble, granite)
SUBCONTRACTORS / SUPPLIERS LIST
3 Tiles
Iron Mongery4
Joinery & Wooden doors5
6
Status
Supply of Readymix Concrete8
Page 4 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project: TWIN TOWER PROJECT Client: H. Sheikh Khalid Bin Hamad Al Thani Project Manager: HamiltonConsultant: Architectural Consulting Group
Main Contractor: Arabtec Construction Co.
S.I. No.
Name of work Name of subcontractor
SUBCONTRACTORS / SUPPLIERS LIST
Status
Power machine
United Equipment
ETA
Technical Parts
Thomas Bennet
Qatar Neoan
Fanar Neoan
Spectra Arts
Art glass
Nabina Glass
Rumaillah Services
Globtech Engineering W.L.L.
GIBCA
Rabya Qatar
Proscape
Roots Qatar
Tadmur Pools
Gemco Pools Div
Al Jabor Trading
Growtech
Prime Technology
Al Hathboor
Sprint
Basco Qatar
Awar
Intertec Group W.L.L.
New Design
Elite Engineering
QASR Al Andalus Co.
Globtech Engineering W.L.L.
Indigatech
Qatar Metal Ind. LLC
Sadah Contracting Co./ GMP
9-Sep-13
23-Jul-13
8-Oct-13
30-Sep-13
6-Aug-13
6-Jun-13
Office, L04, Planned Start (as revised prog.):
Planned Start (as revised prog.):
Office, L04, Planned Start (as revised prog.): 23-Jan-13
21-May-13
26-Jun-13
Office, L04, Planned Start (as revised prog.):
Podium, Planned Start (as revised prog.):
Planned Start (as revised prog.):
Planned Start (as revised prog.):
Fixing Restrain Socket, Planned Start (as revised prog.):
Planned Start (as revised prog.):
Window Cleaning System
15
Signage8
Swimming pool12
11
Steel Doors
9
7
Landscaping & Irrigation
Mirrors
13
14 Suspended Ceilling & Partition
Toilet Partition10
Kitchen & Laundry Eqpt.
Page 5 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project: TWIN TOWER PROJECT Client: H. Sheikh Khalid Bin Hamad Al Thani Project Manager: HamiltonConsultant: Architectural Consulting Group
Main Contractor: Arabtec Construction Co.
S.I. No.
Name of work Name of subcontractor
SUBCONTRACTORS / SUPPLIERS LIST
Status
Salam Enterprises
Coastal Trad & Cont
ManTech
Rafco
Spyro Hotel Supplies
Al Ali Sports
Poineer
Electra Trad & Cont.
Total Flooring
Mentech Office System
29-Aug-13
11-Aug-13
25-Apr-13
Planned Start (as revised prog.):
Planned Start (as revised prog.):
Planned Start (as revised prog.):
Carpet Flooring16
Linoleum Flooring & PVC Skirting18
Gym Equipment17
Page 6 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Procurement Schedule
Page 7 of 106 TT, Weekly Report No. 86 As of 2012-10-20
MEP Procurement schedule
Page 8 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManager: HPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContractor: ArabtecConstructionCo.
MEPContractor: EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
1 E ACC‐MAR‐E‐G‐376 00E16/31‐36,43‐44,122‐125
MVPanelsABB‐Power&
AutomationControl(PAC)
15‐Oct‐11 6‐Sep‐12 16‐Sep‐12 30‐Sep‐12 11‐Oct‐12 14 126 23‐Mar‐12 13‐Feb‐13 17‐Feb‐13 28‐Feb‐13
2 E ACC‐MAR‐E‐G‐375 00E16/31‐36,43‐44,122‐125
SubMainDistributionBoards(SMDBs)upto630A
ABB‐Power&AutomationControl
(PAC)15‐Oct‐11 6‐Sep‐12 16‐Sep‐12 30‐Sep‐12 18‐Aug‐12 14 90 29‐Feb‐12 15‐Nov‐12 12‐Jan‐13 30‐Nov‐12
3 E ACC‐MAR‐E‐G‐378 00E16/31‐36,43‐44,122‐125
DistributionBoards(DBs)ABB‐Power&
AutomationControl(PAC)
15‐Oct‐11 6‐Sep‐12 16‐Sep‐12 30‐Sep‐12 2‐Sep‐12 14 75 31‐Jan‐12 15‐Nov‐12 28‐Dec‐12 30‐Nov‐12
00 12‐Jul‐12 21‐Jul‐12 4‐Aug‐12 1‐Aug‐12 C
01 15‐Aug‐12 11‐Aug‐12 25‐Aug‐12 27‐Aug‐12 C
02 9‐Sep‐12 16‐Sep‐12 30‐Sep‐12
5 E ACC‐MAR‐E‐G‐389 00E16/31‐36,43‐44,122‐125
MCC'sPower&Automation
Control(PAC)15‐Oct‐11 20‐Sep‐12 25.09.12 9‐Oct‐12 23‐Aug‐12 14 105 7‐Aug‐12 5‐Dec‐12 10‐Feb‐13 20‐Dec‐12
PartialDeliveryasperSiteConditions.ProcurementandmaterialsubmitalstartedbasedonrevisedIFCreceivedon28‐4‐2012/AwaitingforKahramaaapproval.POshallbereleasedonlyafterKahramaaapproval.
00 20‐Oct‐11 31‐Jan‐12 14‐Feb‐12 14‐Mar‐12 C
01 17‐Jul‐12 18‐Jul‐12 1‐Aug‐12 9‐Aug‐12 C
02 29‐Aug‐12 25‐Aug‐12 8‐Sep‐12 9‐Sep‐12 C
03 18‐Sep‐12 23‐Sep‐12 7‐Oct‐12
00 15‐Sep‐11 21‐Jul‐11 4‐Aug‐11 21‐Sep‐11 C
01 1‐Oct‐11 17‐Oct‐11 31‐Oct‐11 12‐Nov‐11 B
02 22‐Nov‐11 27‐Nov‐11 11‐Dec‐11 26‐Dec‐11 A
00QatariIndustrialEquipment‐Doha
Qatar15‐Jun‐11 26‐Jun‐11 10‐Jul‐11 8‐Aug‐11 C
01 NBK&Sons 15‐Aug‐12 26‐Aug‐12 9‐Sep‐12 9‐Sep‐12 C
02 CumminsQatar 23‐Sep‐12 27‐Sep‐12 11‐Oct‐12
9 E 00 E16/72‐79 UPS 05‐Sep‐11 5‐Sep‐11 11‐Oct‐12 14 150 7‐Nov‐12 9‐Mar‐13 31‐Mar‐12 24‐Mar‐13ProcurementandmaterialsubmitalonholdawaitingRFIreplyACC‐RFI‐E‐G‐330REV01
00 20‐Sep‐11 10‐Aug‐11 24‐Aug‐11 24‐Sep‐11 C
01 4‐Oct‐11 8‐Oct‐11 22‐Oct‐11 15‐Nov‐11 A
00 20‐Sep‐11 10‐Aug‐11 24‐Aug‐11 9‐Oct‐11 C
01 19‐Oct‐11 22‐Oct‐11 5‐Nov‐11 11‐Dec‐11 C
02 21‐Dec‐11 11‐Mar‐12 25‐Mar‐12 3‐Apr‐12 C
03 30‐Jul‐12 25‐Jul‐12 8‐Aug‐12 13‐Aug‐12 C
04 29‐Aug‐12 26‐Aug‐12 9‐Sep‐12 30‐Sep‐12 B
E ACC‐MAR‐E‐G‐379 00 E16/39‐41LightingFixtures‐Internal(Podium,TowerA&BOHAreainTowerB)‐Part1
Arluce/Disano‐HUDALighting
15‐Dec‐11 15‐Sep‐12 12‐Sep‐12 26‐Sep‐12 11‐Sep‐12 14 120 1‐Jun‐12 8‐Jan‐13 7‐Feb‐13 23‐Jan‐13
E 00 E16/39‐41LightingFixtures‐Internal(Podium,TowerA&BOHAreainTowerB)‐Part2
Sylvania‐HUDALighting
15‐Dec‐11 8‐Oct‐12 11‐Sep‐12 14 120 1‐Jun‐12 8‐Jan‐13 20‐Feb‐13 23‐Jan‐13
13 E ACC‐MAR‐E‐G‐366 00 E16/39‐41LightingFixtures‐Internal(TowerBGuestRooms,Corridor&LiftLobby)
WhitwamInternationalWLL
15‐Dec‐11 30‐Sep‐12 3‐Sep‐12 17‐Sep‐12 22‐Dec‐12 14 120 16‐Sep‐12 20‐Apr‐13 22‐Apr‐13 5‐May‐13
MaterialProcurementandSubmittalarestarted.POshallbereleasedonlyafter
Kahramaaapproval.
10‐Oct‐12
12‐Jun‐12Materialson
site
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
duration
120
03‐Apr‐1202‐Oct‐12
LPONo.1637LPONo.2274
10514
14
DieselGeneratorSetwithSynchronizingPanel 15‐Jun‐11
EngineeringSuppliesCo.WLL
PowerCablesE16/28‐30
15‐Oct‐11
1420‐Sep‐11
30‐Oct‐12
12‐Dec‐12
E16/80‐101
14EngineeringSupplies
Co.WLL
15‐Sep‐11
ACC‐MAR‐E‐G‐251 E16/19‐22
ACC‐MAR‐M‐H‐355
2‐Mar‐12
23‐Jul‐12
20‐Oct‐11
Rev.
DB's‐(GuestRooms)E16/31‐36,43‐44,122‐125
RequiredonSitedateasperApproved
BaselineRev5Programme
31‐Jan‐12
ApprovalCutOffdate
DateSubmittedtoACG(Actual)
28‐Jul‐12Power&Automation
Control(PAC)14
ApprovalRequiredBy
DateofReturn
13‐Dec‐12
DeliveryDate
60
E
ProcurementandmaterialsubmitalrestartedbasedonrevisedIFCreceivedon
28‐4‐2012.AwaitingforKahramaaapproval..ReplytoRFIref.ACC‐RFI‐E‐G‐460Rev.01receivedon5thJuly2012.
30‐Dec‐1223‐Feb‐13BusBarRisers&Tappoffs 18‐Aug‐12
16‐Feb‐12
15‐Jan‐13
29‐Apr‐13
30‐May‐12
15‐Dec‐12
30‐Sep‐12
7‐Aug‐12
30‐Sep‐12
3‐Apr‐13
2‐Apr‐13
12‐May‐13
17‐Apr‐13
15‐Mar‐13 30‐Jan‐1315‐Mar‐12
DohaCables‐QatarLLC
20‐Sep‐11Ducab
E
27‐Apr‐13
112
14 180
E16/11‐18 TransformerACC‐MAR‐E‐G‐112
ACC‐MAR‐E‐G‐103
LPONo.1966R1
E
7
10
12
11 E
8
E
‐ FireRatedPowerCables(FP400)ACC‐MAR‐E‐G‐129
ACC‐MAR‐E‐G‐127
Specs.Ref.Discipline SubmittalNo.Subcontractor/
Supplier
PurchaseOrder
DateofSubmittal(Planned)
5‐Dec‐12
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE
LONGLEADITEMS
Description
StatusCodeDateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
4
SlNo.
E
6
PartialDeliveryasperSiteConditions.ProcurementandmaterialsubmitalstartedbasedonrevisedIFCreceivedon28‐4‐
2012/DB'sschedulesarebeingfinalizedasperactualloadsandapprovedshopdrawings(LoadScheduleDrawings)
Partialmaterialsonsite.Forbalancematerials,POshallbereleasedonlyafter
Kahramaaapproval.NewRequisitionNo.03084dtd19.l9.12&
03085dtd30.09.12
PartialDeliveryasperSiteConditions.ProcurementandmaterialsubmitalstartedbasedonrevisedIFCreceivedon28‐4‐
2012/AwaitingforKahramaaapproval.POshallbereleasedonlyafterKahramaa
approval.
Remarks(LL:LongLeadItems)
DateRequiredonSite
ProcurementandmaterialsubmitalstartedbasedonrevisedIFCreceivedon28‐4‐2012
Kahramaaapprovalawaitedfor9th
Transformer
EFECO QATAR
ProjectManager: HPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContractor: ArabtecConstructionCo.
MEPContractor: EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
durationRev.
RequiredonSitedateasperApproved
BaselineRev5Programme
ApprovalCutOffdate
DateSubmittedtoACG(Actual)
ApprovalRequiredBy
DateofReturn
DeliveryDate
Specs.Ref.Discipline SubmittalNo.Subcontractor/
Supplier
PurchaseOrder
DateofSubmittal(Planned)
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE
LONGLEADITEMS
Description
StatusCodeDateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
SlNo.Remarks
(LL:LongLeadItems)DateRequired
onSite
EFECO QATAR
14 E 00 FaçadeLighting MASQ 30‐Sep‐12
14 E
ALLELVSYSTEMS(CABLING)(a)CCTV(b)ACS(c)D&V
10‐Nov‐11 15‐Sep‐12 28‐Jun‐12 14 90 30‐Dec‐11 30‐Sep‐12 21‐Jan‐13 10‐Oct‐12
ProcurementandmaterialsubmitalstartedbasedonrevisedIFCreceivedon
28‐4‐2012‐referitemno11,12,13,14,15,16,19,20OFOTHER
MATERIALS.BOQreceivedon2ndJuly2012
PartialDeliveryasperSiteCondition
00 17‐Sep‐11 1‐Oct‐11 22‐Oct‐11 A
01 1‐Nov‐11 3‐Mar‐12 17‐Mar‐12 26‐Mar‐12 C
02 5‐Apr‐12 20‐May‐12 3‐Jun‐12 6‐Jun‐12 C
03 25‐Jul‐12 24‐Jul‐12 7‐Aug‐12 13‐Aug‐12 C
04 2‐Sep‐12 1‐Sep‐12 15‐Sep‐12
00 3‐Sep‐11 12‐Apr‐12 26‐Apr‐12 8‐May‐12 C
01 18‐May‐12 16‐May‐12 30‐May‐12 18‐Jun‐12 C
02 7‐Jul‐12 5‐Jul‐12 19‐Jul‐12 9‐Aug‐12 C
03 2‐Sep‐12 27‐Aug‐12 10‐Sep‐12 4‐Oct‐12 C
04 14‐Oct‐12
00 MaicoGulfLLCU.A.E 11‐Jun‐11 14‐Nov‐11 28‐Nov‐11 7‐Dec‐11 C
01 21‐Jun‐12 20‐Jun‐12 4‐Jul‐12 22‐Jul‐12 C
02 18‐Jul‐12 20‐Jul‐12 3‐Aug‐12 1‐Aug‐12 C
03 8‐Aug‐12 9‐Aug‐12 23‐Aug‐12 25‐Aug‐12 C
04 6‐Sep‐12 10‐Sep‐12 24‐Sep‐12 25‐Sep‐12 C
05 1‐Oct‐12 1‐Oct‐12 15‐Oct‐12
00 MaicoGulfLLCU.A.E 14‐Nov‐11 14‐Nov‐11 28‐Nov‐11 7‐Dec‐11 C
01 21‐Jun‐12 20‐Jun‐12 4‐Jul‐12 22‐Jul‐12 C
02 18‐Jul‐12 20‐Jul‐12 3‐Aug‐12 1‐Aug‐12 C
03 8‐Aug‐12 9‐Aug‐12 23‐Aug‐12 25‐Aug‐12 C
04 6‐Sep‐12 10‐Sep‐12 24‐Sep‐12 25‐Sep‐12 C
05 1‐Oct‐12 1‐Oct‐12 15‐Oct‐12
ACC‐MAR‐M‐G‐249 00 25‐Nov‐11 19‐Jan‐12 2‐Feb‐12 7‐Feb‐12 C
ACC‐MAR‐M‐G‐230 01 30‐Jul‐12 17‐Jul‐12 31‐Jul‐12 13‐Aug‐12 C
ACC‐MAR‐M‐G‐249 01 26‐Sep‐12 25‐Sep‐12 9‐Oct‐12
4‐Sep‐121‐Jan‐12
4‐Sep‐121‐Jan‐12
ProcurementandmaterialsubmitalrestartedbasedonrevisedIFCschedule
receivedon28‐4‐2012.Capacity,airflowrateandquantityincreasedcomparedto
previousAIFC.PartialDeliveryasperSiteCondition
19‐Sep‐1214‐Jan‐13
19‐Sep‐1214‐Jan‐13
4‐Mar‐12140
06‐Sep‐11
29‐Nov‐127‐Mar‐13
15‐Jan‐13
FaisalJassimTradingCo.(L.L.C)Qatar
ChilledWaterPumps
FanCoilUnits(FCU),forHotelTower
14
98
1430‐May‐12
15992/3&15990
ACC‐MAR‐M‐G‐318
ACC‐MAR‐M‐G‐183
15720/2&15810/9
ACC‐MAR‐M‐H‐184
15720/2&15810/8
30‐Jun‐11
03‐Sep‐11
19‐Oct‐12
28‐Jun‐12
112
14
14 100
14 4‐Apr‐1211‐Sep‐12
18
16
15 M
M
19
17
M
M
M GRILLES&DIFFUSER
15993ACC‐MAR‐M‐G‐149 PlateHeatExchanger
FanCoilUnits(FCU),forOfficeTower&Podium
31‐Dec‐12 12‐Feb‐13
5‐Jun‐12
14‐Nov‐12
FaisalJassimTradingCo.(LLC)Qatar
25‐Nov‐11
30‐Jun‐11
Mekar
BetaInd.LLC.
30‐May‐12
98
Mekar
10‐Feb‐13
ProjectManager: HPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContractor: ArabtecConstructionCo.
MEPContractor: EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
durationRev.
RequiredonSitedateasperApproved
BaselineRev5Programme
ApprovalCutOffdate
DateSubmittedtoACG(Actual)
ApprovalRequiredBy
DateofReturn
DeliveryDate
Specs.Ref.Discipline SubmittalNo.Subcontractor/
Supplier
PurchaseOrder
DateofSubmittal(Planned)
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE
LONGLEADITEMS
Description
StatusCodeDateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
SlNo.Remarks
(LL:LongLeadItems)DateRequired
onSite
EFECO QATAR
00 4‐Dec‐11 6‐Jun‐12 20‐Jun‐12 5‐Jul‐12 C
01 20‐Aug‐12 11‐Aug‐12 25‐Aug‐12 25‐Aug‐12 C
02 21‐Sep‐12 24‐Sep‐12 8‐Oct‐12
21 M ACC‐MAR‐M‐G‐317 00 ‐ AirSeparatorforChilledWaterSystemQatarInternationalTradingCo.WLL
10‐Dec‐11 10‐Dec‐11 12‐Apr‐12 26‐Apr‐12 2‐May‐12 A 17‐Jul‐12 14 105 LPO#1818 23‐May‐12 13‐Feb‐12 29‐Oct‐12 20‐Sep‐12 13‐Nov‐12
00 18‐Jul‐12 17‐Jul‐12 31‐Jul‐12 6‐Aug‐12 C
01 5‐Sep‐12 6‐Sep‐12 20‐Sep‐12 10‐Oct‐12 C
02 20‐Oct‐12
23 E 00 ‐ HVSwitchgear/11KVInstallationworks ENAContractor 2‐Apr‐13 17‐Apr‐13
Installationonly,ByKahramaaApprovedContractorafterReceiptofIFCDrawing&11KVScheme&awaitingreplytoletterref#TT‐3.6.3001‐244dated31.01.12
00 12‐Jul‐11 3‐Nov‐11 17‐Nov‐11 4‐Dec‐11 C
01 25‐Jul‐12 7‐Jul‐12 21‐Jul‐12 31‐Jul‐12 C
02 19‐Sep‐12
00 18‐Jun‐12 24‐Jun‐12 8‐Jul‐12 1‐Aug‐12 C
01 19‐Sep‐12 2‐Oct‐12 16‐Oct‐12
00 29‐Feb‐12 29‐Feb‐12 14‐Mar‐12 1‐Apr‐12 C
01 11‐Apr‐12 9‐May‐12 23‐May‐12 25‐Jun‐12 C
02 30‐Jul‐12 21‐Jul‐12 4‐Aug‐12 22‐Aug‐12 C
03 10‐Sep‐12 12‐Sep‐12 26‐Sep‐12 2‐Oct‐12 C
04 12‐Oct‐12
00 29‐Feb‐12 29‐Feb‐12 14‐Mar‐12 1‐Apr‐12 C
01 11‐Apr‐12 9‐May‐12 23‐May‐12 5‐Jul‐12 C
02 30‐Jul‐12 21‐Jul‐12 4‐Aug‐12 22‐Aug‐12 C
03 10‐Sep‐12 12‐Sep‐12 26‐Sep‐12 2‐Oct‐12 C
04 12‐Oct‐12
120
28‐Nov‐12
10‐Feb‐138‐May‐12 25‐Feb‐1315‐Feb‐13
InternationalEngineeringSupplies
VentilationFans(ExcludingCarPark&KitchenVentilationFANS)
ACC‐MAR‐M‐G‐291
ACC‐MAR‐M‐P‐338M
ACC‐MAR‐M‐G‐269
UL/FMFirePumpSet(1000GPM@290BAR)
QatarTechnicalServices
UL/FMFirePumpSet750GPM@260PSIM
15830/12,14&1
6
27 1681415‐Sep‐1220‐Oct‐11QatarTechnical
ServicesACC‐MAR‐M‐G‐292M
25
16‐Mar‐1311‐May‐131‐Mar‐1320‐Oct‐12
2615‐Sep‐12
12‐Jul‐12
16‐Aug‐12
14‐Oct‐12
14
14
24 M
20 M PressurizationUnit&ExpansionTanks
22 MEKARAirHandlingUnits(AHU)&FreshAirHandlingUnits
15720/1&15810/8
ACC‐MAR‐M‐G‐350M
14 168
120
ACC‐MAR‐M‐G‐171
‐ 15‐May‐12
20‐Oct‐11
140
12‐Jul‐11
12‐Jul‐11
04‐Dec‐11
28‐Jul‐11
CARPARKVENTILATIONSYSTEM
105
13‐Aug‐12International
EngineeringSupplies14
14FaisalJassimTrading
Co.(LLC)Qatar
11‐May‐13
25‐Dec‐12
9‐Feb‐13
1‐Mar‐13
07‐Jul‐12
20‐Oct‐12
07‐Jul‐12
10‐Dec‐12 24‐Feb‐13
28‐Nov‐12
16‐Mar‐13
18‐Mar‐13 13‐Dec‐12
13‐Dec‐12
ProjectManageHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracto ArabtecConstructionCo.
MEPContractorEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
00 10‐Jul‐11 14‐Jun‐11 28‐Jun‐11 26‐Jun‐11 C
01 6‐Jul‐11 11‐Jul‐11 25‐Jul‐11 20‐Aug‐11 B
02 30‐Aug‐11 6‐Sep‐11 20‐Sep‐11 9‐Oct‐11 B
03 19‐Oct‐11 23‐Nov‐11 7‐Dec‐11 17‐Dec‐11 B
04 27‐Dec‐11 15‐May‐12 29‐May‐12 18‐Jun‐12 C
05 30‐Jul‐12 25‐Jul‐12 8‐Aug‐12 27‐Aug‐12 C
06Unicorn‐AlMehrab
Trading20‐Sep‐12 7‐Oct‐12 21‐Oct‐12
1 GICableTraysandLaddersE16/24‐26ACC‐MAR‐E‐G‐100‐AE
MaterialonSite(75%)
Alternateproposal
8‐Mar‐12 15‐May‐12Materialon
Site
SlNo. Discipline SubmittalNo. Rev. Specs.Ref.
UnitechQatarforBldg.Co.Materials
DateRequiredonSite
Description Subcontractor/Supplier
DeliveryDate
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
MATERIALINSIDETHESHAFT
DateofSubmittal(Planned)
ApprovalCutOffdate Remarks(LL:LongLeadItems)
ApprovalRequiredBy
TiscoElectricalSuppliesDivisionDoha,Qatar
StatusCodeDate
SubmittedtoACG(Actual)
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
durationDateofReturn
PurchaseOrder
LPONo.1529
RequiredonSitedateasperApproved
BaselineRev5Programme
10‐Jul‐11 10‐Dec‐11
EFECO QATAR
00 10‐Jul‐11 14‐Jun‐11 28‐Jun‐11 26‐Jun‐11 C
01 6‐Jul‐11 11‐Jul‐11 25‐Jul‐11 20‐Aug‐11 B
02 30‐Aug‐11 6‐Sep‐11 20‐Sep‐11 9‐Oct‐11 C
03 19‐Oct‐11 23‐Nov‐11 7‐Dec‐11 21‐Dec‐11 D
04 31‐Dec‐11 31‐Jan‐12 14‐Feb‐12 14‐Mar‐12 C
05 24‐Mar‐12 3‐Jun‐12 17‐Jun‐12 25‐Jun‐12 C
06 25‐Jul‐12 18‐Jul‐12 1‐Aug‐12 27.08.12 B
3 M ACC‐MAR‐M‐G‐073 00 15060/3 BlackSteelChilled&CondenserWaterPipes EconostoMideastB.V 21‐May‐11 21‐May‐11 21‐May‐11 4‐Jun‐11 24‐May‐11 ALPONo.823LPONo.1875Rev.1
6‐Aug‐1205‐June‐12
10‐Dec‐11 24‐Aug‐12Materialon
SiteMaterialonSite
00 24‐May‐11 6‐Jun‐11 20‐Jun‐11 18‐Jun‐11 C
01 28‐Jun‐11 9‐Jul‐11 23‐Jul‐11 8‐Aug‐11 A
5 M ACC‐MAR‐M‐G‐091 00 15060/3 CHWButtWeldedFittings EconostoMideastB.V 16‐Jul‐11 5‐Jun‐11 19‐Jun‐11 18‐Jun‐11 ALPONo.1915LPONo.2027
17‐Jun‐1225‐Jul‐12
MaterialonSite
MaterialsonSitePartialDeliveryasperSiteCondition
M ACC‐MAR‐M‐G‐092Materialon
Site10‐Dec‐11
ACC‐MAR‐E‐G‐100‐B
Al‐MehrabTrading&ContractingCo
E E16/26‐27 LPONo.2197561411‐Jun‐122
4 15060/3 CHWThreadedPipeFittings
G.ICableTrunking&Accessories 5‐Aug‐12 4‐Dec‐1216‐Sep‐12 20‐Aug‐12 RequisitionNo.03083dtd11.09.12
UnitechQatarforBldg.Co.Materials
NAFFCOQatar 24‐May‐11
16‐Jul‐11
10‐Dec‐11
10‐Dec‐11
LPONo.988,STV,LPONo.2018
29‐Sep‐1124‐Jul‐12
10‐Jul‐11
MaterialonSite(95%)NewReq.No.5582dtd17.07.12,
06321dtd07.10.12
00 13‐Jun‐11 24‐Jul‐11 7‐Aug‐11 20‐Aug‐11 C
01 30‐Aug‐11 5‐Sep‐11 19‐Sep‐11 22‐Oct‐11 A
7 M ACC‐MAR‐M‐G‐093 00 ‐ ThreadedRods&AccessoriesUnitechQatarforBldg.
Co.Materials13‐Jun‐11 13‐Jun‐11 6‐Jun‐11 20‐Jun‐11 18‐Jun‐11 A
LPONo.716LPONo.991
4‐Jul‐1102‐Oct‐11
20‐Oct‐11Materialon
SiteMaterialOnSite
00 21‐Jun‐11 15‐May‐11 29‐May‐11 28‐May‐11 C
01 7‐Jun‐11 19‐Jun‐11 3‐Jul‐11 7‐Jul‐11 A
9 M ACC‐MAR‐M‐G‐069 00 ‐ RubberInsertsforCHWPipeClamps HiraLLC 21‐Jul‐11 21‐Jul‐11 15‐May‐11 29‐May‐11 28‐May‐11 A
LPONo.1011LPONo.1010LPONo.1923LPONo.2100
4‐Oct‐1125‐Oct‐1103‐Jul‐1214‐Aug‐12
10‐Dec‐11Materialon
SiteMaterialOnSite
NewRequisitionNo.0598dtd23.08.12
00 28‐Jun‐11 3‐Jul‐11 17‐Jul‐11 16‐Jul‐11 C
01 26‐Jul‐11 5‐Sep‐11 19‐Sep‐11 29‐Sep‐11 C
02 9‐Oct‐11 7‐Dec‐11 21‐Dec‐11 26‐Dec‐11 C
03 5‐Jan‐12 26‐Mar‐12 9‐Apr‐12 15‐Apr‐12 B
11 M ACC‐MAR‐M‐G‐126 00 15810/6&10 G.IDuctSheetsQad‐NetManufacturing
FactoryLLC30‐Jul‐11 30‐Jul‐11 8‐Aug‐11 22‐Aug‐11 9‐Oct‐11 A
LPONo.1214LPONo.1905
26‐Nov‐1114‐Jun‐12
10‐Dec‐11 20‐Jun‐12 13‐Jun‐12 5‐Jul‐12MaterialOnSite(5%)
NewRequisitionNo.06315dtd29.09.12
17‐Jul‐12 1‐Aug‐12MaterialOnSite(20%)
PartialDeliveryasperSiteCondition10 M ACC‐MAR‐M‐G‐104 15260/1,4&7 ChilledWater(CHW)PipeInsulation
MaterialOnSite
MaterialonSite
10‐Dec‐018 M ACC‐MAR‐M‐G‐068 ‐PipeSupportandHangersforAirConditioningWorks
HiraLLCLPONo.1118LPONo.2147
MaterialOnSiteMaterialon
Site
03‐Oct‐1101‐Aug‐1217‐Sep‐12
LPONo.1008,LPONo.2059,LPO
No.22046 M ACC‐MAR‐M‐G‐113 ‐ ConcreteAnchors MettalicMaterialsLLC
MiddleEastMerchants,DohaQatar
21‐Jun‐11
28‐Jun‐11
13‐Jun‐11
25‐Oct‐1126‐Aug‐12
LPONo.1862
25‐Nov‐11
03‐June‐12 20‐Jan‐12 17‐Jul‐12
00 1‐Sep‐11 7‐Jul‐11 21‐Jul‐11 14‐Aug‐11 B
01 24‐Aug‐11 23‐Oct‐11 6‐Nov‐11 21‐Nov‐11 B
02 1‐Dec‐11 22‐May‐12 5‐Jun‐12 5‐Jul‐12 B
00 23‐Oct‐11 12‐Oct‐11 26‐Oct‐11 15‐Nov‐11 C
01 25‐Nov‐11 27‐Oct‐11 10‐Nov‐11 2‐Jan‐12 C
00 18‐Jul‐11 28‐Jul‐11 11‐Aug‐11 9‐Oct‐11 B
00 13‐Oct‐12 13‐Oct‐12 27‐Oct‐12
00 17‐Sep‐11 19‐Nov‐11 3‐Dec‐11 21‐Dec‐11 C
01 31‐Dec‐11 26‐Feb‐12 11‐Mar‐12 14‐Mar‐12 C
14 Materialonsite(50%)Materialon
Site10‐Jan‐12
15260/1,4,5&6
ACC‐MAR‐M‐G‐120M23‐Nov‐1116‐Sep‐1206‐Oct‐12
LPONo.1215LPONo.2200LPONo.2293
18‐Jul‐11MiddleEastMerchantsDuctInsulation
15100/10 3‐Dec‐12BasedonreceivedrevisedIFCdrawingdated
28.04.12,materialsubmittalprocess
15‐Dec‐1230‐Nov‐1207‐Jul‐1213 M ACC‐SCAR‐M‐G‐015 15820/12 KitchenExhaustDuctArabianSpecializedMaterialsCompany
25‐Jul‐12Willbesubmittedcomplyingbasedon
revisedIFCdrawing(RequisitionNo.06313&6316dtd29.09.12)
23‐Nov‐1210‐Jul‐121‐Sep‐1112 M ACC‐MAR‐M‐G‐106 15810/21 FireRatingDuct
ACC‐MAR‐M‐G‐178M15 FlexiblePipeConnector&ExpansionJoints 16‐Dec‐12LeminarAir
Conditioning Co.WLL18‐Nov‐12
AlMoayyedInt'lGroup
23‐Oct‐11
70
14 10‐Dec‐11
1410‐Sep‐12
45
7‐Jul‐1217‐Sep‐12
27‐May‐12
02 24‐Mar‐12 14‐May‐12 28‐May‐12 1‐Jul‐12 C restarted.ConditioningCo.WLL
Page 12 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManageHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracto ArabtecConstructionCo.
MEPContractorEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
SlNo. Discipline SubmittalNo. Rev. Specs.Ref.DateRequired
onSiteDescription Subcontractor/Supplier
DeliveryDate
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
MATERIALINSIDETHESHAFT
DateofSubmittal(Planned)
ApprovalCutOffdate Remarks(LL:LongLeadItems)
ApprovalRequiredBy
StatusCodeDate
SubmittedtoACG(Actual)
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
durationDateofReturn
PurchaseOrder RequiredonSitedateasperApproved
BaselineRev5Programme
EFECO QATAR
03 30‐Jul‐12 31‐Jul‐12 14‐Aug‐12 22‐Aug‐12 C
04 25‐Sep‐12
00 2‐Jul‐11 3‐Nov‐11 17‐Nov‐11 2‐Jan‐12 C
01 12‐Jan‐12 24‐Mar‐12 7‐Apr‐12 12‐Apr‐12 C
02 12‐Jan‐12 17‐May‐12 31‐May‐12 1‐Jul‐12 C
03 30‐Jul‐12 1‐Aug‐12 15‐Aug‐12 27‐Aug‐12 B
11‐Jun‐12
BestFlowTradingQatarWLL
9816 M ACC‐MAR‐M‐G‐17315100/1‐9&
20ChilledWaterValves 16‐Sep‐12 15‐Jan‐13 1‐Oct‐12
PartialDeliveryasperSiteConditionCommentneedstobediscussedwith
consultant&tobeagreed.(RequisitionNo.06315dated29.09.12)
14 20‐Jan‐1202‐Jul‐11
03 30 Jul 12 1 Aug 12 15 Aug 12 27 Aug 12 B
01 9‐Dec‐11 2‐Feb‐12 16‐Feb‐12 21‐Feb‐12 C
ACC‐MAR‐M‐G‐168 02 FireDampers Qad‐Net 2‐Mar‐12 29‐Feb‐12 14‐Mar‐12 24‐Mar‐12 C
03 3‐Apr‐12 31‐Mar‐12 14‐Apr‐12 12‐Apr‐12 B
00 31‐Oct‐11 1‐Nov‐11 15‐Nov‐11 29‐Nov‐11 C
01 9‐Dec‐11 5‐Feb‐12 19‐Feb‐12 11‐Mar‐12 B
02 21‐Mar‐12 17‐Apr‐12 1‐May‐12 2‐May‐12 B
00AccessDoors/Panels(NonFireRated)
15‐Nov‐11 1‐Nov‐11 15‐Nov‐11 29‐Nov‐11 C
01 9‐Dec‐11 4‐Feb‐12 18‐Feb‐12 21‐Feb‐12 C
02 2‐Mar‐12 12‐Mar‐12 26‐Mar‐12 1‐Apr‐12 B
20 M 00 15020 Paint JOTUN 28‐Jul‐11 5‐Sep‐12 8‐Sep‐12 22‐Sep‐12 10‐Jan‐12 15‐Aug‐12 30‐Aug‐12RequisitionNo.4133&4134dtd06.10.12
(forFFPipes)
10‐Jan‐12 31‐Jul‐12 15‐Aug‐12ACC‐MAR‐M‐G‐170 15820/5 Qad‐Net
AccessDoors
23‐Nov‐1219 M 4517‐Jun‐12
MaterialonSite
MaterialonSiteRequisitionNo.5660dtd28.05.12Requisitionno.6309dtd23.09.12
14‐May‐1202‐Oct‐12
10‐Dec‐1118 M ACC‐MAR‐M‐G‐16915820/10&15810/5
VolumeControlDampers Qad‐Net
17 15‐Aug‐12MaterialonSite
Requisitionno.6309dtd23.09.1231‐Jul‐12
03‐Jun‐1202‐Oct‐12
LPONo.1860LPO2269
M
LPONo.1777LPO2269
14
31‐Oct‐11
31‐Oct‐11
10‐Dec‐11
15‐Nov‐11
21 M ACC‐MAR‐M‐G‐036 00UPVCPipesandFittings(BelowGround)
13‐Mar‐11 14‐Mar‐11 28‐Mar‐11 24‐Mar‐11 ALPO#340LPO#382LPO#413LPO#1488
02‐Apr‐1112‐Apr‐1120‐Apr‐1125‐Feb‐12
ImmediateMaterialon
SiteMaterialsonSite
RequisitionNo:4061Date:20.02.12
00 5‐May‐11 5‐May‐11 19‐May‐11 10‐May‐11 B
01 20‐May‐11 15‐May‐11 29‐May‐11 24‐May‐11 A
23 M ACC‐MAR‐M‐G‐085 00 15060/5&6UPVCPipesandFittings(AboveGround)
HepworthPMEQatarW.L.L
30‐Apr‐11 30‐Apr‐11 1‐Jun‐11 15‐Jun‐11 18‐Jun‐11 BLPONo.757LPONo.2033LPONo.2104
16‐Aug‐1128‐Jul‐1215‐Aug‐12
15‐Sep‐11Materialon
SiteMaterialsonsite(20%)
RequisitionNo.4099&4100dtd12.08.12
M ACC‐MAR‐M‐G‐391 00 15060/5&6 DrainagePipes&Fittings‐HDPE Aqazone 6‐Oct‐12 6‐Oct‐12 20‐Oct‐12
00 10‐Apr‐11 12‐Apr‐11 26‐Apr‐11 28‐Apr‐11 C
01 2‐May‐11 2‐May‐11 16‐May‐11 10‐May‐11 A
25 M ACC‐MAR‐M‐G‐070 00 UPVCPressurePipes&Fittings‐BS3505HepworthPMEQatar
W.L.L18‐May‐11 2‐May‐11 16‐May‐11 28‐May‐11 A
LPONo.382LPONo.2214
12‐Apr‐1118‐Sep‐12
ImmediateMaterialon
SiteMaterialsonSite
00 28‐Jul‐11 08‐Aug‐11 22‐Aug‐11 29‐Sep‐11 C
01 9‐Oct‐11 13‐Oct‐11 27‐Oct‐11 15‐Dec‐11 C
02 25‐Dec‐11 29‐Feb‐12 14‐Mar‐12 1‐Apr‐12 C
MaterialsonSite
15‐Apr‐11
MaterialonSite
ATADInternationalGeneralTrading
CosmoplastIndustrialCo.LLC
15‐Apr‐11
24 M ACC‐MAR‐M‐G‐053
15060/5&6
UPVCPressurePipes&FittingsMaterialon
SiteMaterialsonSite
RequisitionNo.5726dtd08.10.12
2‐Jul‐11
HepworthPMEQatarW.L.L
LPONo.69922 M ACC‐MAR‐M‐G‐063 Immediate
15060/5&6
UPVCPipesandFittings(BelowGroundtoCoverlessthan110mmsize)
25‐Jun‐12 5‐Dec‐12
13‐Mar‐11
10‐Apr‐11
03 1‐Jul‐12 1‐Jul‐12 15‐Jul‐12 25‐Jul‐12 C
04 21‐Jul‐12 22‐Jul‐12 05‐Aug‐12 9‐Aug‐12 C
05 9‐Sep‐12 9‐Sep‐12 23‐Sep‐12 25‐Sep‐12 A
LPO2118LPONo.2207LPONo.2228LPONo.2229
16‐Aug‐1217‐Sep‐1220‐Sep‐1220‐Sep‐12
MaterialonSite(75%)RequisitionNo.5733dtd09.10.12
27 M ACC‐MAR‐M‐G‐066 00 ‐‐‐‐ PipeSuports&Hangers‐HorizontalSupports HiraLLC 13‐May‐11 13‐May‐11 15‐May‐11 29‐May‐11 24‐May‐11 ALPONo.1010LPONo.1011
10‐Sep‐11Materialson
SiteMaterialonSite
28 M ACC‐MAR‐M‐G‐156 00 15100 PressureReducingValvesAl‐MunasibBuildingMaterialTradingLLC.
Sharjah08‐Dec‐11 8‐Dec‐11 5‐Oct‐11 19‐Oct‐11 29‐Nov‐11 B 18‐Jul‐12 14 75 LPONo.1893 12‐Jun‐12 04‐Jun‐12 30‐Sep‐12 23‐Sep‐12 15‐Oct‐12
00 15‐Aug‐11 3‐Nov‐11 17‐Nov‐11 17‐Dec‐11 C
01 27‐Dec‐11 24‐Jan‐12 7‐Feb‐12 27‐Feb‐12 B
02 9‐Oct‐12 9‐Oct‐12 23‐Oct‐12
00 8‐Jul‐11 10‐Sep‐11 24‐Sep‐11 29‐Sep‐11 C
MaterialsonSite(10%)BestFlowTradingQatar
WLLLPONo.1892
26
1‐Oct‐1216‐Sep‐1215100
10‐Dec‐11
20‐Jan‐12ACC‐MAR‐M‐G‐172M29 Valves(PlumbingValves)
PexPipes&Fittings‐‐‐ACC‐MAR‐M‐G‐125M
MetcoQatar
5614
12‐Jun‐12
10‐Jul‐121‐May‐1228‐Jul‐11
15‐Aug‐11
00 8‐Jul‐11 10‐Sep‐11 24‐Sep‐11 29‐Sep‐11 CInsulationCalculationResubmittedon
15‐Sep‐1215260 08‐Jul‐11ACC‐MAR‐M‐G‐141JerseyEngineering&
9‐Nov‐1231‐Aug‐1211‐Aug‐1230 M Hot Water Pipe Insulation 14 21 10‐Jan‐12
Page 13 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManageHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracto ArabtecConstructionCo.
MEPContractorEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
SlNo. Discipline SubmittalNo. Rev. Specs.Ref.DateRequired
onSiteDescription Subcontractor/Supplier
DeliveryDate
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
MATERIALINSIDETHESHAFT
DateofSubmittal(Planned)
ApprovalCutOffdate Remarks(LL:LongLeadItems)
ApprovalRequiredBy
StatusCodeDate
SubmittedtoACG(Actual)
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
ProcurementLongLeadDuration
HeadofficeLPOrelease/Order
durationDateofReturn
PurchaseOrder RequiredonSitedateasperApproved
BaselineRev5Programme
EFECO QATAR
01 20‐Sep‐12
31 M ACC‐MAR‐M‐G‐107 00 15260 CondensateDrainPipeInsulationAerodyneCooling
System18‐Aug‐11 18‐Aug‐11 7‐Jul‐11 21‐Jul‐11 31‐Jul‐11 A LPONo.1670 15‐Apr‐12 10‐Jan‐12 22‐Jul‐12
MaterialsonSite
32 M ACC‐MAR‐M‐G‐099 00 15060 GIPipeSleeves EconostoMideastB.V 22‐Jun‐11 22‐Jun‐11 14‐Jun‐11 28‐Jun‐11 29‐Jun‐11 BLPO#721,STVLPO#1659,LPO#1968
5‐Jul‐1109‐Apr‐1210‐Jul‐12
2weeks 10‐Jul‐11Materialson
SiteMaterialsonSite
(NewRequisitionNo.06311dtd29.09.12)
33 M ACC‐MAR‐M‐G‐067 00 15310 PipeSupportsandHangersforFireFighting HiraLLC 16‐May‐11 16‐May‐11 15‐May‐11 29‐May‐11 24‐May‐11 A
LPONo.781LPO1824R1LPO2102R1
19‐July‐1123‐Aug‐1223‐Aug‐12
1‐Dec‐11
3‐Aug‐11 26.09.11Materialson
Site
MaterialsonSite
00 21‐May‐11 2‐Jun‐11 16‐Jun‐11 5‐Jun‐11 C
01 15‐Jun‐11 1‐Oct‐11 15‐Oct‐11 15‐Nov‐11 C
16.08.12.Awaitingconsultantsapproval15‐Sep‐1215260 08‐Jul‐11ACC‐MAR‐M‐G‐141
TradingCo.9‐Nov‐1231‐Aug‐1211‐Aug‐1230 M HotWaterPipeInsulation 14 21 10‐Jan‐12
02 25‐Nov‐11 26‐Nov‐11 10‐Dec‐11 25‐Dec‐11 C
03 4‐Jan‐12 31‐Dec‐11 14‐Jan‐12 2‐Jan‐12 C
04 12‐Jan‐12 1‐Mar‐12 15‐Mar‐12 24‐Mar‐12 C
05 3‐Apr‐12 1‐Apr‐12 15‐Apr‐12 12‐Apr‐12 C
06 22‐Apr‐12 7‐May‐12 21‐May‐12 22‐May‐12 C
07 Surya‐PetrofacQatar 1‐Jun‐12 6‐Jun‐12 20‐Jun‐12 5‐Jul‐12 ALPONo.1918
LPONo.1928LPONo.1979
19‐Jun‐1230‐Jun‐1212‐Jul‐12
31‐Jul‐12 10‐Jul‐12 15‐Aug‐12MaterialsonSite
(70%)
35 M ACC‐MAR‐M‐G‐273 00 15310 FireProtectionSystemPipesforRisers Surya‐PetrofacQatar 21‐May‐11 12‐Jun‐12 12‐Jun‐12 26‐Jun‐12 22‐Jul‐12 A 24‐May‐12 14 84 LPONo.2036 29‐Jul‐12 10‐Dec‐11 15‐Aug‐12 5‐Nov‐12 30‐Aug‐12
00 24‐May‐11 5‐Jun‐11 19‐Jun‐11 18‐Jun‐11 C
01 28‐Jun‐11 3‐Oct‐11 17‐Oct‐11 15‐Nov‐11 C
02 25‐Nov‐11 28‐Nov‐11 12‐Dec‐11 24‐Dec‐11 C
03 8‐Dec‐11 3‐Jan‐12 17‐Jan‐12 22‐May‐12 C
MaterialsonSite(50%)RequisitionNo.04132dtd01.10.12
15‐Aug‐1231‐Jul‐12NAFFCOQatar
EconostoQatar
21‐May‐11
LPONo.201224‐May‐1115310M ACC‐MAR‐M‐G‐089 ThreadedFittings
FireProtectionSystemPipes15310ACC‐MAR‐M‐G‐088M34
36 22‐Jul‐12
10‐Dec‐11
20‐Oct‐11
04 1‐Jun‐12 30‐May‐12 13‐Jun‐12 1‐Jul‐12 A
37 M ACC‐MAR‐M‐G‐090 00 15310 GroovedFittings NAFFCOQatar 24‐May‐11 24‐May‐11 5‐Jun‐11 19‐Jun‐11 18‐Jun‐11 BLPONo.789LPONo.2067
31‐Jul‐1105‐Aug‐12
25‐Oct‐11 1‐Jul‐12Materialon
SiteRequisitionNO.04131dtd01.10.12
00 30‐Nov‐11 6‐Sep‐11 20‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 8‐Nov‐11 22‐Nov‐11 29‐Nov‐11 C
02 15‐Aug‐12 4‐Aug‐12 18‐Aug‐12 13‐Aug‐12 C
25‐Sep‐12
00 10‐Nov‐11 11‐Sep‐11 25‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 13‐Oct‐11 27‐Oct‐11 29‐Nov‐11 C
02 9‐Dec‐11 15‐Jan‐12 29‐Jan‐12 7‐Feb‐12 A
40 M ACC‐MAR‐M‐G‐190 00Angle/ChannelsforSupports(MSAngleHotDipGalvanized50x50x5mm)
Tissco 29‐Nov‐11 29‐Nov‐11 13‐Dec‐11 24‐Dec‐11 ALPONo.1207LPONO.2159LPONo.2160
22‐Nov‐1129‐Aug‐1229‐Aug‐12
6‐Jan‐12Materialon
SiteMaterialsonSite
RequisitionNo.6320dtd02.10.12
00 25‐Aug‐12 25‐Aug‐12 8‐Sep‐12 2‐Oct‐12 C
12 Oct 12M41 TisscoTisscoMSAngle/Channels‐ACC‐MAR‐M‐G‐360
AsperAIFC,Qtychanged.AwaitedconfirmationACG
30‐Sep‐12
NAFFCOQatar
NAFFCOQatar 22‐Jan‐13 15‐Oct‐12
30‐Sep‐12 6‐Feb‐13 15‐Oct‐12
15310 Pressurereducingvalve
ChubbFire
GateValve15310/1.13
18‐Jun‐1210‐Nov‐11
1051430‐Sep‐11
39 M ACC‐MAR‐M‐G‐143
38 ACC‐MAR‐M‐G‐139M
105
18‐Jun‐12
20‐Oct‐1214
20‐Jan‐12
12‐Oct‐12
00 20‐May‐12 21‐May‐12 4‐Jun‐12 5‐Jun‐12 C
01 15‐Jun‐12 20‐Jun‐12 4‐Jul‐12 22‐Jul‐12 C
02 28‐Jul‐12 24‐Jul‐12 7‐Aug‐12 27‐Aug‐12 B
00 23‐May‐12 23‐May‐12 6‐Jun‐12 18‐Jun‐12 C
01 28‐Jun‐12 19‐Jun‐12 3‐Jul‐12 22‐Jul‐12 C
02 28‐Jul‐12 24‐Jul‐12 7‐Aug‐12 22‐Aug‐12 B
00 5‐Jul‐12 5‐Jul‐12 19‐Jul‐12 1‐Aug‐12 C
01 13‐Aug‐12 13‐Aug‐12 27‐Aug‐12 30‐Aug‐12 C
02 NextEngineering 19‐Sep‐12 22‐Sep‐12 6‐Oct‐12
MaterialsonSite
03‐Jul‐1219‐Jun‐12 30‐Sep‐12
GlassCloth
LPONo.1921VapourBarrier
42
EquipmentTrading&ContractingCo.
ACC‐MAR‐M‐G‐239M
44
BuildWellTradingCo.LLC
ACC‐MAR‐M‐G‐261
MCopperPipes&FittingsforHotWaterSupplyRiserPiping(TowerA&TowerB)
ACC‐MAR‐M‐G‐347
43 M
AerodyneCoolingSystem
MaterialsonSite
1‐Jul‐1230‐Sep‐12
24‐Dec‐1226‐Sep‐12 14 75
LPONo.1922LPONo.2291
19‐Jun‐1204‐Oct‐12
Page 14 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracArabtecConstructionCo.
MEPContrac EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
00 18‐Mar‐11 17‐Mar‐11 31‐Mar‐11 24‐Mar‐11 B
01 9‐Apr‐11 9‐Apr‐11 23‐Apr‐11 28‐Apr‐11 C
02 30‐Apr‐11 30‐Apr‐11 14‐May‐11 14‐May‐11 A
ACC‐MAR‐E‐G‐058 00JaidahMotors&TradingCo.‐Doha,
Qatar28‐Apr‐11 28‐Apr‐11 12‐May‐11 09‐May‐11 A
LPONO.401LPO#1670
LPONo.2083LPONo.2154
7‐May‐1115‐Apr‐1208‐Aug‐1228‐Aug‐12
Materialsonsite(95%)RequisitionNo.3082dtd28.08.12
00 18‐Jun‐11 30‐May‐11 13‐Jun‐11 05‐Jun‐11 C
01 15‐Jun‐11 11‐Jun‐11 25‐Jun‐11 26‐Jun‐11 C
02 6‐Jul‐11 20‐Aug‐11 3‐Sep‐11 9‐Oct‐11 C
MaterialonSite
Materialonsite
MaterialonSite
MaterialsonSite
2 E ACC‐MAR‐E‐G‐080 E16/23‐24 G.IConduits&AccessoriesTiscoElectricalSuppliesDivisionDoha,Qatar
LPONo.1454
SlNo.
LPONo.056STVNo.451‐STVNo.452STVNo.
049
30‐Oct‐1118‐Apr‐1117‐Apr‐112‐Apr‐11
DeliveryDateDateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
ApprovalRequiredBy
1 E
ACC‐MAR‐E‐G‐040
E16/23‐24 PVCConduits&Accessories
ConstructionMaterialServices&TradingCo.
(CMS)
DateRequiredonSite
Remarks(LL:LongLeadItems)
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
MATERIALABOVEFALSECEILING
HeadofficeLPOrelease/Orderduration
isciplin SubmittalNo. Rev. Specs.Ref. DescriptionSubcontractor/
Supplier
12‐June‐12
ProcurementLongLeadDuration
16‐Feb‐12 10‐Dec‐11
ApprovalCutOffdate
RequiredonSitedateasperApproved
BaselineRev5Programme
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
18‐Mar‐11
18‐Jun‐11
EFECO QATAR
03 19‐Oct‐11 17‐Oct‐11 31‐Oct‐11 21‐Nov‐11 B
3 E ACC‐MAR‐E‐G‐093 00 E16/24‐27 Hangers&SupportsUnitechQatarforBldg.
Co.Materials06‐Jul‐11 6‐Jul‐11 6‐Jun‐11 20‐Jun‐11 18‐Jun‐11 A
LPONo.716LPONo.991
4‐Jul‐1102‐Oct‐11
30‐Nov‐11Materialon
SiteMaterialonSite
00 15‐Jun‐11 22‐May‐11 5‐Jun‐11 5‐Jun‐11 C
01 15‐Jun‐11 11‐Jun‐11 25‐Jun‐11 26‐Jun‐11 C
02 6‐Jul‐11 11‐Jul‐11 25‐Jul‐11 24‐Sep‐11 C
03 4‐Oct‐11 5‐Oct‐11 19‐Oct‐11 29‐Nov‐11 B
00 5‐Jul‐11 20‐Aug‐11 3‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 17‐Oct‐11 31‐Oct‐11 21‐Nov‐11 B
00 20‐Nov‐11 14‐Aug‐11 28‐Aug‐11 9‐Oct‐11 C
01 19‐Oct‐11 14‐Nov‐11 28‐Nov‐11 17‐Dec‐11 C
02 27‐Dec‐11 5‐Jan‐12 19‐Jan‐12 24‐Jan‐12 B
03 3‐Feb‐12 4‐Feb‐12 18‐Feb‐12 11‐Mar‐12 A
00 18‐Jun‐11 28‐Jul‐11 11‐Aug‐11 29‐Sep‐11 C
01 9‐Oct‐11 10‐Oct‐11 24‐Oct‐11 15‐Nov‐11 C
6 E ACC‐MAR‐E‐G‐130 E16/37‐38 Isolators/DisconnectingSwitches PartialDeliveryasperSiteConditions18‐Dec‐12 22‐Jan‐13 2‐Jan‐13
MaterialsonSite
MaterialsonSite
MaterialonSite
MaterialonSite
5 E ACC‐MAR‐E‐G‐131 ‐PVCCoatedG.I.FlexibleConduits&Accessories
TiscoElectricalSuppliesDivisionDoha,Qatar
14‐Jun‐12
4 E ACC‐MAR‐E‐G‐074 E16/28‐30 HeatResistantFlexibleCables AlfanarEnergyCo.
5‐Sep‐12 14Gazzaoui&Partners
QatarWLL15‐Mar‐1220‐Nov‐11
12‐June‐12
16‐Feb‐12
16‐Feb‐12
105
16‐Feb‐12
LPONo.1261 11‐Dec‐11
LPONo.1453
15‐Jun‐11
05‐Jul‐11
02 25‐Nov‐11 20‐Nov‐11 4‐Dec‐11 11‐Dec‐11 C
03 21‐Dec‐11 21‐Dec‐11 4‐Jan‐12 2‐Jan‐12 C
04 12‐Jan‐12 21‐Jan‐12 4‐Feb‐12 7‐Feb‐12 C
05 17‐Feb‐12 25‐Feb‐12 10‐Mar‐12 14‐Mar‐12 C
06 30‐Aug‐12 30‐Aug‐12 13‐Sep‐12 30‐Sep‐12 C
00 7‐Sep‐11 3‐Aug‐11 17‐Aug‐11 15‐Sep‐11 B
01 25‐Sep‐11 9‐Nov‐11 23‐Nov‐11 11‐Dec‐11 B
02 21‐Dec‐11 7‐Jan‐12 21‐Jan‐12 18‐Jan‐12 B
9 M ACC‐MAR‐M‐G‐247 00 15820/8 FireRatedFlexibleDuctconnectorEquipmentTrading&
ContractingCo.3‐Jan‐12 3‐Jan‐12 17‐Jan‐12 24‐Jan‐12 A 4‐Oct‐12 14 45 17‐Nov‐12 21‐Nov‐12 2‐Dec‐12
00 12‐Sep‐11 28‐Jul‐11 11‐Aug‐11 21‐Sep‐11 C
01 1‐Oct‐11 24‐Oct‐11 7‐Nov‐11 15‐Nov‐11 C
02 25‐Nov‐11 1‐Feb‐12 15‐Feb‐12 7‐Apr‐12 A
00 8‐Apr‐12 8‐Apr‐12 22‐Apr‐12 2‐May‐12 C
EquipmentTrading&ContractingCo.
10 FlexibleductM ACC‐MAR‐M‐G‐121 15810/7&14 MaterialonSite100%
30‐Sep‐12 MaterialonSite100%
8‐Jun‐12
ChangetoG.IDucting5‐Jul‐12PALMiddleEast 18‐Jun‐11 7‐May‐12 24‐Nov‐12
MaterialonSite
8 M ACC‐MAR‐M‐G‐123 15820/8 FlexibleDuctConnectors
PreInsulatedDuctACC‐MAR‐M‐G‐119M7 ‐
QAD‐Net LPONo.1835 10‐Dec‐11
10‐Dec‐11
LPONo.1885 10‐Dec‐117‐Jun‐12
4514
07‐Sep‐11
27‐May‐1207‐Sep‐11
15‐Sep‐12
20‐Jun‐12
01 12‐May‐12 22‐May‐12 5‐Jun‐12 1‐Jul‐12 C
02 28‐Sep‐12 3‐Oct‐12 17‐Oct‐12
00 31‐Oct‐12 2‐May‐12 16‐May‐12 22‐May‐12 C
01 1‐Jun‐12 9‐Jun‐12 23‐Jun‐12 5‐Jul‐12 C
02 22‐Sep‐12 4‐Oct‐12 18‐Oct‐12
00 31‐Oct‐11 1‐Nov‐11 15‐Nov‐11 29‐Nov‐11 C
01 9‐Dec‐11 7‐Feb‐12 21‐Feb‐12 11‐Mar‐12 B
00 1‐Oct‐11 1‐Nov‐11 15‐Nov‐11 29‐Nov‐11 C
01 9‐Dec‐11 22‐Feb‐12 7‐Mar‐12 18‐Mar‐12 B
31‐Jul‐1212
18‐Dec‐1215‐Dec‐12
6‐Dec‐12
12 60
Qad‐Net
Qad‐Net
60
MAXELLIndustriesLLC
1,PObasedonrevisedIFCdrawingreceivedon28‐4‐2012isinprogress&basedshop
drawingapproval15‐Aug‐12ACC‐MAR‐M‐G‐16614 Qad‐Net 31‐Oct‐11M 6‐Dec‐1231‐Jul‐1215820/12 MotorizedFire/SmokeDamper
12 Non‐ReturnDamperACC‐MAR‐M‐G‐208M 15820/11
13 M ACC‐MAR‐M‐G‐165 15820/12 MotorizedSmokeDamper 15‐Aug‐12
1,PObasedonrevisedIFCdrawingreceivedon28‐4‐2012isinprogress&basedshop
drawingapproval
30‐Dec‐12
30‐Dec‐1217‐Nov‐1211 M ACC‐MAR‐M‐G‐316 ‐VariableAirVolume&ConstantAirValume(VAV&CAV)
15‐Dec‐12
10‐Dec‐11
19‐Oct‐12
4‐Jun‐12
4‐Jun‐12
31‐Oct‐11
31‐Oct‐11
28‐Mar‐1260
31‐Oct‐11 1‐Nov‐12 45 10‐Dec‐11
12
14
10‐Dec‐11
Page 15 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracArabtecConstructionCo.
MEPContrac EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
SlNo.
DeliveryDateDateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
ApprovalRequiredBy
DateRequiredonSite
Remarks(LL:LongLeadItems)
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
MATERIALABOVEFALSECEILING
HeadofficeLPOrelease/Orderduration
isciplin SubmittalNo. Rev. Specs.Ref. DescriptionSubcontractor/
SupplierProcurementLongLead
DurationApprovalCutOff
date
RequiredonSitedateasperApproved
BaselineRev5Programme
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
EFECO QATAR
00 MiddleEastMerchants 9‐Jan‐12 9‐Jan‐12 23‐Jan‐12 29‐Jan‐12 A
01 12‐Jul‐12 12‐Jul‐12 26‐Jul‐12 6‐Aug‐12 B
02 2‐Oct‐12 2‐Oct‐12 16‐Oct‐12
16 M 00 ‐ RefrigerantPipe&Accessories/CCU 26‐Dec‐11 30‐Sep‐12 18‐Feb‐13 14 75 23‐May‐12 3‐May‐13 11‐Feb‐13 18‐May‐13Waitingforfinalequipmentschedule/heatdissipationasperreplytoRFIref.no.
ACC‐RFI‐M‐G‐545Rev.0
17 M ACC‐MAR‐M‐G‐392 00 DX‐FreeStandingUnit‐QtelRoomALMalkiTrading&
Contracting3‐Oct‐12 3‐Oct‐12 17‐Oct‐12
00 5‐Oct‐11 19‐Oct‐11 2‐Nov‐11 15‐Nov‐11 B 6‐Aug‐12 14 56 30‐Sep‐12 4‐Dec‐12 15‐Oct‐12 Uponfinalizationofequipment
10‐Dec‐11 15‐Aug‐1214 31‐Jul‐12AcousticInsulation/Liner15810/4 28MiddleEastCooling&Insulation
4‐Jul‐12 6‐Dec‐1215
15010/28M
ACC‐MAR‐M‐G‐248M 28‐Jun‐11
LeminarAirConditioningCo.WLL
VibrationIsolatorsACC‐MAR‐M‐G‐16018 28‐Dec‐1105‐Oct‐11
01 27‐Sep‐12 27‐Sep‐12 11‐Oct‐12
00 29‐Nov‐11 8‐Oct‐11 22‐Oct‐11 15‐Nov‐11 C
01 25‐Nov‐11 4‐Apr‐12 18‐Apr‐12 24‐Apr‐12 C
02 4‐May‐12 23‐May‐12 6‐Jun‐12 5‐Jun‐12 C
03 15‐Jun‐12 30‐Jun‐12 14‐Jul‐12 22‐Jul‐12 B
00 22‐Jun‐11 08‐Aug‐11 22‐Aug‐11 29‐Sep‐11 C
01 9‐Oct‐11 13‐Oct‐11 27‐Oct‐11 4‐Dec‐11 C
02 14‐Dec‐11 30‐Jan‐12 13‐Feb‐12 18‐Mar‐12 C
03 28‐Mar‐12 31‐Mar‐12 14‐Apr‐12 7‐Apr‐12 B
04 14‐Jul‐12 14‐Jul‐12 28‐Jul‐12 6‐Aug‐12 B
05 8‐Oct‐12 8‐Oct‐12 22‐Oct‐12
02 14‐Dec‐11 31‐Jan‐12 14‐Feb‐12 18‐Mar‐12 C
20
1‐Aug‐128‐Dec‐1217‐Jul‐12
‐‐‐
22‐Jun‐11 19‐May‐12
16‐Jun‐12
30‐Dec‐12
12‐Jul‐12
15‐Dec‐12 18‐Dec‐12
MaterialsonSite(forMockUp)NewRequisition04086dtd13.06.12
(ForMock‐upTowerA)
MaterialsonSite
ATADInternationalGeneralTrading
M PPRPipeandFittings
TechnoGulfTradingWLL
PPRPipes&FittingsColdWaterSupplyHorizontalPipesforFloors
ACC‐MAR‐M‐G‐124A
19 M ACC‐MAR‐M‐G‐157
ACC‐MAR‐M‐G‐124
29‐Nov‐11 14
ATADInternationalGeneralTrading
M
707‐Oct‐12
g
LeminarAirConditioningCo.WLL
AutomaticAirVents15100/11
‐‐‐
PPRPipeandFittingsColdWaterSupplyHorizontalPipingFloors
26‐Apr‐12
10‐Dec‐11LPONo.1750
14
08‐May‐12
60
03 28‐Mar‐12 31‐Mar‐12 14‐Apr‐12 15‐Apr‐12 D
04 25‐Apr‐12 24‐Apr‐12 08‐May‐12 22‐May‐12 C
05 1‐Jun‐12 29‐May‐12 12‐Jun‐12 31‐Jul‐12 C
06 14‐Jul‐12 14‐Jul‐12 28‐Jul‐12 31‐Jul‐12 B
07 8‐Oct‐12 8‐Oct‐12 22‐Oct‐12
22 M ACC‐MAR‐M‐G‐351 00 ‐‐‐PPRPipes&FittingsColdWaterSupplyRiserPiping
TechnoGulfTradingWLL
14‐Jul‐12 14‐Jul‐12 28‐Jul‐12 31‐Jul‐12 C 19‐May‐12 14 60 17‐Jul‐12 9‐Dec‐12 1‐Aug‐12
00 13‐Dec‐11 30‐Apr‐12 14‐May‐12 22‐May‐12 C
01 15‐Jul‐12 4‐Jul‐12 18‐Jul‐12 22‐Jul‐12 B
00 10‐Jul‐12 11‐Jul‐12 25‐Jul‐12 1‐Aug‐12 C
01 12‐Aug‐12 14‐Aug‐12 28‐Aug‐12 27‐Aug‐12 C
02 11‐Sep‐12 10‐Sep‐12 24‐Sep‐12 30‐Sep‐12 C
ACC‐MAR‐M‐G‐124BM
15‐Jul‐128‐Dec‐1230‐Jun‐12
2‐May‐1221
27‐Aug‐1206‐Oct‐12
LPONo.2149LPONo.2265
Rejected
AlMunasibBldg.MaterialsTradingLLC
12‐Oct‐1228‐Jul‐12 30‐Sep‐12M
M24
23 15‐Oct‐12 RequisitionNo.04095dtd25.07.1209‐Jun‐12
ACC‐MAR‐M‐H‐346
WaterhammerArrestorsACC‐MAR‐M‐G‐336 LPONo.2038602‐Aug‐12
26‐Sep‐12
ATADInternationalGeneralTrading
PPRPipeandFittingsHotWaterSupplyHorizontalPipingFloors
‐‐‐
RichmondSustainableEng'gSolutionsInc.
15100
LowNoiseAboveGroundDrainagePipesFittingsforHorizontal(Apartment&GuestRooms)Tower‐B
TechnoGulfTradingWLL
13‐Dec‐11
19‐Dec‐12
14
6014
7014
03 10‐Oct‐12
00 27‐Nov‐11 6‐Sep‐11 20‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 26‐Oct‐11 9‐Nov‐11 15‐Nov‐11 B
02 25‐Nov‐11 15‐Jan‐12 29‐Jan‐12 26‐Jan‐12 C
03 28‐Jun‐12 24‐Jun‐12 8‐Jul‐12 22‐Jul‐12 C
04 22‐Sep‐12
00 30‐Nov‐11 27‐Aug‐11 10‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 13‐Oct‐11 27‐Oct‐11 29‐Nov‐11 C
02 9‐Dec‐11 15‐Jan‐12 29‐Jan‐12 7‐Feb‐12 A
00 16‐Dec‐11 11‐Sep‐11 25‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 8‐Nov‐11 22‐Nov‐11 29‐Nov‐11 C
02 9‐Dec‐11 15‐Jan‐12 29‐Jan‐12 7‐Feb‐12 C
03 ChubbFire 30‐Jun‐12 28‐Jun‐12 12‐Jul‐12 12‐Jul‐12 C
30‐Oct‐12
31‐Dec‐12 15‐Jan‐13
18‐Dec‐12 30‐Oct‐1270
14
14
25
CheckValve15310/1.14
ACC‐MAR‐M‐G‐133
ACC‐MAR‐M‐G‐145M
26 M
M ACC‐MAR‐M‐G‐140
15310
2‐Jan‐13
15‐Oct‐12
20‐Oct‐1216‐Dec‐11
15‐Oct‐12
27
13‐Dec‐12
NAFFCOQatar 30‐Sep‐11
NAFFCOQatar
ChubbFire
NAFFCOQatar
TamperSwitch
15310/1.21&31
20‐Jan‐1270
20‐Jan‐12
75
14
18‐Oct‐12
7‐Aug‐12
7‐Aug‐12
30‐Sep‐11ZoneControlValve(ButterflyValve,flowSwitch,Test&Drainvalve)
04 20‐Sep‐12
Page 16 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContracArabtecConstructionCo.
MEPContrac EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned
AnticipatedDate
Actual
SlNo.
DeliveryDateDateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
ApprovalRequiredBy
DateRequiredonSite
Remarks(LL:LongLeadItems)
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
MATERIALABOVEFALSECEILING
HeadofficeLPOrelease/Orderduration
isciplin SubmittalNo. Rev. Specs.Ref. DescriptionSubcontractor/
SupplierProcurementLongLead
DurationApprovalCutOff
date
RequiredonSitedateasperApproved
BaselineRev5Programme
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
EFECO QATAR
00 15‐Jul‐12 9‐Jul‐12 23‐Jul‐12 31‐Jul‐12 C
01 10‐Sep‐12 12‐Sep‐12 26‐Sep‐12 30‐Sep‐12 C
02 10‐Oct‐12
29 M ACC‐MAR‐M‐G‐114 00 StuckUpPins/AdhesiveHangerAerodyneCooling
SystemLLC23‐Jul‐11 23‐Jul‐11 6‐Aug‐11 20‐Aug‐11 A LPONo.1221 27‐Nov‐11 10‐Jan‐12
MaterialonSite
MaterialonSite
30 M ACC‐MAR‐M‐G‐111 00 AluminumTape Qad‐Net 21‐Jul‐11 21‐Jul‐11 4‐Aug‐11 20‐Aug‐11 A LPONo.1220 27‐Nov‐11 10‐Jan‐12Materialon
SiteMaterialonSite
31 M ACC‐MAR‐M‐G‐101 00 DuctAdhesives&Sealants(Ideal)EqiupmentTrading&ContractiongCo.
6‐Aug‐11 7‐Aug‐11 21‐Aug‐11 9‐Oct‐11 A LPONo.1295 21‐Dec‐11 10‐Jan‐12Materialon
SiteMaterialonSite
00EquipmentTrading&
ContractingCo.30‐Jul‐11 13‐Aug‐11 30‐Jul‐11 15‐Sep‐11 C
01Al‐KindiTradingEST.
25‐Sep‐11 6‐Oct‐11 20‐Oct‐11 15‐Nov‐11 A
MaterialonSite
MaterialonSite15‐Sep‐12
MaterialonSite
15310 ChubbFire1"TestandDrainValveACC‐MAR‐M‐G‐345M 31‐Aug‐1206‐Jun‐1228 03‐Nov‐11
ACC‐MAR‐M‐G‐12232 BandingStripCableTieM
01Doha‐Qatar
25 Sep 11 6 Oct 11 20 Oct 11 15 Nov 11 A
00Al‐Asheera
AdvertisingWLL23‐Nov‐11 23‐Nov‐11 7‐Dec‐11 17‐Dec‐11 C
01KakarasElect.&
SanitaryWareTrading31‐Jul‐12 22‐Jul‐12 5‐Aug‐12 13‐Aug‐12 C
02 12‐Sep‐12
1‐Oct‐1231‐Oct‐1216‐Sep‐1233 IdentificationTagsandNamePlates‐ACC‐MAR‐M‐G‐187M 201428‐Aug‐12
Page 17 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManageHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContractoArabtecConstructionCo.
MEPContracto EFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned AnticipatedDate Actual
1 E ACC‐MAR‐E‐G‐310 00 262726 WiringDevices Al‐Mashreq 15‐Dec‐11 15‐Dec‐11 2‐Apr‐12 16‐Apr‐12 2‐Apr‐12 B 31‐Oct‐12 14 70LPONo.2023LPONo.2116
06‐Aug‐1215‐Aug‐12
15‐Dec‐12 8‐Jan‐13 8‐Nov‐12 23‐Jan‐13 RequisitionNo.5611(forQatarCoolRoom)
00 7‐Aug‐12 7‐Aug‐12 21‐Aug‐12 22‐Aug‐12 C
01 8‐Sep‐12
3 M ACC‐MAR‐M‐G‐159 00 ‐ AluminiumCladding AlphaStarTrading 31‐Aug‐11 31‐Aug‐11 12‐Oct‐11 26‐Oct‐11 26‐Dec‐11 A 16‐Dec‐12 14 60 14‐Oct‐12 13‐Feb‐13 8‐Dec‐12 28‐Feb‐13 RequisitionNo:03988Date:17.03.12
4 M 00 15820/9 SoundAttenuatorforAHU'sandFans Seagull 09‐Jan‐12 30‐Sep‐12 8‐Oct‐12 22‐Oct‐12 17‐Jan‐13 14 60 06‐Jun‐12 17‐Mar‐13 13‐Dec‐12 1‐Apr‐13
5 M 00 15830/P‐166 SandTrapLouversforAHU 26‐Dec‐11 25‐Sep‐12 17‐Jan‐13 14 60 07‐Jul‐12 17‐Mar‐13 27‐Jan‐13 1‐Apr‐13
21‐Nov‐12E2 JaidahIndustrySupplyACC‐MAR‐E‐G‐359 CeilingRose 23‐Sep‐12 14
Subcontractor/Supplier
ApprovalRequiredBy
DateofReturn
StatusCode DeliveryDate
DateRequiredonSite
Remarks(LL:LongLeadItems)
ApprovalCutOffdateHeadofficeLPOrelease/Order
duration
ProcurementLongLeadDuration
RequiredonSitedateasperApproved
BaselineRev5Programme
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE
THIRDFIXMATERIAL
SlNo. Disciplin SubmittalNo. Rev. Specs.Ref. DescriptionDateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
PurchaseOrder
45
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
EFECO QATAR
00 10‐Sep‐11 31‐Dec‐11 14‐Jan‐12 5‐Jan‐12 C
01 20‐Jun‐12 17‐Jun‐12 1‐Jul‐12 22‐Jul‐12 C
02 30‐Sep‐12
00 15‐Nov‐11 20‐Sep‐11 4‐Oct‐11 9‐Oct‐11 C
01 19‐Oct‐11 30‐Jan‐12 13‐Feb‐12 11‐Mar‐12 C
02 21‐Mar‐12 13‐Jun‐12 27‐Jun‐12 22‐Jul‐12 C
03 29‐Jul‐12 1‐Aug‐12 15‐Aug‐12 27‐Aug‐12 C
04 15‐Sep‐12 6‐Sep‐12 20‐Sep‐12
00 6‐Sep‐12 6‐Sep‐12 20‐Sep‐12 19‐Sep‐12 C
30‐Sep‐12
M 00Sanitarywares&Accessories‐WCConcealedCistern+DualFlushPlate(TB‐Mock‐UpRoomOnly)
15‐May‐12 16‐May‐12 30‐May‐12 22‐May‐12 A LPONo.1952R2 6‐Aug‐12Materialson
site
PartialDeliveryasperSiteConditionsRequisitionNo.04087dtd20.06.12&
04093dtd21.07.12
9‐Dec‐1214‐Jan‐13
12‐Feb‐13
ParkingDrain 29‐Jan‐13
AlMunasibBldg.MaterialsTradingLLC
AlMunasibBldg.MaterialsTradingLLC
20‐Nov‐12
10‐Feb‐13
ACC‐MAR‐M‐G‐368
15440ACC‐MAR‐M‐H‐233HamadBinMohamad
Group Qatar
26‐Jan‐13
M
15482
RoofDrain15420
14
M
23‐Sep‐12
7
GrundfosGulfDistributionTransferPump/Filteration/BoosterPumps
15420ACC‐MAR‐M‐G‐151
6 M ACC‐MAR‐M‐G‐243
8
9
5614
10‐Sep‐11
15‐Nov‐11
15‐Nov‐11
20‐May‐12
07‐Jul‐12
01‐Jan‐13
126
M 01SanitaryWares&Accessories‐WCCisternInBuilt&Bidet&WashBasin‐TowerB
16‐Sep‐12 16‐Sep‐12 30‐Sep‐12 6‐Oct‐12 A
10 M ACC‐MAR‐M‐H‐244 01 15440SanitaryWares&Accessories‐WallMountedWC&Bidet(TB‐MockUpRoomOnly)
HamadBinMohamadGroup‐Qatar
15‐May‐12 16‐May‐12 30‐May‐12 22‐May‐12 A LPONo.1952R2 6‐Aug‐12Materialson
sitePartialDeliveryasperSiteConditionsRequisitionNo.04087dtd20.06.12&
d dACC‐MAR‐M‐G‐142A 02 15440 SanitaryWares&Accessories‐OfficeTower
HamadBinMohamadGroup‐Qatar
18‐Jan‐12 21‐Feb‐12 6‐Mar‐12 28‐Mar‐12 C
ACC‐MAR‐M‐G‐142A 03 15440 SanitaryWares(Mixers)TowerAHamadBinMohamadGroup‐Qatar
20‐Sep‐11 1‐Jul‐12 1‐Jul‐12 15‐Jul‐12 17‐Jul‐12 A 18‐Oct‐12 14 124 16‐Sep‐12
12 M ACC‐MAR‐M‐O‐342 00 15440 SanitaryWares‐TowerA(Offices)HamadBinMohamadGroup‐Qatar
2‐Jul‐12 2‐Jul‐12 16‐Jul‐12 25‐Jul‐12 B 11‐Feb‐13
00 28‐Jul‐12 28‐Jul‐12 11‐Aug‐12 9‐Aug‐12 C
01 25‐Sep‐12
00 30‐Jul‐12 30‐Jul‐12 13‐Aug‐12 9‐Aug‐12 C
01 25‐Sep‐12
15 M ACC‐MAR‐M‐H‐263 00 15440SanitaryWares‐BathTub(TB‐MockUpRoomOnly)
Al‐Futaim 26‐May‐12 27‐May‐12 10‐Jun‐12 5‐Jun‐12 B LPONo.1958R1 17‐Jul‐12 31‐Aug‐12 02‐01‐13 15‐Sep‐12PartialDeliveryasperSiteConditionsRequisitionNo.04091dtd15.07.12
00 BathRoomAccessories‐TBMockuponly 20‐Sep‐11 15‐May‐12 16‐May‐12 30‐May‐12 22‐May‐12 A
01 BathroomAccessories(TowerB) 20‐Sep‐11 16‐Sep‐12 16‐Sep‐12 30‐Sep‐12 10‐Oct‐12 B
00 15440ShowerRoomLinearChannelDrainforMockupOnly
15‐May‐12 15‐May‐12 29‐May‐12 6‐Jun‐12 ALPONo.1819LPONo.1934LPONo.
2134
22‐May‐1201‐Jul‐1222‐Aug‐12
30‐Sep‐12 8‐Jan‐13 15‐Oct‐12 MaterialonSite
h h l f
RequisitionNo.04084dtd28.06.12(ForMockuproomonly‐TowerA)
25‐Feb‐13 AfterMockUpapproval
25‐Feb‐13 AfterMockUpapproval
5‐Mar‐13
11‐Feb‐13 5‐Mar‐1318‐Feb‐13
ProtosTradingLLC
BathroomAccessories‐TowerA(ToiletTissueHolder,SoapDispenser&PaperTowelDispenser)
M
M
M14
15440
11 M
AlHamouriGroup
30‐Apr‐12
HamadBinMohamadGroup‐Qatar
15440
15440
Group‐Qatar
16
ACC‐MAR‐M‐O‐358
SanitaryWares‐TowerA(Offices)‐Wash&Basins&KitchenSinks
13
ACC‐MAR‐M‐H‐231
ACC‐MAR‐M‐G‐357
12414
18‐Oct‐12
17 ACC‐MAR‐M‐H‐232M AlbinaQatarLLC
30‐Oct‐11
30‐Oct‐11
16‐Sep‐12
16‐Sep‐12
16‐Sep‐1214
30‐Oct‐11
124 10‐Feb‐1318‐Feb‐13
16‐Sep‐1201 ShowerRoomLinearChannelDrainforTowerB 23‐Sep‐12 23‐Sep‐12 07‐Oct‐12
18 M ACC‐MAR‐M‐H‐333 00 15440 UnderCounterWashBasin‐TowerBHamadBinMohamad
Group26‐Apr‐12 26‐Apr‐12 10‐May‐12 12‐May‐12 A LPONo.1952R2 6‐Aug‐12 16‐Aug‐12
MaterialonSite
MaterialonSite
00 20‐Dec‐11 11‐Sep‐11 25‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 20‐Oct‐11 3‐Nov‐11 7‐Dec‐11 C
02 17‐Dec‐11 28‐Jan‐12 11‐Feb‐12 13‐Feb‐12 B
M 00 15310/1.22 SprinklerHeads‐Alternative ChubbFire 30‐Aug‐12 30‐Aug‐12 13‐Sep‐12 9‐Sep‐12 C
00 27‐Nov‐11 27‐Aug‐11 10‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 24‐Oct‐11 7‐Nov‐11 15‐Nov‐11 C
02 25‐Nov‐11 17‐Jan‐12 31‐Jan‐12 7‐Feb‐12 C
03 ChubbFire 22‐Sep‐12 18‐Sep‐12 2‐Oct‐12
00 30‐Jul‐12 18‐Jul‐12 1‐Aug‐12 6‐Aug‐12 C
15‐Sep‐12 9‐Sep‐12 23‐Sep‐12 4‐Oct‐12 B
00 15‐Nov‐11 27‐Aug‐11 10‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 22‐Oct‐11 5‐Nov‐11 15‐Nov‐11 A
16‐Jan‐13PortableFireExtinguishers
ChubbFire
12‐Jan‐13 31‐Jan‐13
16‐Jan‐13
22 M ACC‐MAR‐M‐G‐134 15310 FireBlanket
21 M ACC‐MAR‐M‐G‐354
19
20 M ACC‐MAR‐M‐G‐132 15310/1.28
M
31‐Jan‐1316‐Jan‐13 23‐Nov‐12
15310/1.32
NAFFCOQatar 4514
Airreleasevalve 28‐Dec‐12 31‐Jan‐1375
100ACC‐MAR‐M‐G‐146 15310/1.22
7514
14
3‐Dec‐12
3‐Nov‐12
143‐Nov‐12
NAFFCOQatar
20‐Dec‐11SprinklerHeads NAFFCOQatar
17‐Jan‐137‐Jan‐13
16‐Sep‐12
30‐Sep‐12
27‐Nov‐11
26‐Oct‐11
15‐Nov‐11 16‐Sep‐12
22‐Jan‐13
01‐Jan‐13
p
16‐Sep‐12
00 21‐May‐12 22‐May‐12 5‐Jun‐12 25‐Jun‐12 C
01 22‐Sep‐12M23 1‐Apr‐1320‐Dec‐1217‐Mar‐13DomesticPlateHeatExchanger 7‐Jan‐13 14 70ACC‐MAR‐M‐G‐240
FaisalJassimTradingCo
Page 18 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContra ArabtecConstructionCo.
MEPContracEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned AnticipatedDate Actual
00 7‐Mar‐11 7‐Mar‐11 21‐Mar‐11 24‐Mar‐11 B
01 3‐Apr‐11 9‐Apr‐11 23‐Apr‐11 28‐Apr‐11 B
02 8‐May‐11 4‐Jun‐11 18‐Jun‐11 26‐Jun‐11 A
2 E ACC‐MAR‐E‐G‐065 00 ‐ UPVCDuctsHepworthPMEQatar
W.L.L15‐Jul‐11 10‐May‐11 24‐May‐11 24‐May‐11 B
LPONo.723LPO#1198LPO#1640
LPO#1727LPO#1859
5‐Jul‐1120‐Nov‐1104‐Apr‐1230‐Apr‐1202‐June‐12
20‐Jul‐11Materialon
SiteMaterialsonSite
00 7‐Mar‐11 8‐Mar‐11 22‐Mar‐11 24‐Mar‐11 B
Materials on Site
15‐Mar‐1113‐Mar‐1122‐May‐1111‐Jun‐113 E ACC‐MAR‐E‐G‐022 E16 / 42‐46 Earthing & Lightning Protection System
10‐Apr‐11
Specs.Ref. Description
AlfanarElectricSystem‐Dubai,UAE
E16/37‐38 Materialsonsite(40%)
Remarks(LL:LongLeadItems)
isciplin SubmittalNo. Rev.Approval
RequiredBySubcontractor/
Supplier
E ACC‐MAR‐E‐G‐021 GIBackBoxes
DateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
RequiredonSitedateasperApproved
BaselineRev5Programme
DeliveryDate
SlNo.
1
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
OTHERMEPMATERIAL
ProcurementLongLeadDuration
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
MaterialonS
DateRequiredonSite
MaterialonSite
Trade House Qatar Co.
LPONo.293LPONo.289LPONo.523LPO No 609
LPONo.373
HeadofficeLPOrelease/Order
duration
07‐Mar‐11
15‐Jul‐11
07‐Mar‐11
ApprovalCutOffdate
01‐May‐11
30‐Apr‐11
EFECO QATAR
01 3‐Apr‐11 9‐Apr‐11 23‐Apr‐11 28‐Apr‐11 B
00 1‐Aug‐11 10‐Aug‐11 24‐Aug‐11 24‐Sep‐11 C
01 4‐Oct‐11 8‐Oct‐11 22‐Oct‐11 15‐Nov‐11 A
00 20‐Oct‐11 27‐Sep‐11 11‐Oct‐11 2‐Oct‐11 C
01 12‐Oct‐11 17‐Oct‐11 31‐Oct‐11 15‐Nov‐11 C
02 25‐Nov‐11 15‐Jan‐12 29‐Jan‐12 7‐Feb‐12 B
03 TradeHouseQatarCo. 17‐Feb‐12 13‐Feb‐12 27‐Feb‐12 11‐Mar‐12 A
00 15‐Jul‐11 14‐Jun‐11 28‐Jun‐11 26‐Jun‐11 C
01 4‐Jul‐11 4‐Jul‐11 18‐Jul‐11 14‐Aug‐11 C
02 24‐Aug‐11 27‐Aug‐11 10‐Sep‐11 9‐Oct‐11 B
03 19‐Oct‐11 25‐Mar‐12 8‐Apr‐12 17‐Apr‐12 C
PartialDeliveryasperSiteConditions1‐Oct‐1224‐Dec‐1216‐Sep‐12E
6
E16/47‐56FireDetection,BackGroundandVoiceEvacuationsystem,FireAlarm,FireTelephone&VASystem
75ACC‐MAR‐E‐G‐101 13‐May‐12Consolidated
EngineeringSystemsCo.
LPO#1771144‐Jul‐1215‐Jul‐11
14 7510‐Sep‐1220‐Oct‐115 E ACC‐MAR‐E‐G‐153 ‐ CableGlands&CableLugs
Al‐MehboobElectricalTradingLLC
23‐Nov‐12 23‐Dec‐12 8‐Dec‐12KAHRAMAAApprovaltoschematicdrawings
awaited
MaterialonSite(55%)01‐Aug‐11Materialon
Site4 E ACC‐MAR‐E‐G‐128 E16/28‐30 PVCInsulatedWires
DohaCables‐QatarLLC
LPONo.1281
MaterialsonSite11 Jun 1111‐July‐1118‐Oct‐1103‐Jul‐12
3 E ACC MAR E G 022 E16/42 46 Earthing&LightningProtectionSystemSite
TradeHouseQatarCo. LPONo.609LPONo.747LPONo.1073LPONo.1944
19‐Dec‐11
07 Mar 11 30 Apr 11
10‐Dec‐11
15‐Mar‐12
15‐Apr‐12
04 27‐Apr‐12 16‐May‐12 30‐May‐12 8‐Jul‐12 C
05 25‐Jul‐12 16‐Jul‐12 30‐Jul‐12 2‐Oct‐12 B
00FireAlarmSystemDevicesBackBox(Sample,Catalogue)
11‐Mar‐12 12‐Mar‐12 26‐Mar‐12 14‐Apr‐12 C
01 24‐Apr‐12 26‐Apr‐12 10‐May‐12 12‐May‐12 C
02 22‐May‐12 23‐May‐12 6‐Jun‐12 5‐Jun‐12 A
8 E ACC‐MAR‐E‐G‐388 00 E16/47‐56EmergencyCallCareSystemforDisableRoominHotelTower
CityElectricalFactor 26‐Sep‐12 26‐Sep‐12 10‐Oct‐12
00 10‐Jun‐11 7‐Jun‐11 21‐Jun‐11 26‐Jun‐11 C
01 6‐Jul‐11 21‐Jul‐11 4‐Aug‐11 21‐Sep‐11 B
02 1‐Oct‐11 1‐Oct‐11 15‐Oct‐11 15‐Nov‐11 B
03 25‐Nov‐11 27‐Nov‐11 11‐Dec‐11 24‐Dec‐11 A
00 15‐Feb‐12 15‐Feb‐12 29‐Feb‐12 11‐Mar‐12 C
FireAlarmSystemDevicesBackBox
CESCOW.L.L 26‐Feb‐12Materialon
Site
19‐Dec‐1124‐Jan‐12
MaterialonSite
MaterialsonSite
MaterialonSite(PartialQty)RequisitionNo:02641Date:19.01.12
4‐Dec‐11
FireResistantCables(FP200) CityElectricalFactorLPONo.1282LPONo.1391
8 E ACC‐MAR‐E‐G‐094 ‐
7 E ACC‐MAR‐E‐G‐302 E16/47‐56 LPONo.1244
01 21‐Mar‐12 29‐Mar‐12 12‐Apr‐12 12‐Apr‐12 C
02 31‐Jul‐12 26‐Jul‐12 9‐Aug‐12 13‐Aug‐12 C
03 22‐Sep‐12
00 15‐Jul‐11 15‐Apr‐12 29‐Apr‐12 22‐May‐12 C
01 1‐Jun‐12 17‐Jun‐12 1‐Jul‐12 11‐Jul‐12 C
02 6‐Sep‐12 12‐Sep‐12 26‐Sep‐12 2‐Oct‐12 C
03 12‐Oct‐12
00 15‐Sep‐12 16‐Sep‐12 30‐Sep‐12 30‐Sep‐12 C
01 10‐Oct‐12
00 8‐Sep‐12 8‐Sep‐12 22‐Sep‐12 30‐Sep‐12 C
01 10‐Oct‐12
00 15‐Aug‐11 28‐Apr‐12 12‐May‐12 21‐Jun‐12 C
8‐Dec‐1224‐Dec‐12
3‐Jan‐1316‐Jan‐13
CableGlandsFP200 CityElectricalFactor 23‐Nov‐12
ProcurementProcessrestartedafterrecevingIFCdrawingson28‐4‐2012
31‐Jan‐1325‐Dec‐1216‐Jan‐13263323ACC‐MAR‐E‐G‐321 CentralEmergencySystem 15‐Dec‐11
ACC‐MAR‐E‐G‐284
JBKControls
E 14 841‐Sep‐129
14
14
8414
3‐Nov‐12
25‐Oct‐12
15‐Jul‐11
10‐Nov‐11ProcurementProcessstartedafterrecevingIFC
drawingson28‐4‐201231‐Jan‐13
TEConnectivityTechnoQ
8‐Nov‐12ProcurementProcessrestartedafterreceving
IFCdrawingson28‐4‐201231‐Jan‐13G4SQatarWL
15‐Dec‐11
16‐Dec‐1216‐Jan‐1315‐Dec‐1115‐Aug‐11
E 75
ACC‐MAR‐E‐G‐380 E16/57‐66
12
E11Telephone&DataSystem/StructuredCablingSystem
70
10
CCTVSystemE16/69‐71ACC‐MAR‐E‐G‐370E
15 A 11
01 7‐Sep‐12 17‐Sep‐12 1‐Oct‐12 4‐Oct‐12 C 148‐Nov‐12AccessControlSystemE16/126‐127ACC‐MAR‐E‐G‐332E13ProcurementProcessrestartedafterreceving
IFCdrawingson28‐4‐201231‐Jan‐1315‐Dec‐1216‐Jan‐13
15‐Aug‐1115‐Dec‐1170G4SQatarWLL
Page 19 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContra ArabtecConstructionCo.
MEPContracEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned AnticipatedDate Actual
Specs.Ref. Description Remarks(LL:LongLeadItems)
isciplin SubmittalNo. Rev.Approval
RequiredBySubcontractor/
Supplier
DateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
RequiredonSitedateasperApproved
BaselineRev5Programme
DeliveryDate
SlNo.
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
OTHERMEPMATERIAL
ProcurementLongLeadDuration
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
DateRequiredonSite
HeadofficeLPOrelease/Order
durationApprovalCutOffdate
EFECO QATAR
02 14‐Oct‐12
14 E ACC‐MAR‐E‐G‐381 00E16/102‐121&
15950BuildingManagementSystem
Honeywell‐IntegraInt'l
05‐Sep‐11 18‐Sep‐12 18‐Sep‐12 2‐Oct‐12 25‐Oct‐12 14 84 15‐Dec‐11 16‐Jan‐13 3‐Jan‐13 31‐Jan‐13
15 E 00 E16/102‐121 ControlCablesforBMS 16‐Oct‐11 25‐Sep‐12 6‐Aug‐12 14 56 07‐Feb‐12 30‐Sep‐12 19‐Dec‐12 15‐Oct‐12BMScablestobesubmittedafterapprovalof
BMSsystem
16 E ACC‐MAR‐E‐G‐384 00 E16/102‐121 IPTVSystemsIkus‐ArgonGlobal
Contracting&Trading19‐Sep‐12 23‐Sep‐12 7‐Oct‐12 4‐Oct‐12 C 25‐Oct‐12 14 84 16‐Jan‐13 3‐Jan‐13 31‐Jan‐13
00 15‐Aug‐11 27‐Sep‐11 11‐Oct‐11 15‐Nov‐11 C
01 25‐Nov‐11 23‐Nov‐11 7‐Dec‐11 24‐Dec‐11 B
02 3 Jan 12 16 Jan 12 30 Jan 12 7 Feb 12 B
1‐Jan‐13E 17‐Jun‐13AirCraftwarninglightsACC‐MAR‐E‐G‐154 2‐Jul‐13Jan201329‐Mar‐12 01‐Jan‐1314 84Tectronics,Doha‐
Qatar‐ 26‐Mar‐1315‐Aug‐11 LPONo.162217
02 3‐Jan‐12 16‐Jan‐12 30‐Jan‐12 7‐Feb‐12 B
03 17‐Feb‐12 3‐Mar‐12 17‐Mar‐12 24‐Mar‐12 A
00 9‐Sep‐12 8‐Sep‐12 22‐Sep‐12 2‐Oct‐12 C
01 12‐Oct‐12
00HotelLock&EnergySavingDeviceforGuestRooms
1‐Oct‐11 25‐Apr‐12 9‐May‐12 5‐Jun‐12 C
01 12‐Jul‐12 12‐Jul‐12 26‐Jul‐12 6‐Aug‐12 C
02 20‐Sep‐12
00 1‐Oct‐11 28‐Apr‐12 12‐May‐12 5‐Jun‐12 C
01 25‐Sep‐12 29‐Sep‐12 13‐Oct‐12
00 16‐Apr‐12 17‐Apr‐12 1‐May‐12 12‐May‐12 C
01 5‐Aug‐12 1‐Aug‐12 15‐Aug‐12 22‐Aug‐12 C
2‐Jan‐1316‐Mar‐13
AirCurtain
E ACC‐MAR‐E‐G‐331
25‐May‐13M
G4SQatarWLL
9‐Jun‐136‐Dec‐12
ACC‐MAR‐M‐G‐330 31‐Mar‐13
98
31‐Mar‐1307‐Jul‐12
14
16‐Mar‐13 28‐Dec‐1220
21 ‐ACC‐MAR‐M‐G‐322CentralAir
ConditioningTrading&ServiceCo.
60
E
27‐Mar‐13
‐ Carparkmanagementsystem
‐
HotelLockingSystemforGuestRooms
18
15‐Dec‐1101‐Oct‐11
G4SQatarWLL
19 E
ACC‐MAR‐E‐G‐371 11‐Oct‐12
1‐Jan‐13
1‐Jan‐1301‐Oct‐11
15‐Sep‐11
14
14
7514
ZeroneTechnologies
75
31‐Jan‐1314‐Jan‐1316‐Jan‐1315‐Dec‐11LightingControlSystem‐
02 8‐Sep‐12
00 Qad‐Net 26‐Oct‐12 2‐May‐12 16‐May‐12 22‐May‐12 C
01 22‐Sep‐12
00 17‐Apr‐11 17‐Apr‐11 1‐May‐11 1‐May‐11 C
01 2‐Jun‐11 19‐Jun‐11 3‐Jul‐11 7‐Jul‐11 A
24 M ACC‐MAR‐M‐G‐179 00 15110 UPVC‐PuddleFlanges(forRetainingWalls)HepworthPMEQatar
W.L.L21‐Apr‐11 17‐Nov‐11 17‐Nov‐11 1‐Dec‐11 7‐Dec‐11 A
LPONo.1575LPONo.2155
18‐Mar‐1228‐Aug‐12
20‐Sep‐11Materialon
SiteMaterialsonSite
RequisitionNo.05708dtd23.08.12
00 20‐Dec‐11 24‐Jul‐11 7‐Aug‐11 20‐Aug‐11 C
01 30‐Aug‐11 23‐Oct‐11 6‐Nov‐11 7‐Dec‐11 C
02 17‐Dec‐11 29‐Dec‐11 12‐Jan‐12 3‐Apr‐12 B
00 20‐Dec‐11 28‐Jul‐11 11‐Aug‐11 29‐Sep‐11 C
01 9‐Oct‐11 24‐Oct‐11 7‐Nov‐11 4‐Dec‐11 A
23‐Dec‐1220‐May‐12
15110/3
13‐Mar‐13
ACC‐MAR‐E‐G‐20822 5‐Dec‐1230‐Apr‐13
MaterialsonSite
28‐Mar‐13
MaterialsonSite(100%)
RequisitionNo:04067Date:14.03.12
MaterialonSite
18‐Apr‐12
7529‐Dec‐12
LPO#1689AlMunasibBldg.
MaterialsTradingLLC
BuildWellTradingCo.LLC
M
10‐Aug‐11 20‐Sep‐11
14
23 M ACC‐MAR‐M‐G‐054 G.IPuddleFlangeforWaterTank QatarGalvanizingCo.
15‐May‐13
2weeksMaterialon
Site
23‐Mar‐12
14
PressureReliefDamper15820/14 17‐Mar‐13
25
26
M
ACC‐MAR‐M‐G‐118FloatValve(EquilibriumType)forGRPTank(sameasFVofFF)
ModulatingFloatValveforConcreteTank(sameasFVofFF)
M 15110/3
ACC‐MAR‐M‐G‐117
LPONo.846
26‐Oct‐11
17‐Apr‐11
20‐Dec‐11
45
00InterModelServices
Co.WLL9‐Nov‐11 30‐Oct‐11 13‐Nov‐11 29‐Nov‐11 C
01AlMuftahFiberglass
ProductsWLL27‐Jun‐12 11‐Jul‐12 25‐Jul‐12 1‐Aug‐12 C
02 25‐Sep‐12
00 29‐Aug‐11 21‐Feb‐12 6‐Mar‐12 24‐Mar‐12 C
01 20‐Jun‐12 19‐Jun‐12 3‐Jul‐12 22‐Jul‐12 C
02 2‐Sep‐12 13‐Aug‐12 27‐Aug‐12 27‐Aug‐12 C
03 30‐Sep‐12
M ACC‐MAR‐M‐G‐309 00 15420PumpHeadCalculationforSubmersiblePumps
2‐Apr‐12 3‐Apr‐12 17‐Apr‐12 24‐Apr‐12 B
00 17‐Sep‐11 17‐Nov‐11 1‐Dec‐11 25‐Dec‐11 C
13‐Mar‐1313‐Mar‐13
17‐Feb‐13
15110GRPwaterTank(PotableWaterStorageTank)
28‐Mar‐13
4‐Mar‐13Gazzaoui&Partners
QatarWLLSubmersiblePumps 29‐Aug‐11 98
14 140
ACC‐MAR‐M‐G‐287
M ACC‐MAR‐M‐G‐16427
28 M 20‐Jan‐1315420 1412‐Nov‐12
25‐Oct‐1209‐Nov‐11 31‐May‐12
07‐Jul‐12
Page 20 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContra ArabtecConstructionCo.
MEPContracEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned AnticipatedDate Actual
Specs.Ref. Description Remarks(LL:LongLeadItems)
isciplin SubmittalNo. Rev.Approval
RequiredBySubcontractor/
Supplier
DateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
RequiredonSitedateasperApproved
BaselineRev5Programme
DeliveryDate
SlNo.
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
OTHERMEPMATERIAL
ProcurementLongLeadDuration
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
DateRequiredonSite
HeadofficeLPOrelease/Order
durationApprovalCutOffdate
EFECO QATAR
01 4‐Jan‐12 21‐Feb‐12 6‐Mar‐12 20‐Mar‐12 C
02 30‐Mar‐12 17‐Apr‐12 1‐May‐12 12‐May‐12 C
03 22‐May‐12 31‐May‐12 14‐Jun‐12 5‐Jul‐12 C
04 15‐Sep‐12 27‐Sep‐12 11‐Oct‐12
30 M ACC‐MAR‐M‐G‐181 00 15420 FloorTrap/FloorDrain/CleanOutCoverHepworthPMEQatar
W.L.L10‐Dec‐11 17‐Nov‐11 1‐Dec‐11 4‐Dec‐11 A 21‐Dec‐12 14 60 10‐Jan‐12 18‐Feb‐13 8‐Dec‐12 5‐Mar‐13 RequisitionNo:04059Date:08.02.12
00 5‐Feb‐12 5‐Feb‐12 19‐Feb‐12 27‐Feb‐12 C
13‐Mar‐13 AwaitingRFIreplyMetito 3‐Feb‐13 28‐Mar‐1314ACC‐MAR‐M‐G‐180 WaterTreatment&SandFiltersM29 15482 11222‐Nov‐1217‐Sep‐11 31‐May‐12
01 26‐Jun‐12 18‐Jun‐12 2‐Jul‐12 22‐Jul‐12 C
02 29‐Jul‐12 26‐Jul‐12 9‐Aug‐12 30‐Aug‐12 C
03 19‐Sep‐12
00 5‐Feb‐12 5‐Feb‐12 19‐Feb‐12 27‐Feb‐12 C
01 26‐Jun‐12 18‐Jun‐12 2‐Jul‐12 31‐Jul‐12 C
02 25‐Sep‐12
00 2‐May‐12 2‐May‐12 16‐May‐12 22‐May‐12 C
01 30‐Jul‐12 13‐Aug‐12 27‐Aug‐12 4‐Sep‐12 C
02 19‐Sep‐12
34 M 00 15450 FuelSystem 30‐Jan‐12 30‐Sep‐12 2‐Jan‐13 14 75 20‐Oct‐12 17‐Mar‐13 24‐Dec‐12 1‐Apr‐13
5‐Mar‐1318‐Feb‐13
9‐Dec‐12 5‐Mar‐13
09‐12‐12
23‐Dec‐12
26‐Mar‐13
FloorCleanOutCover
ALBINAQatar
60
ACC‐MAR‐M‐H‐21633
ACC‐MAR‐M‐G‐255M
ALBINAQatarFloorDrainCover
ALBINAQatar
14 60 18‐Feb‐13
10‐Apr‐13FloorDrainCover‐TowerB
32
M
M31 ACC‐MAR‐M‐G‐254
15420
15420 21‐Dec‐12
21‐Dec‐12
26‐Jan‐13 14
14
60
y J p J p
35 M ACC‐MAR‐M‐G‐099 00 15060 GIPipeSleeves EconostoMideastB.V 22‐Jun‐11 14‐Jun‐11 28‐Jun‐11 29‐Jun‐11 BLPONo.721,
STV5‐Jul‐11 2weeks
MaterialonSite
MaterialsonSiteNewReq.05688dtd12.7.12
00 15‐Dec‐11 6‐Sep‐11 20‐Sep‐11 29‐Sep‐11 C
01 9‐Oct‐11 10‐Nov‐11 24‐Nov‐11 7‐Dec‐11 C
02 17‐Dec‐11 2‐Feb‐12 16‐Feb‐12 29‐Feb‐12 C
03 ChubbFire 30‐Sep‐12
00 22‐Dec‐11 3‐Sep‐11 17‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 28‐Nov‐11 12‐Dec‐11 25‐Dec‐11 C
02 4‐Jan‐12 31‐Jan‐12 14‐Feb‐12 29‐Feb‐12 C
03 ChubbFire 30‐Sep‐12
00 10‐Nov‐11 11‐Sep‐11 25‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 22‐Oct‐11 5‐Nov‐11 15‐Nov‐11 C
02 25‐Nov‐11 31‐Mar‐12 14‐Apr‐12 17‐Apr‐12 C30‐Mar‐13
26‐Dec‐12
26‐Dec‐12NAFFCOQatar
36
ACC‐MAR‐M‐G‐135M37 LandingValve
NAFFCOQatar
14NAFFCOQatar
60
7538 M 15310
AfterapprovalofSchematicDiagramDrawing10‐Jan‐1323‐Dec‐12
20‐Oct‐12
AfterapprovalofSchematicDiagramDrawing23‐Dec‐12
15‐Mar‐1310‐Nov‐11 31‐Dec‐12
22‐Dec‐11 20‐Jan‐12
10‐Jan‐13
23‐Dec‐12
16‐Sep‐1215310/1.26
ACC‐MAR‐M‐G‐144
ACC‐MAR‐M‐G‐138
SprinklerAlarmcheckvalve
FireHoseCabinet&Hose
15310/1.27
M 14 60
14
28‐Oct‐12
28‐Oct‐12
15‐Dec‐11
03 ChubbFire 27‐Apr‐12 9‐Jun‐12 23‐Jun‐12 5‐Jul‐12 B
00 16‐Sep‐12 16‐Sep‐12 30‐Sep‐12 30‐Sep‐12 C
01 10‐Oct‐12
00 3‐Jul‐12 3‐Jul‐12 17‐Jul‐12 1‐Aug‐12 C
01 15‐Sep‐12 12‐Sep‐12 26‐Sep‐12
00 13‐Nov‐11 3‐Sep‐11 17‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 20‐Nov‐11 4‐Dec‐11 4‐Dec‐11 C
02 ChubbFire 30‐Jul‐12 5‐Jul‐12 19‐Jul‐12 31‐Jul‐12 B
00 18‐Dec‐11 3‐Sep‐11 17‐Sep‐11 9‐Oct‐11 C
01 19‐Oct‐11 23‐Oct‐11 6‐Nov‐11 5‐Dec‐11 C
02 ChubbFire 30‐Jul‐12 18‐Jul‐12 1‐Aug‐12 6‐Aug‐12 C
03 25‐Sep‐12
28‐Dec‐12
2‐May‐13
60
17‐Apr‐13 23‐Dec‐1216‐Sep‐12
17‐Apr‐1316‐Sep‐12BreechingInlet&Cabinet
NAFFCOQatar
FireHydrant 18‐Dec‐11
ChubbFire
Strainer
15310/1.35ACC‐MAR‐M‐G‐137
ACC‐MAR‐M‐G‐343
M ACC‐MAR‐M‐G‐13641
42
NAFFCOQatar2‐May‐138‐Dec‐1217‐Feb‐1313‐Nov‐11
ACC‐MAR‐M‐G‐377
M
M
15310
21100040
M39
SupervisoryControlValve(ButterflyValveWithInternalSupervisorySwitch)
14 60
14 60
14
17‐Feb‐13
15‐Oct‐12
ChubbFire
00 20‐Jun‐12 18‐Jun‐02 2‐Jul‐02 22‐Jul‐12 C
Page 21 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ProjectManaHPM Discipline: ALL
Consultant: ACG Date: 13‐Oct‐12
MainContra ArabtecConstructionCo.
MEPContracEFECOQATARLLC
A B C D LPONo. LPODateDeliveryPeriodfromReceiptof
OrderPlanned AnticipatedDate Actual
Specs.Ref. Description Remarks(LL:LongLeadItems)
isciplin SubmittalNo. Rev.Approval
RequiredBySubcontractor/
Supplier
DateofSubmittal(Planned)
DateSubmittedtoACG(Actual)
RequiredonSitedateasperApproved
BaselineRev5Programme
DeliveryDate
SlNo.
TWINTOWERS‐WESTBAYDOHA,QATARMATERIALSUBMITTALREGISTER(MAR)&PROCUREMENTSCHEDULE‐
DateofReturn
StatusCode PurchaseOrder
OTHERMEPMATERIAL
ProcurementLongLeadDuration
DateofSubmittal(Planned)‐AsperapprovedBaselineRev5Programme
DateRequiredonSite
HeadofficeLPOrelease/Order
durationApprovalCutOffdate
EFECO QATAR
01 20‐Sep‐12 24‐Sep‐12 8‐Oct‐12 10‐Oct‐12 C
02 20‐Oct‐12
00 20‐Jun‐12 18‐Jun‐02 2‐Jul‐02 1‐Aug‐12 C
01 20‐Sep‐12 27‐Sep‐12 11‐Oct‐12
00 5‐May‐12 7‐May‐12 21‐May‐12 25‐Jul‐12 C
1‐Feb‐13154 22‐Mar‐1317‐Jan‐13FoamFireSuppressionSystemThompson's
SpecialtiesMiddleEast14FM‐20044 M ACC‐MAR‐M‐G‐278
ACC‐MAR‐M‐G‐277M43
17‐Aug‐12
16‐Dec‐11Thompson's
SpecialtiesMiddleEastCleanAgentFireSuppressionSystemComponents&Accessories
FM‐200 1541417‐Aug‐12 1‐Feb‐1322‐Mar‐1317‐Jan‐1320‐Oct‐12
y y y J
01 8‐Aug‐12 11‐Aug‐12 25‐Aug‐12 25‐Aug‐12 C
02 10‐Sep‐12 3‐Oct‐12 17‐Oct‐12
00 20‐Nov‐11 26‐Nov‐11 10‐Dec‐11 21‐Dec‐11 C
01 31‐Dec‐11 29‐Feb‐12 14‐Mar‐12 21‐Mar‐12 B
47 M 00 ‐ LPGSystem QatarGasGroup 26‐Sep‐12 14 100 18‐Jan‐13
M ACC‐SCAR‐M‐G‐028 00 Pre‐QualificationDocumentsforLPGSystem QatarGasGroup 23‐Jun‐12 23‐Jun‐12 07‐Jul‐12 22‐Jul‐12 B
08‐12‐12
26‐Jul‐127‐Jan‐13 LPONO.202914 70 1‐Apr‐13LeminarAir
ConditioningCo.WLL46 M ACC‐MAR‐M‐G‐188 15950
PressureGauge&Thermometers(ForHVACSystem)
17‐Mar‐13 19‐Oct‐12
AutomaticChemicalDosingSystem(ChilledWaterPumps)
VeoliaWaterSolution&Tech.
14M ACC‐MAR‐M‐G‐222 ‐45 6025‐09‐12
Page 22 of 106 TT, Weekly Report No. 86 As of 2012-10-20
ID Procurement schedule
Page 23 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Legend: Material Submittal is Delayed Legend: Discipline : Architectural
Consultant : Architectural Consulting Group PROCUREMENT SCHEDULE BY DEPA Material Submittal is less than 1 month from due date Run date : 22-Oct-12
Main Contractor : Arabtec Construction Co. PROJECT ID: 10001 LPO is delayed
LPO is less than 1 month from due date
LPO was issued
Material Deliviered on Site
A B C DPlanned LPO or L/C
DateActual LPO or L/C No.
and Date
Delivery Period from Receipt of
OrderPlanned Actual
A-1 FIT-OUT
A.1.1 FLOORING MATERIALS
A CARPET
0 Carpet for Corridor, All Corridor Hotel 10-Dec-11 7-Mar-12 24-Apr-12 25-Apr-12 A approved for mock-up only
1 Carpet for Corridor, All Corridor Hotelinitiated by
ACC on 15-May-12
17-May-12 11-Jun-12 13-Jun-12 A approved for mock-up only
2 Carpet for Corridor, Floor 4-26 17-Jun-12 19-Jun-12 30-Jun-12 2-Jul-12 BFAF was submitted (ACC-FAF-A-H- 041 rev.00) and approval received on 07-O f f
19-Feb-1317-Sep-13Dhurrie,
DHR12, FlaxenBolyuWalltracts 301 Div 9, 24 3-Oct-11 29-Jun-12 29-Jul-12 180 18-Aug-13
Sl No.Lead Time
(days)
Total Float (Planned Start Date - Planned
Delivery)
Discipline Submittal No.Activity IDSpecs.
Ref.Rev.
ACC-MAR-A-G-211Architectural
Revise plan Work Start
DateRemarks (LL : Long Lead Items)
Date of Return from Arabtec
Date of Submittal (Planned)
As per revised program
Approval Required By
Status Code Purchase Order Delivery Date
Description
Date Submitted to
ACG(Actual)
Sample / Brand Name
Subcontrator/Supplier
Date of Submittal (Planned)
As per base line
Specified Supplier by
Designer
Date Submitted to
Arabtec(Actual)
Date of Return from ACG
2 Carpet for Corridor, Floor 4 26 17 Jun 12 19 Jun 12 30 Jun 12 2 Jul 12 BOct-12 for 27 to 46th floors only.
0 Carpet for Rooms, Hotel Rooms 13-Feb-12 13-Mar-12 25-Apr-12 25-Apr-12 A approved for mock-up only
1 Carpet for Rooms, Hotel Guest Areainitiated by
ACC on 15-May 12
15-May-12 14-Jun-12 16-Jun-12 A approved for mock-up only
2 Carpet for Rooms, Floor 4-26 17-Jun-12 19-Jun-12 27-Jun-12 28-Jun-12 B
0 Carpet Underlay, Hotel Tower Interfloor EstillonTredaire
Technics 519-Apr-12 21-Apr-12 29-Apr-12 30-Apr-12 C to follow specified, alternative is not accepted
1IFC Spec
SheetCarpet Underlay, Hotel Tower Estillon Estillon Black Pearl 24-Apr-12 25-Apr-12 29-Apr-12 30-Apr-12 A
4 Architectural Carpet for Junior Suites, 4-26 17-Sep-13 20-Dec-11 21-Nov-12 05-Dec-12 19-Feb-13 180 18-Aug-13 30 Physical sample is required from the Interior Designer
5 Architectural Carpet for Exe. Junior Suites 7-Dec-13 21-Feb-12 12-Dec-12 26-Dec-12 11-May-13 180 7-Nov-13 30
6 Architectural Carpet for Executive Suites 21-Dec-13 21-Feb-12 26-Dec-12 09-Jan-13 25-May-13 180 21-Nov-13 30
7 Architectural Carpet for Apartments 24-Dec-13 11-Mar-12 29-Dec-12 12-Jan-13 28-May-13 180 24-Nov-13 30
8 Architectural Carpet for Grand Suite 13-Feb-14 22-May-12 19-Jan-13 02-Feb-13 18-Jul-13 180 14-Jan-14 30 no specifications
9 Architectural Carpet for Meeting Rooms 17-Dec-13 26-Apr-12 22-Dec-12 05-Jan-13 21-Apr-13 180 18-Oct-13 60
10 Architectural Carpet for Chill Out Room 17-Dec-13 26-Apr-12 22-Dec-12 05-Jan-13 21-Apr-13 180 18-Oct-13 60
11 Architectural Carpet for Business Centre 17-Dec-13 26-Apr-12 22-Dec-12 05-Jan-13 21-Apr-13 180 18-Oct-13 60
180 18-Aug-132 Architectural ACC-MAR-A-G-193 17-Sep-13 29-Jul-12 19-Feb-13 3029-Jun-123-Oct-11Walltracts BolyuVisual Order,
VOB14
3 Architectural ACC-MAR-A-G-323 17-Sep-13 3-Oct-11 29-Jun-12 29-Jul-12 19-Feb-13 180 18-Aug-13 30
12 Architectural Carpet for Levantine Café , All Day Dining 17-Dec-13 11-Apr-12 22-Dec-12 05-Jan-13 21-Apr-13 180 18-Oct-13 60
13 Architectural Carpet for VIP Lounge & Bride Room 8-Jan-14 26-Apr-12 13-Jan-13 27-Jan-13 13-May-13 180 9-Nov-13 60 no specifications
14 Architectural Carpet for Ballroom & Prefunction 17-Dec-13 26-Apr-12 21-Jan-13 04-Feb-13 21-Apr-13 180 18-Oct-13 60 no specifications
B TILES (FLOOR)
0 Floor and Wall Tile, Hote Rooms 12-Feb-12 7-Mar-12 23-Apr-12 24-Apr-12 A
1
Floor and Wall Tile, Brera for Guest Rooms, Junior Suites, Exe. Junior Suites & Executive Suites (*suites as per RFI response) & ACC-FAF-A-H-047 rev.00 - approved for L4-31
initiated by ACC on 15-
May-1215-May-12 22-May-12 22-May-12 A
16 Architectural ACC-MAR-A-G-383 0 Floor & Wall Porcelain Tiles for Apartments 19-May-13 Alfalux 14-Nov-11 15-Oct-12 23-Sep-12 25-Sep-12 30-Oct-12 6-Oct-12 8-Oct-12 A 11-Dec-12 75 24-Feb-13 84
17 Architectural Ceramic Tiles for Grand Suite 9-Jul-13 14-Dec-11 11-Dec-12 25-Dec-12 10-Jan-13 150 9-Jun-13 30 no specifications
18 Architectural Ceramic Tiles for Executive Lounge 3-Sep-13 14-Jan-12 6-Jan-13 20-Jan-13 5-Feb-13 150 5-Jul-13 60 no specifications
19 Architectural Ceramic Tiles for Public Toilets at 2nd Floor 3-Nov-13 14-Jan-12 8-Mar-13 22-Mar-13 7-Apr-13 150 4-Sep-13 60 no specifications and drawings
20 Architectural Ceramic Tiles for VIP Lounge & Bride Room 22-Aug-13 14-Jan-12 25-Dec-12 08-Jan-13 24-Jan-13 150 23-Jun-13 60 no specifications
21 Architectural Ceramic Tiles for Health Club 22-Sep-13 14-Dec-11 25-Jan-13 08-Feb-13 24-Feb-13 150 24-Jul-13 60 no specifications and drawings
ACC-MAR-A-G-195 0 Adhesive for Tiles, General All Building TadmurNitotile GP,
F13-Feb-12 7-Mar-12 28-Apr-12 29-Apr-12 C
15 Architectural ACC-MAR-A-G-199 Div 9, 15 20-Oct-12 18-Jul-13 23-Jun-12 80 6-Oct-12 Delivered on site26-Sep-12 1410-Jul-12Jamco Trading & Contracting
Ceramiche Caesar
Nordic Stone, Brera in
14-Aug-11 3-Jul-12
, gFosroc
8 p 9 p
ACC-MAR-A-G-195 1 Adhesive for Tiles, Hotel TadmurNitotille XS,
Fosroc6-May-12 6-May-12 14-May-12 15-May-12 A hotel, FOH areas
ACC-MAR-A-G-195 2 Adhesive for Tiles TadmurNitotille XS,
Fosroc
initiated by ACC on 15-
May 12
15-May-12 11-Jun-12 13-Jun-12 B Hotel, only ID areas
22 ACC-MAR-A-G-364 0 Adhesive for Tiles ( option 2) BASF Mastertile 21 1-Sep-12 1-Sep-12 2-Oct-12 3-Oct-12 B
0 17-Feb-12 7-Mar-12 9-Apr-12 24-Apr-12 B
1 1-May-12 2-May-12 12-May-12 12-May-12 A
19-Oct-12
10-Oct-12Architectural 24-Oct-12 N/A 14-Aug-11 21-Aug-12 08-Sep-12 09-Oct-12Div 9, 18.1
10 19-Oct-12 5
21
Tadmur N/ANitotille Grout,
Fosroc23 Architectural ACC-MAR-A-G-194 Grout for Tiles
Div 9, 18.2.1
24-Oct-12 14-Aug-11 21-Aug-12 08-Sep-12 09-Oct-12 1010-Oct-12 5
Page 1 of 5 Form#13006PS- Rev.0
Page 24 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Legend: Material Submittal is Delayed Legend: Discipline : Architectural
Consultant : Architectural Consulting Group PROCUREMENT SCHEDULE BY DEPA Material Submittal is less than 1 month from due date Run date : 22-Oct-12
Main Contractor : Arabtec Construction Co. PROJECT ID: 10001 LPO is delayed
LPO is less than 1 month from due date
LPO was issued
Material Deliviered on Site
A B C DPlanned LPO or L/C
DateActual LPO or L/C No.
and Date
Delivery Period from Receipt of
OrderPlanned Actual
Sl No.Lead Time
(days)
Total Float (Planned Start Date - Planned
Delivery)
Discipline Submittal No.Activity IDSpecs.
Ref.Rev.
Revise plan Work Start
DateRemarks (LL : Long Lead Items)
Date of Return from Arabtec
Date of Submittal (Planned)
As per revised program
Approval Required By
Status Code Purchase Order Delivery Date
Description
Date Submitted to
ACG(Actual)
Sample / Brand Name
Subcontrator/Supplier
Date of Submittal (Planned)
As per base line
Specified Supplier by
Designer
Date Submitted to
Arabtec(Actual)
Date of Return from ACG
D STONE
0 Marble for Guest Rooms 7-May-12 9-May-12 21-May-12 22-May-12 A
1 Marble for Guest Roomsinitiated by
ACC on 15-May-12
15-May-12 7-Jun-12 9-Jun-12 A
2 Marble for Guest Rooms 18-Jun-12 19-Jun-12 1-Jul-12 2-Jul-12 B
3Marble for Guest Rooms, Floor 4-26 (Door threshold, vanity counter top & bathtub top & bidet back wall coping)
21-Jul-12 28-Jul-12 23-Aug-12 27-Aug-12 B
20mm thick Marble for Guest Bathrooms,
30 12-Jan-1314-Aug-11 18-Jul-12 4-Aug-1213-Mar-13IFC Spec
Sheet24 Architectural ACC-MAR-A-G-221 13-Dec-12 60
4Apartment Kitchens & Window Coping, Floor 4-47 (Door threshold, vanity counter top & bathtub top & bidet back wall coping)
Stone Gallery N/A Dallia 23-Sep-12 25-Sep-12 1-Oct-12 3-Oct-12 B
25 Architectural Marble for Grand Suite 9-Jul-13 14-Mar-12 11-Dec-12 25-Dec-12 10-Jan-13 150 9-Jun-13 30 no specifications
26 ArchitecturalMarble for Lift Lobby at 1st & 2nd Basement, Ground, 1st, 2nd & 3-47 Floor
07-Feb-13 14-Nov-11 10-Sep-12 24-Sep-12 10-Oct-12 90 8-Jan-13 30 Consultant to provide the design and specs for lift lobby
27 Architectural Marble for Break Out & Foyer 10-Oct-13 14-Nov-11 12-Feb-13 26-Feb-13 14-Mar-13 150 11-Aug-13 60
28 Architectural Marble for Asian Restaurant 14-Nov-13 14-Nov-11 19-Mar-13 02-Apr-13 18-Apr-13 150 15-Sep-13 60
29 Architectural Marble for Main Lobby & Deli Shop 17-Oct-13 14-Dec-11 19-Feb-13 05-Mar-13 21-Mar-13 150 18-Aug-13 60
30 Architectural Marble for Levantine Café , All Day Dining 29-Oct-13 14-Mar-12 3-Mar-13 17-Mar-13 2-Apr-13 150 30-Aug-13 60
31 Architectural Marble for La Trattoria, Italian Resturant 13-Nov-13 3-Mar-12 18-Mar-13 01-Apr-13 17-Apr-13 150 14-Sep-13 60
32 Architectural Marble for Bakery & Coffee Area 17-Oct-13 25-Mar-12 19-Feb-13 05-Mar-13 21-Mar-13 150 18-Aug-13 60
33 Architectural Marble for Ballroom and Ante Room 22-Oct-13 24-Feb-12 24-Feb-13 10-Mar-13 26-Mar-13 150 23-Aug-13 60 no specifications
0 13-Feb-12 28-Apr-12 17-May-12 20-May-12 A
1initiated by
ACC on 15-May 12
15-May-12 3-Jun-12 3-Jun-12 A
E WOODEN FLOOR
33 Architectural ACC-MAR-A-G-329 06-Jan-13 Bison N/AMontagekit
Super Strength14-Aug-11 18-Jul-12 4-Aug-12 07-Nov-12 30 7-Dec-12 30Adhesive for Wood, Metal & Marble
34 Architectural Wooden Floor for Business Centre 17-Dec-13 25-Jun-12 22-Mar-13 05-Apr-13 21-Apr-13 150 18-Sep-13 90
35 Architectural Wooden Floor for La Trattoria, Italian Resturant 13-Nov-13 22-May-12 16-Feb-13 02-Mar-13 18-Mar-13 150 15-Aug-13 90
36 Architectural Wooden Floor for Enoteca, Wine Bar 17-Nov-13 26-May-12 20-Feb-13 06-Mar-13 22-Mar-13 150 19-Aug-13 90
37 Architectural Wooden Floor for Rugby Man Pub 17-Oct-13 25-Apr-12 20-Jan-13 03-Feb-13 19-Feb-13 150 19-Jul-13 90
38 Architectural Wooden Floor for Health Club 22-Aug-13 29-Feb-12 25-Nov-12 09-Dec-12 25-Dec-12 150 24-May-13 90 no specifications
F METALS
39 Architectural Stainless Steel at 2nd Floor 31-Oct-13 29-Sep-12 3-Jul-13 17-Jul-13 2-Aug-13 30 1-Sep-13 60
0 Stainless Steel at Lift Lobby 13-Feb-12 11-Mar-12 28-Apr-12 19-Apr-12 A
1 Stainless Steel at Lift Lobby, 4-26 Floor 20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 A
0 Stainless Steel at Toilets 6-Dec-11 11-Mar-12 29-Apr-12 30-Apr-12 A
1 Stainless Steel at Toiletsinitiated by
ACC on 15-May 12
15-May-12 14-Jun-12 16-Jun-12 A
2 Stainless Steel at Toilets, 4-26 Floor 20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 A
42 Architectural012-MIS-MT-MIS-00-061
0 Signage for Room Number and Room Direction 28-Jul-13 Arabian Wings 16-Dec-11 30-Mar-13 8-Sep-12 8-Sep-12 13-Apr-13 24-Sep-12 27-Sep-12 C 29-Apr-13 30 29-May-13 60
A.1.2 WALL FINISHES
27-Jan-1340 Architectural ACC-MAR-A-G-197 28-Mar-13 MetalicaBrush FinishGrade 304
29-Apr-12
29-Apr-12
28-Nov-12 04-Jul-12 28-Dec-12 30
23-Mar-13 04-Jul-12 22-Apr-13
60FAF was submitted (FAF-045) and approval received on 07-Oct-12 for Lift Lobby of Basement 1 & 2, Ground, 1st, 2nd & 3rd Floor, 4th to 46th Floor, & base support for desk.
41 Architectural ACC-MAR-A-G-297 21-Jul-13 22-May-13 60 FAF was submitted (FAF-046)30Brush FinishGrade 316
Metalica
B MOSAIC TILES
43 Architectural Mosaic Tiles for La Trattoria, Italian Resturant 13-Nov-13 14-Feb-12 18-Mar-13 01-Apr-13 17-Apr-13 150 14-Sep-13 60
C PAINT (Primer, Stucco & Topcoats)
0 Paint for Guest Rooms Walls, General JotunNCS S 1502 -
Y50R15-Nov-11 22-Nov-11 6-Dec-11 30-Apr-12 C
1 Paint for Guest Rooms Walls, Hotel Guest Rooms JotunNCS S 1502 -
Y50R
initiated by ACC on 01-
May 12
1-May-12 12-May-12 12-May-12 A approved for mock-up only
2 Paint for Guest Rooms Walls, Hotel Guest Rooms JotunNCS S 1502 -
Y50R
initiated by ACC on 15-
May 12
15-May-12 3-Jun-12 3-Jun-12 B approved for mock-up only
3 Paint for Guest Rooms Walls, Floors 4-46 JotunNCS S 1502 -
Y50R20-Jun-12 20-Jun-12 5-Jul-12 5-Jul-12 A FAF was submitted (FAF-050) and was approved for L27-46 only
45 Architectural Paint for Grand Suite 28-Sep-13 23-May-12 31-May-13 14-Jun-13 30-Jun-13 30 30-Jul-13 60 no specifications
46 Architectural Paint for Public Area at 2nd floor 25-Jul-13 30-May-12 27-Mar-13 10-Apr-13 26-Apr-13 30 26-May-13 60
47 Architectural Paint for Health Club 6-Aug-13 30-May-12 8-Apr-13 22-Apr-13 8-May-13 30 7-Jun-13 60 no specifications
48 Architectural Paint for Executive Lounge 17-Aug-13 23-May-12 19-Apr-13 03-May-13 19-May-13 30 18-Jun-13 60 no specifications
0 Paint for Guest Rooms & Corridor Ceiling 13-Feb-12 12-Mar-12 28-Apr-12 29-Apr-12 A
1 Paint for Guest Rooms & Corridor Ceilinginitiated by
ACC on 15-May 12
15-May-12 3-Jun-12 3-Jun-12 B
44 Architectural ACC-MAR-A-G-186 24-Dec-12 1517-Nov-11 11-Jul-12 28-Jul-12 30 9-Dec-12
2-Dec-12Architectural ACC-MAR-A-G-200 1-Jan-13 11-Jul-12 30
09-Nov-12
14-Dec-11Jotun47 30Emulsion Matt,
RAL 901628-Jul-12 02-Nov-12
Page 2 of 5 Form#13006PS- Rev.0
Page 25 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Legend: Material Submittal is Delayed Legend: Discipline : Architectural
Consultant : Architectural Consulting Group PROCUREMENT SCHEDULE BY DEPA Material Submittal is less than 1 month from due date Run date : 22-Oct-12
Main Contractor : Arabtec Construction Co. PROJECT ID: 10001 LPO is delayed
LPO is less than 1 month from due date
LPO was issued
Material Deliviered on Site
A B C DPlanned LPO or L/C
DateActual LPO or L/C No.
and Date
Delivery Period from Receipt of
OrderPlanned Actual
Sl No.Lead Time
(days)
Total Float (Planned Start Date - Planned
Delivery)
Discipline Submittal No.Activity IDSpecs.
Ref.Rev.
Revise plan Work Start
DateRemarks (LL : Long Lead Items)
Date of Return from Arabtec
Date of Submittal (Planned)
As per revised program
Approval Required By
Status Code Purchase Order Delivery Date
Description
Date Submitted to
ACG(Actual)
Sample / Brand Name
Subcontrator/Supplier
Date of Submittal (Planned)
As per base line
Specified Supplier by
Designer
Date Submitted to
Arabtec(Actual)
Date of Return from ACG
2Paint for Guest Rooms & Corridor Ceiling , Floors 4-26
20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 A FAF was submitted (ACC-FAF-A-H-051) and approved for L27-46 only
0 Paint for Guest Rooms Wet Areas Ceiling 29-Apr-12 30-Apr-12 12-May-12 12-May-12 A
1 Paint for Guest Rooms Wet Areas Ceilinginitiated by
ACC on 15-May 12
15-May-12 3-Jun-12 3-Jun-12 B
2Paint for Guest Rooms Wet Areas Ceiling, Floors 4-26
20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 AFAF was submitted (ACC-FAF-A-H-052 rev.00) and was approval for 27 to 46th floors only.
E WOOD CLADDING
0 Wood Cladding for Guest Rooms & Corridor 13-Feb-12 24-Jan-12 25-Apr-12 25-Apr-12 A
1 Wood Cladding for Guest Rooms & Corridorinitiated by ACC on 15 15-May-12 14-Jun-12 17-Jun-12 A
48 Architectural ACC-MAR-A-G-335 29-Dec-12 30-Oct-12 30 30Enamel Gloss,
RAL 9016Jotun 29-Nov-1211-Jul-1214-Dec-11 28-Jul-12
17-Jul-13 N/A 26-Jul-12 18-Jan-1349 Architectural ACC-MAR-A-G-250 16-Aug-12 150 17-Jun-13 303-Dec-11EldiarQuarter cut red
1 Wood Cladding for Guest Rooms & Corridor ACC on 15-May 12
15 May 12 14 Jun 12 17 Jun 12 A
2Wood Cladding for Guest Rooms & Corridor, 4-26 Floor
18-Jun-12 19-Jun-12 30-Jun-12 2-Jul-12 B
0 8-May-12 10-May-12 14-May-12 15-May-12 B
1 19-Jun-12 20-Jun-12 30-Jun-12 2-Jul-12 B
1 Architectural ACC-MAR-A-G-226 0 Treated Wood Backing, 11-May-13 Cora & Jotun N/A 3-Dec-11 26-Jul-12 9-May-12 12-May-12 16-Aug-12 21-May-12 22-May-12 A 10-Feb-13 30 12-Mar-13 60
2 Architectural ACC-MAR-A-G-225 0 Marine Plywood and Treatment for cut edges, 11-Mar-13Marineplex &
JotunN/A 3-Dec-11 26-Jul-12 9-May-12 12-May-12 16-Aug-12 21-May-12 22-May-12 A 15-Oct-12 15-Sep-12 150 28-Jan-13 15-Sep-12 42 Delivered on site
3 ArchitecturalWood Cladding for Junior Suite & Executive Junior Suite
17-Jul-13 27-Feb-12 19-Nov-12 03-Dec-12 19-Dec-12 150 18-May-13 60 Designer to provide controlled sample
4 Architectural Wood Cladding for Apartment 22-Oct-13 5-May-12 24-Feb-13 10-Mar-13 26-Mar-13 150 23-Aug-13 60 Designer to provide controlled sample
5 Architectural Wood Cladding for Grand Suite 10-Dec-13 26-Jun-12 14-Apr-13 28-Apr-13 14-May-13 150 11-Oct-13 60 no specifications
6 Architectural Wood for Public Area at 2nd Floor 6-Nov-13 10-Apr-12 11-Mar-13 25-Mar-13 10-Apr-13 150 7-Sep-13 60 Designer to provide controlled sample
F WALL COVERING
0 Wall Covering for Corridors 20-Dec-11 8-Mar-12 24-Apr-12 25-Apr-12 A
1 Wall Covering for Corridorsinitiated by
ACC on 15-May 12
15-May-12 11-Jun-12 13-Jun-12 A
2 Wall Covering for Corridors, 4-26 Floor 18-Jun-12 19-Jun-12 1-Jul-12 2-Jul-12 B FAF was submitted (FAF-042) and was approved for L27-46 only
17 Jul 13 N/A 26 Jul 12 18 Jan 1349 Architectural ACC MAR A G 250 16 Aug 12 150 17 Jun 13 303 Dec 11
50 Architectural ACC-MAR-A-G-224 Painted Wood Skirting, 4-26 Floor 17-Jul-13
Eldiaroak veneer
Jotun N/A 3-Dec-11 26-Jul-12 16-Aug-12 18-May-13 30 17-Jun-13 30
5 Architectural ACC-MAR-A-G-212 2-Apr-13 Newmor NewmorDarnell GND
221628-Jan-12 25-Aug-12 11-Sep-12 16-Oct-12 120 12-Feb-13 49
0 Wall Covering for Guest Rooms above headboard Seltex WC A 68-11 31-May-12 31-May-12 27-Jun-12 28-Jun-12 B
1Wall Covering for Guest Rooms above headboard, 4-26 Floor
Newmor custom 8-Sep-12 9-Sep-12 6-Oct-12 8-Oct-12 A
2 Architectural Wall Covering for Grand Suite 13-Oct-13 23-Aug-12 21-Mar-13 11-Apr-13 16-May-13 120 13-Sep-13 30 no specifications
3 Architectural Wall Covering for Public Areas at 2nd Floor 10-Aug-13 2-May-12 28-Nov-12 08-Mar-13 12-Apr-13 90 11-Jul-13 30
G METALS
4 Architectural Metal for Ballroom and Ante Room no specifications
H GLASS
5 Architectural ACC-MAR-A-G-279 0Laminated Glass for Guest Rooms Sliding Door, 4-26 Floor
10-Mar-13Guardian Glass
/ Trosofil( ART GLASS)
11.14 thick( 5mm glass /
BG R20 1.14)14-Dec-11 11-Jul-12 20-Jun-12 21-Jun-12 29-Jul-12 2-Jul-12 5-Jul-12 B 30-Dec-12 60 28-Feb-13 10 FAF was submitted (FAF-043) and was approved for L27-46 only
0 Mirror for Guest Rooms 6mm thick 6-Dec-11 26-Apr-12 8-May-12 12-May-12 A
1 Mirror for Guest Rooms, 4-26 Floor 6mm thick 19-Jun-12 20-Jun-12 27-Jun-12 28-Jun-12 BFAF was submitted (FAF-049) and was approved for Junior Suite L4-26, L27-46 only
0 Clear Glass for Guest Rooms 12-Mar-12 25-Apr-12 25-Apr-12 A
1 Clear Glass for Guest Rooms, 4-26 Floor 18-Jun-12 19-Jun-12 30-Jun-12 2-Jul-12 C
2Clear Glass with Sand Blasted finish , hotel (4-46 Floor) & podium
29-Aug-12 30-Aug-12 2-Sep-12 5-Sep-12 C
60 28-Feb-13
10
Architectural ACC-MAR-A-G-214 10-Mar-13Guardian Glass(ART GLASS)
10mm thick 30-Dec-12
60
14-Dec-11 11-Jul-12 29-Jul-12
28-Feb-1330-Dec-12
7
ACC-MAR-A-G-213 29-Jul-12Guardian Glass(ART GLASS)
14-Dec-11 11-Jul-1210-Mar-136 Architectural
150 22-May-13 6021-Jul-13 28-Feb-12 25-Sep-12 9-Oct-12 23-Dec-121 Architectural ACC-MAR-A-G-266
58
3Clear Glass with Back Painted, hotel (4-46 Floor) & podium
16-Sep-12 19-Sep-12 6-Oct-12 8-Oct-12 B
0 Glass Door Handles (shower), 4-26 Floor 1-May-12 3-May-12 8-May-12 12-May-12 A approved for mock-up only
1 Handle for Shower Glass Door, 4-46 Floor 27-Sep-12 29-Sep-12 6-Oct-12 8-Oct-12 A
ACC-MAR-A-G-2058 Architectural 27-Jul-13 Hafele 14-Dec-11 11-Jul-12 29-Jul-12 27-Feb-13 120 27-Jun-13 30
Page 3 of 5 Form#13006PS- Rev.0
Page 26 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Legend: Material Submittal is Delayed Legend: Discipline : Architectural
Consultant : Architectural Consulting Group PROCUREMENT SCHEDULE BY DEPA Material Submittal is less than 1 month from due date Run date : 22-Oct-12
Main Contractor : Arabtec Construction Co. PROJECT ID: 10001 LPO is delayed
LPO is less than 1 month from due date
LPO was issued
Material Deliviered on Site
A B C DPlanned LPO or L/C
DateActual LPO or L/C No.
and Date
Delivery Period from Receipt of
OrderPlanned Actual
Sl No.Lead Time
(days)
Total Float (Planned Start Date - Planned
Delivery)
Discipline Submittal No.Activity IDSpecs.
Ref.Rev.
Revise plan Work Start
DateRemarks (LL : Long Lead Items)
Date of Return from Arabtec
Date of Submittal (Planned)
As per revised program
Approval Required By
Status Code Purchase Order Delivery Date
Description
Date Submitted to
ACG(Actual)
Sample / Brand Name
Subcontrator/Supplier
Date of Submittal (Planned)
As per base line
Specified Supplier by
Designer
Date Submitted to
Arabtec(Actual)
Date of Return from ACG
9 Architectural ACC-MAR-A-G-361 0Glass Door Handles (bathroom entrance & toilet, 4-47 Floor
27-Jul-13 Dorma Dorma TG9025 14-Dec-11 11-Jul-12 28-Aug-12 29-Aug-12 29-Jul-12 9-Sep-12 10-Sep-12 A 27-Feb-13 120 27-Jun-13 30
0 Manual Sliding Door System Hawa Junior 80/GS 12-Dec-11 10-Mar-12 28-Apr-12 29-Apr-12 C
1 Manual Sliding Door System, 4-26 Floor 26-Jul-12 11-Aug-12 16-Aug-12 21-Aug-12 C
2 Manual Sliding Door System, 4-46 Floor 23-Sep-12 25-Sep-12 waiting for approval
11 Architectural Glass for Grand Suite 11-Nov-13 13-Jun-12 9-Jan-13 27-Jan-13 22-Apr-13 140 9-Sep-13 63 no specifications
12 Architectural Glass for Asian Restaurant 21-Aug-13 3-Jun-12 30-Dec-12 03-Feb-13 28-Feb-13 105 13-Jun-13 69
13 Architectural Glass for La Trattoria Italian Resturant 28-Jul-13 3-Jun-12 30-Dec-12 03-Feb-13 28-Feb-13 105 13-Jun-13 45
27-Jul-13012-IRI-MT-IRI-00-
013Perlan 140
14-Dec-11 11-Jul-12 29-Jul-12Architectural10
Geze
27-Feb-13 120 27-Jun-13 30
13 Architectural Glass for La Trattoria, Italian Resturant 28 Jul 13 3 Jun 12 30 Dec 12 03 Feb 13 28-Feb-13 105 13-Jun-13 45
14 Architectural Glass for Health Club 26-Sep-13 13-Aug-12 11-Mar-13 01-Apr-13 29-Apr-13 105 12-Aug-13 45 no specifications
15 Architectural ACC-MAR-A-G-328 0 Silicone Sealant for Glass 10-Mar-13 Dow Corning 974N 14-Dec-11 11-Jul-12 6-Dec-11 26-Apr-12 29-Jul-12 14-May-12 15-May-12 A 09-Jan-13 30 8-Feb-13 30
G FABRICS / LEATHER
16 Architectural ACC-MAR-A-G-280 0Leather for Headboard for Guest Rooms, 4-26 Floor
30-Sep-13 PrototypeRanchero,
Bonanza, 13-T
29-Dec-11 26-Jul-12 20-Jun-12 21-Jun-12 16-Aug-12 2-Jul-12 5-Jul-12 B 03-Apr-13 150 31-Aug-13 30 FAF was submitted (012-FAF-ME-0008)
17 Architectural ACC-MAR-A-G-344 0 Decorative Curtain Fabric for Guest Rooms 30-Sep-13 Vigano Vigano 27-Jan-12 24-Aug-12 1-Jul-12 7-Jul-12 14-Sep-12 16-Jul-12 4-Sep-12 A 03-Apr-13 150 31-Aug-13 30
B FALSE CEILING
0 9-Nov-11 11-Nov-11 29-Apr-12 B
1 9-Nov-11 15-May-12 11-Jun-12 B
0 9-Nov-11 19-Nov-11 3-May-12 6-May-12 A
1initiated by
ACC on 15-May 12
15-May-12 11-Jun-12 13-Jun-12 A
1 Architectural ACC-MAR-A-175 0 Gypsum Board - Moisture Resistant 2-Dec-12United Mining
Industries
12.5mm thick, moisture
i t t
26-Jul-11 26-Jun-12 9-Nov-11 19-Nov-11 03-Jul-12 28-Apr-12 29-Apr-12 A 29-Jul-12 24-Jul-12 70 7-Oct-12 56
0 Access Panels Al Areesh GA Series 11-Dec-11 11-Mar-12 23-Apr-12 24-Apr-12 C
1 Access Panels Knauf Knauf Alustar 24-Apr-12 24-Apr-12 30-Apr-12 2-May-12 A
18 20-Nov-12United Mining
Industries12.5mm thick,
regular
Delivered on site
Architectural ACC-MAR-A-174 Gypsum Board - Regular
1-Oct-12 2124-Jul-12 70 7-Oct-1226-Jun-12 03-Jul-12 29-Jul-1213-Jun-1226-Jul-1117 Architectural ACC-MAR-A-177 Suspended Ceiling System 28-Oct-12 Exmet
26-Jul-11 26-Jun-12 03-Jul-12 29-Jul-12 24-Jul-12 70 7-Oct-12 8-Oct-12 44
2 Architectural ACC-MAR-A-209 12-Feb-13 16-Aug-11 16-Jul-12 01-Aug-12 14-Nov-12 60 13-Jan-13 30
Delivered on site
0 24-Apr-12 25-Apr-12 12-May-12 12-May-12 A
1initiated by
ACC on 15-May 12
15-May-12 14-Jun-12 16-Jun-12 A
A-2 FF&E
A DOORS
1 Architectural ACC-MAR-A-229 0 Wooden Door for Guest Rooms 17-Jul-13 Eldiar N/A 2-Oct-11 28-Jun-12 7-May-12 15-May-12 12-Jul-12 7-Jun-12 9-Jun-12 B 18-Jan-13 150 17-Jun-13 30
2 Architectural Wooden Door for Grand Suite 23-Sep-13 26-Mar-12 21-Dec-12 4-Jan-13 15-Mar-13 142 4-Aug-13 50 no specifications
3 Architectural Wooden Door for 2nd Floor 3-Aug-13 19-Mar-12 14-Dec-12 28-Dec-12 19-Feb-13 142 11-Jun-13 53
4 Architectural Wooden Door for 3rd Floor 8-Aug-13 21-Mar-12 16-Dec-12 06-Jan-13 20-Jan-13 100 30-Apr-13 100 no specifications
0 Ironmongery for Wooden Door Dorma 11-Dec-11 4-Feb-12 4-Mar-12 5-Mar-12 C
1 Ironmongery for Wooden Door Hafele 23-Apr-12 29-Apr-12 8-May-12 12-May-12 B
2 Ironmongery for Wooden Door Hafeleinitiated by
ACC on 15-May 12
15-May-12 14-Jun-12 16-Jun-12 B
3 Ironmongery for Wooden Door, floor 4-26 Hafele 20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 C
B IRONMONGERY FOR CARPENTRY & FIXED FURNITURE
0 Ironmongery for Furniture 23-Apr-12 25-Apr-12 8-May-12 12-May-12 B
2 Architectural ACC-MAR-A-326 Joint Compound 20-Dec-12United States Gypsum Co.
Sheetrock 26-Jul-11 03-Sep-12 21-Oct-12 30 20-Nov-12 30
2 Architectural ACC-MAR-A-252 2-Mar-13 2-Oct-11 12-Jul-1228-Jun-12 02-Nov-12 90 31-Jan-13 30
g y p p y y
1 Ironmongery for Furnitureinitiated by
ACC on 15-May 12
15-May-12 14-Jun-12 16-Jun-12 B
2 Ironmongery for Furniture, 4-26 Floor 20-Jun-12 21-Jun-12 2-Jul-12 5-Jul-12 B
1 Architectural Ironmongery for Public Areas 3-Aug-13 10-Feb-12 6-Nov-12 10-Jan-13 31-Jan-13 140 20-Jun-13 44
C LOOSE FURNITURE
2 Architectural Loose Furniture for Guest Rooms 30-Sep-13 25-Jan-12 3-Jan-13 17-Jan-13 02-Feb-13 180 1-Aug-13 60
0 Chair for Desk at Guest Rooms, Floor 4-26 Doimo 29-Feb-12 10-Mar-12 28-Apr-12 29-Apr-12 C
1 Chair for Desk at Guest Rooms, Floor 4-26 Solver Space 1-Jul-12 5-Jul-12 14-Jul-12 15-Jul-12 C
2 Chair for Desk at Guest Rooms, Floor 4-47 Solver SpaceSO.YU.60.40.S
BT29-Aug-12 30-Aug-12 27-Sep-12 B
4 Architectural Loose Furniture for Apartment 6-Oct-13 7-Jun-12 3-Jan-13 17-Jan-13 28-Feb-13 180 27-Aug-13 40
5 Architectural Loose Furniture for Grand Suite 7-Dec-13 24-Jun-12 20-Jan-13 10-Feb-13 20-Jun-13 140 7-Nov-13 30 no specifications
6 Architectural Loose Furniture for 2nd Floor 1-Oct-13 14-Jun-12 10-Jan-13 03-Mar-13 28-Mar-13 142 17-Aug-13 45
7 Architectural Loose Furniture for 3rd Floor 7-Nov-13 14-Jun-12 10-Jan-13 03-Mar-13 27-Mar-13 180 23-Sep-13 45 no specifications
30-Jan-12 27-Aug-12 10-Sep-12
1 Architectural ACC-MAR-A-325 22-Mar-1321-Apr-13 Hafele 29-Dec-11 24-Sep-12 08-Oct-12 22-Nov-12 120
60
30
3 Architectural ACC-MAR-A-294 30-Sep-13Herman
Miller02-Feb-13 180 1-Aug-13
Page 4 of 5 Form#13006PS- Rev.0
Page 27 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Legend: Material Submittal is Delayed Legend: Discipline : Architectural
Consultant : Architectural Consulting Group PROCUREMENT SCHEDULE BY DEPA Material Submittal is less than 1 month from due date Run date : 22-Oct-12
Main Contractor : Arabtec Construction Co. PROJECT ID: 10001 LPO is delayed
LPO is less than 1 month from due date
LPO was issued
Material Deliviered on Site
A B C DPlanned LPO or L/C
DateActual LPO or L/C No.
and Date
Delivery Period from Receipt of
OrderPlanned Actual
Sl No.Lead Time
(days)
Total Float (Planned Start Date - Planned
Delivery)
Discipline Submittal No.Activity IDSpecs.
Ref.Rev.
Revise plan Work Start
DateRemarks (LL : Long Lead Items)
Date of Return from Arabtec
Date of Submittal (Planned)
As per revised program
Approval Required By
Status Code Purchase Order Delivery Date
Description
Date Submitted to
ACG(Actual)
Sample / Brand Name
Subcontrator/Supplier
Date of Submittal (Planned)
As per base line
Specified Supplier by
Designer
Date Submitted to
Arabtec(Actual)
Date of Return from ACG
D SOFT FURNISHING
0 Curtain Rail System for Guest Rooms, 4-26 Floor 30-Sep-13 Rilox3 way full system
8-May-12 10-May-12 14-May-12 15-May-12 C
1Curtain Track SystemHand Operated, 4-46 Floor
30-Sep-13 Silent Gliss 3-Jul-03 8-Oct-12
9 Architectural Curtains for Grand Suite 7-Dec-13 19-Jul-12 14-Feb-13 06-Mar-13 10-Jun-13 150 7-Nov-13 30 no specifications
10 Architectural Curtains for Asian Restaurant 19-Sep-13 8-May-12 4-Dec-12 23-Jan-13 23-Mar-13 150 20-Aug-13 30
11 Architectural Curtains for Main Lobby & Deli Shop 19-Sep-13 8-May-12 4-Dec-12 23-Jan-13 23-Mar-13 150 20-Aug-13 30
12 Architectural Curtains for La Trattoria Italian Resturant 19-Sep-13 8-May-12 4-Dec-12 23-Jan-13 23-Mar-13 150 20-Aug-13 30
14-Sep-12 150 31-Aug-1303-Apr-13 30 waiting for approval8 Architectural ACC-MAR-A-223 27-Jan-12 24-Aug-12
12 Architectural Curtains for La Trattoria, Italian Resturant 19 Sep 13 8 May 12 4 Dec 12 23 Jan 13 23-Mar-13 150 20-Aug-13 30
13 Architectural Curtains for The Rugby Man Pub 19-Sep-13 8-May-12 4-Dec-12 23-Jan-13 23-Mar-13 150 20-Aug-13 30
14 Architectural Curtains for Levantine Café , All Day Dining 19-Sep-13 8-May-12 4-Dec-12 23-Jan-13 23-Mar-13 150 20-Aug-13 30
E DECORATIVE LIGHTS
15 Architectural Decorative Lights for Guest Rooms, Floor 4-26 30-Sep-13 9-Feb-12 2-Feb-13 16-Feb-13 04-Mar-13 180 31-Aug-13 30
16 ArchitecturalDecorative Lights for Junior Suite & Executive Junior Suite
30-Sep-13 14-May-12 2-Feb-13 16-Feb-13 04-Mar-13 180 31-Aug-13 30
17 Architectural Decorative Lights for Apartment 29-Dec-13 21-Jun-12 3-May-13 17-May-13 02-Jun-13 180 29-Nov-13 30
18 Architectural Decorative Lights for Grand Suite 13-Feb-14 29-Jun-12 18-Jun-13 02-Jul-13 18-Jul-13 180 14-Jan-14 30 no specifications
19 Architectural Decorative Lights for 2nd Floor 28-Sep-13 23-May-12 31-Jan-13 14-Feb-13 02-Mar-13 180 29-Aug-13 30
Page 5 of 5 Form#13006PS- Rev.0
Page 28 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Civil & Finishes Procurement schedule
Page 29 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG HOTEL (From 4th Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE (BACK OF HOUSE) Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
1 Structural ACC-MAR-S-G-046 00 Division 07 Twin Walls Pelypropylene Alternative Protection Board 28-Mar-11 Tadmur 15-Feb-11 30-Mar-11 30-Mar-11 13-Apr-11 05-Apr-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 1-May-11 1-May-11 Part of Subcontract Work
2 Structural ACC-MAR-S-G-008 00 Division 03 Polyethylene Sheet (Sizes: 1000 gauge - 250 micron) 28-Mar-11 Petro Plastic Factory 15-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 15-Mar-11 15-Mar-11
3 Structural ACC-MAR-S-G-001 00 Division 04
Hollow & Solid Concrete Block (Hollow Concrete Block Sizes: 400 x 200 x 200, 400 x 150 x 200, 400 x 100 x 200, Solid Concrete Block Sizes: 400 x 100 x 200, 400 x 150 x 200, 400 x 200 x 200)
3-Mar-11 Aamal Cement Indu. 15-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 15-Mar-11 15-Mar-11 The first using for Block work shuttering
Sl No. Discipline Submittal No. Rev. DescriptionSpecs. Ref. Remarks Date of Return
Date of Submittal (Planned)
Baseline dates
Subcontractor / Supplier
Work Start Date
Baseline dates
Approval Required By
Status Code Delivery DatePurchase Order
Planned Date of Submittal
Date Submitted
to ACG (Actual)
4 Structural ACC-MAR-S-G-002 00 Division 04 Ordinary Portland Cement for Masonary Mortar 3-Mar-11 Tayseer Bldg. Mtrls. Co. 15-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 23-Feb-11 A 15-Mar-11 15-Mar-11
5 Structural ACC-MAR-S-G-025 00 Division 03 Mix Design for Screed. 28-Mar-11 NBK 5-Mar-11 12-Mar-11 12-Mar-11 26-Mar-11 17-Mar-11 A ATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Site requirement 1-Apr-11 1-Apr-11 Part of Supplier Work
6 Structural ACC-MAR-S-G-028 00 Division 03 Fibre Concrete Spacers. 10-Apr-11 Castle 10-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
7 Structural ACC-MAR-S-G-030 00 Division 03 Formwork Release Agent - Formcoat S 8-Jun-11 Ayla 13-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
8 Structural ACC-MAR-S-G-020 00 Division 03 High Yield Steel Reinforcement Deformed Bar. 10-Apr-11 Qatar Steel 5-Mar-11 5-Mar-11 05-Mar-11 19-Mar-11 10-Mar-11 A ACC/WTC/VK/LOI/1002-001 27th March 2011 As per Site requirement 25-Mar-11 25-Mar-11 Part of Supplier Work
9 Structural ACC-MAR-S-G-044 00 - Injection Epoxy Chemical Adhesive 10-Apr-11 Fischer Fixing 15-Mar-11 26-Mar-11 26-Mar-11 09-Apr-11 29-Mar-11 A 13-Apr-11 13-Apr-11
10 Structural ACC-MAR-S-G-043 00 Division 03 Mechanical Splice, BSG Cold Swaged 10-Apr-11 Castle 25-Feb-11 22-Mar-11 22-Mar-11 05-Apr-11 26-Mar-11 A 10-Apr-11 10-Apr-11
11 Structural ACC-MAR-S-G-033 00 Division 03 Curing Compound - Setcrete AW (can be over coated) 10-Apr-11 Ayla 13-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
12 Structural ACC-MAR-S-G-029 00 Division 03 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. 10-Apr-11 Modern Building 13-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
Concrete Mix Design for Ground Slab SuspendedStructural ACC-MAR-S-G-023 00 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 10-Apr-11 NBK 1-Mar-11 9-Apr-11 08-Mar-11 22-Mar-11 13-Mar-11 C
Structural ACC-MAR-S-G-023 01 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 10-Apr-11 NBK 1-Mar-11 9-Apr-11 15-Mar-11 29-Mar-11 26-Mar-11 A
Structural ACC-MAR-S-G-023 02 Division 03 Concrete Mix Design for Ground Slab (Fcu=56MPa). 10-Apr-11 NBK 1-Mar-11 9-Apr-11 22-Mar-11 05-Apr-11 31-Mar-11 B
Structural ACC-MAR-S-G-023 03 Division 03 Concrete Mix Design for Raft and Retaining Wall (Fcu=56MPa). 10-Apr-11 NBK 1-Mar-11 9-Apr-11 09-Apr-11 23-Apr-11 10-Apr-11 A
14 Architectural ACC-MAR-A-G-078 00 Division 09 Block work Accessories 24-Nov-11 Unitech / SFSP 5-Feb-11 29-May-11 29-May-11 12-Jun-11 31-May-11 A 1-Mar-12 1-Mar-12
15 Architectural ACC-MAR-A-G-056 00 Division 09 Galvanized & Stainless Plastering Accessories 24-Dec-11 Unitech Qatar 18-Aug-11 25-Apr-11 25-Apr-11 09-May-11 28-Apr-11 A 1-May-12 1-Sep-12
16 Architectural ACC-MAR-A-G-163 00 Division 09 Ready Mix Plaster (Concrete Rush Coat SRC-2, Cement Plaster - SP 11) 24-Dec-11 Sodamco 18-Aug-11 31-Oct-11 31-Oct-11 14-Nov-11 17-Nov-11 B 1-May-12 1-Sep-12
17 Architectural ACC-MAR-A-G- 00 Division 09 Ceramic Tiles (Floor) 15-Mar-12 Sayyar/Farman 14-Aug-11 5-May-12 14-Jan-00 1-Jan-13 Bid Summary is Ready,
waiting for final approvel from consultant
Architectural ACC-MAR-A-G-257 00 Division 09 Ceramic Wall Tile, Vitra Option1: Color 7500, Option2: Color 7047 Option3:Color 8000
15-Mar-12 Sayyar / Vitra 14-Aug-11 5-May-12 23-May-12 06-Jun-12 28-May-12 A
13 ATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Site requirement 25-Apr-11 25-Apr-11 Part of Supplier Work
Architectural ACC-MAR-A-G-257 01 Division 09
Ceramic Wal Tile 15x15cm (ALFARMAN - Option 1: CINZA -196.0, Option 2: BRANCO-001.0, Option 3 : CINZA ESCURO-640.0,Option 4: BEGE-514.0, Option 5: BEGE CLARO -441.0, Option 6: MARFIM-002.0, Option 7: CRÈME-302.0, Option 8: BEGE ROSA-675.0 (For Sayyar Option 9: RAL 0006500A K891571, Option 10: RAL 0809005A K878793, Option 11: RAL 0809010A K787632, Option 12: RAL 0007500A K502843, Option 13: RAL 0008000A K891582, Option 14: RAL 1009005A K855376
15-Mar-12Al Farman-Primus
Vitoria / Sayyar-Vitra14-Aug-11 5-May-12 29.09.12 13-Oct-12 06.10.12 A
19 Architectural ACC-MAR-A-G- 00 Division 11 Cleaning Cradle 29-Jan-12Power Machine
/United Eqpt22-Jun-11 17-Sep-12 25-Jun-13 Bid Summary & Draft L.O.I is Ready,
waiting for consultant approvel
20 Architectural ACC-MAR-A-G- 00 Division 10 Linen Chute 2-Mar-12 Globtech 2-Dec-11 1-Oct-12ACC/TT/VK/LOI – 3025 - 001
9th September 2012 1-Jan-13 Part of Subcontract Work
18 1-Jan-13 Bid Summary is Ready,
waiting for final approvel from consultant
Page 30 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG HOTEL (From 4th Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE (BACK OF HOUSE) Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Sl No. Discipline Submittal No. Rev. DescriptionSpecs. Ref. Remarks Date of Return
Date of Submittal (Planned)
Baseline dates
Subcontractor / Supplier
Work Start Date
Baseline dates
Approval Required By
Status Code Delivery DatePurchase Order
Planned Date of Submittal
Date Submitted
to ACG (Actual)
Architectural ACC-MAR-A-G-305 00 Division 07 Adeprimaire Siplast Wet Area Water Proofing Tadmur / Siplast 0-Jan-00 28-Jun-00 01-Apr-12 15-Apr-12 09-Apr-12 C
Architectural ACC-MAR-A-G-305 01 Division 07 Adeprimaire Siplast Wet Area Water Proofing 11-Jan-12 Tadmur / Siplast 3-Sep-11 1-Mar-12 09-May-12 23-May-12 28-May-12 B
22 Architectural ACC-MAR-A-G-115 00 Division 07 Fire Stoping Sealant 24-Dec-11 Unitech Qatar 6-Sep-11 4-Mar-12 25-Jul-11 08-Aug-11 06-Aug-11 A 1-May-12 1-May-12
23 Architectural ACC-MAR-A-G- 00 Division 09 PVC Skirting 12-Mar-12 12-Dec-11 15-Oct-12 1-Dec-12Bid summary is ready, technical submission forwrad to technical
D t tArchitectural ACC-MAR-A-G-217 00 Division 07 20mm / 25mm Backing Rod for Joint Sealant 12-Mar-12 Arnon Plastic / Castle 12-Dec-11 9-Jun-12 05-May-12 19-May-12 17-May-12 C
21 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 1-Oct-12 Part of Subcontract Work
Architectural ACC MAR A G 217 00 Division 07 20mm / 25mm Backing Rod for Joint Sealant 12 Mar 12 Arnon Plastic / Castle 12 Dec 11 9 Jun 12 05 May 12 19 May 12 17 May 12 C
Architectural ACC-MAR-A-G-217 01 Division 07 20mm / 25mm / 30mm Backing Rod for Joint Sealant
12-Mar-12Arnon Plastic /
Modern Builders12-Dec-11 9-Jun-12 20-May-12 03-Jun-12 28-May-12 A
Architectural ACC-MAR-A-G-283 00 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 19-Feb-12 04-Mar-12 27-Feb-12 C
Architectural ACC-MAR-A-G-283 01 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 20-Mar-12 03-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-283 02 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 08-May-12 22-May-12 21-May-12 A
Architectural ACC-MAR-A-G-285 00 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 19-Feb-12 04-Mar-12 26-Feb-12 C
Architectural ACC-MAR-A-G-285 01 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 20-Mar-12 03-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-285 02 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout)
12-Mar-12 Sodamco 12-Dec-11 9-Jun-12 08-May-12 22-May-12
27 Architectural ACC-MAR-A-G- 00 Division 06 Wooden Doors 26-Sep-121000 Walls /Ramco
Carpentry3-Dec-11 30-Aug-12 1-Jul-13 Bid Summary is Ready
waiting consultant approvel
28 Architectural ACC-MAR-A-G- 00 Division 08 Hardware 26-Sep-12 Hafele/ Dorma 3-Dec-11 30-Aug-12 1-Jul-13 Bid Summary is Ready,Dorma sample to submit
24
25
26
1-Sep-12
1-Sep-12 1-Sep-12
1-Sep-121-Sep-12
1-Sep-12
29 Architectural ACC-MAR-A-G- 00 Division 08 Steel Doors & Hardware 1-Apr-12 Indigatech 3-Dec-11 30-Aug-12 1-May-13 Bid Summary is Ready, waiting final approvel form consultant
Architectural ACC-MAR-A-G-312 00 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability
21-May-12 Juton 17-Nov-11 15-May-12 11-Apr-12 25-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-312 01 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability
21-May-12 Juton/Roots Qatar 17-Nov-11 15-May-12 26-Jul-12 09-Aug-12 05-Aug-12 B
31 Architectural ACC-MAR-A-G- 00 Division 09 Paint Systems(/Epoxy & road marking & deck coating) 21-May-12 JUTON / ROOTS 17-Nov-11 20-Jun-12 1-Jan-14 Bid Summary is Ready,
L.O.I to be issue
32 Architectural ACC-MAR-A-G- 00 Division 09 Aluminium Tiles on Suspended Ceiling 8-Apr-12 Elite Engineering 9-Jul-11 20-May-12 1-Jan-13 subcontractor preqalification to submit
Architectural ACC-MAR-A-G-352 00 Division 09 Metal Strip Ceiling(100 mm, 150 mm, 200 mm & 300 mm)
8-Apr-12QASR AL
ANDALUS/ SADDI METAL
9-Jul-11 5-Jan-12 21-Jul-12 04-Aug-12 06-Aug-12 C
Architectural ACC-MAR-A-G-352 01 Division 09 Matador (100 mm, 150 mm, 200 mm & 300 mm) Linear Metal Strip Ceiling
8-Apr-12Marconi/
INTERARC9-Jul-11 5-Jan-12 31-Jul-12 14-Aug-12 13-Aug-12 C
34 Architectural ACC-MAR-A-G- 00 Division 05 G.S. Handrails & Rails 26-Mar-12 Qatar Indo Fab 26-Dec-11 23-Jun-12 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Siterequirement 1-May-13 Part of Subcontract Work
33
30 Bid Summary is Ready,L.O.I to be issue1-May-13
1-Jan-13 subcontractor preqalification to submit
2012 requirement
35 Architectural ACC-MAR-A-G- 00 Division 03 Concrete Tiles 4-Feb-13 31-Jan-12 25-Nov-12 1-Aug-13
36 Architectural ACC-MAR-A-G- 00 Division 09 Gravel for Planters 16-Apr-13 31-Jan-12 25-Nov-12 1-Aug-13
37 Architectural ACC-MAR-A-G- 00 Division 05 S. Steel Ladder /Cat walk 25-Feb-13 Qatar Indo Fab 3-Dec-11 25-Sep-12 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-Aug-13 Part of Subcontract Work
38 Architectural ACC-MAR-A-G- 00 Division 05 Steel Guardrails 26-Mar-13 Qatar Indo Fab 3-Dec-11 25-Sep-12 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-May-13 Part of Subcontract Work
39 Architectural ACC-MAR-A-G- 00 Division 07 Thermal Insulation System (roof system) 4-Feb-13 Tadmur 3-Sep-11 15-Nov-12 1-Aug-13 Roof - Waterproofing & Protection and Thermal Insulation
40 Architectural ACC-MAR-A-G- 00 Division 10 Signage 11-Apr-13 2-Nov-12 1-Jan-13 1-Jan-14 Quotation Under Review
41 Architectural ACC-MAR-A-G-259 00 Division 09 Porcelain Tile for Step Tread, Riser & Skirtings 26-Mar-12 Sayyar / Vitra 26-Dec-11 23-Jun-12 23-May-12 06-Jun-12 28-May-12 A 1-Aug-13 Bid Summary is Ready waiting consultant approvel
Architectural ACC-MAR-A-G-305 00 Division 07 Adeprimaire Siplast Wet Area Water Proofing 28-Jan-12 Tadmur / Siplast 22-Jun-11 19-Dec-11 01-Apr-12 15-Apr-12 09-Apr-12 C
42 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site 1-Sep-12 1-Sep-12 Part of Subcontract Work
Page 31 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG HOTEL (From 4th Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE (BACK OF HOUSE) Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Sl No. Discipline Submittal No. Rev. DescriptionSpecs. Ref. Remarks Date of Return
Date of Submittal (Planned)
Baseline dates
Subcontractor / Supplier
Work Start Date
Baseline dates
Approval Required By
Status Code Delivery DatePurchase Order
Planned Date of Submittal
Date Submitted
to ACG (Actual)
Architectural ACC-MAR-A-G-305 01 Division 07 Adeprimaire Siplast Wet Area Water Proofing 28-Jan-12 Tadmur / Siplast 22-Jun-11 19-Dec-11 09-May-12 23-May-12 28-May-12 B
43 Architectural ACC-MAR-A-G- 00 Division 09 Mirror 26-Jan-13 Spectra Arts 1-Apr-12 30-Jun-12 1-Oct-13 Quotation Under Review
44 Architectural ACC-MAR-A-G- 00 - Floating floor for MEP Equipment 10-Apr-12 10-Jan-12 9-Apr-12 1-Dec-12
45 Architectural ACC-MAR-A-G- 00 - ANTI-STATIC LINOLEUM 10-Apr-12 10-Jan-12 8-Jul-12 1-Dec-12 Quotation Under Review
46 Architectural ACC MAR A G 00 Minibar 15 Jun 12 13 Sep 12 13 Sep 12 1 May 13 Quotation Under Review
42 ACC/TT/VK/LOI-3012-001 13th March 2011 requirement 1-Sep-12 1-Sep-12 Part of Subcontract Work
46 Architectural ACC-MAR-A-G- 00 - Minibar 15-Jun-12 13-Sep-12 13-Sep-12 1-May-13 Quotation Under Review
47 Architectural ACC-MAR-A-G- 00 - Save 26-Jan-13 13-Sep-12 13-Sep-12 1-Dec-13 Quotation Under Review
48 Architectural ACC-MAR-A-G- 00 - T.V. 26-Jan-13 13-Sep-12 13-Sep-12 1-Dec-13
Page 32 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG OFFICE (From 4th Level) TOWER MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
1 Structural ACC-MAR-S-G-046 00 Division 07 Twin Walls Pelypropylene Alternative Protection Board 14-Apr-11 Tadmur 15-Feb-11 30-Mar-11 30-Mar-11 13-Apr-11 05-Apr-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 20-Apr-11 20-Apr-11 Part of Subcontract Work
2 Structural ACC-MAR-S-G-008 00 Division 03 Polyethylene Sheet (Sizes: 1000 gauge - 250 micron) 14-Apr-11 Petro Plastic Factory 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 7-Mar-11 7-Mar-11
3 Structural ACC-MAR-S-G-001 00 Division 04
Hollow & Solid Concrete Block (Hollow Concrete Block Sizes: 400 x 200 x 200, 400 x 150 x 200, 400 x 100 x 200, Solid Concrete Block Sizes: 400 x 100 x 200, 400 x 150 x 200, 400 x 200 x 200)
21-Mar-11 Aamal Cement Indu. 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 7-Mar-11 7-Mar-11
4 S l ACC MAR S G 002 00 O di P l d C f M M 21 M 11 Tayseer Bldg. Mtrls. 8 F b 11 8 F b 11 08 F b 11 22 F b 11 23 F b 11 10 M 11 10 M 11
Remarks Approval Required By
Date of Return
Status Code
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Purchase Order Delivery Date
Planned Date of Submittal
Date Submitted to ACG (Actual)
DescriptionWork Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref.
4 Structural ACC-MAR-S-G-002 00 Division 04 Ordinary Portland Cement for Masonary Mortar 21-Mar-11 Tayseer Bldg. Mtrls. Co. 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 23-Feb-11 A 10-Mar-11 10-Mar-11
5 Structural ACC-MAR-S-G-025 00 Division 03 Mix Design for Screed 14-Apr-11 NBK 5-Mar-11 12-Mar-11 12-Mar-11 26-Mar-11 17-Mar-11 A ATC/TT/VK/LOI/1001-001 19th April 2011 As per Site requirement 1-Apr-11 1-Apr-11 Part of Supplier Work
6 Structural ACC-MAR-S-G-028 00 Division 03 Fibre Concrete Spacers. 27-Apr-11 Castle 10-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
Structural ACC-MAR-S-G-072 00 Division 03 Concrete Mix Design for Retaining Wall (Fcu=75MPa) 27-Apr-11 NBK 10-Mar-11 24-May-11 21.05.11 04-Jun-11 28.05.11 A
Structural ACC-MAR-S-G-072 01 Division 03Concrete Mix Design for Retaining Wall (Fcu=75MPa) (Trial Mix Data Sheet Observation for Retaining Wall)
27-Apr-11 NBK 10-Mar-11 24-May-11 24.05.11 07-Jun-11 29.05.11 A
8 Structural ACC-MAR-S-G-030 00 Division 03 Formwork Release Agent - Formcoat S 27-Apr-11 Ayla 13-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
9 Structural ACC-MAR-S-G-020 00 Division 03 High Yield Steel Reinforcement Deformed Bar. 27-Apr-11 Qatar Steel 5-Mar-11 5-Mar-11 05-Mar-11 19-Mar-11 10-Mar-11 A ACC/WTC/VK/LOI/1002-001 27th March 2011 As per Site requirement 25-Mar-11 25-Mar-11 Part of Supplier Work
10 Structural ACC-MAR-S-G-044 00 - Injection Epoxy Chemical Adhesive 27-Apr-11 Fischer Fixing 15-Mar-11 26-Mar-11 26-Mar-11 09-Apr-11 29-Mar-11 A 13-Apr-11 13-Apr-11
11 Structural ACC-MAR-S-G-043 00 Division 03 Mechanical Splice, BSG Cold Swaged 27-Apr-11 Castle 15-Mar-11 22-Mar-11 22-Mar-11 05-Apr-11 26-Mar-11 A 10-Apr-11 10-Apr-11
12 Structural ACC-MAR-S-G-033 00 Division 03 Curing Compound - Setcrete AW (can be over coated) 27-Apr-11 Ayla 5-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
7 ATC/TT/VK/LOI/1001-001 Part of Supplier Work19th April 2011 As per Site requirement 13-Jun-11 13-Jun-11
)
13 Structural ACC-MAR-S-G-029 00 Division 03 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. 27-Apr-11 Modern Building 6-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
Structural ACC-MAR-S-G-023 00 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 22-Aug-11 NBK 9-Apr-11 9-Apr-11 08-Mar-11 22-Mar-11 13-Mar-11 C
Structural ACC-MAR-S-G-023 01 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 22-Aug-11 NBK 9-Apr-11 9-Apr-11 15-Mar-11 29-Mar-11 26-Mar-11 A
Structural ACC-MAR-S-G-023 02 Division 03 Concrete Mix Design for Ground Slab (Fcu=56MPa). 22-Aug-11 NBK 9-Apr-11 9-Apr-11 22-Mar-11 05-Apr-11 31-Mar-11 B
Structural ACC-MAR-S-G-023 03 Division 03 Concrete Mix Design for Raft and Retaining Wall (Fcu=56MPa). 22-Aug-11 NBK 9-Apr-11 9-Apr-11 09-Apr-11 23-Apr-11 10-Apr-11 A
15 Architectural ACC-MAR-A-G-078 00 Division 09 Block work Accessories 21-Mar-11 Unitech / SFSP 5-Feb-11 29-May-11 29-May-11 12-Jun-11 31-May-11 A 1-Mar-12 1-Mar-12
16 Architectural ACC-MAR-A-G-056 00 Division 09 Galvanized & Stainless Plastering Accessories 30-Jan-12 Unitech Qatar 18-Aug-11 25-Apr-11 25-Apr-11 09-May-11 28-Apr-11 A 1-May-12 1-May-12
17 Architectural ACC-MAR-A-G-163 00 Division 09 Ready Mix Plaster (Concrete Rush Coat SRC-2, Cement Plaster - SP 11) 30-Jan-12 Sodamco 18-Aug-11 31-Oct-11 31-Oct-11 14-Nov-11 17-Nov-11 B 1-May-12 1-Sep-12
Architectural ACC-MAR-A-G-198 00 Division 09 Floor Tile, Vitra Size 30X30 Code:K855586, Uni Graf - Grey
19-Apr-12 Sayyar / Vitra 14-Aug-11 23-May-12 23.05.12 06-Jun-12 28.05.12 A
14 ATC/TT/VK/LOI/1001-001 19th April 2011 As per Site requirement 25-Apr-11 25-Apr-11 Part of Supplier Work
Architectural ACC-MAR-A-G-198 01 Division 09Floor Tile, Vitra Size 30X30 (Option 1 : UNI IVORY K835803, Option 2: UNI MARKET K843514, Option 3: UNI S. WHITE K835910
19-Apr-12 Sayyar / Vitra 14-Aug-11 23-May-12 29.09.12 13-Oct-12 07.10.12 A
18 1-Nov-12 Bid Summary is Ready waiting consultant approvel
Page 33 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG OFFICE (From 4th Level) TOWER MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Remarks Approval Required By
Date of Return
Status Code
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Purchase Order Delivery Date
Planned Date of Submittal
Date Submitted to ACG (Actual)
DescriptionWork Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref.
Architectural ACC-MAR-A-G-257 00 Division 09 Ceramic Wall Tile, Vitra Option1: Color 7500, Option2: Color 7047 Option3:Color 8000
19-Apr-12 Sayyar / Vitra 14-Aug-11 23-May-12 23.05.12 06-Jun-12 28.05.12 A
Architectural ACC-MAR-A-G-257 01 Division 09
Ceramic Wal Tile 15x15cm (ALFARMAN - Option 1: CINZA -196.0, Option 2: BRANCO-001.0, Option 3 : CINZA ESCURO-640.0,Option 4: BEGE-514.0, Option 5: BEGE CLARO -441.0, Option 6: MARFIM-002.0, Option 7: CRÈME-302.0, Option 8: BEGE ROSA-675.0 (For Sayyar Option 9: RAL 19-Apr-12 Al Farma-Primus
Vitoria / Sayyar Vitra14-Aug-11 23-May-12 29.09.12 13-Oct-12 06.10.12 A
19 Bid Summary is Ready waiting final approvel from consultant1-Oct-12
0006500A K891571, Option 10: RAL 0809005A K878793, Option 11: RAL 0809010A K787632, Option 12: RAL 0007500A K502843, Option 13: RAL 0008000A K891582, Option 14: RAL 1009005A K855376
Vitoria / Sayyar-Vitra
20 Architectural ACC-MAR-A-G- 00 Division 09 Granite Flooring 14-May-12 Specialized Marble / Stone Gallary
14-Aug-11 23-Aug-12 1-Feb-13 waiting for revised I.D Drawing
21 Architectural ACC-MAR-A-G- 00 Division 08 Wooden Cladding 14-May-12 1000 walls 3-Dec-11 31-May-12 1-Jul-13 waiting for revised I.D Drawing
22 Architectural ACC-MAR-A-G- 00 N/A Stainless steel decorative jamb 14-May-12 Sasco/ Globtech 5-Jan-12 3-Jul-12 1-Mar-13 waiting for revised I.D Drawing
23 Architectural ACC-MAR-A-G- 00 Division 09 Marble Cladding 14-May-12 Specialized Marble / Stone Gallary
14-Aug-11 23-Aug-12 1-Feb-13 waiting for revised I.D Drawing
24 Architectural ACC-MAR-A-G- 00 Division 09 Marble Flooring 14-May-12 Specialized Marble / Stone Gallary
14-Aug-11 23-Aug-12 1-Feb-13 waiting for revised I.D Drawing
25 Architectural ACC-MAR-A-G- 00 Division 11 Cleaning Cradle 30-Jan-12 Power Machine / United Eqpt
22-Jun-11 17-Sep-12 1-Jun-13 Bid Summary is Ready waiting consultant approvel
26 Architectural ACC-MAR-A-G- 00 Division 10 Garbage Chute 1-Feb-13 Globtech 1-Apr-12 1-Oct-12ACC/TT/VK/LOI 3025 001
9th September 2012 1-Jan-13 Part of Subcontract Work
ACC/TT/VK/LOI – 3025 - 001 2012
Architectural ACC-MAR-A-G-305 00 Division 07 Adeprimaire Siplast Wet Area Water Proofing 30-Jan-12 Tadmur / Siplast 31-Oct-11 9-May-12 01.04.12 15.04.12 09.04.12 C
Architectural ACC-MAR-A-G-305 01 Division 07 Adeprimaire Siplast Wet Area Water Proofing 30-Jan-12 Tadmur / Siplast 31-Oct-11 9-May-12 09.05.12 23.05.12 28.05.12 B
28 Architectural ACC-MAR-A-G-115 00 Division 07 Fire Stoping Sealant 16-Jan-12 Unitech Qatar 25-Jul-11 25-Jul-11 25-Jul-11 08.08.11 06-Aug-11 A 1-Sep-12 1-Sep-12
29 Architectural ACC-MAR-A-G- 00 Division 09 PVC Skirting 31-Mar-12 31-Dec-11 28-Jun-12 1-Jan-13
Architectural ACC-MAR-A-G-217 00 Division 07 20mm / 25mm Backing Rod for Joint Sealant 31-Mar-12 Arnon Plastic / Modern Builders
31-Dec-11 20-May-12 05.05.12 19.05.12 17.05.12 C
Architectural ACC-MAR-A-G-217 01 Division 07 20mm / 25mm / 30mm Backing Rod for Joint Sealant
31-Mar-12 Arnon/Modern Builders
31-Dec-11 20-May-12 20.05.12 03.06.12 28.05.12 A
Architectural ACC-MAR-A-G-283 00 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
27-Feb-12 Sodamco 28-Nov-11 8-May-12 19.02.12 04.03.12 27.02.12 C
Architectural ACC-MAR-A-G-283 01 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
27-Feb-12 Sodamco 28-Nov-11 8-May-12 20.03.12 03.04.12 03.05.12 B
Architectural ACC-MAR-A-G-283 02 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive)
27-Feb-12 Sodamco 28-Nov-11 8-May-12 08.05.12 22.05.12 21.05.12 A
Architectural ACC-MAR-A-G-285 00 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 27-Feb-12 Sodamco 28-Nov-11 8-May-12 19.02.12 04.03.12 26.02.12 C
30
31
27 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 1-Sep-12 1-Sep-12 Part of Subcontract Work
1-Oct-12
1-Oct-12
j ( ) y
Architectural ACC-MAR-A-G-285 01 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 27-Feb-12 Sodamco 28-Nov-11 8-May-12 20.03.12 03.04.12 03.05.12 B
Architectural ACC-MAR-A-G-285 02 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 27-Feb-12 Sodamco 28-Nov-11 8-May-12 08.05.12 22.05.12
33 Architectural ACC-MAR-A-G-385 00 Division 06
Sample For Pantry & Toilet Doors Option 1: Mahogany Laminate with Beech wood frame & Architrave stained to Mahogany color Option 2: Ivory Laminate w/ Beech wood frame & Architrave with RAL color 7011 Option 3: Beech Laminate with Beech wood frame & Architrave with natural Finish Option 4: Beige color Laminate with Beech wod frame & Architrave with RAL color 8017
24-May-12 1000 Walls 3-Dec-11 30-Aug-12 26-Sep-12 10.10.12 30-Sep-12 C 1-Jul-13 Bid Summary is Ready waiting consultant approvel
34 Architectural ACC-MAR-A-G- 00 Division 08 Steel Doors & Hardware 14-Apr-12 Indigatech 3-Dec-11 31-May-12 1-May-13 Bid Summary is Ready, waiting final approvel form consultant
32 1-Oct-12
Page 34 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG OFFICE (From 4th Level) TOWER MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Remarks Approval Required By
Date of Return
Status Code
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Purchase Order Delivery Date
Planned Date of Submittal
Date Submitted to ACG (Actual)
DescriptionWork Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref.
35 Architectural ACC-MAR-A-G- 00 Division 08 Hardware 14-Apr-12 Dorma / Hafele 3-Dec-11 31-May-12 1-May-13 Bid Summary is Ready,Dorma sample to submit
36 Architectural ACC-MAR-A-G-339 00 Division 10 Lavender Blue Vanity Unit 19-May-12 Stone Gallery 11-Dec-11 8-Jun-12 30-Jun-12 14-Jul-12 07-Jul-12 A 1-Feb-13 Bid Summary is Ready waiting consultant approvel
37 Architectural ACC-MAR-A-G-340 00 Division 11 Pantry Countertop ( Option 1: Black Absolute, Option 2: Black Galaxy)
24-May-12 Specialized Marble & Granite WLL
16-Dec-11 13-Jun-12 30-Jun-12 14-Jul-12 07-Jul-12 A 1-Feb-13 Bid Summary is Ready waiting consultant approvel
38 Architectural ACC-MAR-A-G- 00 Division 09 Fiber Cement Borad Partition System 1-Sep-12 Elite enginnring 2-Jun-12 29-Nov-12 1-Feb-13 subcontractor preqalification to submit
A li C l E l i ith O t t diArchitectural ACC-MAR-A-G-312 00 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability
20-May-12 Juton 19-Feb-12 17-Aug-12 11-Apr-12 25-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-312 01 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability
20-May-12 Juton/Roots Qatar 19-Feb-12 17-Aug-12 26-Jul-12 09-Aug-12 05-Aug-12 B
40 Architectural ACC-MAR-A-G- 00 Division 09 Gypsum Board Ceiling - Regular 2-May-12 Interarc / Elite 24-Dec-11 21-Jun-12 1-Jan-13 Bid Summary is Ready waiting consultant approvel
41 Architectural ACC-MAR-A-G- 00 Division 11 Pantry Cabinet 19-May-12 1000 Walls 10-Jan-12 8-Jul-12 1-May-13 Bid Summary is Ready waiting consultant approvel
Architectural ACC-MAR-A-G-352 00 Division 09 Metal Strip Ceiling(100 mm, 150 mm, 200 mm & 300 mm)
26-Apr-12QASR AL
ANDALUS/ SADDI METAL
26-Jan-12 24-Jul-12 21-Jul-12 04-Aug-12 06-Aug-12 C
Architectural ACC-MAR-A-G-352 01 Division 09 Matador (100 mm, 150 mm, 200 mm & 300 mm) Linear Metal Strip Ceiling
26-Apr-12 Marconi/ INTERARC
26-Jan-12 24-Jul-12 31-Jul-12 14-Aug-12 13-Aug-12 C
43 Architectural ACC-MAR-A-G- 00 Division 05 G.S. Handrails & Rails 14-Apr-12 Qatar Indo Fab 14-Jan-12 12-Jul-12 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-May-13 Part of Subcontract Work
44 Architectural ACC-MAR-A-G- 00 Division 03 Concrete Tiles 27-Feb-12 28-Nov-11 26-May-12 1-Oct-13
45 Architectural ACC-MAR-A-G- 00 Division 09 Gravel for Planters 16-Apr-12 16-Jan-12 14-Jul-12 1-Jan-14 External Works
42
39
subcontractor preqalification to submit 1-Feb-13
1-Dec-12 Bid Summary is Ready,L.O.I to be issue
46 Architectural ACC-MAR-A-G- 00 Division 05 S. Steel Ladder /Cat walk 27-Feb-12 Qatar Indo Fab 28-Nov-11 26-May-12 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-Nov-13 Part of Subcontract Work
47 Architectural ACC-MAR-A-G- 00 Division 07 Thermal Insulation System (roof system) 27-Feb-12 Tadmur 28-Nov-11 26-May-12 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 1-Oct-13 Part of Subcontract Work
48 Architectural ACC-MAR-A-G- 00 Division 10 Signage 11-Apr-12 3-Nov-11 1-May-12 1-Jun-13 Quotation Under Evalution
49 Architectural ACC-MAR-A-G-259 00 Division 09 Porcelain Tile for Step Tread, Riser & Skirtings 15-Mar-12 Sayyar / Vitra 15-Dec-11 12-Jun-12 23-May-12 06-Jun-12 28-May-12 A 1-Apr-13 Bid Summary is Ready waiting consultant approvel
50 Architectural ACC-MAR-A-G- 00 - FULLY VITRIFIED MOSAIC TILES 150 X 150 X 9MM 14-May-12 Farman / sayyar 13-Feb-12 11-Aug-12 1-Jan-14
51 Architectural ACC-MAR-A-G- 00 - Speed lanes 14-May-12 13-Feb-12 11-Aug-12 1-Dec-13
Architectural ACC-MAR-A-G-305 00 - Adeprimaire Siplast Wet Area Water Proofing 21-Jun-12 Tadmur / Siplast 22-Mar-12 18-Sep-12 01-Apr-12 15-Apr-12 09-Apr-12 C
Architectural ACC-MAR-A-G-305 01 - Adeprimaire Siplast Wet Area Water Proofing 21-Jun-12 Tadmur / Siplast 22-Mar-12 18-Sep-12 09-May-12 23-May-12 28-May-12 B
53 Architectural ACC-MAR-A-G- 00 - Floating floor for MEP Equipment 13-Jun-12 14-Mar-12 10-Sep-12 1-Feb-13
54 Architectural ACC-MAR-A-G- 00 Division 09 Mirror 26-Jan-13 Spectra Arts 27-Oct-12 26-Dec-12 1-Jun-13 Quotation Under Evalution
52 Part of Subcontract WorkACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-Oct-12
55 Architectural ACC-MAR-A-G- 00 - ANTI-STATIC LINOLEUM 13-Jun-12 14-Mar-12 10-Sep-12 1-Apr-13 Quotation Under Evalution
56 Architectural ACC-MAR-A-G- 00 - Counter at reception in ground floor 15-May-13 1-Oct-12 30-Dec-12 1-Dec-13 Need detail Drg, & Specs
Page 35 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG PODIUM (Project from 3rd Basement : 3rd Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
1 Structural ACC-MAR-S-G-046 00 Division 07 Twin Walls Pelypropylene Alternative Protection Board 18-May-11 Tadmur 5-Mar-11 30-Mar-11 30-Mar-11 13-Apr-11 05-Apr-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 20-Apr-11 20-Apr-11 Part of Subcontract Work
2 Structural ACC-MAR-S-G-048 00 Cementitious Grout for Pile Head Treatment 25-Apr-11 Tadmur 5-Mar-11 2-Apr-11 02-Apr-11 16-Apr-11 05-Apr-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 20-Apr-11 20-Apr-11 Part of Subcontract Work
3 Structural ACC-MAR-S-G-061 00 NITOFILL EPLV - Low Viscosity Epoxy Injection Resin System Crack Repair Material for Pile Head 18-May-11 Tadmur/Fosroc 5-Mar-11 7-May-11 07-May-11 21-May-11 12-May-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 27-May-11 27-May-11 Part of Subcontract Work
4 Structural ACC-MAR-S-G- 00 Division 05 Expansion Bolts (Podium Steel St.) 12-Aug-12 GSI 19-Oct-11 15-Sep-12 ACC/TT/VK/LOI-3013-001 10th September 2012
As per Site requirement 15-Mar-13 Part of Subcontract Work
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Delivery Date
RemarksApproval Required By
Date of Return
Status Code Purchase Order
Planned Date of Submittal
Date Submitted to ACG (Actual)
Work Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref. Description
5 Structural ACC-MAR-S-G- 00 Division 05 Steel Decking Sheet (Podium Steel St.) 12-Aug-12 GSI 19-Oct-11 15-Sep-12 ACC/TT/VK/LOI-3013-001 10th September 2012
As per Site requirement 15-Mar-13 Part of Subcontract Work
6 Structural ACC-MAR-S-G- 00 Division 05 Welding Rod (Podium Steel St.) 12-Aug-12 GSI 19-Oct-11 15-Sep-12 ACC/TT/VK/LOI-3013-001 10th September 2012
As per Site requirement 15-Mar-13 Part of Subcontract Work
7 Structural ACC-MAR-S-G- 00 Division 05 Fasteners from Swenn for Structural Steel Works 12-Aug-12 GSI 19-Oct-11 15-Sep-12 ACC/TT/VK/LOI-3013-001 10th September
2012As per Site
requirement 15-Mar-13 Part of Subcontract Work
8 Structural ACC-MAR-S-G-009 00 Division 03 Design Mix for Blinding Concrete 31-Mar-11 NBK RM 13-Feb-11 13-Feb-11 13-Feb-11 27-Feb-11 20-Feb-11 A ATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Site requirement 7-Mar-11 7-Mar-11 Part of Supplier Work
9 Structural ACC-MAR-S-G-008 00 Division 03 Polyethylene Sheet (Sizes: 1000 gauge - 250 micron) 4-May-11 Petro Plastic
Factory 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 7-Mar-11 7-Mar-11
10 Structural ACC-MAR-S-G-001 00 Division 04
Hollow & Solid Concrete Block (Hollow Concrete Block Sizes: 400 x 200 x 200, 400 x 150 x 200, 400 x 100 x 200, Solid Concrete Block Sizes: 400 x 100 x 200, 400 x 150 x 200, 400 x 200 x 200)
10-Apr-11 Aamal Cement Indu. 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 20-Feb-11 A 7-Mar-11 7-Mar-11
11 Structural ACC-MAR-S-G-002 00 Division 04 Ordinary Portland Cement for Masonary Mortar 10-Apr-11 Tayseer Bldg. Mtrls. Co. 8-Feb-11 8-Feb-11 08-Feb-11 22-Feb-11 23-Feb-11 A 10-Mar-11 10-Mar-11
12 Structural ACC-MAR-S-G-0176 00 Division 07 Alternative Waterproofing for Substructural and Water tank 4-May-11 Tadmur 8-Feb-11 8-Feb-11 14-Nov-11 28-Nov-11 04-Feb-12 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 19-Feb-12 19-Feb-12 Part of Subcontract Work
13 Structural ACC-MAR-S-G-025 00 Division 03 Mix Design for Screed 4-May-11 NBK 5-Mar-11 12-Mar-11 12-Mar-11 26-Mar-11 17-Mar-11 A ATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Siterequirement 1-Apr-11 1-Apr-11 Part of Supplier Work requirement
14 Structural ACC-MAR-S-G-028 00 Division 03 Fibre Concrete Spacers. 6-Jun-11 Castle 10-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
Structural ACC-MAR-S-G-072 00 Division 03 Concrete Mix Design for Retaining Wall (Fcu=75MPa) 20-Jul-11 NBK 10-Mar-11 24-May-11 21-May-11 04-Jun-11 28-May-11 A
Structural ACC-MAR-S-G-072 01 Division 03Concrete Mix Design for Retaining Wall (Fcu=75MPa) (Trial Mix Data Sheet Observation for Retaining Wall)
20-Jul-11 NBK 10-Mar-11 24-May-11 24-May-11 07-Jun-11 29-May-11 A
16 Structural ACC-MAR-S-G-030 00 Division 03 Formwork Release Agent - Formcoat S 20-Jul-11 Ayla 13-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
17 Structural ACC-MAR-S-G-020 00 Division 03 High Yield Steel Reinforcement Deformed Bar. 6-Jun-11 Qatar Steel 5-Mar-11 5-Mar-11 05-Mar-11 19-Mar-11 10-Mar-11 A ACC/WTC/VK/LOI/1002-001 27th March 2011 As per Site requirement 25-Mar-11 25-Mar-11 Part of Supplier Work
18 Structural ACC-MAR-S-G-044 00 - Injection Epoxy Chemical Adhesive 6-Jun-11 Fischer Fixing 15-Mar-11 26-Mar-11 26-Mar-11 09-Apr-11 29-Mar-11 A 13-Apr-11 13-Apr-11
19 Structural ACC-MAR-S-G-043 00 Division 03 Mechanical Splice, BSG Cold Swaged 6-Jun-11 Castle 15-Mar-11 22-Mar-11 22-Mar-11 05-Apr-11 26-Mar-11 A 10-Apr-11 10-Apr-11
20 Structural ACC-MAR-S-G-033 00 Division 03 Curing Compound - Setcrete AW (can be over coated) 6-Jun-11 Ayla 5-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
21 Structural ACC-MAR-S-G-029 00 Division 03 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. 6-Jun-11 Modern Building 5-Mar-11 13-Mar-11 13-Mar-11 27-Mar-11 17-Mar-11 A 1-Apr-11 1-Apr-11
St t l ACC MAR S G 023 00 Di i i 03 Concrete Mix Design for Ground Slab, Suspended 6 J 11 NBK 5 M 11 9 A 11 08 M 11 22 M 11 13 M 11 C
15 13-Jun-11 Part of Supplier WorkATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Site requirement 13-Jun-11
Structural ACC-MAR-S-G-023 00 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 6-Jun-11 NBK 5-Mar-11 9-Apr-11 08-Mar-11 22-Mar-11 13-Mar-11 C
Structural ACC-MAR-S-G-023 01 Division 03 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). 6-Jun-11 NBK 5-Mar-11 9-Apr-11 15-Mar-11 29-Mar-11 26-Mar-11 A
Structural ACC-MAR-S-G-023 02 Division 03 Concrete Mix Design for Ground Slab (Fcu=56MPa). 6-Jun-11 NBK 5-Mar-11 9-Apr-11 22-Mar-11 05-Apr-11 31-Mar-11 B
Structural ACC-MAR-S-G-023 03 Division 03 Concrete Mix Design for Raft and Retaining Wall (Fcu=56MPa). 6-Jun-11 NBK 5-Mar-11 9-Apr-11 09-Apr-11 23-Apr-11 10-Apr-11 A
23 Structural ACC-MAR-S-G-014 00 Division 03 & 7 PVC Waterstop - Fosroc Supercast PVC. 6-Jun-11 Tadmur 2-Mar-11 2-Mar-11 02-Mar-11 16-Mar-11 06-Mar-11 A ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site
requirement 21-Mar-11 21-Mar-11 Part of Subcontract Work
24 Structural ACC-MAR-S-G- 00 Division 05 Chequered Plate Cover 14-Sep-11 Qatar Indo Fab 15-Jun-11 12-Dec-11 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 15-Mar-13 Part of Subcontract Work
Architectural ACC-MAR-A-G-26 00 Division 07 Waterproofing for Sub structural and Water Tank. 4-May-11 Tadmur 2-Feb-11 15-Mar-11 12-Mar-11 26-Mar-11 15-Mar-11 C
Architectural ACC-MAR-A-G-26 01 Division 07 Waterproofing for Sub structural and Water Tank. 4-May-11 Tadmur 2-Feb-11 15-Mar-11 15-Mar-11 29-Mar-11 17-Mar-11 A
26 Architectural ACC-MAR-A-G- 00 Division 08 Fire Rated Trap 16-Feb-13 1000 Walls 1-Jun-12 1-Nov-12 1-Dec-12 Bid Summary is Ready waiting consultant approvel
25
25-Apr-11 Part of Supplier Work
1-Apr-11 Part of Subcontract WorkACC/WTC/VK/LOI/1002-001 27th March 2011 As per Site requirement 1-Apr-11
22 ATC/TT/VK/LOI/1001-A/001 9th April 2011 As per Site requirement 25-Apr-11
Page 36 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG PODIUM (Project from 3rd Basement : 3rd Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Delivery Date
RemarksApproval Required By
Date of Return
Status Code Purchase Order
Planned Date of Submittal
Date Submitted to ACG (Actual)
Work Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref. Description
27 Architectural ACC-MAR-A-G-078 00 Division 09 Block work Accessories 10-Apr-11 Unitech / SFSP 5-Feb-11 29-May-11 29-May-11 12-Jun-11 31-May-11 A 7-Jun-11 7-Jun-11
Page 37 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG PODIUM (Project from 3rd Basement : 3rd Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Delivery Date
RemarksApproval Required By
Date of Return
Status Code Purchase Order
Planned Date of Submittal
Date Submitted to ACG (Actual)
Work Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref. Description
28 Architectural ACC-MAR-A-G-056 00 Division 09 Galvanized & Stainless Plastering Accessories 26-Apr-12 Unitech Qatar 18-Aug-11 25-Apr-11 25-Apr-11 09-May-11 28-Apr-11 A 5-May-11 5-May-11
29 Architectural ACC-MAR-A-G-163 00 Division 09 Ready Mix Plaster (Concrete Rush Coat SRC-2, Cement Plaster - SP 11) 26-Apr-12 Sodamco 18-Aug-11 31-Oct-11 31-Oct-11 14-Nov-11 17-Nov-11 B 24-Nov-11 1-Sep-12
Architectural ACC-MAR-A-G-198 00 Division 09 Floor Tile, Vitra Size 30X30 Code:K855586, Uni Graf - Grey 12-Dec-12 Sayyar / Vitra 14-Aug-11 23-May-12 23-May-12 06-Jun-12 28-May-12 A
Architectural ACC-MAR-A-G-198 01 Division 09Floor Tile, Vitra Size 30X30 (Option 1 : UNI IVORY K835803, Option 2: UNI MARKET K843514 Option 3: UNI S WHITE K835910
12-Dec-12 Sayyar / Vitra 14-Aug-11 23-May-12 29-Sep-12 13-Oct-12 07-Oct-12 A
30 1-Dec-12 Bid Summary is Ready waiting final approvel from consultant
K843514, Option 3: UNI S. WHITE K835910
Architectural ACC-MAR-A-G-257 00 Division 09 Ceramic Wall Tile, Vitra Option1: Color 7500, Option2: Color 7047 Option3:Color 8000 12-Dec-12 Sayyar / Vitra 14-Aug-11 23-May-12 23-May-12 06-Jun-12 28-May-12 A
Architectural ACC-MAR-A-G-257 01 Division 09
Ceramic Wal Tile 15x15cm (ALFARMAN - Option 1: CINZA -196.0, Option 2: BRANCO-001.0, Option 3 : CINZA ESCURO-640.0,Option 4: BEGE-514.0, Option 5: BEGE CLARO -441.0, Option 6: MARFIM-002.0, Option 7: CRÈME-302.0, Option 8: BEGE ROSA-675.0 (For Sayyar Option 9: RAL 0006500A K891571, Option 10: RAL 0809005A K878793, Option 11: RAL 0809010A K787632, Option 12: RAL 0007500A K502843, Option 13: RAL 0008000A K891582, Option 14: RAL 1009005A K855376
12-Dec-12Al Farma-Primus Vitoria / Sayyar-
Vitra14-Aug-11 23-May-12 29-Sep-12 13-Oct-12 06-Oct-12 A
32 Architectural ACC-MAR-A-G- 00 Division 09 Granite Flooring 3-Feb-13Specialized
Marble / Stone G ll
14-Aug-11 23-Aug-12 1-Apr-13 waiting for revised I.D Drawing
33 Architectural ACC-MAR-A-G- 00 Division 09 Marble Cladding 3-Feb-13Specialized
Marble / Stone 14-Aug-11 23-Aug-12 1-Apr-13 waiting for revised I.D Drawing
31 1-Dec-12 Bid Summary is Ready waiting final approvel from consultant
33 c tectu a CC G 00 s o 09 a b e C add g 3 eb 3 Marble / Stone G ll
ug 3 ug p 3 a t g o e sed a g
34 Architectural ACC-MAR-A-G- 00 Division 09 Marble Flooring 3-Feb-13Specialized
Marble / Stone G ll
14-Aug-11 23-Aug-12 1-Apr-13 waiting for revised I.D Drawing
Architectural ACC-MAR-A-G-305 00 Division 07 Adeprimaire Siplast Wet Area Water Proofing 17-Oct-12 Tadmur / Siplast 9-May-12 9-May-12 01-Apr-12 15-Apr-12 09-Apr-12 C
Architectural ACC-MAR-A-G-305 01 Division 07 Adeprimaire Siplast Wet Area Water Proofing 17-Oct-12 Tadmur / Siplast 9-May-12 9-May-12 09-May-12 23-May-12 28-May-12 B
36 Architectural ACC-MAR-A-G-115 00 - Fire Stoping Sealant 26-Aug-12 Unitech Qatar 9-May-12 25-Jul-11 25-Jul-11 08-Aug-11 06-Aug-11 A 1-May-12 1-May-12
37 Architectural ACC-MAR-A-G-349 00 Division 08 GEZE Automatic Door Operator 28-Apr-13 AGR/ GEZE- Company 17-Jul-12 17-Jul-12 17-Jul-12 31-Jul-12 06-Oct-12 C ACC/TT/VK/LOI-3006-001 15th April 2012 As per Site
requirement 1-Dec-13 Part of Subcontract Work
38 Architectural ACC-MAR-A-G- 00 - Expansion Joint Covers 4-Jan-13 28-Jun-12 26-Oct-12 1-Apr-13
39 Architectural ACC-MAR-A-G- 00 Division 09 PVC Skirting 10-Jan-13 11-Oct-12 8-Feb-13 1-Apr-13
Architectural ACC-MAR-A-G-217 00 Division 07 20mm / 25mm Backing Rod for Joint Sealant 3-Feb-13 Arnon Plastic / Modern Builders 20-May-12 20-May-12 05-May-12 19-May-12 17-May-12 C
Architectural ACC-MAR-A-G-217 01 Division 07 20mm / 25mm / 30mm Backing Rod for Joint Sealant 3-Feb-13 Arnon/Modern
Builders 20-May-12 20-May-12 20-May-12 03-Jun-12 28-May-12 A
Architectural ACC-MAR-A-G-283 00 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive) 28-Mar-13 Sodamco 8-May-12 8-May-12 19-Feb-12 04-Mar-12 27-Feb-12 C
40
35 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 1-Oct-12 Part of Subcontract Work
1-Dec-12
Adhesive)
Architectural ACC-MAR-A-G-283 01 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive) 28-Mar-13 Sodamco 8-May-12 8-May-12 20-Mar-12 03-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-283 02 Division 09 Carrocolle WP (Regular Cement Based Tile Adhesive) 28-Mar-13 Sodamco 8-May-12 8-May-12 08-May-12 22-May-12 21-May-12 A
Architectural ACC-MAR-A-G-285 00 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 28-Mar-13 Sodamco 8-May-12 8-May-12 19-Feb-12 04-Mar-12 26-Feb-12 C
Architectural ACC-MAR-A-G-285 01 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 28-Mar-13 Sodamco 8-May-12 8-May-12 20-Mar-12 03-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-285 02 Division 09 Carrojoint Thin / Thick (Cementitious Tile Grout) 28-Mar-13 Sodamco 8-May-12 8-May-12 08-May-12 22-May-12
43 Architectural ACC-MAR-A-G- 00 Division 06 Wooden Doors 14-Mar-13 1000 Walls 1-Jul-12 30-Aug-12 1-Aug-13 Bid Summary is Ready waiting consultant approvel
44 Architectural ACC-MAR-A-G- 00 Division 08 Steel Doors & Hardware 19-Mar-13 Indigatech 1-Aug-12 29-Dec-12 1-Apr-13 Bid Summary is Ready Door sample to submit
45 Architectural ACC-MAR-A-G- 00 Division 08 Hardware 19-Mar-13 Dorma/ Hafele 1-Aug-12 29-Dec-12 1-Apr-13 Bid Summary is Ready,Dorma sample to submit
46 Architectural ACC-MAR-A-G-339 00 Division 10 Lavender Blue Vanity Unit 11-Mar-13 Stone Gallery 30-Jun-12 30-Jun-12 30-Jun-12 14-Jul-12 07-Jul-12 A 1-Jul-13 Bid Summary is Ready waiting consultant approvel
42
41
1-Dec-12
1-Dec-12
Page 38 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG PODIUM (Project from 3rd Basement : 3rd Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Delivery Date
RemarksApproval Required By
Date of Return
Status Code Purchase Order
Planned Date of Submittal
Date Submitted to ACG (Actual)
Work Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref. Description
47 Architectural ACC-MAR-A-G-340 00 Division 11 Pantry Countertop ( Option 1: Black Absolute, Option 2: Black Galaxy) 11-Mar-13
Specialized Marble & Granite
WLL30-Jun-12 30-Jun-12 30-Jun-12 14-Jul-12 07-Jul-12 A 1-Jul-13 Bid Summary is Ready
waiting consultant approvel
48 Architectural ACC-MAR-A-G- 00 Division 09 Dry Wall Partition System 13-Feb-13 Elite engineering 1-Nov-12 31-Dec-12 1-Jun-13 Subcontractor preqalification to submit
Architectural ACC-MAR-A-G-312 00 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability 21-Feb-13 Juton 1-Nov-12 31-Dec-12 11-Apr-12 25-Apr-12 03-May-12 B
Architectural ACC-MAR-A-G-312 01 Division 09 Acrylic Copolymer Emulsion with Outstanding Washability 21-Feb-13 Juton/Roots
Qatar 1-Nov-12 31-Dec-12 26-Jul-12 09-Aug-12 05-Aug-12 B
49 1-Mar-13 Bid Summary is Ready,L.O.I to be issue
50 Architectural ACC-MAR-A-G- 00 Division 09 Paint Systems(/Epoxy & road marking & deck coating) 21-Feb-13 JUTON / ROOTS 1-Nov-12 31-Dec-12 1-Mar-13 Bid Summary is Ready,
L.O.I to be issue
51 Architectural ACC-MAR-A-G- 00 Division 09 Gypsum Ceiling 27-Feb-13 Interarc / Elite 1-Jul-12 29-Oct-12 1-Jan-13 Bid Summary is Ready waiting consultant approvel
Architectural ACC-MAR-A-G-352 00 Division 09 Metal Strip Ceiling(100 mm, 150 mm, 200 mm & 300 mm) 27-Feb-13
QASR AL ANDALUS/
SADDI METAL31-Jul-12 31-Jul-12 21-Jul-12 04-Aug-12 06-Aug-12 C
Architectural ACC-MAR-A-G-352 01 Division 09 Matador (100 mm, 150 mm, 200 mm & 300 mm) Linear Metal Strip Ceiling 27-Feb-13 Marconi/
INTERARC 31-Jul-12 31-Jul-12 31-Jul-12 14-Aug-12 13-Aug-12 C
53 Architectural ACC-MAR-A-G- 00 - Cubical Doors and Partitions 16-Feb-13 1-Jun-12 29-Oct-12 1-Jan-14 Quotation Under Evalution
54 Architectural ACC-MAR-A-G- 00 Division 11 Pantry Cabinet 16-Feb-13 1000 Walls 9-Oct-12 8-Mar-13 1-Oct-13 Bid Summary is Ready waiting consultant approvel
55 Architectural ACC-MAR-A-G-349 00 Division 08 GEZE Automatic Door Operator 15-May-13 AGR/ GEZE- Company 17-Jul-12 17-Jul-12 17-Jul-12 31-Jul-12 06-Oct-12 C ACC/TT/VK/LOI-3006-001 15th April 2012 As per Site
requirement 1-Jan-14 Part of Subcontract Work
Sample For Pantry & Toilet Doors Option 1: Mahogany Laminate with Beech wood frame & Architrave stained to Mahogany
52 1-Jan-13 Bid Summary is Ready waiting consultant approvel
56 Architectural ACC-MAR-A-G-385 00 Division 08
wood frame & Architrave stained to Mahogany color Option 2: Ivory Laminate w/ Beech wood frame & Architrave with RAL color 7011 Option 3: Beech Laminate with Beech wood frame & Architrave with natural Finish Option 4: Beige color Laminate with Beech wod frame & Architrave with RAL color 8017
16-Feb-13 1000 Walls 24-Oct-12 23-Mar-13 26-Sep-12 10-Oct-12 30-Sep-12 C 1-Aug-13 Bid Summary is Ready waiting consultant approvel
57 Architectural ACC-MAR-A-G- 00 Division 05 S. Steel Handrails 7-Feb-13 Qatar Indo Fab 8-Nov-12 7-Apr-13 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-May-13 Part of Subcontract Work
58 Architectural ACC-MAR-A-G- 00 Division 05 G.S. Handrails & Rails 2-May-13 Qatar Indo Fab 31-Jan-13 30-Jun-13 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-May-13 Part of Subcontract Work
59 Architectural ACC-MAR-A-G- 00 Division 03 Concrete Tiles 28-Mar-13 27-Dec-12 26-May-13 1-Oct-13
60 Architectural ACC-MAR-A-G- 00 Division 09 Traffic /Road Marking Paint 11-Apr-13 Roots Qatar 10-Jan-13 9-Jun-13 1-Jan-14 Bid Summary is Ready,L.O.I to be issue
61 Architectural ACC-MAR-A-G- 00 Division 03 Kerb Stone 1-Jan-13 2-Oct-12 1-Mar-13 1-Oct-13
62 Architectural ACC-MAR-A-G- 00 Division 09 Gravel for Planters 16-Apr-13 15-Jan-13 14-Jun-13 1-Oct-13
63 Architectural ACC-MAR-A-G- 00 Division 05 S. Steel Ladder /Cat walk 13-Apr-13 Qatar Indo Fab 12-Jan-13 11-Jun-13 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-Oct-13 Part of Subcontract Work
64 Architectural ACC-MAR-A-G- 00 Division 05 Steel Guardrails 28-Mar-13 Qatar Indo Fab 27-Dec-12 26-May-13 ACC/TT/VK/LOI-3025-001 15th September 2012
As per Site requirement 1-Oct-13 Part of Subcontract Work
65 Architectural ACC-MAR-A-G- 00 Division 07 Thermal Insulation System (roof system) 29-Jan-13 Tadmur 30-Oct-12 29-Mar-13 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site requirement 1-Oct-13 Part of Subcontract Work
66 Architectural ACC-MAR-A-G- 00 Division 10 Wall & Corner Guards 11-Apr-13 10-Jan-13 9-Jun-13 1-Oct-13
67 Architectural ACC-MAR-A-G- 00 Division 10 Wheel Stopper & Speed Hump 11-Apr-13 10-Jan-13 9-Jun-13 1-Oct-13
68 Architectural ACC-MAR-A-G- 00 Division 10 Signage 11-Apr-13 2-Nov-12 1-Apr-13 1-Dec-13 Quotation Under Evalution
69 Architectural ACC-MAR-A-G- 00 Division 10 Traffic Guard / Barrier 11-Apr-13 10-Jan-13 9-Jun-13 1-Oct-13 Enquiry to float
70 Architectural ACC-MAR-A-G- 00 Division 09 Carpet 3-Jun-13 25-Dec-12 24-May-13 1-Aug-13 Quotation Under Evalution
71 Architectural ACC-MAR-A-G- 00 Division 03 Soft & Hard Landscape 1-Jan-13 2-Oct-12 1-Mar-13 1-Oct-13 Quotation Under Evalution
72 Architectural ACC-MAR-A-G-259 00 Division 09 Porcelain Tile for Step Tread, Riser & Skirtings 27-Dec-12 Sayyar / Vitra 23-May-12 23-May-12 23-May-12 06-Jun-12 28-May-12 A 1-Aug-13 Bid Summary is Ready waiting consultant approvel
Page 39 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager: HPM TWIN TOWERS DOHA, QATAR Discipline : Structural / Architectural
Consultant: ACG PODIUM (Project from 3rd Basement : 3rd Level) MATERIAL SUBMITTAL REGISTER (MAR) & PROCUREMENT SCHEDULE Data date : 21-Oct-12
Main Contractor: Arabtec Construction Co.
A B C D LPO No. DateDelivery Period from Receipt of
OrderPlanned Actual
Subcontractor / Supplier
Date of Submittal (Planned)
Baseline dates
Delivery Date
RemarksApproval Required By
Date of Return
Status Code Purchase Order
Planned Date of Submittal
Date Submitted to ACG (Actual)
Work Start Date
Baseline datesSl No. Discipline Submittal No. Rev. Specs. Ref. Description
73 Architectural ACC-MAR-A-G- 00 - FULLY VITRIFIED MOSAIC TILES 150 X 150 X 9MM 27-Jan-13 Sayyar/Farman 28-Oct-12 27-Mar-13 1-Jun-13 Bid Summary is Ready
waiting consultant approvel
74 Architectural ACC-MAR-A-G- 00 - GLASS FLAKES EPOXY PAINT 28-Mar-13 Roots Qatar 27-Dec-12 26-May-13 1-Jun-13 Bid Summary is Ready,L.O.I to be issue
75 Architectural ACC-MAR-A-G- 00 - SHEET STEEL FINISH IN ENAMEL PAIN Ceiling 1-Jan-13 Roots Qatar 2-Oct-12 1-Mar-13 1-Jun-13 Bid Summary is Ready,
L.O.I to be issue
76 Architectural ACC-MAR-A-G- 00 - lockers 3-Jun-13 4-Mar-13 1-Aug-13 1-Dec-13 Enquiry to float
Architectural ACC-MAR-A-G-305 00 - Adeprimaire Siplast Wet Area Water Proofing 26-Nov-12 Tadmur / Siplast 9-May-12 9-May-12 01-Apr-12 15-Apr-12 09-Apr-12 C77 ACC/TT/VK/LOI-3012-001 13th March 2011 As per Site 1-Dec-12 Part of Subcontract Work
Architectural ACC-MAR-A-G-305 01 - Adeprimaire Siplast Wet Area Water Proofing 26-Nov-12 Tadmur / Siplast 9-May-12 9-May-12 09-May-12 23-May-12 28-May-12 B
78 Architectural ACC-MAR-A-G- 00 Division 09 Mirror 3-Jun-13 Spectra Arts 4-Mar-13 1-Aug-13 1-Dec-12 Quotation Under Evalution
79 Architectural ACC-MAR-A-G- 00 - Floating floor for MEP Equipment 16-Feb-13 17-Nov-12 16-Jan-13 1-May-13
80 Architectural ACC-MAR-A-G- 00 - ANTI-STATIC LINOLEUM 16-Feb-13 17-Nov-12 15-Feb-13 1-Jun-13 Quotation Under Evalution
81 Architectural ACC-MAR-A-G- 00 - Back of House Furniture 3-Jun-13 1-Nov-12 31-Dec-12 1-Dec-13 Need Details to float the enquiry
77 ACC/TT/VK/LOI-3012-001 13th March 2011 requirement 1-Dec-12 Part of Subcontract Work
Page 40 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Lifts Procurement schedule
Page 41 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Lifts
Consultant : Architectural Consulting Group Lift Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : Schindler
A B C D Planned LPO or L/C Date Actual LPO or L/C No. and Date
Delivery Period from Receipt of Order Planned Actual
1 Schipment nr 1/ Group 40
Deliver of Material Guide Rails, Compensator, BuffersTower A Com nr 5062141-49Tower B Com nr 5062151-59
14-Nov-12 Schindler 15.10.2012
Approximately landed on construction site
2 Schipment nr 2/ Group 30
Delivery of MaterialMachine , guide arils fixing, Grik - Plumbing templateTower A Com nr 5062141-49Tower B Com nr 5062151-59
14-Nov-12 Schindler 23.10.2012
Approximately landed on construction site
3 Schipment nr 3/ Group 20
Delivery Of material Shaft DoorsTower A Com nr 5062141-49Tower B Com nr 5062151-59
Different date for different
Elevators acc to latest time
Schedule
Schindler 30.03.2013
Material not ordered in case Technical submittal is not approved with minimum status B
4 Schipment nr 4/ Group 10
Delivery Of materialController TX-GCCar operating Panel, Landing Indicator Panels, Landing Operation PanelsCar Door MaterialCar BodyFixing PointsCounterweight GGM2
Different date for different
Elevators acc to latest time
Schedule
Schindler 30.03.2013
Material not ordered in case Technical submittal is not approved with minimum status B
21-Oct-12
Sl No. Submittal No. Subcontrator /Supplier Remarks Date of
Return
Date of Submittal (Planned)
Approval Required By
Date Submitted
(Actual)
Delivery Date
Rev.Work
Planned Start Date
Purchase Order
Description
Status Code
gCompensation device ASS2-APTG Material 10 Car groupTower A Com nr 5062141-49Tower B Com nr 5062151-59
Schedule
5 Schipment nr 5 Delivery of Complete elevator P1 18-Apr-13 Schindler 28-Oct-12 Wed 17/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
6 Schipment nr 6 Delivery of Complete elevator P2 18-Apr-13 Schindler 28-Oct-12 Wed 17/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
7 Schipment nr 7 Delivery of Complete elevator P3 18-Apr-13 Schindler 28-Oct-12 Wed 17/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
8 Schipment nr 8 Delivery of Complete elevator P4 18-Apr-13 Schindler 28-Oct-12 Wed 17/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
9 Schipment nr 9 Delivery of Complete Elevator P5 9-May-13 Schindler 28-Oct-12 Wed 08/05/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
10 Schipment nr 10 Delivery of Complete elevator P6 9-May-13 Schindler 28-Oct-12 Wed 08/05/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
11 Schipment nr 11 Delivery of Complete elevator 10B 9-May-13 Schindler 28-Oct-12 Thu 02/05/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
12 Schipment nr 12 Delivery of Complete elevator 11B 9-May-13 Schindler 28-Oct-12 Thu 02/05/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
Page 42 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Lifts
Consultant : Architectural Consulting Group Lift Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : Schindler
A B C D Planned LPO or L/C Date Actual LPO or L/C No. and Date
Delivery Period from Receipt of Order Planned Actual
21-Oct-12
Sl No. Submittal No. Subcontrator /Supplier Remarks Date of
Return
Date of Submittal (Planned)
Approval Required By
Date Submitted
(Actual)
Delivery Date
Rev.Work
Planned Start Date
Purchase Order
Description
Status Code
13 Schipment nr 13 Delivery of Complete Elevator K1 30-Apr-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
14 Schipment nr 14 Delivery of Complete Elevator K2 17-May-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
15 Schipment nr 15 Delivery of Complete Elevator K3 9-Jun-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
16 Schipment nr 16 Delivery of Complete Elevator K4 30-Jun-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
17 Schipment nr 17 Delivery of Complete Elevator K5 27-Jul-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
18 Schipment nr 18 Delivery of Complete Elevator K6 22-Aug-13 Schindler 5-Dec-12 Mon 29/04/13
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
19 ACC-TS-G-G-1239 0
Technical Submittal For High Rise Elevators For Tower A and Tower B (Tower - A Lift No. 1A-9A Tower - B Lift No 1B - 9B) 30-Oct-12 Schindler 13-Sep-12 30-Jun-12 30 09 2012 26-Jul-12 C
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B19 ACC TS G G 1239 0 1A 9A, Tower B Lift No. 1B 9B)
Tower A 1A to 9ATower B 1B to 9B
30 Oct 12 Schindler 13 Sep 12 30 Jun 12 30.09.2012 26 Jul 12 C minimum status B.
20 ACC-TS-G-G-1239 1
Technical Submittal For High Rise Elevators For Tower A and Tower B (Tower - A Lift No. 1A-9A, Tower - B Lift No. 1B - 9B)Tower A 1A to 9ATower B 1B to 9B
30-Oct-12 Schindler 13-Sep-12 16-Sep-12 23-Sep-12 14-Oct-12 C
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
21 3.6 3004-30 Technical Submital for ElevatorsP1-P4 , P5 and P6 10B 11B
18.04.201309.05.201303.05.2013
Schindler 16-Oct-12
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
22 Technical Submittal for elevatorsK1-K6 29-Apr-13 Schindler 6-Dec-12
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
23 ACC-SD-G-O-1783 Rev 00 Lift Well Layout Plan Tower A-Lift 1A-81(A-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
Layout Drawings aspproved with Status B , Finishing of materila is not approved any other materila instead rails and brackets and machine can not be ordered and produced
24 ACC-SD-G-O-1784 Rev 00 Pit Builders Work Plan Tower A- Lift 1A-81 (A-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 23-Jul-12 C
25 ACC-SD-G-O-1785 Rev 00
Machine Room Layout Plan Tower A Lift 1A-4A(A-D) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
26 ACC-SD-G-O-1786 Rev 00
Machine Room Builder;s Work Plan Tower A- Lift 1A- 4A (A-D) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
27 ACC-SD-G-O-1787 Rev 00
Machine Room Layout Plan Tower A Lift 5A-8A (E-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
28 ACC-SD-G-O-1788 Rev 00
Machine Room Builder's Workplan Tower-A Lift 5A-8A (E-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
29 ACC-SD-G-O-1789 Rev 00
Section A-A Tower A Lift 1A-4A (A-D) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
30 ACC-SD-G-O-1790 Rev 00
Section B-B Well Head/ Well Pit Tower 5A-8A (D-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
31 ACC-SD-G-O-1791 Rev 00 Section B-B Tower A Lift 5A - 8A (D-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
32 ACC-SD-G-O-1792 Rev 00
Door Details Tower A Lift 1A -8A (A-H) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
Page 43 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Lifts
Consultant : Architectural Consulting Group Lift Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : Schindler
A B C D Planned LPO or L/C Date Actual LPO or L/C No. and Date
Delivery Period from Receipt of Order Planned Actual
21-Oct-12
Sl No. Submittal No. Subcontrator /Supplier Remarks Date of
Return
Date of Submittal (Planned)
Approval Required By
Date Submitted
(Actual)
Delivery Date
Rev.Work
Planned Start Date
Purchase Order
Description
Status Code
33 ACC-SD-G-O-1793 Rev 00
Well & Machine Room Layout & Builders Work Plan Tower A- Lift 9A 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
34 ACC-SD-G-O-1794 Rev 00 Well Head /Well Pit Tower A- Lift 9A 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 5-Aug-12 B
35 ACC-SD-G-O-1795 Rev 00 Section A-A & Door Detail Tower A Lift 9A 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
36 ACC-SD-G-H-1796 Rev 00
Lift Well Layout Plan Tower B Lift 1B- 7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
37 ACC-SD-G-H-1797 Rev 00
Pit Builders Work Plan Tower B Lift 1B-7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
38 ACC-SD-G-H-1798 Rev 00
Machine Room Layout Plan Tower B Lift 1B - 7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
39 ACC-SD-G-H-1799 Rev 00
Machine Room Builder;s Work Plan Tower B Lift 1B - 7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
40 ACC-SD-G-H-1800 Rev 00 Well Head /Well Pit Tower B Lift 1B-7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
41 ACC-SD-G-H-1801 Rev 00 Section A-A & Tower B Lift 1B -7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
42 ACC-SD-G-H-1802 Rev 00 Door Details Tower B Lift 1B -7B (A-G) 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 30-Jul-12 B
43 ACC-SD-G-H-1803 Rev 00 Builders Work Plan /Layout Tower B Lift 8B-9B 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
44 ACC-SD-G-H-1804 Rev 00 Builders Work Plan /Layout Tower B Lift 8B-9B 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 2-Aug-12 B
45 ACC-SD-G-H-1805 Rev 00 Builders Work Plan /Layout Tower B Lift 8B-9B 30-Oct-12 Schindler 30-Jun-12 1-Jul-12 15-Jul-12 26-Jul-12 B
ACC SD G P 2127 Shaft @ Car Plan Pit Headroom Scaffolding Material not ordered in case Technical submittal46 ACC-SD-G-P-2127
Rev 00Shaft @ Car Plan, Pit Headroom, Scaffolding Plan and Cable Layout For 1P-2P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
Material not ordered in case Technical submittal and Layout drawings are not approved with
47 ACC-SD-G-P-2128 Rev 00 Door, Rough Door Elevations & Details For 1P-2P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
48 ACC-SD-G-P-2129 Rev 00 Shaft & Headroom Section For 1P-2P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
49 ACC-SD-G-P-2130 Rev 00
Shaft & Car Plan, Pit, Headroom, Scaffolding Plan and Cable Layout For 3P-4P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
50 ACC-SD-G-P-2131 Rev 00 Door , Rough Door Elevation & Details For 3P-4P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
51 ACC-SD-G-P-2132 Rev 00 Shaft & Headroom Section For 3P-4P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
52 ACC-SD-G-P-2133 Rev 00
Shaft & Car Plan, Pit, Headroom, Scaffolding Plan and Cable Layout For 5P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
53 ACC-SD-G-P-2134 Rev 00 Door, Rough Door Elevations & Details For 5P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
54 ACC-SD-G-P-2135 Rev 00 Shaft & Headroom Section For 5P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
55 ACC-SD-G-P-2136 Rev 00
Shaft @ Car Plan, Pit, Headroom, Scaffolding Plan and Cable Layout For 6P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
56 ACC-SD-G-P-2137 Rev 00 Door, Rough Door Elevations & Details For 6P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
57 ACC-SD-G-P-2138 Rev 00 Shaft & Headroom Section For 6P 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
58 ACC-SD-G-P-2139 Rev 00
Shaft @ Car Plan, Pit, Headroom, Scaffolding Plan ,Door Elevation and Cable Layout For 10B 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
59 ACC-SD-G-P-2140 Rev 00 Shaft , Headroom Section & Details For 10B 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
60 ACC-SD-G-P-2141 Rev 00
Shaft @ Car Plan, Pit, Headroom, Scaffolding Plan ,Door Elevation and Cable Layout For 11B 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
61 ACC-SD-G-P-2142 Rev 00 Shaft , Headroom Section & Details For 11B 17-Apr-13 Schindler 16-Sep-12 18-Sep-12 2-Oct-12
62 Layout drawings for Elevators K1-K6 29-Apr-13 Schindler 7-Nov-12
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
Page 44 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Lifts
Consultant : Architectural Consulting Group Lift Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : Schindler
A B C D Planned LPO or L/C Date Actual LPO or L/C No. and Date
Delivery Period from Receipt of Order Planned Actual
21-Oct-12
Sl No. Submittal No. Subcontrator /Supplier Remarks Date of
Return
Date of Submittal (Planned)
Approval Required By
Date Submitted
(Actual)
Delivery Date
Rev.Work
Planned Start Date
Purchase Order
Description
Status Code
63 ACC-TS-G-G-1764 0 Divider Beams Calculation For Elevators 30-Oct-12 Schindler 19-Sep-12 19-Sep-12 30-Sep-12 22-Sep-12 C 15.10.2012
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
64 ACC-TS-G-G-1764 1 Divider Beams Calculation For Elevators 30-Oct-12 Schindler 30-Oct-12 3-Oct-12 10-Oct-12 15.10.2012
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
ACC-TS-G-G-1447 0Technical Submittal for Calculation Guide Rails , Motors and Cars -TOWER-A PASSENGER LIFTS 1A-4A, 5A-8A, 9A
30-Oct-12 Schindler 15-Sep-12 31-Jul-12 14-Aug-12 1-Oct-12 C 30.10.2012
Material not ordered in case Technical submittal and Layout drawings are not approved with minimum status B.
ACC-TS-G-G-1447 1Technical Submittal for Calculation Guide Rails , Motors and Cars -TOWER-A PASSENGER LIFTS 1A-4A, 5A-8A, 9A
Schindler 8-Oct-12 15-Oct-12
66 ACC-TS-G-G-1750 0 Deviation List for Elevators Revision nr 1 Schindler 11-Sep-12 25-Sep-12
67 ACC-RFI-G-P-692 0 PODIUM ELEVATORS Schindler 21-Oct-12 4-Nov-12
65
Page 45 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Aluminum Procurement schedule
Page 46 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Architectural
Consultant : Architectural Consulting Group Aluminum Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : AGR
A B C DPlanned LPO or
L/C DateActual LPO or
L/C No. and Date
Delivery Period from Receipt of
Order
Planned Actual
Section 1- Document
ACC-TS-S-G-870 0 Structural Calculation for Curtain Wall 10-May-12 24-May-12 5-Jun-12 C
ACC-TS-S-G-870 1 Structural Calculation for Curtain Wall 13-Jun-12 27-Jun-12 16-Jul-12 B
ACC-TS-S-G-870 2 Structural Calculation for Curtain Wall 1 Sep 12 15 Sep 12 6 Oct 12 C
Approval Required By
Date of ReturnSubmittal No Rev. DescriptionWork Start
Date(Expected)
Status Code Purchase Order Delivery Date
Remarks
21-Oct-12
Work Start Date
(Baseline dates)
Date of Submittal
(Planned as per
Baseline)
S/NoSubcontractor
/Supplier
Date of Submittal (Revised Planned )
Date Submitted
(Actual)
ACC-TS-S-G-870 2 Structural Calculation for Curtain Wall 1-Sep-12 15-Sep-12 6-Oct-12 C
ACC-TS-S-G-870 3Structural Calculation for Curtain Wall For Typical Curtain Wall
17-Sep-12 1-Oct-12 30-Sep-12 B
ACC-TS-S-G-870 4Structural Calculation for Curtain Wall For Typical Curtain Wall (Calculation based on QCS 2010 Section 25 Part 3)
2-Oct-12 16-Oct-12 9-Oct-12 C
ACC-TS-S-G-870 5Structural Calculation for Curtain Wall For Typical Curtain Wall for Tower A & Tower B
20-Oct-12 3-Nov-12
Section 2-Aluminium
ACC-MAR-A-G-262 0 Sample Board: Gutman -F50/Curtain Wall Profiles AGR / Gutmann 26-May-12 9-Jun-12 14-Jun-12 C
ACC-MAR-A-G-262 1 Sample Board: SCHUCO FW F50+ /Curtain Wall ProfilesAGR/ SCHUCO /
Gutmann20-Jun-12 4-Jul-12 16-Jul-12 C
ACC-MAR-A-G-262 2 SCHUCO FW F50+ /Curtain Wall ProfilesAGR/ SCHUCO /
Gutmann9-Aug-12 23-Aug-12 13-Aug-12 C
ACC-MAR-A-G-262 3 Sample Board : Schuco FW 50+/ Curtain Wall ProfilesAGR/
SCHUCO11-Sep-12 25-Sep-12 24-Sep-12 B
90 30‐Jan‐13 06‐Feb‐13
1 AGR 22-Jun-11 17-Sep-12
16‐Jun‐12 22-Jun-11 11-Sep-12 01-Nov-122
pSCHUCO
p p p
Section 3-Glass
ACC-MAR-A-G-228 08mm Pilkington YBE (Blue) Tempered Glass, 16mm Airspace, 4mm Clear Anneld Glass,
AGR / Shanghai 14-May-12 28-May-12 14-Jun-12 C
ACC-MAR-A-G-228 1
Saint Gobain Glass(8 mm Cool-Lite Nano Misty Blue(KNT 755) tempered (Saint Gobain), 8mm Cool-Lite Orion Advantage/SGG EVO (ET725) tempered
(Saint Gobain)
AGR/Saint- Gobain Glass
2-Jul-12 16-Jul-12 21-Jul-12 C
Saint Gobain Glass:Option 1: 8 mm Stopray Vision‐50 T Tempered Glass ,16 mm Air Space ‐ 10mm Clear Tempered Glass
AGR/AGC
Option2: 8 mm Cool Lite Smoke Silver KNT 140,16 Air Space,10 mm Clear Glass
AGR/St. Gobain
Option 3: 8mm Pilkington Silver Sunshade Glass 16 mm Air Space + 10 mm Clear Glass
AGR/PILKINGTON
Option 4: 8 mm Solar E Grey Glass 16 mm Air Space + 10 mm Clear Glass
AGR/PILKINGTON
Curtain Wall Glazing -Material Submittal for Option 1
C06‐Feb‐13
9-Oct-12ACC-MAR-A-G-228 2 23-Sep-12 7-Oct-123 16‐Jun‐12 22‐Jun‐11 20‐Sep‐12 01-Nov-12 90 30‐Jan‐13
ACC-MAR-A-G-228 3 Glaverbel , 800 Temepered Stopray Vision 50T (AGC Belgium) + 16 mm Air Space + 8.38 mm Laminated Annealed Glass with Normal PVB (AGC Belgium)
AGR-Glaverbel (AGC)
20-Oct-12 03-Nov-12
ACC-MAR-A-G-341 010 mm clear Fully Tempered Glass : Guardian - as inner pane in façade
AGR/Guardian 9-Aug-12 23-Aug-12 11-Aug-12 C
ACC-MAR-A-G-341 1
Curtain Wall Glazing -Material Submittal for Option 2, 8mm Cool Lite Smoke Silver KNT 140 Tempered Saint Gobain -Spain , 8.38 mm clear Laminated Annealed with Normal PVB - Glaverbel AGC
AGR - Saint Gobain -Spain/ Glaverbel (AGC)-Belgium
20-Oct-12 3-Nov-12
Section 4-Façade
5 ACC-MAR-A-G-204 0Rockwool Insulation for Curtain Wall and Metal Cladding (50kg/m3)
AGR / Azel 02-May-12 2-May-12 16-May-12 14-May-12 A 30-Sep-12 70 09‐Dec‐12 16‐Dec‐12
6 ACC-MAR-A-G-276 0Option 2: NOVELIS 2mm Solid Panel For Metal Cladding
AGR/ Alucobond 20-Jun-12 20-Jun-12 4-Jul-12 7-Jul-12 B 01-Nov-12 90 30‐Jan‐13 06‐Feb‐13
Section 5- Accessories
06‐Feb‐13
22-Jun-1116‐Jun‐12
4 16‐Jun‐12 22‐Jun‐11 09-Aug-12 01-Nov-12 90 30‐Jan‐13
Page 47 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Project Manager : Hamilton Project Management TWIN TOWERS DOHA, QATAR Discipline : Architectural
Consultant : Architectural Consulting Group Aluminum Work PROCUREMENT SCHEDULE Run date :
Main Contractor : Arabtec Construction Co.
Sub Contractor : AGR
A B C DPlanned LPO or
L/C DateActual LPO or
L/C No. and Date
Delivery Period from Receipt of
Order
Planned Actual
Approval Required By
Date of ReturnSubmittal No Rev. DescriptionWork Start
Date(Expected)
Status Code Purchase Order Delivery Date
Remarks
21-Oct-12
Work Start Date
(Baseline dates)
Date of Submittal
(Planned as per
Baseline)
S/NoSubcontractor
/Supplier
Date of Submittal (Revised Planned )
Date Submitted
(Actual)
ACC-MAR-A-G-275 0Option 1: Alucobond 4mm thickness Fire Rated Composite Panel For Metal Cladding
4‐Feb‐12 AGR/ Alucobond 19-Jun-12 3-Jul-12 8-Jul-12 C
ACC-MAR-A-G-275 1SINCO Product - Non Combustible: 4MM Thick
Aluminum Cladding With Corrugated Aluminum Core
4‐Feb‐12 AGR/ Q-NAP 31-Jul-12 14-Aug-12 23-Aug-12 C
8 ACC-MAR-A-G-282 0 Sample Board: Steel Brackets & Accessories 4‐Feb‐12 AGR 22-Jun-11 23-Jun-12 23-Jun-12 7-Jul-12 18-Jul-12 B 10-Oct-12 15-Oct-12
9 ACC MAR A G 349 0 GEZE A t ti D O t AGR/GEZE 17 J l 12 17 J l 12 31 J l 12 6 O t 12 C
7 22-Jun-11 31-May-12 10-Oct-12 15-Oct-12
9 ACC-MAR-A-G-349 0 GEZE Automatic Door Operator AGR/GEZE 17-Jul-12 17-Jul-12 31-Jul-12 6-Oct-12 C
10 0 Stainless Steel Door AGR/ GEZE 15-Oct-12
11 0 Stainless Steel Handrail AGR 15-Oct-12
Section 6- Paint
ACC-MAR-A-G-218 0 Juton Powder Coating PE 7-May-12 21-May-12 17-May-12 C
ACC-MAR-A-G-218 1 Juton Powder Coating PE-SDF 19-Jun-12 3-Jul-12 16-Jul-12 B
ACC-MAR-A-G-237 00 Powder Coating PE RAL Color Samples 20-May-12 3-Jun-12 14-Jun-12 C
ACC-MAR-A-G-237 01Joseph Industries: KYNAR PVDF Powder Coating (Samples: RAL 7048, 9023, 9018,9007,5011
7-Jul-12 21-Jul-12 21-Jul-12 B
ACC-MAR-A-G-227 0 Silicone Dow Corning 813 C 21-May-12 4-Jun-12 14-Jun-12 C
12
3-Dec-114‐Oct‐12
22‐Sep‐12 22-Jun-11
14 21-May-12AGR / Dow
C i
13 00‐Jan‐00 07‐Jan‐0007-May-12
30-Sep-12 60 00‐Jan‐00
08-Apr-1301-Apr-13
AGR / Juton
AGR / Juton
01‐May‐13 08‐May‐13
07‐Jan‐0007-May-12
30-Sep-12 60
ACC-MAR-A-G-227 1 Silicone Dow Corning 813C, 895 & 791 7-Jul-12 21-Jul-12 14-Jul-12 B
15 ACC-MAR-A-G-393 0 Fischer: Firestop - RFS 640 Rapid Fire Seal AGR/FIscher 05-Oct-12 10-Oct-12 24-Oct-12 01‐Mar‐13 08‐Mar‐13
yCorning
y y
Page 48 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Material Submittal Register (MARS)
Page 49 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
1 S ACC-MAR-S-G-001 00 Div 4
Hollow & Solid Concrete Block (Hollow Concrete Block Sizes: 400 x 200 x 200, 400 x 150 x 200, 400 x 100 x 200, Solid Concrete Block Sizes: 400 x 100 x 200, 400 x 150 x 200, 400 x 200 x 200)
Aamal Cement Indu. 08.02.11 22.02.11 20.02.11 A
2 S ACC-MAR-S-G-002 00 Div 4 Ordinary Portland Cement for Masonary Mortar Tayseer Bldg. Mtrls. Co. 08.02.11 22.02.11 23.02.11 A
3 S ACC-MAR-S-G-003 00 Div 4 Ordinary Portland Cement for Masonary Mortar United Gulf Cement 08.02.11 22.02.11 23.02.11 A
4 S ACC-MAR-S-G-004 00 Div 4 Ordinary Portland Cement for Masonary Mortar Tayseer Bldg. Mtrls. Co. 08.02.11 22.02.11 23.02.11 A
5 S ACC-MAR-S-G-005 00 Div 4 Washed Sand Helal Eastern Const. 08.02.11 22.02.11 23.02.11 A
6 S ACC-MAR-S-G-006 00 Div 4 Washed Sand Dafan 08.02.11 22.02.11 23.02.11 A
7 S ACC-MAR-S-G-007 00 Div 4 Washed Sand Elrezq for Trdg. & Contg. 08.02.11 22.02.11 23.02.11 A
8 S ACC-MAR-S-G-008 00 Div 3 Polyethylene Sheet (Sizes: 1000 gauge - 250 micron)
Petro Plastic Factory 08.02.11 22.02.11 20.02.11 A
9 S ACC-MAR-S-G-009 00 Div 3 Design Mix for Blinding Concrete NBK RM 13.02.11 27.02.11 20.02.11 A
10 S ACC-MAR-S-G-010 00 Div 4 Solid & Hollow Concrete Block (Dimension: 400 x 200 x100, 400x200x150, 400x200x200 Al Sehmiah 20.02.11 06.03.11 22.02.11 A
11 S ACC-MAR-S-G-011 00 Div 4
Solid & Hollow Concrete Block (Hollow Concrete Block Sizes: 400x200x200, 400x150x200, 400x100x200, Solid Concrete Block Sizes: 400x100x200 and 400x200x200)
Khalid Cement Indu. 20.02.11 06.03.11 23.02.11 A
12 S ACC-MAR-S-G-012 00 Div 3 & 7 PVC Waterstop - Hydrostop AW Ayla 02.03.11 16.03.11 06.03.11 C
13 S ACC-MAR-S-G-013 00 High-Rip - 0.4 for Concrete Formwork. Modern Building 05.03.11 19.03.11 10.03.11 A
14 S ACC-MAR-S-G-014 00 Div 3 & 7 PVC Waterstop - Fosroc Supercast PVC. Tadmur 02.03.11 16.03.11 06.03.11 A
15 S ACC-MAR-S-G-015 00 Parallel Thread Rebar Splice - CABR WSQ 10.03.11 24.03.11 19.03.11 A
16 S ACC-MAR-S-G-016 00 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. Modern Building 06.03.11 20.03.11 10.03.11 A
17 S ACC-MAR-S-G-017 00 HY-RIB - 0.40 (Grade 2811) for Concrete Formwork. Bardawil 05.03.11 19.03.11 10.03.11 A
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
Page 50 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
18 S ACC-MAR-S-G-018 00 Div 3 & 7 PVC Waterstop - Spectite Bardawil 05.03.11 19.03.11 10.03.11 A
19 S ACC-MAR-S-G-019 00 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. Qatar Pipeline 05.03.11 19.03.11 10.03.11 A
20 S ACC-MAR-S-G-020 00 Div 3 High Yield Steel Reinforcement Deformed Bar. Qatar Steel 05.03.11 19.03.11 10.03.11 A
E ACC-MAR-E-G-021 00 Sec. E16/ 37-38 G.I. Back Boxes. Efeco 07.03.11 08.03.11 22.03.11 19.03.11 B
E ACC-MAR-E-G-021 01 Sec. E16/ 37-38 G.I. Back Boxes. Efeco 03.04.11 11.04.11 25.04.11 26.04.11 B
E ACC-MAR-E-G-021 02 G.I. Back Boxes. Efeco 05.06.11 19.06.11 22.06.11 A
E ACC-MAR-E-G-022 00 Sec. E16/42-46 Earthing and Lightning Protection. Efeco 07.03.11 08.03.11 22.03.11 19.03.11 B
E ACC-MAR-E-G-022 01 Sec.E16/42-46 Earthing and Lightning Protection. Efeco 03.04.11 11.04.11 25.04.11 27.04.11 B
S ACC-MAR-S-G-023 00 Div 3 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). NBK 08.03.11 22.03.11 13.03.11 C
S ACC-MAR-S-G-023 01 Div 3 Concrete Mix Design for Ground Slab, Suspended Slab and Beams (Fcu=56MPa). NBK 15.03.11 29.03.11 26.03.11 A
S ACC-MAR-S-G-023 02 Div 3 Concrete Mix Design for Ground Slab (Fcu=56MPa). NBK 22.03.11 05.04.11 31.03.11 B
S ACC-MAR-S-G-023 03 Div 3 Concrete Mix Design for Raft and Retaining Wall (Fcu=56MPa). NBK 09.04.11 23.04.11 10.04.11 A
24 S ACC-MAR-S-G-024 00 Div 3 1.6mm Diameter Soft Annealed Iron Wire. WSQ 12.03.11 26.03.11 20.03.11 A
25 S ACC-MAR-S-G-025 00 Div 3 Mix Design for Screed. NBK 12.03.11 26.03.11 17.03.11 A
S ACC-MAR-S-G-026 00 Div 7 Waterproofing for Sub structural and Water Tank. Tadmur 12.03.11 26.03.11 15.03.11 C
S ACC-MAR-S-G-026 01 Div 7 Waterproofing for Sub structural and Water Tank. Tadmur 15.03.11 29.03.11 17.03.11 A
E ACC-MAR-E-G-027 00 Sec.E16/37-38 PVC Adaptable Box. Efeco 13.03.11 13.03.11 27.03.11 21.03.11 C
E ACC-MAR-E-G-027 01 Sec.E16/37-38 PVC Adaptable Box. Efeco 11.04.11 11.04.11 25.04.11 26.04.11 B
28 S ACC-MAR-S-G-028 00 Div 3 Fibre Concrete Spacers. Castle 13.03.11 27.03.11 17.03.11 A
29 S ACC-MAR-S-G-029 00 Concrete Acessories PVC Spacer (Chair and Wheel Type) and PVC Chamfer. Modern Building 13.03.11 27.03.11 17.03.11 A
30 S ACC-MAR-S-G-030 00 Div 3 Formwork Release Agent - Formcoat S Ayla 13.03.11 27.03.11 17.03.11 A
23
22
26
21
27
Page 51 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
31 S ACC-MAR-S-G-031 00 Div 3 Formwork Release Agent - Reebol Concentrate Tadmur 13.03.11 27.03.11 17.03.11 A
32 S ACC-MAR-S-G-032 00 Div 3 Curing Compound - Setcrete 22 (can't be over coated) Ayla 13.03.11 27.03.11 17.03.11 D
33 S ACC-MAR-S-G-033 00 Div 3 Curing Compound - Setcrete AW (can be over coated) Ayla 13.03.11 27.03.11 17.03.11 A
34 S ACC-MAR-S-G-034 00 Div 3 Curing Compound - Fosroc Concure WB (can't be over coated) Tadmur 14.03.11 28.03.11 17.03.11 D
35 S ACC-MAR-S-G-035 00 Div 3 Curing Compound - Fosroc Concure 1315 (can be over coated) Tadmur 14.03.11 28.03.11 17.03.11 A
36 M ACC-MAR-M-G-036 00 Sec. 15060/5&6 UPVC Pipes & Fittings Efeco 14.03.11 28.03.11 22.03.11 A
37 S ACC-MAR-S-G-037 00 Bonding Agent - Fosroc Nitobond EP Tadmur 15.03.11 29.03.11 19.03.11 A
38 S ACC-MAR-S-G-038 00 Bonding Agent - Sodamco-Admix 225 MB Sodamco 15.03.11 29.03.11 19.03.11 A
39 S ACC-MAR-S-G-039 00 Bonding Agent - Cempatch SBR100 Ayla 15.03.11 29.03.11 19.03.11 A
E ACC-MAR-E-G-040 00 PVC Conduits & Accessories. Decoduct 18.03.11 17.03.11 31.03.11 21.03.11 B
E ACC-MAR-E-G-040A 01 PVC Conduits & Accessories. Jaidah/Clipsal 03.04.11 06.04.11 20.04.11 27.04.11 C
E ACC-MAR-E-G-040 02 PVC Conduits & Accessories. Decoduct 28.04.11 30.04.11 14.05.11 12.05.11 A
41 S ACC-MAR-S-G-041 00 Curing Compound - Cure Y 40 Sodamco 19.03.11 02.04.11 21.03.11 A
42 G ACC-MAR-G-G-042 00 Material Submittal Register (MAR) & Procurement Schedule. ACC 20.03.11 03.04.11 28.03.11 C
43 S ACC-MAR-S-G-043 00 Mechanical Splice, BSG Cold Swaged Castle 22.03.11 05.04.11 26.03.11 A
44 S ACC-MAR-S-G-044 00 Injection Epoxy Chemical Adhesive Fischer Fixing 26.03.11 09.04.11 29.03.11 A
45 S ACC-MAR-S-G-045 00 Injection Epoxy Chemical Adhesive – EPCON C8 Ramco 27.03.11 10.04.11 31.03.11 A
46 S ACC-MAR-S-G-046 00 Twin Walls Pelypropylene Alternative Protection Board Tadmur 30.03.11 13.04.11 05.04.11 A
47 S ACC-MAR-S-G-047 00 1200 Guage Polyethylene Separation Layer Tadmur 31.03.11 14.04.11 10.04.11 A
48 S ACC-MAR-S-G-048 00 Alternative Conbextra GP Non-Shrink Cementitious Grout for Pile Head Treatment. Tadmur 02.04.11 16.04.11 05.04.11 A
49 S ACC-MAR-S-G-049 00Injection Epoxy Chemical Adhesive – Hilti Hit-RE500 for anchoring Reinforcing Bars and anchor Rods in Concrete.
Hilti Qatar 03.04.11 17.04.11 05.04.11 A
40
Page 52 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
50 S ACC-MAR-S-G-050 00 Concrete Mix Design for Raft (Fau=56 Mpa) Rabban RM 10.04.11 24.04.11 12.04.11 A
51 S ACC-MAR-S-G-051 00 Parrallel Threaded (DTR) Rebar Splicing System WSQ 11.04.11 25.04.11 13.04.11 A
52 M ACC-MAR-M-G-052 00 Puddle Flange for Water Tank Efeco 05.04.11 14.04.11 28.04.11 16.08.12 C
M ACC-MAR-M-G-053 00 UPVC Pressure Pipes & Fittings Cosmoplast 10.04.11 14.04.11 28.04.11 27.04.11 C
M ACC-MAR-M-G-053 01 UPVC Pressure Pipes & Fittings Cosmoplast 02.05.11 04.05.11 18.05.11 09.05.11 A
M ACC-MAR-M-G-054 00 G.I. Puddle Flange for Water Supply + Sample Efeco 17.04.11 18.04.11 02.05.11 02.05.11 C
M ACC-MAR-M-G-054 01 G.I. Puddle Flange for Water Supply Efeco 20.06.11 04.07.11 06.07.11 A
M ACC-MAR-M-G-055 00 UPVC Puddle Flange for Water Tank Hepworth 21.04.11 23.04.11 07.05.11 02.05.11 D
M ACC-MAR-M-G-055 01 UPVC Puddle Flange for Water Tank Hepworth 20.06.11 04.07.11 26.07.11 C
56 A ACC-MAR-A-G-056 00 Galvanized & Stainless Plastering Accessories Unitech Qatar 25.04.11 09.05.11 28.04.11 A
57 S ACC-MAR-S-G-057 00 Fosroc Conbextra EPGP AL Gurg Fosroc LLC 26.04.11 10.05.11 02.05.11 A
58 E ACC-MAR-E-G-058 00 PVC Conduits & Accessories. Jaidah/Clipsal 30.04.11 14.05.11 08.05.11 A
59 S ACC-MAR-S-G-059 00 Supercast SW30 High Swell Hydrophilic, Water Stop & Supercast SWX
AL Gurg Fosroc LLC 03.05.11 17.05.11 08.05.11 A
60 S ACC-MAR-S-G-060 00 twin Walls Pelypropylene Alternative Protection Board Tadmur/Sika 05.05.11 19.05.11 15.05.11 ASika Grout -Code A & Sikadur -
Code D
61 S ACC-MAR-S-G-061 00 NITOFILL EPLV - Low Viscosity Epoxy Injection Resin System Crack Repair Material for Pile Head Tadmur/Fosroc 07.05.11 21.05.11 12.05.11 A
62 S ACC-MAR-S-G-062 00 Steel Lintel Unitech / SFSP 12.05.11 26.05.11 12.06.11 A
M ACC-MAR-M-G-063 00 UPVC Pipe & Fittings (Below Ground) Hepworth 05.05.11 07.05.11 21.05.11 09.05.11 B
M ACC-MAR-M-G-063 01 UPVC Pipe & Fittings (Below Ground) Hepworth 16.05.11 30.05.11 24.05.11 A
64 S ACC-MAR-S-G-064 00 Sikadur -42 LP: Epoxy Resin Castable Grout for Pile Cap Treatment Tadmur/Sika 08.05.11 22.05.11 10.05.11 A
65 E ACC-MAR-E-G-065 00 UPVC Ducts Hepworth 15.07.11 10.05.11 24.05.11 23.05.11 B
55
53
54
63
Page 53 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
66 M ACC-MAR-M-G-066 00 Pipe Supports & Hangers for Plumbing Hira LLC 13.05.11 16.05.11 30.05.11 23.05.11 A
67 M ACC-MAR-M-G-067 00 Pipe Supports & Hangers for Fire Fighting Hira LLC 16.05.11 16.05.11 30.05.11 23.05.11 A
M ACC-MAR-M-G-068 00 Pipe Supports & Hangers for HVAC Hira LLC 21.06.11 16.05.11 30.05.11 25.05.11 C
M ACC-MAR-M-G-068 01 Pipe Supports & Hangers for HVAC Hira LLC 20.06.11 04.07.11 06.07.11 A
69 M ACC-MAR-M-G-069 00 Rubber Support Insert for CHW Pipe Hira LLC 21.07.11 16.05.11 30.05.11 25.05.11 A
70 M ACC-MAR-M-G-070 00 UPVC Pressure Pipes & Fittings - BS 3505 Hepworth 19.05.11 02.06.11 25.05.11 A
S ACC-MAR-S-G-071 00 Concrete Mix Design for Core Walls, Shear Walls and Columns (Fcu=75MPa) NBK 21.05.11 04.06.11 28.05.11 A
S ACC-MAR-S-G-071 01Concrete Mix Design for Core Walls, Shear Walls and Columns (Fcu=75MPa) (trial Mix Data Sheet Observations for Column, Corewall & Shearwall)
NBK 24.05.11 07.06.11 29.05.11 A
S ACC-MAR-S-G-072 00 Concrete Mix Design for Retaining Wall (Fcu=75MPa) NBK 21.05.11 04.06.11 28.05.11 A
S ACC-MAR-S-G-072 01 Concrete Mix Design for Retaining Wall (Fcu=75MPa) (Trial Mix Data Sheet Observation for Retaining Wall) NBK 24.05.11 07.06.11 29.05.11 A
73 M ACC-MAR-M-G-073 00 Black Steel Chilled Water Pipes Econosto 21.05.11 21.05.11 04.06.11 23.05.11 A
E ACC-MAR-E-G-074 00 Heat Resistant Flexible Cables Alfanar / Electrica 15.06.11 23.05.11 06.06.11 04.06.11 C
E ACC-MAR-E-G-074 01 Heat Resistant Flexible Cables Alfanar / Electrica 12.06.11 12.06.11 26.06.11 22.06.11 C
E ACC-MAR-E-G-074 02 Heat Resistant Flexible Cables Alfanar / Electrica 14.07.11 28.07.11 22.09.11 C
E ACC-MAR-E-G-074 03 Heat Resistant Flexible Cables Al-Ameer Group Electricals 10.10.11 24.10.11 27.11.11 B
75 S ACC-MAR-S-G-075 00Fosroc Renderoc Hsxtra - Shrinkage Controlled, Polymer Modified, cementitious, High Specification Repair Mortar System (For Vertical Elements)
AL Gurg Fosroc LLC 24.05.11 07.06.11 25.05.11 A
S ACC-MAR-S-G-076 00 CONREP 331 TX: Non-shrink Thixotropic Repair Mortar for Concrete Repair, Slab on Grade, Beams and Slabs Sodamco 25.05.11 08.06.11 28.05.11 A
S ACC-MAR-S-G-076 01 CONREP 331 TX: Non-shrink Thixotropic Repair Mortar of All Structural Elements Including Verticals Sodamco 27.02.12 12.03.12 04.03.12 B
74
68
71
72
76
Page 54 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
77 S ACC-MAR-S-G-077 00
Fosroc Renderoc HS-Shrinkage Compensated Polymer Modified, Fibre Reinforced, Thixotrapic Repair Mortar System for Honeycombing Repairs - for Raft, Slab on Grade and Suspended Slabs
AL Gurg Fosroc LLC 29.05.11 12.06.11 31.05.11 D
78 A ACC-MAR-A-G-078 00 Blockwork Accessories Unitech / SFSP 29.05.11 12.06.11 31.05.11 A
79 S ACC-MAR-S-G-079 00 CONREP 360 FFR : Pre-mixed Cementitious Paste for Fair Face Repair Sodamco 30.05.11 13.06.11 31.05.11 A
E ACC-MAR-E-G-080 00 GI Conduits & Accessories Lanric Malaysia 31.05.11 31.05.11 14.06.11 05.06.11 C
E ACC-MAR-E-G-080 01 GI Conduits & Accessories Lanric Malaysia 12.06.11 12.06.11 26.06.11 22.06.11 C
E ACC-MAR-E-G-080 02 GI Conduits & Accessories Lanric Malaysia 23.08.11 23.08.11 06.09.11 05.10.11 C
E ACC-MAR-E-G-080 03 GI Conduits & Accessories Lanric Malaysia 19.10.11 02.11.11 20.11.11 B
81 S ACC-MAR-S-G-081 00 Fosroc Renderoc BF2 : Two Component Polymer Modified Cementitious Blow Hole Filler
AL Gurg Fosroc LLC 31.05.11 14.06.11 07.06.11 A
82 S ACC-MAR-S-G-082 00 CONREP 405 BFX : Pure Epoxy Anchoring Resin in Cartridge Sodamco 31.05.11 14.06.11 07.06.11 A
83 S ACC-MAR-S-G-083 00 Fiberboard Ayla / DCP 31.05.11 14.06.11 07.06.11 A
84 S ACC-MAR-S-G-084 00 Jolly Bitulex Board - Bitumen Impregnated Board Mannai / Jolly Board 31.05.11 14.06.11 07.06.11 A
85 M ACC-MAR-M-G-085 00 Above Ground Drainage Pipes and Fittings Hepworth 30.04.11 02.06.11 16.06.11 15.06.11 B
86 S ACC-MAR-S-G-086 00 Concrete Mix Design for Conventional Slab and Beams (Fcu=56MPa) NBK 02.06.11 16.06.11 06.06.11 A
87 S ACC-MAR-S-G-087 00 DEM 22 : Based Shutter Release Agent Sodamco 04.06.11 18.06.11 07.06.11 A
M ACC-MAR-M-G-088 00 ERW Steel Pipes Petrofac 04.06.11 18.06.11 05.06.11 C
M ACC-MAR-M-G-088 01 Fire Protection System Pipes Econosto 03.10.11 17.10.11 13.11.11 C
M ACC-MAR-M-G-088 02 Fire Protection System Pipes Econosto 28.11.11 12.12.11 22.12.11 C
88
80
Page 55 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-088 03 Fire Protection System Pipes Econosto 31.12.11 14.01.12 01.01.12 C
M ACC-MAR-M-G-088 04 Fire Protection System Pipes Econosto 04.03.12 18.03.12 21.03.12 C
M ACC-MAR-M-G-088 05 Fire Protection System Pipes Econosto 03.04.12 17.04.12 10.04.12 C
M ACC-MAR-M-G-088 06 Fire Protection System Pipes Econosto 09.05.12 23.05.12 21.05.12 C
M ACC-MAR-M-G-088 07 Fire Protection System Pipes (For Horizontal Application) Petrofac / Surya 10.06.12 24.06.12 01.07.12 A
M ACC-MAR-M-G-089 00 UL & FM Approved Black Threaded Fittings for Fire Fighting Shield Nafco 24.05.11 07.06.11 21.06.11 15.06.11 C
M ACC-MAR-M-G-089 01 Threaded Fittings for Fire Fighting Pipes Nafco 05.10.11 19.10.11 13.11.11 C
M ACC-MAR-M-G-089 02 Threaded Fittings for Fire Fighting Pipes Nafco 08.12.11 22.12.11 22.12.11 C
M ACC-MAR-M-G-089 03 Threaded Fittings for Fire Fighting Pipes Nafco 05.05.12 19.05.12 21.05.12 C
M ACC-MAR-M-G-089 04 Threaded Fittings for Fire Fighting Pipes Nafco 31.05.12 14.06.12 27.06.12 A
90 M ACC-MAR-M-G-090 00 UL & FM Approved Red Painted Grooved Fittings for Fire Fighting System Shield Nafco 24.05.11 07.06.11 21.06.11 15.06.11 B
91 M ACC-MAR-M-G-091 00 Chilled Water Butt Weld Fittings Econosto 16.07.11 07.06.11 21.06.11 15.06.11 A
M ACC-MAR-M-G-092 00 Black Threaded Fittings for Chilled Water Shield Nafco 24.05.11 08.06.11 22.06.11 15.06.11 C
M ACC-MAR-M-G-092 01 Black Threaded Fittings for Chilled Water Shield Nafco 11.07.11 25.07.11 06.08.11 A
93 M ACC-MAR-M-G-093 00 Threaded Rods and Accessories Unitech 13.06.11 08.06.11 22.06.11 15.06.11 A
E ACC-MAR-E-G-094 00 Fire Resistant Cables City Electrical Factor 09.06.11 09.06.11 23.06.11 22.06.11 C
E ACC-MAR-E-G-094 01 Fire Resistant (FP 200) Cables City Electrical Factor 24.07.11 24.07.11 07.08.11 20.09.11 B
E ACC-MAR-E-G-094 02 Fire Resistant (FP 200) Cables City Electrical Factor 02.10.11 16.10.11 13.11.11 B
E ACC-MAR-E-G-094 03 Fire Resistant Cables (FP 200) City Electrical Factor 28.11.11 12.12.11 21.12.11 A
95 S ACC-MAR-S-G-095 00 Uncoated Seven Steel Wire strand for Prestressed Concrete (First Supplier)
CCL / National Metal Manufac. 14.06.11 28.06.11 03.07.11 A
96 S ACC-MAR-S-G-096 00 Uncoated Seven Steel Wire strand for Prestressed Concrete (Second Supplier)
CCL / Silvery Dragon 14.06.11 28.06.11 04.07.11 A
92
94
88
89
Page 56 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
97 S ACC-MAR-S-G-097 00 CCL Stressing Systems Flat Anchor Sets CCL 14.06.11 28.06.11 03.07.11 A
98 S ACC-MAR-S-G-098 00 Corrugated Galvanized Flat Ducts with Couplers CCL 14.06.11 28.06.11 03.07.11 A
99 M ACC-MAR-M-G-099 00 GI Pipe Sleeves Econosto 22.06.11 15.06.11 29.06.11 28.06.11 B
E ACC-MAR-E-G-100 00 GI Cable Trays, Trunking & Ladders Al Mehrab Trading 10.07.11 18.06.11 02.07.11 22.06.11 C
E ACC-MAR-E-G-100 01 GI Cable Trays, Trunking & Ladders Al Mehrab Trading 10.07.11 13.07.11 27.07.11 16.08.11 B
E ACC-MAR-E-G-100 02 GI Cable Trays, Trunking & Ladders Al Mehrab Trading 08.09.11 22.09.11 05.10.11 B
E ACC-MAR-E-G-100A 03 GI Cable Trays & Cable Ladders Al Mehrab Trading 27.11.11 11.12.11 14.12.11 B
E ACC-MAR-E-G-100A 04 GI Cable Trays & Cable Ladders Al Mehrab Trading 16.05.12 30.05.12 16.06.12 C
E ACC-MAR-E-G-100A 05 GI Cable Trays & Cable Ladders TISCO/LAN-RIC 29.07.12 12.08.12 25.08.12 C
E ACC-MAR-E-G-100A 06 GI Cable Trays & Cable Ladders Al-Mehrab /UNICORN 08.10.12 22.10.12
E ACC-MAR-E-G-100B 03 GI Cable Trunking & Accessories Al Mehrab Trading 27.11.11 11.12.11 20.12.11 D
E ACC-MAR-E-G-100B 04 GI Cable Trunking & Accessories Al Mehrab Trading 01.02.12 15.02.12 11.03.12 C
E ACC-MAR-E-G-100B 05 Cable Trunking & Accessories Al Mehrab Trading 04.06.12 18.06.12 23.06.12 C
E ACC-MAR-E-G-100B 06 Cable Trunking & Accessories Al Mehrab Trading 21.07.12 04.08.12 23.08.12 B
E ACC-MAR-E-G-101 00 Fire Alarm, Fire Telephone & VA System Consolidated Engineering 15.07.11 18.06.11 02.07.11 22.06.11 C
E ACC-MAR-E-G-101 01 Fire Alarm, Fire Telephone & VA System Consolidated Engineering 07.07.11 21.07.11 13.08.11 C
E ACC-MAR-E-G-101 02 Fire Alarm, Fire Telephone & VA System Edward / Cesco WLL 28.08.11 11.09.11 05.10.11 B
E ACC-MAR-E-G-101 03 Fire Alarm, Fire Telephone & VA System Edward / Cesco WLL 29.03.12 12.04.12 14.04.12 C
E ACC-MAR-E-G-101 04 Fire Alarm, Fire Telephone & VA System Edward / Cesco WLL 20.05.12 03.06.12 07.07.12 C
E ACC-MAR-E-G-101 05 Fire Alarm, Fire Telephone & VA System Edward / Cesco WLL 18.07.12 01.08.12 29.09.12 B
103 S ACC-MAR-S-G-102 00 Midmac Block Factory Midmac 18.06.11 02.07.11 22.06.11 A
100
101
102
Page 57 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
E ACC-MAR-E-G-103 00 Diesel Generator Set with Synchronizing PanelQatari Insdutrial Equipment / FG
Wilson15.06.11 29.06.11 13.07.11 07.08.11 C
E ACC-MAR-E-G-103 01 Diesel Generator Set with Synchronizing Panel NBK & Sons 02.09.12 16.09.12 08.09.12 C
E ACC-MAR-E-G-103 02 Diesel Generator Set with Synchronizing Panel Cummins Qatar 01.10.12 15.10.12
M ACC-MAR-M-G-104 00 Chilled Water (CHW) Pipe Insulation Jersey Engineering 28.06.11 04.07.11 18.07.11 14.07.11 C
M ACC-MAR-M-G-104 01 Chilled Water Pipe Insulation Middle East Merchants 06.09.11 20.09.11 28.09.11 C
M ACC-MAR-M-G-104 02 Chilled Water Pipe Insulation Middle East Merchants 10.12.11 24.12.11 24.12.11 C
M ACC-MAR-M-G-104 03 Chilled Water Pipe Insulation Middle East Merchants 28.03.12 11.04.12 14.04.12 B
M ACC-MAR-M-G-105 00 BIB Tap Techno Gulf Trading 10.12.11 10.07.11 24.07.11 30.07.11 C
M ACC-MAR-M-G-105 01 BIB Tap Techno Gulf Trading 05.10.11 19.10.11 13.11.11 A
M ACC-MAR-M-G-106 00 Fire Rating DuctsAlmoayyed International
Group01.09.11 10.07.11 24.07.11 13.08.11 B
M ACC-MAR-M-G-106 01 Fire Rating DuctsAlmoayyed International
Group24.10.11 07.11.11 20.11.11 B
M ACC-MAR-M-G-106 02 Fire Rating DuctsAlmoayyed International
Group28.05.12 11.06.12 30.06.12 B
108 M ACC-MAR-M-G-107 00 Condensate Drain Pipe Insulation Aerodyne Cooling System 18.08.11 10.07.11 24.07.11 30.07.11 A
109 A ACC-MAR-A-G-108 00 Steel Lintel Expanded Metal Manufacturing 21.07.11 04.08.11 26.07.11 A
110 A ACC-MAR-A-G-109 00 Galvanized & Stainless Plastering Accessories Expanded Metal Manufacturing 21.07.11 04.08.11 26.07.11 A
111 A ACC-MAR-A-G-110 00 Blockwork Accessories Expanded Metal Manufacturing 21.07.11 04.08.11 26.07.11 A
112 M ACC-MAR-M-G-111 00 Aluminum Tape Qad-Net 24.07.11 07.08.11 16.08.11 A
E ACC-MAR-E-G-112 00 TransformerEngineering
Supplies Company
15.09.11 24.07.11 07.08.11 20.09.11 C
E ACC-MAR-E-G-112 01 TransformerEngineering
Supplies Company
20.10.11 03.11.11 09.11.11 B
106
104
105
107
113
Page 58 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
E ACC-MAR-E-G-112 02 TransformerEngineering
Supplies Company
28.11.11 12.12.11 25.12.11 A
M ACC-MAR-M-G-113 00 Concrete Anchors Metallic Building Materials 13.06.11 25.07.11 08.08.11 16.08.11 C
M ACC-MAR-M-G-113 01 Concrete Anchors Metallic Building Materials 06.09.11 20.09.11 18.10.11 A
115 M ACC-MAR-M-G-114 00 Stuck Up Pins (Durodyne) / Adhesive Hanger Aerodyne Cooling System 25.07.11 08.08.11 16.08.11 A
116 A ACC-MAR-A-G-115 00 Fire Stoping Sealant Unitech Qatar 25.07.11 08.08.11 06.08.11 A
117 M ACC-MAR-M-G-116 00 Duct Adhesive & Sealants (ideal) Equipment Trading & Cont. 10.08.11 24.08.11 05.10.11 A
M ACC-MAR-M-G-117 00 Modulating Float Valve for Concrete Tank Al Munasib Bldg. Material 20.12.11 26.07.11 09.08.11 16.08.11 C
M ACC-MAR-M-G-117 01 Modulating Float Valve for Concrete Tank Al Munasib Bldg. Material 24.10.11 07.11.11 05.12.11 C
M ACC-MAR-M-G-117 02 Modulating Float Valve for Concrete Tank Al Munasib Bldg. Material 31.12.11 14.01.12 01.04.12 B
M ACC-MAR-M-G-118 00 Float Valve (Equilibrium Type) Buildwell Trading 31.07.11 14.08.11 28.09.11 C
M ACC-MAR-M-G-118 01 Float Valve (Equilibrium Type) Buildwell Trading 24.10.11 07.11.11 04.12.11 A
M ACC-MAR-M-G-119 00 Pre-insulated Ducting System Pal 18.06.11 31.07.11 14.08.11 28.09.11 C
M ACC-MAR-M-G-119 01 Pre-insulated Ducting System Pal 12.10.11 26.10.11 13.11.11 C
M ACC-MAR-M-G-119 02 Pre-insulated Ducting System Pal 22.11.11 06.12.11 10.12.11 C
M ACC-MAR-M-G-119 03 Pre-insulated Ducting System Pal 27.12.11 10.01.12 01.01.12 C
M ACC-MAR-M-G-119 04 Pre-insulated Ducting System Pal 23.01.12 06.02.12 04.02.12 C
M ACC-MAR-M-G-119 05 Pre-insulated Ducting System Pal 28.02.12 13.03.12 12.03.12 C
M ACC-MAR-M-G-119 06 Pre-insulated Ducting System (Phenolic Foam) Pal 02.09.12 16.09.12 25.09.12 C
M ACC-MAR-M-G-120 00 Duct Insulation & Acoustic Liner Middle East Merchants 18.07.11 31.07.11 14.08.11 05.10.11 B
M ACC-MAR-M-G-120 01 Duct Insulation Middle East Merchants 16.10.12 30.10.12
M ACC-MAR-M-G-121 00 Flexible Duct Qatar Air Distribution 12.09.11 31.07.11 14.08.11 20.09.11 C
122
113
114
120
118
119
121
Page 59 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-121 01 Flexible Duct Qatar Air Distribution 25.10.11 08.11.11 13.11.11 C
M ACC-MAR-M-G-121 02 Flexible Duct Qatar Air Distribution 11.02.12 25.02.12 02.04.12 A
M ACC-MAR-M-G-122 00 Banding Strip Equipment Trading & Cont. 02.08.11 16.08.11 14.09.11 C
M ACC-MAR-M-G-122 01 Banding Strip AL-Kindi Trading Est. 10.10.11 24.10.11 13.11.11 A
M ACC-MAR-M-G-123 00 Flexible Duct Connector Equipment Trading & Cont. 07.09.11 06.08.11 20.08.11 14.09.11 B
M ACC-MAR-M-G-123 01 Flexible Duct Connector Equipment Trading & Cont. 12.11.11 26.11.11 10.12.11 B
M ACC-MAR-M-G-123 02 Flexible Duct Connector Equipment Trading & Cont. 09.01.12 23.01.12 16.01.12 B
M ACC-MAR-M-G-124 00 PPR Pipe & FittingsAtad
International Gen. Trading
22.06.11 10.08.11 24.08.11 28.09.11 C
M ACC-MAR-M-G-124 01 PPR Pipe & FittingsAtad
International Gen. Trading
20.10.11 03.11.11 04.12.11 C
M ACC-MAR-M-G-124 A 02 PPR Pipe & Fittings Cold Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
01.02.12 15.02.12 17.03.12 C
M ACC-MAR-M-G-124 A 03 PPR Pipe & Fittings Cold Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
01.04.12 15.04.12 05.04.12 B
M ACC-MAR-M-G-124 A 04 PPR Pipe & Fittings Cold Water Supply Horizontal Piping for Floors
Techno Gulf Trading/POLOP
LAST
17.07.12 31.07.12 01.08.12 B
M ACC-MAR-M-G-124 A 05 PPR Pipe & Fittings Cold Water Supply Horizontal Piping for Floors
Techno Gulf Trading/POLOP
LAST
13.10.12 27.10.12
M ACC-MAR-M-G-124 B 02 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
01.02.12 15.02.12 17.03.12 C
M ACC-MAR-M-G-124 B 03 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
01.04.12 15.04.12 14.04.12 D
M ACC-MAR-M-G-124 B 04 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
26.04.12 10.05.12 21.05.12 C
M ACC-MAR-M-G-124 B 05 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Atad International Gen. Trading
31.05.12 14.06.12 23.07.12 C
M ACC-MAR-M-G-124 B 06 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Techno Gulf Trading/POLOP
LAST
17.07.12 31.07.12 26.07.12 B
M ACC-MAR-M-G-124 B 07 PPR Pipe & Fittings Hot Water Supply Horizontal Piping for Floors
Techno Gulf Trading/POLOP
LAST
13.10.12 27.10.12
M ACC-MAR-M-G-125 00 Pex Pipes & FittingsAtad
International Gen. Trading
28.07.11 10.08.11 24.08.11 28.09.11 C
M ACC-MAR-M-G-125 01 Pex Pipes & FittingsAtad
International Gen. Trading
20.10.11 03.11.11 12.12.11 C
126
125
122
123
127
124
Page 60 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-125 02 Pex Pipes & FittingsAtad
International Gen. Trading
01.03.12 15.03.12 29.03.12 C
M ACC-MAR-M-G-125 03 Pex Pipes & Fittings Metco Qatar 02.07.12 16.07.12 19.07.12 C
M ACC-MAR-M-G-125 04 Pex Pipes & Fittings Metco Qatar 23.07.12 06.08.12 07.08.12 C
M ACC-MAR-M-G-125 05 Pex Pipes & Fittings Metco Qatar 10.09.12 24.09.12 22.09.12 A
128 M ACC-MAR-M-G-126 00 GI Duct Sheets Qatar Air Distribution 30.07.11 11.08.11 25.08.11 05.10.11 A
E ACC-MAR-E-G-127 00 Power Cables Doha Cables Qatar LLC 20.09.11 11.08.11 25.08.11 22.09.11 C
E ACC-MAR-E-G-127 01 Power Cables Doha Cables Qatar LLC 10.10.11 24.10.11 14.11.11 A
E ACC-MAR-E-G-128 00 PVC Insulated Wires Doha Cables Qatar LLC 01.08.11 11.08.11 25.08.11 22.09.11 C
E ACC-MAR-E-G-128 01 PVC Insulated Wires Doha Cables Qatar LLC 10.10.11 24.10.11 13.11.11 A
E ACC-MAR-E-G-129 00 Fire Resistance Power Cables (FP400) Elsewedy Cables Qatar 20.09.11 11.08.11 25.08.11 05.10.11 C
E ACC-MAR-E-G-129 01 Fire Resistance Power Cables (FP400) Elsewedy Cables Qatar 24.10.11 07.11.11 10.12.11 C
E ACC-MAR-E-G-129 02 Fire Resistance Power Cables (FP400) Elsewedy Cables Qatar 12.03.12 26.03.12 02.04.12 C
E ACC-MAR-E-G-129 03 Fire Resistance Power Cables (FP400) JBK DUCAB- 28.07.12 11.08.12 11.08.12 C
E ACC-MAR-E-G-129 04 Fire Resistance Power Cables (FP400) JBK DUCAB- 28.08.12 11.09.12 24.09.12 B
E ACC-MAR-E-G-130 00 Isolators Gazzaoui & Partners 20.11.11 17.08.11 31.08.11 05.10.11 C
E ACC-MAR-E-G-130 01 Isolators (Katko) Gazzaoui & Partners 16.01.12 19.11.11 03.12.11 14.12.11 C
E ACC-MAR-E-G-130 02 Isolators (Katko) Gazzaoui & Partners 07.01.12 21.01.12 23.01.12 B
E ACC-MAR-E-G-130 03 Isolators / Disconnecting Switch Gazzaoui & Partners 05.02.12 19.02.12 08.03.12 A
E ACC-MAR-E-G-131 00 PVC Coated G.I. Flexible Conduit & Accessories Lanric Malaysia 23.08.11 06.09.11 05.10.11 C
E ACC-MAR-E-G-131 01 PVC Coated G.I. Flexible Conduit & Accessories Lanric Malaysia 19.10.11 02.11.11 20.11.11 B
M ACC-MAR-M-G-132 00 Portable Fire Extinguishers Nafco 29.08.11 12.09.11 28.09.11 C
134
129
132
130
131
127
133
Page 61 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-132 01 Portable Fire Extinguishers Nafco 24.10.11 07.11.11 13.11.11 C
M ACC-MAR-M-G-132 02 Portable Fire Extinguishers Nafco 18.01.12 01.02.12 04.02.12 C
M ACC-MAR-M-G-132 03 Portable Fire Extinguishers Nafco 22.09.12 06.10.12 15.10.12 C
M ACC-MAR-M-G-133 00 Tamper Switches Nafco 29.08.11 12.09.11 28.09.11 C
M ACC-MAR-M-G-133 01 Tamper Switches Nafco 24.10.11 07.11.11 13.11.11 A
M ACC-MAR-M-G-134 00 Fire Blanket Nafco 29.08.11 12.09.11 28.09.11 C
M ACC-MAR-M-G-134 01 Fire Blanket Nafco 23.10.11 06.11.11 14.11.11 A
M ACC-MAR-M-G-135 00 Landing Valve Nafco 05.09.11 19.09.11 05.10.11 C
M ACC-MAR-M-G-135 01 Landing Valve Nafco 08.12.11 22.12.11 24.12.11 C
M ACC-MAR-M-G-135 02 Landing Valve Nafco 01.02.12 15.02.12 26.02.12 C
M ACC-MAR-M-G-136 00 Breeching Inlet & Cabinet Nafco 05.09.11 19.09.11 05.10.11 C
M ACC-MAR-M-G-136 01 Breeching Inlet & Cabinet Nafco 22.11.11 06.12.11 04.12.11 C
M ACC-MAR-M-G-136 02 Breeching Inlet & CabinetInternational Gulf Trading Company-
08.07.12 22.07.12 23.07.12 B
M ACC-MAR-M-G-137 00 Fire Hydrant Nafco 05.09.11 19.09.11 05.10.11 C
M ACC-MAR-M-G-137 01 Fire Hydrant Nafco 24.10.11 07.11.11 05.12.11 C
M ACC-MAR-M-G-137 02 Fire Hydrant & nrs Gate Valve Nafco 21.07.12 04.08.12 02.08.12 C
M ACC-MAR-M-G-138 00 Fire Hose Cabinet Nafco 05.12.11 08.09.11 22.09.11 28.09.11 C
M ACC-MAR-M-G-138 01 Fire Hose Cabinet Nafco 12.11.11 26.11.11 04.12.11 C
M ACC-MAR-M-G-138 02 Fire Hose Cabinet Nafco 05.02.12 19.02.12 26.02.12 C
M ACC-MAR-M-G-139 00 Gate Valves Nafco 30.09.11 08.09.11 22.09.11 28.09.11 C
M ACC-MAR-M-G-139 01 Gate Valves Nafco 09.11.11 23.11.11 27.11.11 C
134
138
136
137
140
135
139
141
Page 62 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-139 02 Gate ValvesChubb Fire
Qatar / Viking Firing
05.08.12 19.08.12 11.08.12 C
M ACC-MAR-M-G-140 00 Zone Control Valve (Butterfly Valve, Flow Switch, Test & Drain Valve) Nafco 30.09.11 08.09.11 22.09.11 28.09.11 C
M ACC-MAR-M-G-140 01 Zone Control Valve (Butterfly Valve, Flow Switch, Test & Drain Valve) Nafco 29.10.11 12.11.11 13.11.11 B
M ACC-MAR-M-G-140 02 Zone Control Valve (Butterfly Valve, Flow Switch, Test & Drain Valve) Nafco 18.01.12 01.02.12 23.01.12 C
M ACC-MAR-M-G-140 03 Zone Control Valve (Butterfly Valve, Flow Switch, Test & Drain Valve, Pressure Gauge)
International Gulf Trading
Company
25.06.12 09.07.12 18.07.12 C
143 M ACC-MAR-M-G-141 00 Hot Water Pipe Insulation Jersey Engineering 11.09.11 25.09.11 28.09.11 C
M ACC-MAR-M-G-142 00 Sanitary Wares and AccessoriesHamad Bin Mohamad
Group
12.09.11 26.09.11 05.10.11 C
M ACC-MAR-M-G-142H 01 Sanitary Wares and Accessories - Under Counter Wash Basin Hotel
Hamad Bin Mohamad
Group
27.12.11 10.01.12 01.01.12 C
M ACC-MAR-M-G-142A 01 Sanitary Wares and Accessories Tower AHamad Bin Mohamad
Group
29.12.11 12.01.12 08.01.12 C
M ACC-MAR-M-G-142A 02 Sanitary Wares and Accessories Tower AHamad Bin Mohamad
Group
25.02.12 10.03.12 25.03.12 C
M ACC-MAR-M-G-142A 03 Sanitary Wares (Mixers) Tower AHamad Bin Mohamad
Group
03.07.12 17.07.12 12.07.12 A
M ACC-MAR-M-G-143 00 Pressure Reducing Valve Nafco 10.11.11 12.09.11 26.09.11 28.09.11 C
M ACC-MAR-M-G-143 01 Pressure Reducing Valve Nafco 16.10.11 30.10.11 27.11.11 C
M ACC-MAR-M-G-143 02 Pressure Reducing Valve Nafco 18.01.12 01.02.12 04.02.12 A
M ACC-MAR-M-G-144 00 Alarm Check Valve Nafco 10.11.11 12.09.11 26.09.11 05.10.11 C
M ACC-MAR-M-G-144 01 Alarm Check Valve Nafco 24.10.11 07.11.11 13.11.11 C
M ACC-MAR-M-G-144 02 Alarm Check Valve Nafco 01.04.12 15.04.12 16.04.12 C
M ACC-MAR-M-G-144 03 Alarm Check Valve Viking / International gulf 10.06.12 24.06.12 30.06.12 B
M ACC-MAR-M-G-145 00 Check Valve Nafco 16.12.11 12.09.11 26.09.11 05.10.11 C
M ACC-MAR-M-G-145 01 Check Valve Nafco 09.11.11 23.11.11 27.11.11 C
M ACC-MAR-M-G-145 02 Check Valve Nafco 18.01.12 01.02.12 04.02.12 C
147
142
145
144
146
141
Page 63 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-145 03 Check Valve Nafco 30.06.12 14.07.12 10.07.12 C
M ACC-MAR-M-G-146 00 Sprinkler Heads Nafco 20.12.11 12.09.11 26.09.11 28.09.11 C
M ACC-MAR-M-G-146 01 Sprinkler Heads Nafco 23.10.11 06.11.11 05.12.11 C
M ACC-MAR-M-G-146 02 Sprinkler Heads Nafco 29.01.12 12.02.12 12.02.12 B
149 S ACC-MAR-S-G-147 00 Grout Mix Design: Fosroc Cebex 100 CCL / Fosroc 15.09.11 29.09.11 20.09.11 A
M ACC-MAR-M-G-148 00 Fire Pump Accessories Nafco 20.10.11 18.09.11 02.10.11 05.10.11 C
M ACC-MAR-M-G-148 01 Fire Pump Accessories Nafco 12.11.11 26.11.11 27.11.11 C
M ACC-MAR-M-G-149 00 Plate Heat Exchanger Faisal Jassim Trading Co. 06.09.11 18.09.11 02.10.11 18.10.11 A
M ACC-MAR-M-G-149 01 Plate Heat Exchanger Faisal Jassim Trading Co. 07.03.12 21.03.12 24.03.12 C
M ACC-MAR-M-G-149 02 Plate Heat Exchanger Faisal Jassim Trading Co. 21.05.12 04.06.12 04.06.12 C
M ACC-MAR-M-G-149 03 Plate Heat ExchangerFaisal Jassim
Trading Co./Sondex
25.07.12 08.08.12 09.08.12 C
M ACC-MAR-M-G-149 04 Plate Heat ExchangerFaisal Jassim
Trading Co./Sondex
02.09.12 16.09.12 13.10.12 C
152 S ACC-MAR-S-G-150 00 Fosroc Nitoprime Zincrich : Zinc primer for Steel Chairs of Post Tension Cables Fosroc 19.09.11 03.10.11 29.10.11 A
M ACC-MAR-M-G-151 00 Parking Drain Al Munasib Bldg. Material 22.09.11 06.10.11 05.10.11 C
M ACC-MAR-M-G-151 01 Parking Drain Al Munasib Bldg. Material 01.02.12 15.02.12 10.03.12 C
M ACC-MAR-M-G-151 02 Parking Drain Al Munasib Bldg. Material 18.06.12 02.07.12 18.07.12 C
M ACC-MAR-M-G-151 03 Parking Drain Al Munasib Bldg. Material 02.08.12 16.08.12 25.08.12 C
M ACC-MAR-M-G-151 04 Parking Drain Al Munasib Bldg. Material 09.09.12 23.09.12 18.10.12 C
154 M ACC-MAR-M-G-152 00 Sanitary Ware Mixers and Accessories Capital Trading 22.09.11 06.10.11 12.12.11 D
E ACC-MAR-E-G-153 00 Cable Glands and Cable LugsAl-Mehboob
Electrical Trading
28.09.11 12.10.11 18.10.11 C
E ACC-MAR-E-G-153 01 Cable Glands and Cable LugsAl-Mehboob
Electrical Trading
19.10.11 02.11.11 13.11.11 C
147
155
148
153
151
150
Page 64 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
E ACC-MAR-E-G-153 02 Cable Glands and Cable LugsAl-Mehboob
Electrical Trading
18.01.12 01.02.12 06.02.12 B
E ACC-MAR-E-G-153 03 Cable Glands and Lugs Trade House Qatar 19.02.12 04.03.12 08.03.12 A
E ACC-MAR-E-G-154 00 Aircraft Warning Light Tectronics 28.09.11 12.10.11 13.11.11 C
E ACC-MAR-E-G-154 01 Aircraft Warning Light Tectronics 27.11.11 11.12.11 21.12.11 B
E ACC-MAR-E-G-154 02 Aircraft Warning Light Tectronics 18.01.12 01.02.12 04.02.12 B
E ACC-MAR-E-G-154 03 Aircraft Warning Light Tectronics 07.03.12 21.03.12 21.03.12 A
157 S ACC-MAR-S-G-155 00 National Rust Remover / Converter National Paints 29.09.11 13.10.11 16.10.11 A
158 M ACC-MAR-M-G-156 00 Pressure Reducing ValveAl-Munasib
Bldg. Material Trading LLC
10.10.11 24.10.11 27.11.11 B
M ACC-MAR-M-G-157 00 Automatic Air Vent Leminar Air Conditioning 10.10.11 24.10.11 13.11.11 C
M ACC-MAR-M-G-157 01 Automatic Air Vent for Chilled Water Application Leminar Air Conditioning 07.04.12 21.04.12 21.04.12 C
M ACC-MAR-M-G-157 02 Automatic Air Vent for Chilled Water Application Leminar Air Conditioning 26.05.12 09.06.12 03.06.12 C
M ACC-MAR-M-G-157 03 Automatic Air Vent for Chilled Water Application Leminar Air Conditioning 02.07.12 16.07.12 18.07.12 B
160 S ACC-MAR-S-G-158 00 Hollow Concrete Blocks (Dimension 400x200x200,400x150x200,400x100x200
Al Rayyan Block Factory 10.10.11 24.10.11 16.10.11 A
161 M ACC-MAR-M-G-159 00 Aluminum Sheet (Cladding) Alpha Star Trading 16.10.11 30.10.11 25.12.11 A
M ACC-MAR-M-G-160 00 Vibration Isolators Leminar Air Conditioning 22.10.11 05.11.11 14.11.11 B
M ACC-MAR-M-G-160 01 Vibration Isolators Leminar Air Conditioning 01.10.12 15.10.12
S ACC-MAR-S-G-161 00 Predimax injection Hose Tadmur 27.10.11 10.11.11 17.11.11 C
S ACC-MAR-S-G-161 01 Predimax injection Hose Tadmur 09.01.12 23.01.12 16.01.12 A
164 A ACC-MAR-A-G-162 00 Ready Made Plaster ( Concrete Rush Coat CRC MS, Cement Plaster - CP 14) Conmix Limited 27.10.11 10.11.11 17.11.11 B
165 A ACC-MAR-A-G-163 00 Ready Mix Plaster (Concrete Rush Coat SRC-2, Cement Plaster - SP 11) Sodamco 31.10.11 14.11.11 17.11.11 B
156
162
163
155
159
Page 65 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-164 00 GRP Water Tank (Portable Water Storage Tank)Inter Model
Services Co. WLL
02.11.11 16.11.11 27.11.11 C
M ACC-MAR-M-G-164 01 GRP Water Tank (Portable Water Storage Tank)Al Muftah Fiberglass
Products WLL
15.07.12 29.07.12 30.07.12 C
M ACC-MAR-M-G-164 02 GRP Water Tank (Portable Water Storage Tank)Al Muftah Fiberglass
Products WLL
16.10.12 30.10.12
M ACC-MAR-M-G-165 00 Motorized Smoke Dampers Qad-Net 03.11.11 17.11.11 27.11.11 C
M ACC-MAR-M-G-165 01 Motorized Smoke Dampers Qad-Net 11.02.12 25.02.12 10.03.12 B
M ACC-MAR-M-G-166 00 Motorized Fire/ Smoke Damper Qad-Net 03.11.11 17.11.11 27.11.11 C
M ACC-MAR-M-G-166 01 Motorized Fire Smoke Damper Qatar Air Distribution 25.02.12 10.03.12 17.03.12 B
A ACC-MAR-A-G-167 00 Sand For Plaster WorksLemas for Trading &
Contracting
03.11.11 17.11.11 17.11.11 C
A ACC-MAR-A-G-167 01 Sand For Plaster WorksLemas for Trading &
Contracting
04.12.11 18.12.11 08.12.11 B
M ACC-MAR-M-G-168 00 Fire Damper Qad-Net 03.11.11 17.11.11 27.11.11 C
M ACC-MAR-M-G-168 01 Fire Damper Qad-Net 05.02.12 19.02.12 19.02.12 C
M ACC-MAR-M-G-168 02 Fire Damper Qad-Net 01.03.12 15.03.12 21.03.12 C
M ACC-MAR-M-G-168 03 Fire Damper Qad-Net 01.04.12 15.04.12 09.04.12 B
M ACC-MAR-M-G-169 00 Volume Control Damper Qad-Net 03.11.11 17.11.11 27.11.11 C
M ACC-MAR-M-G-169 01 Volume Control Damper Qad-Net 08.02.12 22.02.12 10.03.12 B
M ACC-MAR-M-G-169 02 Volume Control Damper Qad-Net 18.04.12 02.05.12 29.04.12 B
M ACC-MAR-M-G-170 00 Access Door Qatar Air Distribution 03.11.11 17.11.11 27.11.11 C
M ACC-MAR-M-G-170 01 Access Door Qatar Air Distribution 06.02.12 20.02.12 19.02.12 C
M ACC-MAR-M-G-170 02 Access Door Qatar Air Distribution 13.03.12 27.03.12 29.03.12 B
M ACC-MAR-M-G-171 00 Ventilation Fans(Car Park and Kitchen Ventilation Fans)
Int'l Engg. Supplies 03.11.11 17.11.11 04.12.11 C
M ACC-MAR-M-G-171 01 Ventilation Fans(Excluding Car Park and Kitchen Ventilation Fans)
Int'l Engg. Supplies 09.07.12 23.07.12 26.07.12 C
169
173
167
166
168
170
172
171
Page 66 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-172 00 Valves (Plumbing Valves) Best Flow Trading 09.11.11 23.11.11 14.12.11 C
M ACC-MAR-M-G-172 01 Valves (Plumbing Valves) Best Flow Trading 28.01.12 11.02.12 25.02.12 B
M ACC-MAR-M-G-172 02 Valves (Plumbing Valves) Best Flow Trading 13.10.12 27.10.12
M ACC-MAR-M-G-173 00 Chilled Water Valves Best Flow Trading 09.11.11 23.11.11 01.01.12 C
M ACC-MAR-M-G-173 01 Chilled Water Valves Best Flow Trading 26.03.12 09.04.12 10.04.12 C
M ACC-MAR-M-G-173 02 Chilled Water Valves Best Flow Trading 19.05.12 02.06.12 27.06.12 C
M ACC-MAR-M-G-173 03 Chilled Water Valves Best Flow Trading 02.08.12 16.08.12 25.08.12 B
A ACC-MAR-A-G-174 00 Gypsum Board - Regular Depa / United Mining 19.11.11 03.12.11 03.05.12 A
A ACC-MAR-A-G-174 01 Gypsum Board - Regular Depa / United Mining 15.05.12 29.05.12 11.06.12 B
A ACC-MAR-A-G-175 00 Gypsum Board - Moisture Resistance Depa / United Mining 19.11.11 03.12.11 28.04.12 A
A ACC-MAR-A-G-175 01 Gypsum Board - Moisture Resistance Depa / United Mining 15.05.12 29.05.12 03.06.12 B
178 S ACC-MAR-S-G-176 00 Alternative Waterproofing for Substructural and Water tank Tadmur 14.11.11 28.11.11 04.02.12 A
A ACC-MAR-A-G-177 00 Suspended Ceiling SystemDepa /
Expanded Metal Manufacturing
19.11.11 03.12.11 29.04.12 B
A ACC-MAR-A-G-177 01 Suspended Ceiling SystemDepa /
Expanded Metal Manufacturing
15.05.12 29.05.12 11.06.12 B
M ACC-MAR-M-G-178 00 Flexible Pipe Connector & Expansion JointsWeicco /
Leminar Air Conditioning
21.11.11 05.12.11 19.12.11 C
M ACC-MAR-M-G-178 01 Flexible Pipe Connector & Expansion JointsWeicco /
Leminar Air Conditioning
28.02.12 13.03.12 11.03.12 C
M ACC-MAR-M-G-178 02 Flexible Pipe Connector & Expansion JointsWeicco /
Leminar Air Conditioning
16.05.12 30.05.12 27.06.12 C
M ACC-MAR-M-G-178 03 Flexible Pipe Connector & Expansion JointsWeicco /
Leminar Air Conditioning
01.08.12 15.08.12 14.08.12 C
181 M ACC-MAR-M-G-179 00 UPVC - Puddle Flanges (for Retaining Walls) Hepworth 21.11.11 05.12.11 04.12.11 A
M ACC-MAR-M-G-180 00 Water Treatment and Sand Filters Metito 21.11.11 05.12.11 24.12.11 C
M ACC-MAR-M-G-180 01 Water Treatment and Sand Filters Metito 25.02.12 10.03.12 19.03.12 C
179
176
182
177
174
180
175
Page 67 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-180 02 Water Treatment and Sand Filters Metito 21.04.12 05.05.12 08.05.12 C
M ACC-MAR-M-G-180 03 Water Treatment and Sand Filters Metito 02.06.12 16.06.12 30.06.12 C
M ACC-MAR-M-G-180 04 Water Treatment and Sand Filters Metito 02.10.12 16.10.12
183 M ACC-MAR-M-G-181 00 Floor Trap / Floor Drain Hepworth 21.11.11 05.12.11 04.12.11 A
184 S ACC-MAR-S-G-182 00 Polyfoam : Extruded Polystyrene Insulation Boards
Qatar Insulation 21.11.11 05.12.11 15.12.11 A
M ACC-MAR-M-G-183 00 Fan Coil Units (FCU) for Office Tower and Podium
Dynair / Maico Gulf 21.11.11 05.12.11 05.12.11 C
M ACC-MAR-M-G-183 01 Fan Coil Units (FCU) for Office Tower and Podium MEKAR 23.06.12 07.07.12 18.07.12 C
M ACC-MAR-M-G-183 02 Fan Coil Units (FCU) for Office Tower and Podium MEKAR 21.07.12 04.08.12 30.07.12 C
M ACC-MAR-M-G-183 03 Fan Coil Units (FCU) for Office Tower and Podium MEKAR 22.07.12 05.08.12 22.08.12 C
M ACC-MAR-M-G-183 04 Fan Coil Units (FCU) for Office Tower and Podium MEKAR 11.09.12 25.09.12 22.09.12 C
M ACC-MAR-M-G-183 05 Fan Coil Units (FCU) for Office Tower and Podium MEKAR 02.10.12 16.10.12
M ACC-MAR-M-H-184 00 Fan Coil Units (FCU) for Hotel Tower Dynair / Maico Gulf 21.11.11 05.12.11 05.12.11 C
M ACC-MAR-M-H-184 01 Fan Coil Units (FCU) for Hotel Tower MEKAR 23.06.12 07.07.12 18.07.12 C
M ACC-MAR-M-H-184 02 Fan Coil Units (FCU) for Hotel Tower MEKAR 21.07.12 04.08.12 30.07.12 C
M ACC-MAR-M-H-184 03 Fan Coil Units (FCU) for Hotel Tower MEKAR 12.08.12 26.08.12 22.08.12 C
M ACC-MAR-M-H-184 04 Fan Coil Units (FCU) for Hotel Tower MEKAR 11.09.12 25.09.12 22.09.12 C
M ACC-MAR-M-H-184 05 Fan Coil Units (FCU) for Hotel Tower MEKAR 02.10.12 16.10.12
187 A ACC-MAR-A-G-185 00 Jotun Paint System as an option for Wood Panel Depa /Jotun Paint 22.11.11 06.12.11 29.04.12 C
A ACC-MAR-A-G-186 00 Jotun Paint System Depa / Jotun Paint 22.11.11 06.12.11 29.04.12 C
A ACC-MAR-A-G-186 01 Jotun Paint System Depa / Jotun Paint 01.05.12 15.05.12 12.05.12 A
A ACC-MAR-A-G-186 02 Jotun Paint System Depa / Jotun Paint 15.05.12 29.05.12 03.06.12 B
186
185
182
188
Page 68 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-186 03 Jotun Paint System for Walls, NCS S 1502 - Y50 R
Depa / Jotun Paint 21.06.12 05.07.12 02.07.12 A
M ACC-MAR-M-G-187 00 Identification Tags and MEP Works Al Sheera Advertising 27.11.11 11.12.11 14.12.11 C
M ACC-MAR-M-G-187 01 Identification Tags for MEP Works Kakaras Elec. & Sanitary 24.07.12 07.08.12 11.08.12 C
M ACC-MAR-M-G-188 00 Pressure Gauge & Thermometers (for HVAC System)
Leminar Air Conditioning / 28.11.11 12.12.11 17.12.11 C
M ACC-MAR-M-G-188 01 Pressure Gauge & Thermometers (for HVAC System)
Leminar Air Conditioning / 01.03.12 15.03.12 20.03.12 B
191 S ACC-MAR-S-G-189 00 PP Fiber for Screed to Floor DCP 28.11.11 12.12.11 05.12.11 C
192 M ACC-MAR-M-G-190 00 Angle / Channel for Support (MS Angle Hot Dip Galvanized, 50x50x5mm) Tissco 04.12.11 18.12.11 21.12.11 A
193 M ACC-MAR-M-G-191 00 Chilled Water Grooved Fittings Hydro / Jinan 08.12.11 22.12.11 20.12.11 C
M ACC-MAR-M-G-192 00 FCU Valve Package Efeco 08.12.11 22.12.11 24.12.11 C
M ACC-MAR-M-G-192 01 FCU Valve Package Efeco 29.03.12 12.04.12 14.04.12 C
A ACC-MAR-A-G-193 00 Carpet Rooms (18'W X 00"L) Depa / Bolyu 13.03.12 27.03.12 25.04.12 A
A ACC-MAR-A-G-193 01 Carpet Rooms (18'W X 00"L) Depa / Bolyu 15.05.12 29.05.12 14.06.12 A
A ACC-MAR-A-G-193 02 Carpet Rooms (18'W X 00"L) Depa / Bolyu 19.06.12 03.07.12 27.06.12 B
A ACC-MAR-A-G-194 00 Grout for Tiles, Nitotile Grout Depa / Fosroc 07.03.12 21.03.12 09.04.12 B
A ACC-MAR-A-G-194 01 Grout for Tiles, Nitotile Grout Depa / Fosroc 02.05.12 16.05.12 12.05.12 A
A ACC-MAR-A-G-195 00 Adhesive for Tiles, Nitotile GP Depa / Fosroc 07.03.12 21.03.12 28.04.12 C
A ACC-MAR-A-G-195 01 Adhesive for Tiles, Nitotile XS Depa / Fosroc 06.05.12 20.05.12 14.05.12 A
A ACC-MAR-A-G-195 02 Adhesive for Tiles, Nitotile XS Depa / Fosroc 15.05.12 29.05.12 11.06.12 B
A ACC-MAR-A-G-197 00 Stainless Steel Cladding in Chrome Finish, Grade 304
Depa / Metalica 11.03.12 25.03.12 28.04.12 A
A ACC-MAR-A-G-197 01 1 mm Stainless Steel Brush Finish for Wall Cladding, Grade 304
Depa / Metalica 21.06.12 05.07.12 02.07.12 A
A ACC-MAR-A-G-198 00 Floor Tile, Vitra Size 30X30 Code:K855586, Uni Graf - Grey Sayyar / Vitra 23.05.12 06.06.12 28.05.12 A
194
190
189
195
197
198
199
196
188
Page 69 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-198 01Floor Tile, Vitra Size 30X30 (Option 1 : UNI IVORY K835803, Option 2: UNI MARKET K843514, Option 3: UNI S. WHITE K835910
Sayyar / Vitra 29.09.12 13.10.12 07.10.12 A
A ACC-MAR-A-G-199 00 Floor and Wall Tile, Brera Depa / Ceramiche 07.03.12 21.03.12 23.04.12 A
A ACC-MAR-A-G-199 01 Floor and Wall Tile, Brera Depa / Ceramiche 15.05.12 29.05.12 21.05.12 A
A ACC-MAR-A-G-200 00 Jotun Paint System for Ceiling, RAL 9016 Depa / Jotun Paint 12.03.12 26.03.12 28.04.12 A
A ACC-MAR-A-G-200 01 Jotun Paint System for Ceiling, RAL 9016 Depa / Jotun Paint 15.05.12 29.05.12 03.06.12 B
A ACC-MAR-A-G-200 02 Jotun Paint System for Ceiling, RAL 9016 Depa / Jotun Paint 21.06.12 05.07.12 02.07.12 A
202 A ACC-MAR-A-G-201 00 Floor and Wall Tile, Roca (Option 2) Depa / Roca 07.03.12 21.03.12 23.04.12 C
203 A ACC-MAR-A-G-202 00 Floor and Wall Tile, Estile (Option 3) Depa / Estile 07.03.12 21.03.12 23.04.12 C
A ACC-MAR-A-G-203 00 Stainless Steel U-Channel in Chrome Finish for Corridor, Grade 304
Depa / Metalica 11.03.12 25.03.12 01.05.12 A
A ACC-MAR-A-G-203 01 Stainless Steel U-Channel in Chrome Finish for Corridor, Grade 304
Depa / Metalica 15.05.12 29.05.12 11.06.12 A
205 A ACC-MAR-A-G-204 00 Rockwool Insulation for Curtain Wall and Metal Cladding (50kg/m3) AGR / Azel 02.05.12 16.05.12 14.05.12 A
A ACC-MAR-A-G-205 00 Glass Door Handles, Hafele Depa / Hafele 03.05.12 17.05.12 08.05.12 A
A ACC-MAR-A-G-205 01 Handle For Shower Glass, Hafele Depa / Hafele 29.09.12 13.10.12 07.10.12 A
207 A ACC-MAR-A-G-206 00 Wood Finish for Custom Furniture, Beech Veneer Stain and Polyurethane Lacquer Finish depa / Eldiar 03.05.12 17.05.12 14.05.12 C
208 M ACC-MAR-M-G-207 00 Pressure Relief Damper Qatar Air Distribution 05.05.12 19.05.12 14.05.12 C
M ACC-MAR-M-G-208 00 Non-Return Damper Qatar Air Distribution 05.05.12 19.05.12 14.05.12 C
M ACC-MAR-M-G-208 01 Non-Return Damper Qatar Air Distribution 11.06.12 25.06.12 30.06.12 C
M ACC-MAR-M-G-208 02 Non-Return Damper Qatar Air Distribution 08.10.12 22.10.12 15.10.12 C
A ACC-MAR-A-G-209 00 Gypsum Access Panel with Pushing Lock (GA Series)
Depa / Al Areesh Interior 11.03.12 25.03.12 23.04.12 C
A ACC-MAR-A-G-209 01 Knauf Access Panel Depa / Knauf 25.04.12 09.05.12 30.04.12 A
200
199
209
201
204
210
206
Page 70 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-210 00 Manual Sliding Door System, Hawa Junior 80/GS Depa / Hawa 10.03.12 24.03.12 28.04.12 C
A ACC-MAR-A-G-210 01 Manual Sliding Door System, GEZE -Perlan 140 Depa / GEZE 11.08.12 25.08.12 16.08.12 C
A ACC-MAR-A-G-210 02 Manual Sliding Door System, GEZE -Perlan 140 with soft stop on one side Depa / GEZE 25.09.12 09.10.12 OVERDUE
A ACC-MAR-A-G-211 00 Carpet for Corridor Depa / Bolyu 07.03.12 21.03.12 25.04.12 A
A ACC-MAR-A-G-211 01 Carpet for Corridor Depa / Bolyu 17.05.12 31.05.12 11.06.12 A
A ACC-MAR-A-G-211 02 Carpet for Corridor Depa / Bolyu 19.06.12 03.07.12 30.06.12 B
A ACC-MAR-A-G-212 00 Wall Covering (Newmor Code No. Darnell GND 2216)
Depa / Newmor 08.03.12 22.03.12 25.04.12 A
A ACC-MAR-A-G-212 01 Wall Covering (Newmor Code No. Darnell GND 2216)
Depa / Newmor 15.05.12 29.05.12 11.06.12 A
A ACC-MAR-A-G-212 02 Wall Covering (Newmor Code No. Darnell GND 2216)
Depa / Newmor 19.06.12 03.07.12 01.07.12 B
A ACC-MAR-A-G-213 00 10mm Thick Mirror Depa / Guardian 26.04.12 10.05.12 08.05.12 A
A ACC-MAR-A-G-213 01 6 mm Thick Mirror Depa / Guardian 20.06.12 04.07.12 27.06.12 B
A ACC-MAR-A-G-214 00 Clear Glass (10mm Thick Clear Glass) Depa / Guardian 12.03.12 26.03.12 25.04.12 A
A ACC-MAR-A-G-214 01 Clear Glass (10mm Thick Clear Glass) Depa / Guardian 19.06.12 03.07.12 30.06.12 C
A ACC-MAR-A-G-214 02 10 mm thick Clear Tempered Glass with Sand Blasted Finish
Depa / Guardian 30.08.12 13.09.12 02.09.12 C
A ACC-MAR-A-G-214 03
10 mm thick Clear Tempered Glass with Back Painted (Option 1 - Beige Color with black top layer paint, Option 2 - Off- White Color with black top layer paint, Option 3 - RAL 1003 with white top layer paint, Option 4 - RAL 1005 with white top layer paint
Depa / Guardian
Glass19.09.12 03.10.12 06.10.12 B
216 A ACC-MAR-A-G-215 00 Bed Matress (2000 X 2000 & 1000 X 2000) Depa / Simmons 11.03.12 25.03.12 02.05.12 C
M ACC-MAR-M-H-216 00 Floor Drain Cover (Tower B) Kessel / Albina 05.05.12 19.05.12 21.05.12 C
M ACC-MAR-M-H-216 01 Floor Drain Cover (Tower B) Kessel / Albina 15.08.12 29.08.12 01.09.12 C
A ACC-MAR-A-G-217 00 20mm / 25mm Backing Rod for Joint Sealant Arnon Plastic / Castle 05.05.12 19.05.12 17.05.12 C
218
215
212
213
214
211
217
Page 71 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-217 01 20mm / 25mm / 30mm Backing Rod for Joint Sealant
Arnon Plastic / Modern 20.05.12 03.06.12 28.05.12 A
A ACC-MAR-A-G-218 00 Juton Powder Coating PE AGR / Juton 07.05.12 21.05.12 17.05.12 C
A ACC-MAR-A-G-218 01 Juton Powder Coating PE-SDF AGR / Juton 19.06.12 03.07.12 16.07.12 B
A ACC-MAR-A-G-219 00 Nitofill EPLV Concrete Cracks Repairing Fosroc 07.05.12 21.05.12 14.05.12 C
A ACC-MAR-A-G-219 01 Nitofill EPLV Concrete Cracks Repairing Fosroc 27.05.12 10.06.12 24.06.12 C
221 A ACC-MAR-A-G-220 00 20mm Thick Manufactured Marble Alternative for Calizia Capri (Option 2)
Depa / Stone Gallery 09.05.12 23.05.12 21.05.12 C
A ACC-MAR-A-G-221 00 20mm Thick Manufactured Marble Alternative for Calizia Capri (Option 1)
Depa / Al farman 09.05.12 23.05.12 21.05.12 A
A ACC-MAR-A-G-221 01 20mm Thick Manufactured Marble Alternative for Calizia Capri (Option 1)
Depa / Al farman 15.05.12 29.05.12 07.06.12 A
A ACC-MAR-A-G-221 02 20mm Thick Manufactured Marble ,for Calizia Capri
Depa / Al farman 19.06.12 03.07.12 01.07.12 B
A ACC-MAR-A-G-221 0320mm Thick Marble For Guest Bathrooms (Royale Beige, Crema Marfil, Bottichino, Marcin Beige, Dallia, Calizia Capri, Piedra Paloma)
Depa / Al farman 28.07.12 11.08.12 23.08.12 B
A ACC-MAR-A-G-221 0420mm Thick Marble For Guest Bathrooms & Apartment Kitchens & Window Coping(Sample 1 - Polished finish - for vanity counter top, bathtub top, bidet back wall coping & window coping /
Depa / Stone Gallery 25.09.12 09.10.12 01.10.12 B
M ACC-MAR-M-G-222 00 Automatic Chemical Dosing System Veolia 09.05.12 23.05.12 19.07.12 C
M ACC-MAR-M-G-222 01 Automatic Chemical Dosing System Veolia 13.08.12 27.08.12 22.08.12 C
M ACC-MAR-M-G-222 02 Automatic Chemical Dosing System Veolia 07.10.12 21.10.12
224 A ACC-MAR-A-G-223 00 Curtain Rail, 3 Way Full System Depa / Rilox 10.05.12 24.05.12 14.05.12 C
A ACC-MAR-A-G-224 00 Beech Wood Painted Skirting Depa / Cora 10.05.12 24.05.12 14.05.12 B
A ACC-MAR-A-G-224 01 Beech Wood Painted Skirting Depa / Cora 20.06.12 04.07.12 30.06.12 B
226 A ACC-MAR-A-G-225 00 Marine Plywood and Treatment for Cut Edges Depa / Marineplex 12.05.12 26.05.12 21.05.12 A
227 A ACC-MAR-A-G-226 00 Treated Wood Backing Depa / Cora 12.05.12 26.05.12 21.05.12 A
A ACC-MAR-A-G-227 00 Silicone Dow Corning 813 C AGR / Dow Corning 21.05.12 04.06.12 14.06.12 C
219
218
228
225
220
222
223
Page 72 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-227 01 Silicone Dow Corning 813C, 895 & 791 AGR / Dow Corning 07.07.12 21.07.12 14.07.12 B
A ACC-MAR-A-G-228 00 8mm Pilkington YBE (Blue) Tempered Glass, 16mm Airspace, 4mm Clear Anneld Glass,
AGR / Shanghai 14.05.12 28.05.12 14.06.12 C
A ACC-MAR-A-G-228 01
Saint Gobain Glass(8 mm Cool-Lite Nano Misty Blue(KNT 755) tempered (Saint Gobain), 8mm Cool-Lite Orion Advantage/SGG EVO (ET725)
tempered (Saint Gobain)
AGR/Saint- Gobain Glass 02.07.12 16.07.12 21.07.12 C
A ACC-MAR-A-G-228 02
Curtain Wall Glass Option 1: 8 mm Stopray Vision-50 T Tempered Glass ,16 mm Air Space - 10mm Clear Tempered Glass Option 1: 8 mm Cool Lite Smoke Silver KNT 140,16 Air Space,10 mm Clear Glass Option 3:
8mm Pilkington Silver Sunshade Glass 16 mm Air Space + 10 mm Clear Glass Option 4:
8 mm Solar E Grey Glass 16 mm Air Space + 10 mm Clear Glass
AGR -AGC/Saint-
Gobain Glass/ Pilkington
23.09.12 07.10.12 09.10.12 C
A ACC-MAR-A-G-228 03
Curtain Wall Glazing -Material Submittal for Option 1 Glaverbel , 800 Temepered Stopray Vision 50T (AGC Belgium) + 16 mm Air Space + 8.38 mm Laminated Annealed Glass with Normal PVB (AGC Belgium)
AGR-Glaverbel
(AGC)20.10.12 03.11.12
230 A ACC-MAR-A-G-229 00 Entrance Door of Guest Room - Wooden Door Depa / Eldiar 15.05.12 29.05.12 07.06.12 B
M ACC-MAR-M-H-230 00 Grills and Diffusers (Mock-up) 1 Slot Diffuser 1000 X 2 slot - 16mm Slot width 2 Linear Grills Beta 16.05.12 30.05.12 03.06.12 C
M ACC-MAR-M-H-230 01 Grills and Diffusers Beta 18.07.12 01.08.12 08.08.12 C
M ACC-MAR-M-H-231 00 Bathroom Accessories - Luigi Montelone Srl (TB - Mock-up Room Only)
Luigi / Protos Trading 16.05.12 30.05.12 21.05.12 A
M ACC-MAR-M-H-231 01 Bathroom Accessories - Luigi Montelone Srl (Tower -B)
Luigi / Protos Trading 19.09.12 03.10.12 06.10.12 B
M ACC-MAR-M-H-232 00 Shower Room Linear Channel Drain for Mock-up Room Only Kessel / Albina 16.05.12 30.05.12 04.06.12 A
M ACC-MAR-M-H-232 01 Shower Room Linear Channel Drain Tower B Kessel / Albina 26.09.12 10.10.12 15.10.12 C
M ACC-MAR-M-H-233 00Sanitary Wares and Accessories - WC Concealed Cistern + Dual Flush Plate (TB - Mock up Room only)
Ideal Standard / Hamda Bin
Mohd.16.05.12 30.05.12 21.05.12 A
233
228
232
231
234
229
Page 73 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-H-233 01 Sanitary Wares and Accessories - WC & Cistern In Built & Bidet & Wash Basin Tower B
Ideal Standard / Hamda Bin
Mohd.19.09.12 03.10.12 03.10.12 A
235 E ACC-MAR-E-H-234 00 Sample Submittal for Wiring Devices as per attached Annexure for Mock up Room only
Legrand / Al Mashreq 16.05.12 30.05.12 28.05.12 A
236 M ACC-MAR-M-H-235 00 Bathroom Accessories - Roca (Mock up) Roca / Hanad and Mohd. 17.05.12 31.05.12 21.05.12 A
237 M ACC-MAR-M-H-236 00 Sample Submittal for Sanitary Fixtures (TB Mock up Room only)
Grohe / Capital 20.05.12 03.06.12 28.05.12 C
A ACC-MAR-A-G-237 00 Powder Coating PE RAL Color Samples AGR / Juton 20.05.12 03.06.12 14.06.12 C
A ACC-MAR-A-G-237 01Joseph Industries: KYNAR PVDF Powder Coating (Samples: RAL 7048, 9023, 9018,9007,5011
AGR / Juton 07.07.12 21.07.12 21.07.12 B
239 M ACC-MAR-M-H-238 00 Sanitary Wares and Accessories - Angle Valves + Bottle Traps (TB- Mock up Room only)
Pex UK + Hepworth / 21.05.12 04.06.12 28.05.12 C
M ACC-MAR-M-G-239 00 Glass Cloth Excel China / Aerodyne 21.05.12 04.06.12 03.06.12 C
M ACC-MAR-M-G-239 01 Glass Cloth Aerodyne Cooling 21.06.12 05.07.12 18.07.12 C
M ACC-MAR-M-G-239 02 Glass Cloth Aerodyne Cooling 28.07.12 11.08.12 25.08.12 B
241 M ACC-MAR-M-G-240 00 Domestic Plate Heat Exchanger Faisal Jassim Trading Co. 23.05.12 06.06.12 23.06.12 C
242 A ACC-MAR-A-G-241 00 Fire Stoping Sealant Hilti Qatar 17.12.11 31.12.11 06.03.12 A
243 S ACC-MAR-S-G-242 00Premix SRC-S Ready Mixed Spatterdash Slurry Coat for the Fairface Concrete of Vertical Elements
Sodamco 22.12.11 05.01.12 27.03.12 B
M ACC-MAR-M-G-243 00 Transfer Pump / Filtration / Booster Pumps Grundfos 31.12.11 14.01.12 04.01.12 C
M ACC-MAR-M-G-243 01 Transfer Pump / Filtration / Booster Pumps Grundfos 19.06.12 03.07.12 16.07.12 C
M ACC-MAR-M-G-244 00 Sanitary Wares and Accessories - Wall mounted WC and Bidet
Efeco / Hamad bin mohd. 04.01.12 18.01.12 16.01.12 B
M ACC-MAR-M-H-244 01 Sanitary Wares and Accessories - Wall Mounted WC and Bidet (Mock up)
Ideal Standard / Hamda Bin 16.05.12 30.05.12 21.05.12 A
246 S ACC-MAR-S-G-245 00 Fosroc Renderoc Plug Fosroc 08.01.12 22.01.12 09.01.12 B
247 S ACC-MAR-S-G-246 00 Fosroc Renderoc TG Fosroc 08.01.12 22.01.12 09.01.12 B
245
238
244
240
234
Page 74 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
248 M ACC-MAR-M-G-247 00 Fire Rated Flexible Duct Connector Equipment Trading & 07.01.12 21.01.12 23.01.12 A
M ACC-MAR-M-G-248 00 Acoustic Insulation / Liner Middle East Cooling & 10.01.12 24.01.12 28.01.12 A
M ACC-MAR-M-G-248 01 Acoustic Insulation / Liner Middle East Cooling & 15.07.12 29.07.12 02.08.12 B
M ACC-MAR-M-G-248 02 Acoustic Insulation / Liner Middle East Cooling & 04.10.12 18.10.12
M ACC-MAR-M-G-249 00 Grilles & Diffusers (Slot diffuser - 1000mm-2X16mm Slot) Beta 23.01.12 06.02.12 04.02.12 C
M ACC-MAR-M-G-249 01 Grilles & Diffusers Beta 27.09.12 11.10.12 15.10.12 C
A ACC-MAR-A-G-250 00 Quarter Cut Red Oak Veneer Wall Panel for Guest Rooms (Sample only) depa / Eldiar 24.01.12 07.02.12 25.04.12 A
A ACC-MAR-A-G-250 01 Quarter Cut Red Oak Veneer Wall Panel for Guest Rooms (Sample only) depa / Eldiar 15.05.12 29.05.12 14.06.12 A
A ACC-MAR-A-G-250 02 Quarter Cut Red Oak Veneer Wood Finish For Wall Cladding , Wardrobe & Doors depa / Eldiar 19.06.12 03.07.12 30.06.12 B
E ACC-MAR-E-G-251 00 Bus Bar & Tap Offs Engineering Supplies 01.02.12 15.02.12 11.03.12 C
E ACC-MAR-E-G-251 01 Bus Bar & Tap Offs Engineering Supplies 22.07.12 05.08.12 07.08.12 C
E ACC-MAR-E-G-251 02 Bus Bar & Tap Offs Engineering Supplies 28.08.12 11.09.12 08.09.12 C
E ACC-MAR-E-G-251 03 Bus Bar & Tap Offs Engineering Supplies 26.09.12 10.10.12 OVERDUE
A ACC-MAR-A-G-252 00 Ironmongery Depa / Dorma 04.02.12 18.02.12 04.03.12 C
A ACC-MAR-A-G-252 01 Ironmongery for Wooden Door Depa / Hefele 29.04.12 13.05.12 08.05.12 B
A ACC-MAR-A-G-252 02 Ironmongery for Wooden Door Depa / Hefele 15.05.12 29.05.12 14.06.12 B
A ACC-MAR-A-G-252 03 Ironmongery for Wooden Door Depa / Hefele 21.06.12 05.07.12 02.07.12 C
254 S ACC-MAR-S-G-253 00 Expanded Polystyrene Al Kawther Steel 05.02.12 19.02.12 13.02.12 B
M ACC-MAR-M-G-254 00 Floor Drain Cover Albina Qatar 08.02.12 22.02.12 25.02.12 C
M ACC-MAR-M-G-254 01 Floor Drain Cover Albina Qatar 20.06.12 04.07.12 18.07.12 C
M ACC-MAR-M-G-254 02 Floor Drain Cover Albina Qatar 28.07.12 11.08.12 29.08.12 C
252
251
250
255
253
249
Page 75 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-255 00 Floor Clean Out Cover Albina Qatar 08.02.12 22.02.12 25.02.12 C
M ACC-MAR-M-G-255 01 Floor Clean Out Cover Albina Qatar 20.06.12 04.07.12 21.07.12 C
257 A ACC-MAR-A-G-256 00 Floor Tile, Vitra Size 30X30 Code: MAXSI DDTO L. Beige, K836503 Sayyar / Vitra 23.05.12 06.06.12 28.05.12 C
A ACC-MAR-A-G-257 00 Ceramic Wall Tile, Vitra Option1: Color 7500, Option2: Color 7047 Option3:Color 8000 Sayyar / Vitra 23.05.12 06.06.12 28.05.12 A
A ACC-MAR-A-G-257 01
Ceramic Wal Tile 15x15cm
(ALFARMAN - Option 1: CINZA -196.0, Option 2:
BRANCO-001.0, Option 3 : CINZA ESCURO-640.0,Option 4: BEGE-514.0, Option 5: BEGE CLARO -441.0, Option 6: MARFIM-002.0, Option
7: CRÈME-302.0, Option 8: BEGE ROSA-675.0 (For Sayyar Option 9: RAL 0006500A K891571, Option 10: RAL 0809005A K878793, Option
11: RAL 0809010A K787632, Option 12: RAL 0007500A K502843, Option 13: RAL 0008000A K891582, Option 14: RAL 1009005A K855376
Al Farman-Primus Vitoria / Sayyar-Vitra
29.09.12 13.10.12 06.10.12 A
259 A ACC-MAR-A-G-258 00 Ceramic Wall Tile, Vitra Option1: Color 807010, Option2: Color 809010, Option3: Color 809005 Sayyar / Vitra 23.05.12 06.06.12 28.05.12 C
260 A ACC-MAR-A-G-259 00 Porcelain Tile for Step Tread, Riser & Skirtings Sayyar / Vitra 23.05.12 06.06.12 28.05.12 A
261 M ACC-MAR-M-H-260 00 Sample Submittal for Sanitary Fixtures (TB Mock up Room only) Giampieri 24.05.12 07.06.12 03.06.12 A
M ACC-MAR-M-G-261 00 Vapour Barrier Equipment Trading & 24.05.12 07.06.12 17.06.12 C
M ACC-MAR-M-G-261 01 Vapour Barrier Equipment Trading & 21.06.12 05.07.12 18.07.12 C
M ACC-MAR-M-G-261 02 Vapour Barrier Equipment Trading & 28.07.12 11.08.12 16.08.12 B
A ACC-MAR-A-G-262 00 Sample Board: Gutman -F50/Curtain Wall Profiles AGR / Gutmann 26.05.12 09.06.12 14.06.12 C
A ACC-MAR-A-G-262 01 Sample Board: SCHUCO FW F50+ /Curtain Wall Profiles
AGR/ SCHUCO / 20.06.12 04.07.12 16.07.12 C
A ACC-MAR-A-G-262 02 SCHUCO FW F50+ /Curtain Wall Profiles AGR/ SCHUCO / 09.08.12 23.08.12 13.08.12 C
A ACC-MAR-A-G-262 03 Sample Board : Schuco FW 50+/ Curtain Wall Profiles
AGR/ SCHUCO 11.09.12 25.09.12 24.09.12 B
262
256
263
258
Page 76 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
264 M ACC-MAR-M-H-263 00 Sanitary Wares - Bath Tub (TB - Mock up Room only)
Roca / Al futtaim 28.05.12 11.06.12 03.06.12 B
265 M ACC-MAR-M-H-264 00 Bath Room Accessories - Roca (TB - Mock up Room only)
Roca / Hamad & Mohd. 28.05.12 11.06.12 03.06.12 B
266 S ACC-MAR-S-G-265 00 Fischer: Galvanized Anchor Bolts AGR/Fischer 31.05.12 14.06.12 14.06.12 A
A ACC-MAR-A-G-266 00 Wall Covering for Bedroom Above Headboard (Code: WC A 68-11)
Depa / Seltex Wall 31.05.12 14.06.12 27.06.12 B
A ACC-MAR-A-G-266 01
Wall Covering for Bedroom Above Headboard (Option 1 - ref. Dixon Turner DP New DUB 07.12.32) (Option 2 - Dixon Turner DP New Dub 07.12.33)
Depa / Seltex Wall
Coverings09.09.12 23.09.12 06.10.12 A
268 A ACC-MAR-A-G-267 00 Conrep 301 GA (Non-shrink Mortar for Grouting and Anchoring) Sodamco 02.06.12 16.06.12 14.06.12 A
269 A ACC-MAR-A-G-268 00 Wall Covering for Bedrooms, Newmor Depa / Newmor 04.06.12 18.06.12 14.06.12 A
M ACC-MAR-M-G-269 00 Pressurization Unit & Expansion Tanks Faisal Jassim Trading Co. 09.06.12 23.06.12 03.07.12 C
M ACC-MAR-M-G-269 01 Pressurization Unit & Expansion Tanks Faisal Jassim Trading Co. 13.08.12 27.08.12 22.08.12 C
M ACC-MAR-M-G-269 02 Pressurization Unit & Expansion Tanks Faisal Jassim Trading Co./IIT 27.09.12 11.10.12 13.10.12 C
271 A ACC-MAR-A-G-270 00 Alternative Sleeve for Steel Head Tie Expanded Metal 10.06.12 24.06.12 20.06.12 D
272 A ACC-MAR-A-G-271 00 150 X 200 ACICO Light Weight Block (Alternative to Cement Block) ACICO 13.06.12 27.06.12 10.07.12 C
273 M ACC-MAR-M-G-272 00 Threaded Fittings for Fire Fighting Pipes (Alternative Submittal) Petrofac 17.06.12 01.07.12 30.06.12 C
274 M ACC-MAR-M-G-273 00 Fire Protection System Pipes (For Risers) Surya /Petrofac 16.06.12 30.06.12 16.07.12 A
M ACC-MAR-M-G-274 00 Insulation Thickness Calculation for Plumbing System
Emirates Falcon 17.06.12 01.07.12 18.07.12 C
M ACC-MAR-M-G-274 01 Insulation Thickness Calculation for Plumbing System
Emirates Falcon 21.08.12 04.09.12 OVERDUE
A ACC-MAR-A-G-275 00 Option 1: Alucobond 4mm thickness Fire Rated Composite Panel For Metal Cladding
AGR/ Alucobond 19.06.12 03.07.12 08.07.12 C
A ACC-MAR-A-G-275 01SINCO Product - Non Combustible: 4MM Thick Aluminum Cladding With Corrugated Aluminum Core
AGR/ Q-NAP 31.07.12 14.08.12 23.08.12 C
277 A ACC-MAR-A-G-276 00 Option 2: NOVELIS 2mm Solid Panel For Metal Cladding
AGR/ Alucobond 20.06.12 04.07.12 07.07.12 B
276
267
275
270
Page 77 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-277 00 Clean Agent Fire Suppression System(FM 200)
Thompson Specialties 21.06.12 05.07.12 18.07.12 C
M ACC-MAR-M-G-277 01 Clean Agent Fire Suppression System(FM 200)
Thompson Specialties/Pyr 27.09.12 11.10.12 07.10.12 C
M ACC-MAR-M-G-278 00 Foam Fire Suppression System Thompson Specialties 21.06.12 05.07.12 30.07.12 C
M ACC-MAR-M-G-278 01 Foam Fire Suppression System Thompson Specialties 01.10.12 15.10.12 13.10.12 C
280 A ACC-MAR-A-G-279 00 11.14 mm thick Laminated Glass for Toilet Sliding Door
Guardian Glass/ Trosofil 21.06.12 05.07.12 02.07.12 B
281 A ACC-MAR-A-G-280 00 Leather For Luggage Rack & Headboard Guardian Glass/ Trosofil 21.06.12 05.07.12 02.07.12 B
282 A ACC-MAR-A-G-281 00 Alternate 4 mm thickeness cartonal protection board for vertical areas sub-structure
Tadmur/ Cartonal 24.06.12 08.07.12 07.07.12 B
283 S ACC-MAR-S-G-282 00 Sample Board: Steel Brackets & Accessories AGR 23.06.12 07.07.12 18.07.12 B
A ACC-MAR-A-G-283 00 Carrocolle WP (Regular Cement Based Tile Adhesive) Sodamco 19.02.12 04.03.12 27.02.12 C
A ACC-MAR-A-G-283 01 Carrocolle WP (Regular Cement Based Tile Adhesive) Sodamco 20.03.12 03.04.12 03.05.12 B
A ACC-MAR-A-G-283 02 Carrocolle WP (Regular Cement Based Tile Adhesive) Sodamco 08.05.12 22.05.12 21.05.12 A
E ACC-MAR-E-G-284 00 Cable Glands FP200 City Electrical Factor 19.02.12 04.03.12 08.03.12 C
E ACC-MAR-E-G-284 01 Cable Glands FP 200 City Electrical Factor 31.03.12 14.04.12 10.04.12 C
E ACC-MAR-E-G-284 02 Cable Glands FP 200 City Electrical Factor 28.07.12 11.08.12 11.08.12 C
A ACC-MAR-A-G-285 00 Carrojoint Thin / Thick (Cementitious Tile Grout) Sodamco 19.02.12 04.03.12 26.02.12 C
A ACC-MAR-A-G-285 01 Carrojoint Thin / Thick (Cementitious Tile Grout) Sodamco 20.03.12 03.04.12 03.05.12 B
A ACC-MAR-A-G-285 02 Carrojoint Thin / Thick (Cementitious Tile Grout) Sodamco 08.05.12 22.05.12 OVERDUE
A ACC-MAR-A-G-286 00 Premix.bloc fix N (Ready Mix Block and Brick Laying Mortar) Sodamco 19.02.12 04.03.12 26.02.12 C
A ACC-MAR-A-G-286 01 Premix Bloc A (Block and Brick Masonry Laying Mortar) Sodamco 26.04.12 10.05.12 08.05.12 A
M ACC-MAR-M-G-287 00 Submersible Pumps Gazzaoui & Partners 25.02.12 10.03.12 21.03.12 C
M ACC-MAR-M-G-287 01 Submersible Pumps Gazzaoui & Partners 21.06.12 05.07.12 18.07.12 C
279
285
286
284
278
287
288
Page 78 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-287 02 Submersible Pumps Gazzaoui & Partners 15.08.12 29.08.12 25.08.12 C
289 A ACC-MAR-A-G-288 00 Epojoint (Three Component Epoxy Grouting System) Sodamco 25.02.12 10.03.12 27.03.12 B
290 A ACC-MAR-A-G-289 00 Conrep 304 VHS Sodamco 26.02.12 11.03.12 28.03.12 A
291 A ACC-MAR-A-G-290 00 Conrep 350 NG: Non Shrink Mortar for Repair and Grouting Sodamco 27.02.12 12.03.12 04.03.12 B
M ACC-MAR-M-G-291 00 UL/FM Fire Pump Set 750GPM @ 270 PSI Naffco 04.03.12 18.03.12 31.03.12 C
M ACC-MAR-M-G-291 01 UL/FM Fire Pump Set 750GPM @ 260 PSI Paint Air / Qatar Tech. 10.05.12 24.05.12 23.06.12 C
M ACC-MAR-M-G-291 02 UL/FM Fire Pump Set 750GPM @ 260 PSI Paint Air / Qatar Tech. 23.07.12 06.08.12 14.08.12 C
M ACC-MAR-M-G-291 03 UL/FM Fire Pump Set 750GPM @ 260 PSI Paint Air / Qatar Tech. 15.09.12 29.09.12 29.09.12 C
M ACC-MAR-M-G-292 00 UL/FM Fire Pump Set (1000gpm @ 20bar) Naffco 04.03.12 18.03.12 31.03.12 C
M ACC-MAR-M-G-292 01 UL/FM Fire Pump Set (1000gpm @ 290 PSI) Paint Air / Qatar Tech. 10.05.12 24.05.12 30.06.12 C
M ACC-MAR-M-G-292 02 UL/FM Fire Pump Set (1000gpm @ 290 PSI) Paint Air / Qatar Tech. 23.07.12 06.08.12 14.08.12 C
M ACC-MAR-M-G-292 03 UL/FM Fire Pump Set (1000gpm @ 290 PSI) Paint Air / Qatar Tech. 15.09.12 29.09.12 29.09.12 C
294 A ACC-MAR-A-G-293 00 Rectangular Coffee Table (900W X 600D X 4300mm H) Depa / Doimo 10.03.12 24.03.12 25.04.12 C
A ACC-MAR-A-G-294 00
Chair for Desk (Item D92B mesh back, reinforced mesh seat steel chrome finished steel arms & frames, gas elevation, tilting device, polished aluminium bas)
Depa / Doimo 10.03.12 24.03.12 28.04.12 C
A ACC-MAR-A-G-294 01Chair for Desk (Desk Chair Mid Back) Option 1: SO.YU.60.40.E-White & Option 2: SO.YU.60.40.EV-Beige
Depa/ Solver Space/ Darwish Trading
05.07.12 19.07.12 14.07.12 C
A ACC-MAR-A-G-294 02 Chair for Desk (Item no. SO.YU.60.40SBT )
Depa/ Solver Space/ Darwish
30.08.12 13.09.12 27.09.12 B
296 A ACC-MAR-A-G-295 00 Arm Chair (750W X 800D X 680mm H) Depa / Doimo 10.03.12 24.03.12 28.04.12 C
297 A ACC-MAR-A-G-296 00 Lorenzo Bellini Two - Seater Sofa (1910W X 970D X 770mm H) Depa / Doimo 10.03.12 24.03.12 28.04.12 C
A ACC-MAR-A-G-297 00 LBA Specs
Stainless Steel Door Jamb in Chrome Finish, Grade 316
Depa / Art Glass 11.03.12 25.03.12 29.04.12 A
293
298
292
295
288
Page 79 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-297 01 Stainless Steel Door Jamb in Chrome Finish, Grade 316
Depa / Art Glass 15.05.12 29.05.12 14.06.12 A
A ACC-MAR-A-G-297 02 Stainless Steel Door Jamb in Chrome Finish, Grade 316
Depa / Art Glass 21.06.12 05.07.12 02.07.12 A
299 A ACC-MAR-A-G-298 00 8900 Clear Glass with Frosted Film (10mm Thick Clear Glass with Frosted Film on One Side)
Depa / Guardian 12.03.12 26.03.12 25.04.12 A
300 A ACC-MAR-A-G-299 00 Div 9 Plastering Accessories Technical Metal Ind. 12.03.12 26.03.12 24.03.12 A
301 A ACC-MAR-A-G-300 00 Div 4 Block Work Accessories Technical Metal Ind. 12.03.12 26.03.12 24.03.12 A
302 A ACC-MAR-A-G-301 00 Div 4 Steel Lintel Technical Metal Ind. 13.03.12 27.03.12 24.03.12 B
E ACC-MAR-E-G-302 00 Fire Alarm System Devices Back Box Cesco /Raco 13.03.12 27.03.12 11.04.12 C
E ACC-MAR-E-G-302 01 Fire Alarm System Devices Back Box Cesco /Raco 29.04.12 13.05.12 08.05.12 C
E ACC-MAR-E-G-302 02 E 16/47-56 Fire Alarm System Devices Back Box Cesco /Raco 24.05.12 07.06.12 03.06.12 A
304 A ACC-MAR-A-G-303 00 Div 9 Jotun Paint System for Wet Areas Depa / Jotun Paint 17.03.12 31.03.12 08.05.12 C
305 A ACC-MAR-A-G-304 00 Div 4 Block Work Accessories Metex 29.03.12 12.04.12 03.04.12 A
A ACC-MAR-A-G-305 00 Div 7 Adeprimaire Siplast Wet Area Water Proofing Tadmur / Siplast 01.04.12 15.04.12 09.04.12 C
A ACC-MAR-A-G-305 01 Div 7 Adeprimaire Siplast Wet Area Water Proofing Tadmur / Siplast 09.05.12 23.05.12 28.05.12 B
307 A ACC-MAR-A-G-306 00 Div 8 Ceramic Tiles Nabina Ceramic / 02.04.12 16.04.12 25.08.12 C
308 A ACC-MAR-A-G-307 00 Premix.bloc fill RM Sodamco 02.04.12 16.04.12 09.04.12 A
309 A ACC-MAR-A-G-308 00 Div 7 Jointseal PS 1000 GG/PG (Jointseal Prime PS) Sodamco 26.04.12 10.05.12 17.05.12 C
310 M ACC-MAR-M-G-309 00 Pump Head Calculation for Submersible Pumps Emirates Falcon / ACC 03.04.12 17.04.12 23.04.12 B
311 E ACC-MAR-E-G-310 00 Wiring Devices for Office Tower & Back of House Areas
Legrand / Al Mashreq 04.04.12 18.04.12 30.04.12 B
A ACC-MAR-A-G-311 00 Div 9 Pure Acrylic WB Anti Carbonation Properties Juton 11.04.12 25.04.12 30.04.12 C
A ACC-MAR-A-G-311 01 Div 9 Pure Acrylic WB Anti Carbonation Properties Juton/Roots Qatar 26.07.12 09.08.12 05.08.12 B
A ACC-MAR-A-G-312 00 Div 9 Acrylic Copolymer Emulsion with Outstanding Washability Juton 11.04.12 25.04.12 03.05.12 B
306
298
313
312
303
Page 80 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-312 01 Div 9 Acrylic Copolymer Emulsion with Outstanding Washability
Juton/Roots Qatar 26.07.12 09.08.12 05.08.12 B
A ACC-MAR-A-G-313 00 Alternative for Oil Paint (Fenomastic Emulsion Silk) Juton 10.04.12 24.04.12 08.05.12 C
A ACC-MAR-A-G-313 01 Alternative for Oil Paint (Fenomastic Emulsion Silk)
Juton/Roots Qatar 26.07.12 09.08.12 23.08.12 B
A ACC-MAR-A-G-314 00 Div 8 Oil Paint (Fenomastic Emulsion + Fenomastic Enamel Semi - Gloss) Juton 10.04.12 24.04.12 14.05.12 C
A ACC-MAR-A-G-314 01 Div 9 Pure Acrylic WB Anti Carbonation Properties Juton/Roots Qatar 26.07.12 09.08.12 05.08.12 B
316 M ACC-MAR-M-G-315 00 Pump Head Calculation for Transfer & Filtration Pumps
Emirates Falcon / ACC 11.04.12 25.04.12 28.04.12 B
M ACC-MAR-M-G-316 00 Variable Air Volume & Constant Air Volume (VAV & CAV) Maxell 11.04.12 25.04.12 30.04.12 C
M ACC-MAR-M-G-316 01 Variable Air Volume & Constant Air Volume (VAV & CAV) Maxell 23.05.12 06.06.12 27.06.12 C
M ACC-MAR-M-G-316 02 Variable Air Volume & Constant Air Volume (VAV & CAV) Maxell 07.10.12 21.10.12
318 M ACC-MAR-M-G-317 00 Air Separators Qatar Internationsl / 14.04.12 28.04.12 30.04.12 A
M ACC-MAR-M-G-318 00 Chilled Water Pumps Bell & Gossett / Faisal 14.04.12 28.04.12 03.05.12 C
M ACC-MAR-M-G-318 01 HVAC Pump Chilled Water Pumps Bell & Gossett
/ Faisal 19.05.12 02.06.12 14.06.12 C
M ACC-MAR-M-G-318 02 HVAC Pump Chilled Water Pumps Faisal Jassim
Trading 08.07.12 22.07.12 07.08.12 C
M ACC-MAR-M-G-318 03 HVAC Pump Chilled Water Pumps Faisal Jassim
Trading 30.08.12 13.09.12 01.10.12 C
M ACC-MAR-M-G-319 00 Pumps Head Calculation for Chilled Water Pumps Emirates Falcon / ACC 14.04.12 28.04.12 03.05.12 C
M ACC-MAR-M-G-319 01 HVAC Pump Pumps Head Calculation for Chilled Water Pumps Emirates
Falcon / ACC 08.07.12 22.07.12 30.07.12 A
A ACC-MAR-A-G-320 00 Div 9 Paint Bathroom & Pantry Walls & Ceilings (Fenomastic Emulsion Gold) Juton 14.04.12 28.04.12 01.05.12 B
A ACC-MAR-A-G-320 01 Div 9 Paint Bathroom & Pantry Walls & Ceilings (Fenomastic Emulsion Gold)
Juton/Roots Qatar 26.07.12 09.08.12 05.08.12 B
E ACC-MAR-E-G-321 00 Elec. 26 33 23 Central Battery System JBK / Cooper 17.04.12 01.05.12 21.05.12 C
E ACC-MAR-E-G-321 01 Elec. 26 33 23 Central Battery System JBK / Cooper 19.06.12 03.07.12 09.07.12 C
E ACC-MAR-E-G-321 02 Elec. 26 33 23 Central Battery System JBK / Cooper 15.09.12 29.09.12 29.09.12 C
313
322
320
319
321
315
314
317
Page 81 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-322 00 Air Curtain Central Air Conditioning 18.04.12 02.05.12 08.05.12 C
M ACC-MAR-M-G-322 01 Air Curtain Central Air Conditioning 02.08.12 16.08.12 15.08.12 C
A ACC-MAR-A-G-323 00 Carpet Underlay, Tredaire Technics 5 Depa / Interfloor 21.04.12 05.05.12 29.04.12 C
A ACC-MAR-A-G-323 01 Carpet Underlay, Black Pearl, Estillon Depa / Estillon 25.04.12 09.05.12 29.04.12 A
325 M ACC-MAR-M-G-324 00 Cooled Water Circulation Pumps Gazzaoui & Partners 21.04.12 05.05.12 08.05.12 C
A ACC-MAR-A-G-325 00 Ironmongery for Furniture Depa / Hafele 25.04.12 09.05.12 08.05.12 B
A ACC-MAR-A-G-325 01 Ironmongery for Furniture Depa / Hafele 15.05.12 29.05.12 14.06.12 B
A ACC-MAR-A-G-325 02 Ironmongery for Furniture Depa / Hafele 21.06.12 05.07.12 02.07.12 B
A ACC-MAR-A-G-326 00 9210 Sheetrock - Joint Compound for Gypsum Panel Joints, Fasteners, Bead and Trim
Depa / US Gypsum 25.04.12 09.05.12 12.05.12 A
A ACC-MAR-A-G-326 01 9210 Sheetrock - Joint Compound for Gypsum Panel Joints, Fasteners, Bead and Trim
Depa / US Gypsum 15.05.12 29.05.12 14.06.12 A
328 A ACC-MAR-A-G-327 00 Div 7 Jointseal PU (One Component Polyurethane Sealant) Sodamco 26.04.12 10.05.12 17.05.12 C
329 A ACC-MAR-A-G-328 00 Div 7 Silicone Sealant for Glass, Dow Corning 794N Depa / Dow Corning 26.04.12 10.05.12 14.05.12 A
A ACC-MAR-A-G-329 00 Adhesive for Wood, Metal and Marble, Montagekit Super Strength Depa / Bison 28.04.12 12.05.12 17.05.12 A
A ACC-MAR-A-G-329 01 Adhesive for Wood, Metal and Marble, Montagekit Super Strength Depa / Bison 15.05.12 29.05.12 03.06.12 A
M ACC-MAR-M-G-330 00 Hotel Lock & Energy Saving Device for Guest Rooms
Kaba-Saflok / G4S Qatar 28.04.12 12.05.12 03.06.12 C
M ACC-MAR-M-G-330 01 Hotel Lock Systems for Guest Rooms G4S Qatar/ KABA 15.07.12 29.07.12 02.08.12 C
326
324
327
330
323
331
Page 82 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
E ACC-MAR-E-G-331 00 Car Park Management System Nortech / G4S Qatar 30.04.12 14.05.12 03.06.12 C
E ACC-MAR-E-G-331 01 Car Park Management System Nortech / G4S Qatar 02.10.12 16.10.12
E ACC-MAR-E-G-332 00 Access Control System G4S Qatar 30.04.12 14.05.12 19.06.12 C
E ACC-MAR-E-G-332 01Elec.
E16/126-127
Access Control System G4S Qatar 19.09.12 03.10.12 01.10.12 C
334 M ACC-MAR-M-H-333 00 Under Counter Wash Basin - Tower BIdeal Standard / Hamda Bin
Mohd.29.04.12 13.05.12 08.05.12 A
335 M ACC-MAR-M-H-334 00 Bath Tub Steel Enamel - Tower B Roca / Hanad and Mohd. 29.04.12 13.05.12 03.05.12 C
A ACC-MAR-A-G-335 00 Div 9 Jotun Paint System for Ceiling Wet Areas, RAL 9016
Depa / Jotun Paint 30.04.12 14.05.12 12.05.12 A
A ACC-MAR-A-G-335 01 Div 9 Jotun Paint System for Ceiling Wet Areas, RAL 9016
Depa / Jotun Paint 15.05.12 29.05.12 03.06.12 B
A ACC-MAR-A-G-335 02 Div 9 Jotun Paint System for Ceiling Wet Areas, RAL 9016
Depa / Jotun Paint 21.06.12 05.07.12 02.07.12 A
M ACC-MAR-M-G-336 00 Stainless Steel Water Hammer Arrestors Envotec USA / Al-munasib 01.05.12 15.05.12 21.05.12 C
M ACC-MAR-M-G-336 01Valves&Specialti
es Stainless Steel Water Hammer Arrestors Envotec USA /
Al-munasib 08.07.12 22.07.12 18.07.12 B
M ACC-MAR-M-P-338 00 Car Park Ventilation SystemInternational Engineering
Supplies/Novo26.06.12 10.07.12 30.07.12 C
M ACC-MAR-M-P-338 01Ventilation Fans 233400
Car Park Ventilation SystemInternational Engineering
Supplies/Novo04.10.12 18.10.12
339 A ACC-MAR-A-G-339 00 Lavender Blue Vanity Unit Stone Gallery 30.06.12 14.07.12 07.07.12 A
340 A ACC-MAR-A-G-340 00 Pantry Countertop ( Option 1: Black Absolute, Option 2: Black Galaxy)
Specialized Marble &
Granite WLL30.06.12 14.07.12 07.07.12 A
332
333
337
336
338
Page 83 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-341 00 Div 8 10 mm clear Fully Tempered Glass : Guardian - as inner pane in façade
AGR/ Guardian 09.08.12 23.08.12 11.08.12 C
A ACC-MAR-A-G-341 01 Div 8
Curtain Wall Glazing -Material Submittal for Option 2, 8mm Cool Lite Smoke Silver KNT 140 Tempered Saint Gobain -Spain , 8.38 mm clear Laminated Annealed with Normal PVB - Glaverbel AGC
AGR - Saint Gobain -Spain/
Glaverbel (AGC)-Belgium
20.10.12 03.11.12
342 M ACC-MAR-M-G-342 00Sanitary Fixtures
15440/15/113-115
Sanitary Wares - Tower A(Offices)Hamad Bin Mohamad
Group/ Efeco05.07.12 19.07.12 19.07.12 B
M ACC-MAR-M-G-343 00Fire
Fighting System
Supervisory Control Valve (Butterfly Valve with internal supervisory switch)
International Gulf Trading
Company-05.07.12 19.07.12 31.07.12 C
M ACC-MAR-M-G-343 01Fire
Fighting System
Supervisory Control Valve (Butterfly Valve with internal supervisory switch)
Int'l Gulf Trading
Company-15.09.12 29.09.12 OVERDUE
344 A ACC-MAR-A-G-344 00 IFC Spec Sheet Decorative Curtain Fabric Depa/Vigano 07.07.12 21.07.12 16.07.12 A
M ACC-MAR-M-G-345 00Fire
Fighting System
Drain ValveInternational Gulf Trading
Company-10.07.12 24.07.12 26.07.12 C
M ACC-MAR-M-G-345 01Fire
Fighting System
Drain ValveInt'l Gulf Trading
Company-15.09.12 29.09.12 26.09.12 C
M ACC-MAR-M-G-346 00 221116Low Noise Above Ground Drainage Pipes Fittings for Horizontal (Apartment & Guest Rooms) Tower B
Efeco-Richmond 12.07.12 26.07.12 30.07.12 C
M ACC-MAR-M-G-346 01 221116Low Noise Above Ground Drainage Pipes Fittings for Horizontal (Apartment & Guest Rooms) Tower B
Efeco-Richmond 15.08.12 29.08.12 26.08.12 C
M ACC-MAR-M-G-346 02 221116Low Noise Above Ground Drainage Pipes & Fittings for Tower B & Podium ( Public Occupied Area)
Efeco-Richmond 15.09.12 29.09.12 25.09.12 C
M ACC-MAR-M-G-347 00 221116 Copper Pipes & Fittings for Hot Water Supply Riser Piping (Tower A & B)
EFECO -Buildwell Trading
09.07.12 23.07.12 30.07.12 C
M ACC-MAR-M-G-347 01 221116 Copper Pipes & Fittings for Hot Water Supply Riser Piping (Tower A & B)
EFECO -Buildwell Trading
15.08.12 29.08.12 28.08.12 C
M ACC-MAR-M-G-347 02 221116 Copper Pipes & Fittings for Hot Water Supply Riser Piping (Tower A & B)
Next Eng'g Co./KME 24.09.12 08.10.12 10.10.12 C
343
345
346
341
347
Page 84 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-348 00 Not Specified
Waterproof.110 FX for waterproofing of shower walls Sodamco 09.07.12 23.07.12 23.07.12 B
A ACC-MAR-A-G-348 01 Not Specified
Waterproof.110 FX for waterproofing of shower walls Sodamco 30.08.12 13.09.12 15.10.12 A
349 A ACC-MAR-A-G-349 00 Div 8 GEZE Automatic Door Operator AGR/ GEZE- Company 17.07.12 31.07.12 06.10.12 C
M ACC-MAR-M-G-350 00Energy
Recovery System
Air Handling Units & Fresh Air Handling Units Mekar/Efeco 18.07.12 01.08.12 01.08.12 C
M ACC-MAR-M-G-350 01Energy
Recovery System
Air Handling Units & Fresh Air Handling Units Mekar/Efeco 09.09.12 23.09.12 07.10.12 C
351 M ACC-MAR-M-G-351 00 221116 PPR Pipes & Fittings Cold Water Supply Riser Piping
Techno Gulf Trading/POLOP
LAST17.07.12 31.07.12 26.07.12 C
A ACC-MAR-A-G-352 00 Div 9 Metal Strip Ceiling(100 mm, 150 mm, 200 mm & 300 mm)
QASR AL ANDALUS/
SADDI 21.07.12 04.08.12 06.08.12 C
A ACC-MAR-A-G-352 01 Div 9 Matador (100 mm, 150 mm, 200 mm & 300 mm) Linear Metal Strip Ceiling
Marconi/ INTERARC 31.07.12 14.08.12 13.08.12 C
A ACC-MAR-A-G-353 00 Div 7 Waterproof.SSP 50 (Waterproofing Rubberized Bitumen Emulsion For Façade Damp Proofing SODAMCO 21.07.12 04.08.12 26.07.12 C
A ACC-MAR-A-G-353 01 Div 7 Adeprimaire cold applied jellified elastomeric bitumen for Façade Damp Proofing
Siplast Icopal/ SODAMCO 24.07.12 07.08.12 02.08.12 A
M ACC-MAR-M-G-354 00Fire
Fighting System
Air Release ValveInternational
Gulf Trading/Val-
24.07.12 07.08.12 02.08.12 C
M ACC-MAR-M-G-354 01Fire
Fighting System
Air Release ValveInternational
Gulf Trading/Val-
10.09.12 24.09.12 01.10.12 B
M ACC-MAR-E-H-355 00Switch Gear
262400Distribution Board (Guest Rooms)
ABB/ Power & Automation
Control24.07.12 07.08.12 31.07.12 C
M ACC-MAR-E-H-355 01Switch Gear
262400Distribution Board (Guest Rooms)
ABB/ Power & Automation
Control13.08.12 27.08.12 25.08.12 C
M ACC-MAR-E-H-355 02Switch Gear
262400Distribution Board (Guest Rooms)
ABB/ Power & Automation
Control17.09.12 01.10.12 20.10.12 C
350
355
354
352
353
348
Page 85 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
M ACC-MAR-M-G-356 00Fan Coil
Unit 23219
ESP Calculation For FCU's ACC/Efeco 26.07.12 09.08.12 11.08.12 C
M ACC-MAR-M-G-356 01Fan Coil
Unit 238219
ESP Calculation For FCU's ACC/Efeco 15.09.12 29.09.12 29.09.12 B
357 M ACC-MAR-M-G-357 00Sanitary Fixtures
15440/15
Sanitary Wares and Accessories - Tower A Offices
Ideal Standard / Hamad Bin
Mohd.30.07.12 13.08.12 06.08.12 C
358 M ACC-MAR-M-G-358 00Sanitary Fixtures
15440/15Bathroom Accessories Tower A - Offices
Al Hammouri Group/ Bradley
31.07.12 14.08.12 07.08.12 C
359 E ACC-MAR-E-G-359 00 Elec. 26 27 26 Ceiling Rose Jaidah Indut'l/
Schneider 09.08.12 23.08.12 15.08.12 C
360 M ACC-MAR-M-G-360 00MS Angle/ Channels (1. Ms. Angle (65x65x5mm) , 2. Ms. Channel (100x50x5mm), 3. Ms. Channel (150x75x5mm)
TISSCO/ TISSCO 27.08.12 10.09.12 29.09.12 C
361 A ACC-MAR-A-G-361 00IFC
Specs. Sheet
Handle for Glass Sliding Door DEPA/Dorma 29.08.12 12.09.12 09.09.12 A
362 E ACC-MAR-E-G-362 00Elec.
E16/37-38
Wiring Devices IP-55 Weather Proof Twin Socket Outlet (Area of Application - Plant Room & Qatar Cool Room)
Al -Masherq /Legrand (Model -069739)
01.09.12 15.09.12 01.09.12 C
363 M ACC-MAR-M-G-363 00Fire
Fighting 211000
Sprinkler Heads (Alternative Material Submittal)Int'lGulf Trading/
Chubb Fire 02.09.12 16.09.12 08.09.12 C
364 A ACC-MAR-A-G-364 00 Div 9 Adhesive For Tiles, Mastertile 21 (OPTION 2) BASF/ DEPA 05.09.12 19.09.12 02.10.12 A
365 M ACC-MAR-M-G-365 00Sanitary Fixtures
15440/15Bidet Trap ( Tower B)
Hamad Bin Mohamad
Group/ Viega -05.09.12 19.09.12 17.09.12 A
366 E ACC-MAR-E-G-366 00 265100 Light Fixtures (Internal) Tower-B Guest Rooms Corridor & Lift Lobby
Whitwam Int'l / LEDS-
C4/GALLIS/M08.09.12 22.09.12 15.10.12 C
367 M ACC-MAR-M-G-368 00 Drainage 221319 Roof Drain Al Munasib
Bldg. Material 09.09.12 23.09.12 17.09.12 C
368 M ACC-MAR-M-G-369 00 Painting 15020 Paint (For MEP Services) Jotun /Jotun 09.09.12 23.09.12 10.10.12 B
356
Page 86 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
369 E ACC-MAR-E-G-370 00 27-2000 CCTV SYSTEM G4S Qatar W.L.L. 09.09.12 23.09.12 25.09.12 C
370 E ACC-MAR-E-G-371 00 260923 Lighting Control System Zerone Technologies 10.09.12 24.09.12 29.09.12 C
371 A ACC-MAR-A-G-372 00 Div 8 Sample Board : Schuco Door Profiles AGR/ SCHUCO 11.09.12 25.09.12 06.10.12 C
372 A ACC-MAR-A-G-373 00 IFC 163 Signage For Room Number and Room Direction DEPA/Arabian Wings 11.09.12 25.09.12 24.09.12 C
373 A ACC-MAR-A-G-374 00 Div 7 Pyrolastic Sealant (Fire Rated Silicone Sealant)Don
Construction Products
16.09.12 30.09.12 22.09.12 C
374 E ACC-MAR-E-G-375 00Switch Gear
262400Sub Main Distribution Board (SMDB) Up To 630 A
Power & Automation Control/ABB
17.09.12 01.10.12 11.10.12 C
375 E ACC-MAR-E-G-376 00Switch Gear
262400MV Panels
Power & Automation Control/ABB
17.09.12 01.10.12 20.10.12 C
376 M ACC-MAR-M-G-377 00Fire
Fighting System
StrainerInt'l Gulf Trading
Company-17.09.12 01.10.12 26.09.12 C
377 E ACC-MAR-E-G-378 00Switch Gear
262400Distribution Board (DB)
Power & Automation Control/ABB
17.09.12 01.10.12 20.10.12 C
378 E ACC-MAR-E-G-379 00 265100 Light Fixtures (Internal) - Podium, Tower A & Back of House area in Tower B (part 1)
Huda Lighting /Arcluce/ Disano
19.09.12 03.10.12 15.10.12 C
379 E ACC-MAR-E-G-380 00 27110 Structured Cabling SYSTEMTechno Q / TE Connectivity(U
SA)19.09.12 03.10.12 25.09.12 C
380 E ACC-MAR-E-G-381 00Elec.
E16/102-121 &
Building Management System Integra Int'l/HoneyWell 20.09.12 04.10.12 OVERDUE
A ACC-MAR-A-G-382 00 Div 9 Porcelain Tile For Step Tread, Riser & Skirting & Landing
Rako-Czech Republic/ Al
Farman23.09.12 07.10.12 01.10.12 C
381
Page 87 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
A ACC-MAR-A-G-382 01 Div 9 Porcelain Tile For Step Tread, Riser & Skirting & Landing
Al-Farman -Rako-Czech
Republic(Taurus Granit)/
10.10.12 24.10.12
382 A ACC-MAR-A-G-383 00Floor & Wall Porcelain Tiles For Apartments (GHIACCIO 60 X 60 cm - Nat & GHIACCIO 30 X 60 cm - Nat)
Depa/ ALFALUX 25.09.12 09.10.12 06.10.12 A
383 E ACC-MAR-E-G-384 00 Elec. 27-6100 IPTV / SMATV System Argon/
IKUSI(Spain) 24.09.12 08.10.12 01.10.12 C
384 A ACC-MAR-A-G-385 00
Sample For Pantry & Toilet Doors
Option 1: Mahogany Laminate with Beech wood frame & Architrave stained to Mahogany color Option 2: Ivory Laminate w/ Beech wood frame & Architrave with RAL color 7011 Option 3: Beech Laminate with Beech wood frame & Architrave with natural Finish Option 4: Beige color Laminate with Beech wod frame & Architrave with RAL color 8017
1000 Walls 26.09.12 10.10.12 30.09.12 C
385 A ACC-MAR-A-G-386 00 Sample for Pantry & Post Foam 1001 Walls 26.09.12 10.10.12 01.10.12 C
386 A ACC-MAR-A-G-387 00 Sample for Lobby Door & Wall Panel 1001 Walls 26.09.12 10.10.12 01.10.12 C
387 E ACC-MAR-E-G-388 00 Emergency Call Care System For Disable Room in Hotel Tower
City Electrical Factor
/Tamlite29.09.12 13.10.12
388 E ACC-MAR-E-G-389 00 Elec. 262400 MCC Panels
Power & Automation
Control29.09.12 13.10.12 11.10.12 C
389 M ACC-MAR-M-G-390 00Fan Coil
Unit 238219
Fan Coil Units (FCU) For Twin Towers (Model No. 09MK 904/3R/HL-1 (Air Flow: 544M3 / h)
Mekar 02.10.12 16.10.12
390 M ACC-MAR-M-G-391 00
Above Ground Drainage Pipes and Fittings -HDPE (Option 1 - HDPE Pipes & Fittings - GEBERIT, Option2 - DB20 Pipes & Fittings - GEBERIT)
Aqazone/Geberit 06.10.12 20.10.12
391 M ACC-MAR-M-G-392 00 DX - Free Standing Unit - Qtel Room Al Malki /York 07.10.12 21.10.12 13.10.12 C
381
Page 88 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Discipline : All Status Code C/D
Rundate : 22.10.12 Revised within 10 days
Main Contractor : Arabtec Construction Co. Revised after 10 days
Date Submitted
(Actual)to ACG A B C D
TWIN TOWERS DOHA, QATAR
Consultant : Architectural Consulting Group
PROJECT ID: 10001
OUTSTANDING
Sl No.
Project Manager : Hamilton Project Management
MATERIAL SUBMITTAL REGISTER (MARS)
Discipline DescriptionSpecs. Ref.Submittal No. RemarksRev.Date of
Return
Date of
Submittal
(Planned)
Subcontractor /
Supplier
Approval
Required
By (+14)
Status Code
392 A ACC-MAR-A-G-393 00 Div 8 Fischer: Firestop - RFS 640 Rapid Fire Seal AGR/FIscher 10.10.12 24.10.12
393 S ACC-MAR-S-G-394 00 Div 5 Painting System for Structural Steel GSI/ Sigma 10.10.12 24.10.12 17.10.12 C
394 M ACC-MAR-M-G-395 00Sound& Vibration 230548
Sound Attenuators Seagull(HVAC) Industry 13.10.12 27.10.12
Page 89 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Summary Progress Status
Page 90 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Concrete Works
Page 91 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Concrete Works Status as of 20-Oct 2012:
Start Finish T. Float % Start Finish
Hotel:
Core (L26:L27) 25-Mar-12 1-Apr-12 0 100% 29-Sep-12 11-Oct-12 -193
Core (L27:L28) 2-Apr-12 9-Apr-12 0 90% 11-Oct-12 22-Oct-12 -196
Vert. (L23: L24) & L24 Slab 27-Mar-12 3-Apr-12 0 100% 30-Sep-12 10-Oct-12 -190
Vert. (L24: L25) & L25 Slab 4-Apr-12 11-Apr-12 0 95% 11-Oct-12 22-Oct-12 -194
Office:
Core (L25:L26) 9-Apr-12 16-Apr-12 21 100% 28-Sep-12 11-Oct-12 -157
Core (L26:L27) 17-Apr-12 24-Apr-12 21 80% 28-Sep-12 23-Oct-12 -161
Vert. (L22 : L23) & L23 Slab 12-Apr-12 19-Apr-12 18 100% 28-Sep-12 10-Oct-12 -156
Vert. (L23 : L24) & L24 Slab 21-Apr-12 28-Apr-12 18 95% 11-Oct-12 22-Oct-12 -159
Podium:
BS1: 3rd floor slab 8-Dec-11 22-Dec-11 206 100% 29-Feb-12 15-Apr-12
BS2: 3rd Floor Slab 8-Feb-12 25-Feb-12 151 100% 05-Apr-12 26-Apr-12
AS1 : Ground floor slab 21-May-12 10-Jun-12 16 100% 18-Jun-12 26-Sep-12 -92
AS1 V ti l (G L01) 11 J 12 21 J 12 16 20% 16 O t 12
ActivityApproved Baseline
Note
Delay(B.L Finish -
Actual Finish + Float)
Actual Status / Target
AS1 : Verticals (G:L01) 11-Jun-12 21-Jun-12 16 20% 16-Oct-12
AS2 : Water Tank Slab (B2 Level) 2-Jan-12 12-Jan-12 68 100% 15-May-12 15-Jul-12 -117
AS2 : Verticals (B2:B1 Level) 14-Jan-12 26-Jan-12 71 90% 20-Feb-12
AS2 : Slab (B1 Level) 21-Jan-12 9-Feb-12 71 45% 04-Oct-12
AS3 : Verticals (B2:B1) 18-Mar-12 31-Mar-12 35 95% 04-Jul-12
AS3 : Slab (B1 Level) 27-Mar-12 16-Apr-12 35 75% 21-Aug-12
BS3 : Slab (G. Floor) 15-May-12 4-Jun-12 10 100% 08-Sep-12 15-Oct-12 -123
BS3 : Verticals (G:L01) 5-Jun-12 16-Jun-12 10 25% 17-Oct-12
Page 92 of 106 TT, Weekly Report No. 86 As of 2012-10-20
All Activities status
Page 93 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Twin Towers Project Legend: Completed
Progress Status ‐ Concrete, Rough Finishes & Facade In progress
Data Date:20‐Oct‐2012Core W
alls
Slab
Concrete
Block W
ork
Chasing
MEP
1st fix ‐ Elec.
Conduits in W
alls
Plaster
Wet Area W/P
Floor Screed
Brackets
Fram
e
Glass
Core W
alls
Slab
Concrete
Block W
ork
Chasing
MEP
1st fix ‐ Elec.
Conduits in W
alls
Plaster
Wet Area W/P
Floor Screed
Brackets
Fram
e
Glass
Roof 0% 0% 0% Roof 0% 0%
L48 0% 0% 0% L48 0% 0% 0%
L47 0% 0% 0% 0% L47 0% 0% 0%
L46 0% 0% 0% 0% L46 0% 0% 0%
L45 0% 0% 0% 0% L45 0% 0% 0%
L44 0% 0% 0% 0% L44 0% 0% 0%
L43 0% 0% 0% 0% L43 0% 0% 0%
L42 0% 0% 0% 0% L42 0% 0% 0%
L41 0% 0% 0% 0% L41 0% 0% 0%
L40 0% 0% 0% 0% L40 0% 0% 0%
L39 0% 0% 0% 0% L39 0% 0% 0%
L38 0% 0% 0% 0% L38 0% 0% 0%
L37 0% 0% 0% 0% L37 0% 0% 0%
L36 0% 0% 0% 0% L36 0% 0% 0%
L35 0% 0% 0% 0% L35 0% 0% 0%
L34 0% 0% 0% 0% L34 0% 0% 0%
L33 0% 0% 0% 0% L33 0% 0% 0%
L32 0% 0% 0% 0% L32 0% 0% 0%
L31 0% 0% 0% 0% L31 0% 0% 0%
Floor #
Hotel Tower
Floor #
Office Tower
Concrete Rough Finishes Façade Concrete Rough Finishes Façade
L31 0% 0% 0% 0% L31 0% 0% 0%
L30 0% 0% 0% 0% L30 0% 0% 0%
L29 0% 0% 0% 0% L29 0% 0% 0%
L28 0% 0% 0% 0% L28 0% 0% 0%
L27 90% 0% 0% 0% 0% L27 0% 0% 0%
L26 100% 0% 0% 0% 0% L26 80% 0% 0% 0%
L25 100% 95% 0% 0% 0% 0% L25 100% 0% 0% 0%
L24 100% 100% 0% 0% 0% 0% L24 100% 95% 0% 0% 0%
L23 100% 100% 0% 0% 0% 0% L23 100% 100% 0% 0% 0%
L22 100% 100% 0% 0% 0% 0% L22 100% 100% 0% 0% 0%
L21 100% 100% 0% 0% 0% 0% L21 100% 100% 0% 0% 0%
L20 100% 100% 0% 0% 0% 0% L20 100% 100% 0% 0% 0%
L19 100% 100% 0% 0% 0% 0% L19 100% 100% 0% 0% 0%
L18 100% 100% 0% 0% 0% 0% L18 100% 100% 0% 0% 0%
L17 100% 100% 0% 0% 0% 0% L17 100% 100% 0% 0% 0%
L16 100% 100% 5% 0% 0% 0% L16 100% 100% 70% 0% 0%
L15 100% 100% 5% 0% 0% 0% L15 100% 100% 70% 0%
L14 100% 100% 10% 0% 0% 0% L14 100% 100% 70% 0%
L13 100% 100% 15% 0% 0% 0% L13 100% 100% 70% 0%
L12 100% 100% 50% 0% 0% 0% L12 100% 100% 70% 0%
L11 100% 100% 90% 0% 0% 0% L11 100% 100% 70% 0%
L10 100% 100% 96% 96% 7% 0% L10 100% 100% 70% 60% 25%
L09 100% 100% 96% 96% 69% 5% L09 100% 100% 70% 60% 33%
L08 100% 100% 96% 96% 84% 5% L08 100% 100% 70% 60% 34%
L07 100% 100% 96% 96% 86% 20% L07 100% 100% 70% 70% 44%
L06 100% 100% 96% 96% 86% 50% L06 100% 100% 95% 70% 47%
L05 100% 100% 96% 96% 86% 85% L05 100% 100% 90% 70% 41%
L04 100% 100% 5% 0% 0% 0% L04 100% 100% 90% 70% 0%
L03 100% 100% 0% 0% #N/A 0% L03 100% 100% 0% 0% 0%
Mez. 100% 100% 0% 0% #N/A 0% Mez. 100% 100% 0% 0% 0%
L02 100% 100% 0% 0% #N/A 0% L02 100% 100% 0% 0% 0%
L01 100% 100% 85% 0% #N/A 0% L01 100% 100% 0% 0% 0%
G.F 100% 100% 85% 0% #N/A 10% G.F 100% 100% 0% 0% 0%
B01 100% 100% 70% 60% #N/A 5% B01 100% 100% 0% 0% 0%B01 100% 100% 70% 60% #N/A 5% B01 100% 100% 0% 0% 0%
B02 100% 100% 90% 80% #N/A 0% B02 100% 100% 90% 0% 0%
Page 94 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Site Progress Photos
Page 95 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Site Progress Photos
Overall View
Corewall (L27 : L28), Slab L25(Hotel Tower)
Page 96 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Slab L25Slab L25(Hotel Tower)
Hotel - L16 : Block works Page 97 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Hotel - L14 : Block works
Hotel - L10 : MEP Marking
Page 98 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Hotel - Level 09 : MEP conduits in walls
Hotel - L08 : MEP Electrical & water supply Conduits in wall
Page 99 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Hotel - L07 : Plastering (Rash coat)
Hotel - L05 : Suspention system installation
Page 100 of 106 TT, Weekly Report No. 86 As of 2012-10-20
(Office Tower)
Corewall (L26 : L27), Slab L24( ),(Office Tower)
Page 101 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Block Work L16(Office Tower)( )
MEP marking - L15g(Office Tower)
Page 102 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Electrical Conduits - L10Electrical Conduits L10(Office Tower)
MEP Electrical & water supply Conduits in wall - L08(Office Tower)
Page 103 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Podium - BS2 - Ramp (G : L01)
Podium - BS3 - Columns (G:L01)
Page 104 of 106 TT, Weekly Report No. 86 As of 2012-10-20
AS3 -Basement 1 Slab
AS2 Verticals (B2 : B1) & Basement 1 slabAS2 -Verticals (B2 : B1) & Basement 1 slab
Page 105 of 106 TT, Weekly Report No. 86 As of 2012-10-20
Podium - AS1 - Columns (G:L01)
Page 106 of 106 TT, Weekly Report No. 86 As of 2012-10-20